BAKAU PILE
2.01 Supply, handle, pitch and drive 75 mm dia. (ave) x 4.5 m long
bakau pile at 450 mm c/c to foundation of concrete pipe
culverts, drains and at locations as directed by the S.O.
Contractor to inform S.O. the source of bakau piles before
order.
200 No.
PILING RECORD
2.02 Prepare and submit three (3) bound copies of piling records
of driven bakau piles complete with photographs and plans
showing their locations,which have been certified by the
Supervising Staff for review by PKNS/MINCONSULT. - Sum -
R.C. SUMP
a) Excavation 30 m3
b) Concrete Grade 25 15 m3
c) Formwork 60 m2
a) Excavation 200 m3
c) Formwork 450 m2
f) Concrete Grade 25 40 m3
Collection
SUBGRADE
ROAD FORMATION
3.02 Prepare formation for receiving road pavement and side -table.
SUB-BASE
BASE COURSE
3.05 Supply, lay and compact crusher run for road base
CBR TEST
a) Subgrade 12 No.
b) Sub-Base 12 No.
Note: The rate of application shall be not less than 0.44 liters per
sq.m 10,200 m2
BINDER COURSE
PONDING TEST
Note: i) Rate shall allow for marking out areas of ponding with
white paint.
ii) Rate shall also allow for ponding test to be repeated
after the initial ponding areas have been regulated. - Sum -
3.10 Supply and applly bituminous tack coat to surface of the Bitumen
Macadam Binder Course.
WEARING COURSE
3.11 Supply, lay, roll and compact Hot Rolled Asphalt final wearing
course (ACWC 14) in accordance with the Specification and as
directed by the Engineer to compacted thickness as specified:
CORING TEST
3.12 Allow for coring tests to determine thickness of binder course and
wearing course in accordance to the B.S. Specification and as
directed by the S.O
Note: i) Coring tests shall be carried out at the rate of one (1)
no. per 500m² of metalled pavement.
ii) Photographs shall be taken of each cored sample
together with a tape alongside to indicate the thickness
of each layer.
iii) Three (3) bound copies of Coring tests results c/w
photographs of samples and plans showing locations of
tests, which have been certified by the Supervising staff
and the Contractor's Site Agent, shall be submitted for
the review of PKNS / MPS / Minconsult.
18 nos.
a) Excavation 2,000 m2
c) BRC A8 2,000 m2
ROAD KERB
SCUPPER PIPE
3.15 Supply and lay 230mm dia. SGW pipe from kerb to outlet drain at
3m c/c along straigth stretches and 1.5m c/c at bends or as
directed by the S.O. 300 m
CARRIAGEWAY MARKINGS
3.16 Supply all materials and labour as specified, set out and paint the
following carriageway markings with "hot applied" tropical-
formulated Thermo-plastic screed as shown in the Drawings.
g) Go Straight Arrow 30 no
ROAD HUMP
Note: Rate shall include keying hump to existing wearing course. 8 nos.
Note: The rate shall include for all posts, concrete footings,
paintings and for steel works as detailed in the drawings.
a) 'Berhenti' sign 10 No
c) Other signs 5 No
3.19 Fabricate, supply and install road name signboards as per Majlis
Perbandaran Selayang (MPS) requirement.
Note: The rate shall allow for all posts, concrete footings,
painting , steel works, etc.
G.I GUARDRAILS
Note: i) The rate shall allow for all posts, concrete footings,
painting , steel works, etc.
G.I RAILING
3.21 Supply and fix 1.0 m height x 50mm dia. 'hot -dipped' G.I (Class
B) pipe railing as directed by the S.O. as per drawing no.
PKNS/MINCO(KA)/G/KP/S8-3A/T/DR/03.
ii) Rate shall also include painting G.I pipe with one (1)
coat of Etching Primer and two (2) coats of gloss paint
in accordance with MPS requirement.
WALKWAY PAVEMENT
3.24 Supply and lay 100mm thick Grade 20 concrete with 'Broom
Finish pattern' with one layer reinforcement BRC A8 to S.O. 2,800 m2
approval.
Collection