FLOWCHART FOR PROJECT COMPLETION & HANDOVER

Review & Approval


List, Form &
Procedures of T&C

Internal T&C
(08/08/2018)

Briefing of T&C:
1. Liaise with SAJ project team to fix date/time/venue for
briefing of T&C
2. Provide copy of the approved list & procedures of T&C
to SAJ
3. Provide schedule of official T&C
4. Issue an invitation letter to SAJ/PAAB/PNSB

PBE submit Draft As-


Built Drawing 1 week
before official T&C

- Official T&C
- Propose CPC Date

Carry out Joint


Inspection 7 Days after
CPC Date

PBE Submit Training


Schedule 1 Month after
CPC