Escolar Documentos
Profissional Documentos
Cultura Documentos
chief
of the achl ef consolidated mine at eureka utah
BY BROTHERS
the first mine in utah to try out the ad- the shaft walls was another important con- and the third for the accommodation of a
vantages of the concrete shaft is the chief sideration incidentally the concrete is very chippy cage and the ladder ways and pip-
consolidated at eureka in the gintic tintic dist- discouraging to rats ing wiring etc it is the intention to sink
rict where it was decided to introduce the work was started in july 1918 at the to a depth of 2000 feet the first 1450 feet
innovation when the company planned its same time that the sinking operations were having been completed at the time of this
large three compartment operating shaft writing
begun the sinking of the shaft is being
known as no 2 and started two years ago
carried on by walter fitch jr contractor the drawing showing the section through
the idea is not new or experimental be- and the concrete work is being put in by thee arrangement of the three
the shaft gives th
cause several mines in the duluth minnes-
ota district and elsewhere have been conc-
az
reted some of the installations dating back
to 1903
the reasons for concreting this
chief consolidated shaft were
first to insure perfect alignment the
17
1aa
most remarkable T
fact that has been establi- I
1
2 s ay 7 avre ceaf
6 farrrr
c
fr
j
c dr
31 k f r
il i 8
4tjJm
egl
S
yta
i t
r
i
i
0
i
1
fc 1
1
t
i t
i
sl
1
1
1
f S
7 1
i
r
rf
I1
0
r s s17
Xt T
L 1
c
fat
i
a
tt k al i
i
T
1I
t
77 7
J
1
1 C
it
i- ij
TV
S
f
5 S jl 3 xa 2 s
y
ll
11 id
ence this is done by constructing a frame-
work of inch timbers to make a false
bottom for the shaft about ten feet above
the actual bottom concreting is carried on
above the and pumping below As
it is evident that the removal of the
will leave a great weight of concrete
suspended without direct support from be-
low it is necessary to pour the first ten feet
in height solid that is extending right
back to the rock walls pouring solid re-
quires at least four to five times as much
AA
concrete as pouring hollow low this is on
account of over breakage which is the dif-
ference between the amount of material
broken away in blasting and the theoretical-
ly correct straight lines of the shaft
the divider frames are lowered
t 3
b into place ahead of any of the reinforcing or
k
comp anys
lowered and raised by the mining companas 4
hoist
various schemes for from the
J
bucket into the forms have been tried but
it is found most satisfactory and gives the at left Is picture of divider frame
at right one unit of reinforcing mat ready
densest concrete to dump the bucket on a to place
1
1
10 Z
C
2tj
as i ma hia kw
dpn IM 10 5 OLM 41
44
r
3 i J
ll
11 afa y
S
section through shaft showing three compartments
shoveling platform and shovel from that sumps at the pumping stations
led into the bumps
into the forms some of the water is of excellent quality for
how water is handled drinking and is pumped to the residences of
the drainage of water from the shaft the mine officials
walls is quite an important consideration in mr cecil fitch Is the general manager
connection with the concrete design the and mr J fred johnson is the general mine
water is led off above each solidly concreted superintendent for the chief consolidated
section through a 2 inch perforated drain all contracting work is done under their su-
pipe which connects with a header running per
pervision
vision
down the shaft there should not be a free the cost of lining with concrete includ-
access of air through the drain pipes to the ing the timbering for this three compart
porphyry behind pumping stations are lo- ment shaft runs from 70 to 90 per linear
cated at intervals of about feet along foot of shaft depending on the character of
the shaft and all drainage from the pipes is the ground