2 Mobilization 4 days Mon 6/25/18 Thu 6/28/18 100% Excavater[4],Skilled Labour[8],Unskilled Labour[12]
3 Rerouting and relocating busses 5 days Thu 6/28/18 Mon 7/2/18 2SS+3 days 100% Skilled Labour[10],Unskilled Labour[40],Tipper truck[20],JCB Machine[5]
4 Clearing the site including removal of 9 days Tue 7/3/18 Wed 7/11/18 3 100% Skilled Labour[18],Unskilled Labour[18],JCB Machine[9]
roots and cut down top soil and
removing exsisting foundation
5 Sample & material approvals such as 20 days Fri 6/29/18 Wed 7/18/18 2SS+4 50% Site Engineer[20],Skilled Labour[20],Unskilled Labour[40]
sand,metal,cement,steel,structural days
steel,Roofing sheet,etc
6 Central province passenger transport 143 days Tue 7/17/18 Fri 12/21/18 5%
survices authority office building Upper
floor
7 Clearing and removing the existing slab 8 days Wed 7/25/18 Wed 8/1/18 2FS-8 30% Concrete bracker[8],Skilled Labour[24]
top wast materials and remove from days
site
8 Demolishing and removing the existing 5 days Tue 7/17/18 Sat 7/21/18 7SS-8 100% JCB Machine[5],Operator[5],Unskilled Labour[10]
additional slab on top of staircase days
9 Construction of column including form 11 days Sun 7/22/18 Wed 8/1/18 8 50% Ready mix concrete[1],Form work [1],Rainforcement[1],Skilled Labour[22],Unskilled Labour[11]
work,r/f and concreting work
10 Construction of roof tie beam and 15 days Thu 8/2/18 Fri 8/31/18 9 5% Mason[30],Unskilled Labour[40]
water tank slab
11 150 mm cement block work 13 days Wed 10/3/18 Mon 10/15/18 14 0% Mason[39],Unskilled Labour[39]
12 Fabricating steel roof 16 days Thu 8/2/18 Sat 9/1/18 10SS 0% Welder[48],Unskilled Labour[48]
13 Erecting steel roof 10 days Sat 9/8/18 Mon 9/17/18 10FS+7 days 0% Welder[30],Unskilled Labour[30]
14 Roof covering and roof plumbing 15 days Tue 9/18/18 Tue 10/2/18 13 0% Pumber[8]
15 Piping water supply ,sewerage and 15 days Tue 10/16/18 Tue 10/30/18 11 0% Pumber[10]
waste water
16 Conduting and wiring for electical 15 days Tue 10/16/18 Tue 10/30/18 11 0% Electrician[10]
fittings
17 Conduting and wiring for telephone 10 days Tue 10/16/18 Thu 10/25/18 11 0% Electrician[10]
system
18 Installating of sanitory fittings and 4 days Mon 12/17/18 Thu 12/20/18 30 0% Pumber[16],Unskilled Labour[16]
accesaries
19 Fixing electrical fittings including DBs 4 days Mon 12/17/18 Thu 12/20/18 30 0% Electrician[8],Unskilled Labour[12]
20 Installating of telephone system 13 days Wed 12/5/18 Mon 12/17/18 30SS 0% Electrician[26],Unskilled Labour[26]
21 instalating of Fire protection system 4 days Mon 12/17/18 Thu 12/20/18 30 0% Fire technician[8],Unskilled Labour[8]
22 Plastering work (Internaly) 13 days Fri 10/26/18 Wed 11/7/18 17 0% Mason[26],Unskilled Labour[26]
23 Plastering work (Externaly) 11 days Thu 11/8/18 Sun 11/18/18 22 0% Mason[44],Unskilled Labour[33]
24 Water proofing of bath rooms and 6 days Thu 11/8/18 Tue 11/13/18 22 0% Skilled Labour[6],Unskilled Labour[12]
water tank slab
25 Floor tiling 9 days Fri 11/23/18 Sat 12/1/18 27 0% Tiling Mason[18],Unskilled Labour[18]
26 Wall tiling 15 days Sun 12/2/18 Sun 12/16/18 25 0% Tiling Mason[30],Unskilled Labour[30]
