Progress up to 18th of September 2018 transitional bus terminal for kandy multimodel transpotation terminal project in Kandy

ID Task Name Duration Start Finish Predecessors


% Complete

July August September October November December January


6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
1 Construction of transitional bus terminal 180 days Mon 6/25/18 Sat 1/5/19 20%
for Kandy Multimodal transpotation
terminal project at Bogambara in Kandy

2 Mobilization 4 days Mon 6/25/18 Thu 6/28/18 100% Excavater[4],Skilled Labour[8],Unskilled Labour[12]
3 Rerouting and relocating busses 5 days Thu 6/28/18 Mon 7/2/18 2SS+3 days 100% Skilled Labour[10],Unskilled Labour[40],Tipper truck[20],JCB Machine[5]
4 Clearing the site including removal of 9 days Tue 7/3/18 Wed 7/11/18 3 100% Skilled Labour[18],Unskilled Labour[18],JCB Machine[9]
roots and cut down top soil and
removing exsisting foundation
5 Sample & material approvals such as 20 days Fri 6/29/18 Wed 7/18/18 2SS+4 50% Site Engineer[20],Skilled Labour[20],Unskilled Labour[40]
sand,metal,cement,steel,structural days
steel,Roofing sheet,etc
6 Central province passenger transport 143 days Tue 7/17/18 Fri 12/21/18 5%
survices authority office building Upper
floor
7 Clearing and removing the existing slab 8 days Wed 7/25/18 Wed 8/1/18 2FS-8 30% Concrete bracker[8],Skilled Labour[24]
top wast materials and remove from days
site
8 Demolishing and removing the existing 5 days Tue 7/17/18 Sat 7/21/18 7SS-8 100% JCB Machine[5],Operator[5],Unskilled Labour[10]
additional slab on top of staircase days

9 Construction of column including form 11 days Sun 7/22/18 Wed 8/1/18 8 50% Ready mix concrete[1],Form work [1],Rainforcement[1],Skilled Labour[22],Unskilled Labour[11]
work,r/f and concreting work
10 Construction of roof tie beam and 15 days Thu 8/2/18 Fri 8/31/18 9 5% Mason[30],Unskilled Labour[40]
water tank slab
11 150 mm cement block work 13 days Wed 10/3/18 Mon 10/15/18 14 0% Mason[39],Unskilled Labour[39]

12 Fabricating steel roof 16 days Thu 8/2/18 Sat 9/1/18 10SS 0% Welder[48],Unskilled Labour[48]
13 Erecting steel roof 10 days Sat 9/8/18 Mon 9/17/18 10FS+7 days 0% Welder[30],Unskilled Labour[30]
14 Roof covering and roof plumbing 15 days Tue 9/18/18 Tue 10/2/18 13 0% Pumber[8]

15 Piping water supply ,sewerage and 15 days Tue 10/16/18 Tue 10/30/18 11 0% Pumber[10]
waste water
16 Conduting and wiring for electical 15 days Tue 10/16/18 Tue 10/30/18 11 0% Electrician[10]
fittings
17 Conduting and wiring for telephone 10 days Tue 10/16/18 Thu 10/25/18 11 0% Electrician[10]
system
18 Installating of sanitory fittings and 4 days Mon 12/17/18 Thu 12/20/18 30 0% Pumber[16],Unskilled Labour[16]
accesaries
19 Fixing electrical fittings including DBs 4 days Mon 12/17/18 Thu 12/20/18 30 0% Electrician[8],Unskilled Labour[12]

20 Installating of telephone system 13 days Wed 12/5/18 Mon 12/17/18 30SS 0% Electrician[26],Unskilled Labour[26]
21 instalating of Fire protection system 4 days Mon 12/17/18 Thu 12/20/18 30 0% Fire technician[8],Unskilled Labour[8]

22 Plastering work (Internaly) 13 days Fri 10/26/18 Wed 11/7/18 17 0% Mason[26],Unskilled Labour[26]

23 Plastering work (Externaly) 11 days Thu 11/8/18 Sun 11/18/18 22 0% Mason[44],Unskilled Labour[33]
24 Water proofing of bath rooms and 6 days Thu 11/8/18 Tue 11/13/18 22 0% Skilled Labour[6],Unskilled Labour[12]
water tank slab
25 Floor tiling 9 days Fri 11/23/18 Sat 12/1/18 27 0% Tiling Mason[18],Unskilled Labour[18]

26 Wall tiling 15 days Sun 12/2/18 Sun 12/16/18 25 0% Tiling Mason[30],Unskilled Labour[30]
27 Ceiling warks 15 days Thu 11/8/18 Thu 11/22/18 22 0% Skilled Labour[30],Unskilled Labour[40]

28 Alumunium works 16 days Mon 11/19/18 Tue 12/4/18 23 0% Skilled Labour[48],Unskilled Labour[48]
29 Lightning protection system instalation 9 days Wed 12/5/18 Thu 12/13/18 28 0% Electrician[18],Skilled Labour[9]

