Elemento Concreto
Medidas PARCIAL TOTAL GENERAL
DESCRIPCION Y UBICACIÓN UNID
L A H (m³) (m³) (m³)
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL 31.00 4.95 153.45
TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR 31.00 4.95 153.45
MOVIMIENTO DE TIERRAS
ZAPATAS
Z-1 6 1.5 1.5 1.2 16.20 32.02 47.73
Z-2 4 1.3 1.3 1.2 8.11
Z-3 2 1.1 1.1 1.2 2.90
Z-4 8 0.8 0.6 0.8 3.07
Z-5 6 0.6 0.6 0.8 1.73
CIMIENTOS
EJE 1-1 ENTRE EJE A-B 1 1.48 0.4 0.6 0.36 6.33
EJE 1-1 ENTRE EJE B-C 1 1.48 0.4 0.6 0.36
EJE 4-4 ENTRE EJE A-C 1 2.4 0.4 0.6 0.58
EJE 5-5 ENTRE EJE A-C 1 2.1 0.4 0.6 0.50
EJE 6-6 ENTRE EJE A-B 1 1.8 0.4 0.6 0.43
INTERIOR EJE 6-7 ENTRE EJE A-B 1 3.25 0.4 0.6 0.78
EJE 7-7 ENTRE EJE A-C 1 2.15 0.4 0.6 0.52
INTERIOR EJE 7-8 ENTRE EJE A-B 1 3.35 0.4 0.6 0.80
EJE 8-8 ENTRE EJE A-C 1 2.25 0.4 0.6 0.54
EJE 9-9 ENTRE EJE A-C 1 2.65 0.4 0.6 0.64
EJE 14-14 ENTRE EJE A-B 1 1.73 0.4 0.6 0.42
EJE 14-14 ENTRE EJE B-C 1 1.73 0.4 0.6 0.42
EJE A-A ENTRE EJE 1-3 1 1.57 0.4 0.6 0.38 4.46
EJE A-A ENTRE EJE 3-4 1 2.02 0.4 0.6 0.48
EJE A-A ENTRE EJE 4-5 1 2.13 0.4 0.6 0.51
EJE A-A ENTRE EJE 5-6 1 0.4 0.4 0.6 0.10
EJE A-A ENTRE EJE 6-7 1 1.05 0.4 0.6 0.25
EJE A-A ENTRE EJE 7-8 1 2.1 0.4 0.6 0.50
EJE A-A ENTRE EJE 8-9 1 1.13 0.4 0.6 0.27
EJE A-A ENTRE EJE 10-12 1 2.3 0.4 0.6 0.55
EJE A-A ENTRE EJE 12-13 1 2.98 0.4 0.6 0.72
EJE A-A ENTRE EJE 12-14 1 2.89 0.4 0.6 0.69
EJE B-B ENTRE EJE 6-7 1 0.9 0.4 0.6 0.22 0.22
EJE C-C ENTRE EJE 1-2 1 0.45 0.4 0.6 0.11 4.71
EJE C-C ENTRE EJE 2-4 1 3.1 0.4 0.6 0.74
EJE C-C ENTRE EJE 4-5 1 2.13 0.4 0.6 0.51
EJE C-C ENTRE EJE 5-7 1 2.55 0.4 0.6 0.61
EJE C-C ENTRE EJE 7-8 1 2.1 0.4 0.6 0.50
EJE C-C ENTRE EJE 8-9 1 1.13 0.4 0.6 0.27
EJE C-C ENTRE EJE 10-12 1 2.3 0.4 0.6 0.55
EJE C-C ENTRE EJE 12-13 1 2.98 0.4 0.6 0.72
EJE C-C ENTRE EJE 13-14 1 2.89 0.4 0.6 0.69