Escolar Documentos
Profissional Documentos
Cultura Documentos
Charles H. Raths
President
Raths, Raths & Johnson, Inc.
Structural Engineers
Hinsdale, Illinois
14
by the general influence of the connec-
tions and their locations, panel mullion
to mullion connections, and general
erection requirements.
6. The preliminary size and shape of
the wall panel should be reviewed rela-
tive to all production requirements for
stripping, general handling, storage,
shipping or transportation, and archi-
tectural finish. In short, the panel size
and shape should be practical.
7. Preliminary development of con-
nection details must consider questions
such as:
(a) If the details are practical, do
they lend themselves to stan-
Charles H. Raths
dardization?
(b) Can the details be plant pro-
duced within required toler-
ances assuring proper quality
and strength?
(c) Can the details be field con-
structed within required toler-
ances assuring proper quality DESIGN PROCEDURE
and strength?
(d) Once details are selected ini- The purpose of this presentation is
tially can they be designed by to illustrate the design approach as dis-
an accepted rational method cussed previously in "Preliminary De-
and will volume change defor- sign Considerations." Rather than pre-
mations (creep, shrinkage, and senting designs for each wall panel
temperature) influence the de- component, a typical 10-ft high x 12-ft
tail or its design. wide panel located between the first
and second floors will be reviewed in
8. Review the creep, shrinkage, and
temperature behavior of the building as depth. The designs for the other wall
panels of the building would be com-
a whole regarding how the structural
pleted in a similar manner.
behavior of the panels is influenced,
and how non-structural items such as The text portion of this paper will
partitions, glass, and caulking are af- discuss the general concepts of the de-
fected. sign presented by the calculations. Cal-
Following the above initial review culations in detail have been prepared
and study, a realistic preliminary de- for the typical panel as well as for the
sign can be made, The preliminary de- probable controlling design conditions.
sign will often serve as the final design Tabel 1 summarizes the major design
considering the usual compromises and section headings together with their
revisions which are normal to any build- corresponding calculation sheet num-
ing design. bers (see next page).
16
Controlling Panel Loads
LATERAL LOADS
Architectural requirements of the
building exterior normally require the
The lateral load analysis considered
building elevations to have wall panels
both seismic and wind forces. The loads
of all the same appearance. Therefore, used for the analysis of forces to the
it initially becomes apparent that the wall panels are based on previous Pa-
wall panels receiving the greatest grav- per 2, "Analysis of Lateral Load Re-
ity loads should be determined. sisting Elements" by John V. Christian-
A study of the typical building floor sen.
plan in the calculations on Sheets B in- The controlling lateral load is wind in
dicates that either Panels W1A or W1B a direction parallel to the 72-ft building
receive the greatest gravity loads due dimension. The calculations on Sheets
to the beam reactions. The manner by B1 and C3 pertain to the lateral load
which Panels W1A or W1B resist the behavior of the wall panel shear walls.
gravity loads is somewhat indetermi- No analysis is presented for wind pres-
nate. sure and suction loads to individual
The loads to the typical panel shown panels. Comparatively, this is of secon-
on Sheet 3/3 B can be resisted by the dary importance although it would be
mullions only, or distributed across the checked in the final design.
panel width by the panel acting as a
deep Vierendeel truss action. Most Lateral Load Behavior
probably, the actual panel load carrying
distribution is somewhere in between. The lateral load behavior of the
Since the panel shape and connec- building indicates that the exterior wall
tions dictate the practicality of panel panels about the perimeter do not be-
load distribution, it is necessary to con- have as a "structural tube" cantilevered
sider the center panel mullion as carry- from the foundations. The 72-ft side
ing most of the load when selecting con- wall plus a portion of the 96-ft walls
nections and mullion cross sections. The just around the corner, acting somewhat
side mullions will receive loadings as a channel section, resist the lateral
greater than those computed in the cal- loads. The channel type behavior is
culations on Sheets B due to the truss summarized on Sheet 2/11 C3 of the
behavior. Selecting side mullions of the calculations, and shown shaded on
same dimensions, except for width, Sheet 3/3 B1. Channel type behavior
solve the problem of how the panel re- is caused by shear lag of the 96-ft walls,
sists the loads, assuming side mullion and the effective channel flange width
reinforcement is similar. varies with the height of the building
depending on axial shear deformations
The preliminary calculations indicate
of the 96-ft wall.