27 Ceiling warks 15 days Thu 11/8/18 Thu 11/22/18 22 0% Skilled Labour[30],Unskilled Labour[40]
28 Alumunium works 16 days Mon 11/19/18 Tue 12/4/18 23 0% Skilled Labour[48],Unskilled Labour[48]
29 Lightning protection system instalation 9 days Wed 12/5/18 Thu 12/13/18 28 0% Electrician[18],Skilled Labour[9]
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
33 Removal of structure and obstruction 8 days Mon 10/1/18 Mon 10/8/18 0% Skilled Labour[16],Unskilled Labour[24],JCB Machine[8]
along the road side
34 Scarify and remove existing bitumen 8 days Tue 10/9/18 Tue 10/16/18 33 0% JCB Machine[8],Skilled Labour[16],Unskilled Labour[32]
layer as directed by the engineer
35 Dence graded aggregate base (Approx 12 days Wed 10/17/18 Sun 10/28/18 34 0%
100mm )(Aggregate base course)
40 Construction of transitional bus terminal 166 days Mon 7/9/18 Sat 1/5/19 25%
43 Removing top surface in building 12 days Fri 7/13/18 Tue 7/24/18 42 30% JCB Machine[12]
area and carted away
44 Excavation to reduce level 25 days Wed 7/25/18 Sun 9/2/18 43 70% JCB Machine[25],Tipper truck[100],Unskilled Labour[25]
45 Ground preparation 25 days Wed 7/25/18 Sun 9/2/18 44SS 70% Excavater[25]
46 setting out works 1 day Wed 8/1/18 Wed 8/1/18 45FS-18 days 70%
47 Excavation of foundation 24 days Thu 8/2/18 Sun 9/9/18 46 70% JCB Machine[24],Operator[24],Unskilled Labour[24]
48 Laying screed concrete 25 days Tue 8/7/18 Sat 9/15/18 47SS+5 days 70% Skilled Labour[25],Unskilled Labour[25]
49 Formwork of base 25 days Fri 8/10/18 Tue 9/18/18 48SS+3 days 70% Skilled Labour[25],Unskilled Labour[25]
50 Rainforcement work of bace 25 days Sun 8/12/18 Thu 9/20/18 49SS+2 days 70%
51 Concreting of base 25 days Wed 8/29/18 Sat 9/22/18 50SS+2 days 70% Ready mix concrete[100],Skilled Labour[50],Unskilled Labour[75]
52 Column reinforcement work 25 days Sat 9/1/18 Tue 9/25/18 51SS+3 days 70% Rainforcement[6],Skilled Labour[25],Unskilled Labour[50]
53 Column formwork 25 days Tue 9/4/18 Fri 9/28/18 52SS+3 days 70% Skilled Labour[50],Unskilled Labour[50]
54 Column concreting work 25 days Fri 9/7/18 Mon 10/1/18 53SS+3 70% Ready mix concrete[10],Skilled Labour[50],Unskilled Labour[75]
days
55 Rubble work 9 days Tue 9/25/18 Wed 10/3/18 54SS+18 days 0% Rubble[1],Skilled Labour[18],Unskilled Labour[36]
56 Plinth beam and tie 7 days Fri 9/28/18 Thu 10/4/18 55SS+3 0% Ready mix concrete[75],Skilled Labour[28],Unskilled Labour[56]
beamr/f,formwork&concreting days
57 Filling under floor and back filling 15 days Sun 11/18/18 Sun 12/2/18 56SS+2 0% Unskilled Labour[60]
days,62
58 Anti-termite treatment 7 days Mon 12/24/18 Sun 12/30/18 63FS+16 days 0% Skilled Labour[14],Unskilled Lab
59 Floor concreting 13 days Mon 12/24/18 Sat 1/5/19 58SS 0% Mason[30],Unskilled Labo
60 Superstructure 90 days Sun 9/9/18 Fri 12/7/18 2%
61 Fabrication of potal frames 45 days Sun 9/9/18 Tue 10/23/18 42FS+8 days 5%
62 Erection of potal frames 25 days Wed 10/24/18 Sat 11/17/18 61 0% Welder[100],Unskilled Labour[100]