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

DGES RR JOINT VENTURE


Progress up to 18th of September 2018 transitional bus terminal for kandy multimodel transpotation terminal project in Kandy
ID Task Name Duration Start Finish Predecessors
% Complete

July August September October November December January


6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
30 Painting works 12 days Wed 12/5/18 Sun 12/16/18 28 0% Skilled Labour[48]
31 Final touchup works 6 days Sun 12/16/18 Fri 12/21/18 19FS-5 days 0% Skilled Labour[24]
32 Improvement of road 58 days Mon 10/1/18 Tue 11/27/18 0%

33 Removal of structure and obstruction 8 days Mon 10/1/18 Mon 10/8/18 0% Skilled Labour[16],Unskilled Labour[24],JCB Machine[8]
along the road side
34 Scarify and remove existing bitumen 8 days Tue 10/9/18 Tue 10/16/18 33 0% JCB Machine[8],Skilled Labour[16],Unskilled Labour[32]
layer as directed by the engineer

35 Dence graded aggregate base (Approx 12 days Wed 10/17/18 Sun 10/28/18 34 0%
100mm )(Aggregate base course)

36 Supplying and application of prime 2 days Mon 10/29/18 Tue 10/30/18 35 0%


coat on prepared base
37 Bituminous track coat 3 days Wed 10/31/18 Fri 11/2/18 36 0%

38 Asphalt concrete surfacing 4 days Sat 11/3/18 Tue 11/6/18 37 0%


39 Repairs to existing drains 21 days Wed 11/7/18 Tue 11/27/18 38 0% Mason[42],Unskilled Labour[84],Ready mix concrete[80]

40 Construction of transitional bus terminal 166 days Mon 7/9/18 Sat 1/5/19 25%

41 Substructural works 166 days Mon 7/9/18 Sat 1/5/19 57%


42 Demolishing existing building and 4 days Mon 7/9/18 Thu 7/12/18 4FS-3 60% Excavater[4]
debris carted away from site days

43 Removing top surface in building 12 days Fri 7/13/18 Tue 7/24/18 42 30% JCB Machine[12]
area and carted away
44 Excavation to reduce level 25 days Wed 7/25/18 Sun 9/2/18 43 70% JCB Machine[25],Tipper truck[100],Unskilled Labour[25]

45 Ground preparation 25 days Wed 7/25/18 Sun 9/2/18 44SS 70% Excavater[25]
46 setting out works 1 day Wed 8/1/18 Wed 8/1/18 45FS-18 days 70%
47 Excavation of foundation 24 days Thu 8/2/18 Sun 9/9/18 46 70% JCB Machine[24],Operator[24],Unskilled Labour[24]
48 Laying screed concrete 25 days Tue 8/7/18 Sat 9/15/18 47SS+5 days 70% Skilled Labour[25],Unskilled Labour[25]

49 Formwork of base 25 days Fri 8/10/18 Tue 9/18/18 48SS+3 days 70% Skilled Labour[25],Unskilled Labour[25]
50 Rainforcement work of bace 25 days Sun 8/12/18 Thu 9/20/18 49SS+2 days 70%
51 Concreting of base 25 days Wed 8/29/18 Sat 9/22/18 50SS+2 days 70% Ready mix concrete[100],Skilled Labour[50],Unskilled Labour[75]
52 Column reinforcement work 25 days Sat 9/1/18 Tue 9/25/18 51SS+3 days 70% Rainforcement[6],Skilled Labour[25],Unskilled Labour[50]

53 Column formwork 25 days Tue 9/4/18 Fri 9/28/18 52SS+3 days 70% Skilled Labour[50],Unskilled Labour[50]
54 Column concreting work 25 days Fri 9/7/18 Mon 10/1/18 53SS+3 70% Ready mix concrete[10],Skilled Labour[50],Unskilled Labour[75]
days
55 Rubble work 9 days Tue 9/25/18 Wed 10/3/18 54SS+18 days 0% Rubble[1],Skilled Labour[18],Unskilled Labour[36]
56 Plinth beam and tie 7 days Fri 9/28/18 Thu 10/4/18 55SS+3 0% Ready mix concrete[75],Skilled Labour[28],Unskilled Labour[56]
beamr/f,formwork&concreting days
57 Filling under floor and back filling 15 days Sun 11/18/18 Sun 12/2/18 56SS+2 0% Unskilled Labour[60]
days,62
58 Anti-termite treatment 7 days Mon 12/24/18 Sun 12/30/18 63FS+16 days 0% Skilled Labour[14],Unskilled Lab

59 Floor concreting 13 days Mon 12/24/18 Sat 1/5/19 58SS 0% Mason[30],Unskilled Labo
60 Superstructure 90 days Sun 9/9/18 Fri 12/7/18 2%
61 Fabrication of potal frames 45 days Sun 9/9/18 Tue 10/23/18 42FS+8 days 5%
62 Erection of potal frames 25 days Wed 10/24/18 Sat 11/17/18 61 0% Welder[100],Unskilled Labour[100]

