Escolar Documentos
Profissional Documentos
Cultura Documentos
Background
The Earned Value Management (EVM) is a method that enables forecasting a project outcome
and it is based on how a project has already progressed up to a certain point. It is performed and
updated by the project manager and used as a decision support by both the project manager and
the project sponsor.
In order to make it easier to use the method, one should already in the planning session divide
planned activities (Planned Value in EVM) over the calendar depending on the update frequency.
If you plan to update every week, distribute over weeks. If you plan to update monthly, distribute
over months.
Prerequisites
The information that is required to perform the EVM method is available in your project plan
(A1):
- The list of activities (e.g. lectures, interview with PM, etc.).
- The planned cost for the activities (project budget) distributed over time
Method
The EVM method is summarized in the following steps:
1. Construct the EVM table with the required information (i.e. Planned Value (PV), Actual
Cost (AC), Earned Value (EV)) with respect to the activities (e.g. lectures, interview with
PM, etc.) and the update frequency (e.g. weeks). Then:
a. Input the PV according to the project budget, i.e. distribute the cost for the activities
during the project lifetime.
b. Quantify the Budget At Completion (BAC).
2. Update the EVM table (i.e. AC, EV) with the up to date information on the performed
activities. Hint: If the activity is completed set the EV according to PV. If not, estimate the value you
earned this far to an appropriate level under PV e.g. 50% of PV.
3. Calculate the Estimate at completion (EAC).
4. Plot the AC and EV up to the current point in time and the PV for the entire project
lifetime. Additionally, include the EAC at project end.
The terms and formulas can be found at the end of the document.
For further info see the following example.
EH2720/EH2070
2018-08-31
© Department of Network and Systems Engineering
KTH p. 2 (4)
EVM example
Assume that you are appointed as a project manager and you and your team are requested to
implement a project. This project has three activities: Activity A (e.g. attend lecture #1), activity B
(e.g. contact a project manager) and activity C (e.g. write an article). Before the project begins, you
estimate that each activity will take 100 hours to complete and that cost per hour is SEK 300. The
total cost can therefore be calculated at SEK 300 * 100 h = SEK 30K per activity. The total
project budget is SEK 90K. Prior to project start, the project can be summarized according to
Table 1.
nn/nn/nn : Planned Value (PV)/Earned Value (EV)/Actual Cost (AC) nn/nn/nn : Planned Value (PV)/Earned Value (EV)/Actual Cost (AC)
Activity Activity
A not started (e.g. attend lecture #1) 30/0/0 A Ready (e.g. attend lecture #1) 30/30/30
B not started (e.g. contact a PM) 30/0/0 B not started (e.g. contact a PM) 30/0/0
C not started (e.g. write an article) 30/0/0 C not started (e.g. write an article) 30/0/0
Week 1 Week 2 Week 3 Week 1 Week 2 Week 3
Planned Value (PV) 30 30 30 Planned Value (PV) 30 30 30
Accumulated PV Accumulated PV 30
Earned Value (EV) Earned Value (EV) 30
Accumulated EV Accumulated EV 30
Actual Cost (AC) Actual Cost (AC) 30
Accumulated AC Accumulated AC 30
Timeline Timeline
When the project begins, everything goes according to plan. Activity A is completed after 100
hours of work, which corresponds to a cost of SEK 30K. The project can now be represented
according to Table 2.
However, problems arise with Activity B. By the time the week 2 draws to a close, a total of SEK
47K has been spent. The value of the completed work is still SEK 30K. Activity B was essentially
completed in time, but at greater expense and effort. See Table 3.
Activity
A Ready (e.g. attend lecture #1) 30/30/30
B Ready (e.g. contact a PM) 30/30/47
C not started (e.g. write an article) 30/0/0
Week 1 Week 2 Week 3
Planned Value (PV) 30 30 30
Accumulated PV 30 60
Earned Value (EV) 30 30
Accumulated EV 30 60
Actual Cost (AC) 30 47
Accumulated AC 30 77
Timeline
EH2720/EH2070
2018-08-31
© Department of Network and Systems Engineering
KTH p. 3 (4)
Now your supervisor, who owns the project, is wondering how the project is going and what cost
you estimate the entire project will amount to when complete. One way to produce an estimate
of the end results is to apply Earned Value Management. This utilizes data from previously
demonstrated trends to calculate a forecast for the future. A few important terms and formulas
that can be used are presented below.
Calculations
Assume now that we are going to try to make an estimate of the final cost for the project using
Earned Value Management.
The budgeted cost for the entire project is SEK 90K (BAC).
The actual cost up to this point in the project is SEK 30K + 47K = SEK 77K.
The earned value of the completed work is SEK 30K + 30K = SEK 60K.
The formula EAC = BAC / CPI together with CPI = EV / AC means that EAC = BAC * AC /
EV, and therefore EAC = SEK 90K * SEK 77K / SEK 60K = SEK 116K.
By using Earned Value Management, we can therefore estimate that the project will have a cost
overrun of SEK 26K if current trends continue.
Activity Prognosis
A Ready (e.g. attend lecture #1) 30/30/30
B Ready (e.g. contact a PM) 30/30/47
C not started (e.g. write an article) 30/30/39
Week 1 Week 2 Week 3
Planned Value (PV) 30 30 30
Accumulated PV 30 60 90
Earned Value (EV) 30 30 30
Accumulated EV 30 60 90
Actual Cost (AC) 30 47 39
Accumulated AC 30 77 116
Timeline
Table 4. Forecast for how the project will progress during Week 3, based on the results of Week 1
and Week 2.
Note that this example is simplified, and that is it important to point out that ALL activities must
be tracked with routine follow-up reviews at discrete points in time, such as once per time
resolution (e.g. week). It is at these times that estimates are made and trends are studied. It is the
trends that are the essential points, not the individual measurements. A single measurement does
not reveal a trend. Earned Value Management is most appropriate when a project with multiple
activities is reviewed through routine follow-up.
EH2720/EH2070
2018-08-31
© Department of Network and Systems Engineering
KTH p. 4 (4)
EVM Graph
Cost EVM
140
60 60 EV
AC
40
30
20
0
Week 1 Week 2 Week 3 Time
More information
www.wikipedia.org Excellent and comprehensive introduction to the term Earned Value.
www.apm.org.UK Association for Project Management has an Earned Value
Management interest group. Several interesting presentations are
available for download here:
www.evm.nasa.gov NASA describes its way of working with Earned Value Management.
EH2720/EH2070
2018-08-31
© Department of Network and Systems Engineering