63 Roof work and roof plumbing 20 days Sun 11/18/18 Fri 12/7/18 62 0% Welder[20],Unskilled Labour[30]
64 Structural work ground floor to first 14 days Fri 10/5/18 Thu 10/18/18 56 0% Mason[28],Unskilled Labour[28]
floor level
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
67 piping for water supply and 10 days Thu 11/1/18 Sat 11/10/18 65 0% Pumber[10],Unskilled Labour[10]
sewerage inside of the building
68 Conduiting and wiring electrical 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[10]
work
69 Conduiting and wiring for fire alarm 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[8]
and fire detection system
installation
70 Conduiting and wiring for CCTV 10 days Thu 11/1/18 Sat 11/10/18 65 0% CCTV Technician[10],Unskilled Labour[10]
system
71 Conduiting and wiring for public 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[10]
address system
72 Water supply,sewerage and waste 15 days Wed 12/12/18 Wed 12/26/18 85 0% Pumber[45],Unskilled Labour[45]
water external works
73 Construction of septic tank,sockage 10 days Wed 12/12/18 Fri 12/21/18 72SS 0% Mason[30],Unskilled Labour[30]
pit and sump
74 Installation of sanitory fittings and 12 days Wed 12/12/18 Sun 12/23/18 73SS 0% Pumber[24],Unskilled Labour[12]
accesaries
75 Installation of electrical fittings and 15 days Wed 12/12/18 Wed 12/26/18 74SS 0% Electrician[22],Unskilled Labour[20]
D board
76 Installation of fire potection and 14 days Wed 12/12/18 Tue 12/25/18 75SS 0% Fire technician[28],Unskilled Labour[5
detection system
77 Installation and fixing public address 13 days Wed 12/12/18 Mon 12/24/18 76SS 0% CCTV Technician[26],Unskilled Labour
system and CCTV system
80 Water proofing bath room and roof 7 days Fri 11/23/18 Thu 11/29/18 79 0% Skilled Labour[14],Unskilled Labour[21]
slab
81 Plastering (external wall) 6 days Sat 12/8/18 Thu 12/13/18 63 0% Mason[28],Unskilled Labour[56]
82 Plinth plater 7 days Fri 12/14/18 Thu 12/20/18 81 0% Skilled Labour[7],Unskilled Labour[14]
83 Aluminium works 20 days Fri 12/14/18 Wed 1/2/19 81 0% Skilled Labour[60],Unskilled
84 Wall tiling bathroom area 12 days Sat 11/17/18 Wed 11/28/18 79SS+6 days 0% Tiling Mason[24],Unskilled Labour[24]
85 Floor tiling 13 days Thu 11/29/18 Tue 12/11/18 84 0% Tiling Mason[39],Unskilled Labour[39]
86 Ceiling finishes 5 days Fri 11/23/18 Tue 11/27/18 79 0% Skilled Labour[10],Unskilled Labour[20]
87 Hand railing and steel staircase 8 days Fri 10/19/18 Fri 10/26/18 64 0% Skilled Labour[16],Unskilled Labour[32]
88 External works paving and aspalt 50 days Sun 11/11/18 Sun 12/30/18 79SS 0%
surfacing including drain,turfing,paving
89 Painting 15 days Thu 12/13/18 Thu 12/27/18 81SS+5 days 0% Skilled Labour[60]
90 Fixing passenger seating 12 days Sat 12/22/18 Wed 1/2/19 89FS-6 0% Skilled Labour[24]
days
91 Final touchup works 8 days Fri 12/28/18 Fri 1/4/19 90SS+6 days 0% Skilled Labour[10],Unskilled
92 Site clearing befor handing over 8 days Fri 12/28/18 Fri 1/4/19 91SS 0% Skilled Labour[10],Unskilled
93 Handing over the project 1 day Sat 1/5/19 Sat 1/5/19 92 0% 1/5
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress