S.L.No. Deep well No.

Water Level below the


Raft Foundation h (m) Tower Status Well closing start
Date
Well closing
completion date
1 W32 2 TB Operational 10‐Sep‐18 13‐Sep‐18
2 W3 3 TA Operational 11‐Sep‐18 15‐Sep‐18
3 W24 7 TB Operational 16‐Sep‐18 17‐Sep‐18
4 W20 8 TB Operational 18‐Sep‐18 19‐Sep‐18
5 W1 1 TA Operational 20‐Sep‐18 22‐Sep‐18
6 W2 3 TA Operational 23‐Sep‐18 24‐Sep‐18
7 W29 3.5 TA Operational 25‐Sep‐18 26‐Sep‐18
8 W25 4 TB Operational 27‐Sep‐18 29‐Sep‐18
9 W23 7.5 TB Operational 30‐Sep‐18 01‐Oct‐18
10 W22 8 TB Operational 02‐Oct‐18 03‐Oct‐18
11 W28 9 TA Operational 04‐Oct‐18 06‐Oct‐18
12 W30 10 TB Operational 07‐Oct‐18 08‐Oct‐18
13 W31 11 TB Operational 09‐Oct‐18 10‐Oct‐18