63 Roof work and roof plumbing 20 days Sun 11/18/18 Fri 12/7/18 62 0% Welder[20],Unskilled Labour[30]

64 Structural work ground floor to first 14 days Fri 10/5/18 Thu 10/18/18 56 0% Mason[28],Unskilled Labour[28]
floor level

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

DGES RR JOINT VENTURE


Progress up to 18th of September 2018 transitional bus terminal for kandy multimodel transpotation terminal project in Kandy
ID Task Name Duration Start Finish Predecessors
% Complete

July August September October November December January


6/17 6/24 7/1 7/8 7/15 7/22 7/29 8/5 8/12 8/19 8/26 9/2 9/9 9/16 9/23 9/30 10/7 10/14 10/21 10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13
65 Cement block work 13 days Fri 10/19/18 Wed 10/31/18 64 0% Mason[39],Unskilled Labour[39]
66 M&E works 56 days Thu 11/1/18 Wed 12/26/18 0%

67 piping for water supply and 10 days Thu 11/1/18 Sat 11/10/18 65 0% Pumber[10],Unskilled Labour[10]
sewerage inside of the building
68 Conduiting and wiring electrical 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[10]
work
69 Conduiting and wiring for fire alarm 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[8]
and fire detection system
installation
70 Conduiting and wiring for CCTV 10 days Thu 11/1/18 Sat 11/10/18 65 0% CCTV Technician[10],Unskilled Labour[10]
system
71 Conduiting and wiring for public 10 days Thu 11/1/18 Sat 11/10/18 65 0% Electrician[10],Unskilled Labour[10]
address system
72 Water supply,sewerage and waste 15 days Wed 12/12/18 Wed 12/26/18 85 0% Pumber[45],Unskilled Labour[45]
water external works
73 Construction of septic tank,sockage 10 days Wed 12/12/18 Fri 12/21/18 72SS 0% Mason[30],Unskilled Labour[30]
pit and sump
74 Installation of sanitory fittings and 12 days Wed 12/12/18 Sun 12/23/18 73SS 0% Pumber[24],Unskilled Labour[12]
accesaries
75 Installation of electrical fittings and 15 days Wed 12/12/18 Wed 12/26/18 74SS 0% Electrician[22],Unskilled Labour[20]
D board
76 Installation of fire potection and 14 days Wed 12/12/18 Tue 12/25/18 75SS 0% Fire technician[28],Unskilled Labour[5
detection system
77 Installation and fixing public address 13 days Wed 12/12/18 Mon 12/24/18 76SS 0% CCTV Technician[26],Unskilled Labour
system and CCTV system

78 Finishes 53 days Sun 11/11/18 Wed 1/2/19 0%


79 Plastering (internal walls 12 days Sun 11/11/18 Thu 11/22/18 71 0% Mason[60],Unskilled Labour[60]

80 Water proofing bath room and roof 7 days Fri 11/23/18 Thu 11/29/18 79 0% Skilled Labour[14],Unskilled Labour[21]
slab
81 Plastering (external wall) 6 days Sat 12/8/18 Thu 12/13/18 63 0% Mason[28],Unskilled Labour[56]
82 Plinth plater 7 days Fri 12/14/18 Thu 12/20/18 81 0% Skilled Labour[7],Unskilled Labour[14]
83 Aluminium works 20 days Fri 12/14/18 Wed 1/2/19 81 0% Skilled Labour[60],Unskilled

84 Wall tiling bathroom area 12 days Sat 11/17/18 Wed 11/28/18 79SS+6 days 0% Tiling Mason[24],Unskilled Labour[24]
85 Floor tiling 13 days Thu 11/29/18 Tue 12/11/18 84 0% Tiling Mason[39],Unskilled Labour[39]

86 Ceiling finishes 5 days Fri 11/23/18 Tue 11/27/18 79 0% Skilled Labour[10],Unskilled Labour[20]
87 Hand railing and steel staircase 8 days Fri 10/19/18 Fri 10/26/18 64 0% Skilled Labour[16],Unskilled Labour[32]

88 External works paving and aspalt 50 days Sun 11/11/18 Sun 12/30/18 79SS 0%
surfacing including drain,turfing,paving

89 Painting 15 days Thu 12/13/18 Thu 12/27/18 81SS+5 days 0% Skilled Labour[60]
90 Fixing passenger seating 12 days Sat 12/22/18 Wed 1/2/19 89FS-6 0% Skilled Labour[24]
days
91 Final touchup works 8 days Fri 12/28/18 Fri 1/4/19 90SS+6 days 0% Skilled Labour[10],Unskilled

92 Site clearing befor handing over 8 days Fri 12/28/18 Fri 1/4/19 91SS 0% Skilled Labour[10],Unskilled
93 Handing over the project 1 day Sat 1/5/19 Sat 1/5/19 92 0% 1/5

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: Kandy project program
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 9/18/18
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

DGES RR JOINT VENTURE