that Panel W1A receives the greatest
Channel type behavior of the build-
gravity load for a panel between the
ing creates large loads to the corners.
first and second floor. In terms of work-
These loads result in 668 kips (work-
ing load, assuming the load carried di-
ing) loads near the corners between the
rectly by the mullions, the center mul-
first and second floors.
lion supports 663 kips and the side
As summarized in the calculations on
mullions about 85 kips.
Sheets B1, a major concern is whether
Final design calculations should re- or not the 668-kip force at the corners
view in detail the load distribution via results in net tension loads to the wall
Vierendeel truss behavior using a com- panel mullions. Dead load of the floor
puter program such as "STRESS." framing, which loads the entire build-
18
erection equipment, temporary connec- mum based on the erection equipment
tions required for erection, and final and methods available for the project.
connections. Equally important when The Wl panel size also lends itself to
considering the shape is how the final minimum handling as it will probably
panel dimension may or may not influ- be plant stored and shipped in its erect-
ence connection tolerances. A prelimi- ed position.
nary check of the panels structural Another consideration for panel size
capabilities should also be made when is to review whether or not vertical
selecting the shape and dimensions. joints between panels should be stag-
It is necessary to have completed the gered floor to floor. That is, should the
connection design for temporary erec- center panel mullion of a panel be
tion or final connections when relating centered over the joint between panels
panel shape to connections. Actually, one floor below?
the connection details, reflecting their While horizontally staggered panels
requirements, should be selected during may be desired, they create many toler-
determination of panel shape, and then ance problems. High rise buildings are
checked at a later time for structural dependent on panel joints widths for
capabilities. accommodating the building's plan di-
The calculations on Sheets C1 show mensions. Staggered panels can serious-
the panel shape and its relation to the ly reduce the available tolerances of coil
building based on the above review. rod dowels into conduits for the mullion
The top of the panel is placed 4 in. connections.
above the finished floor. This arrange- The most serious drawback to using
ment allows for easy down hand com- horizontally staggered panels is location
pletion of temporary floor tee to panel of the floor beams. If staggered panels
connections with tolerance. Another are used, this means that on every other
advantage of plates cast into the panel floor the beam must bear on two differ-
for temporary connections is that their en: panels. The beam connection prob-
capacities are not controlled by edge lerls created by staggered panels should
boundary conditions at the panel top be avoided if at all possible.
(Sections Fl and F2 of the calculations
on Sheets C4).
Further, the 4-in, projection of the PANEL GRAVITY CONNECTIONS
panel above the finished floor allows for
elimination of boundary or edge condi- Aside from the mullion-to-mullion
tions regarding shear cones for floor dia- connection already discussed, two typi-
phragm connections (Section F of the cal panel gravity connections must be
calculations on Sheets C4). Another ad- selected. One connection is for the floor
vantage of the 4-in, projection is the tees and the other for the floor beams.
ease by which grouted vertical panel
joint shear connections can be made Floor Tees
and inspected (Section E of the calcu- The design of the floor tee haunch
lations on Sheets C4). connection is given by the calculations
on Sheets C2. The haunch design is
Overall Panel Dimensions based on the PCI Design Handbook.
A general rule is to make any precast This connection design brings out sev-
panel as large as possible. For this 23- eral practical considerations. Probably
story building, the largest panel is that the most important is the practical fac-
shown by the calculations on Sheets C1. tors involving the selection of the
This panel size appears to be the maxi- haunch depth. The haunch must not
M11
for the precast panel shear walls is one both design requirements and methods
which insures that individual wall pan- of rational design.
els act compositely with each other. An For the reasons just cited, concern-
ultimate design approach, based on ing weld plates, a preliminary review
shear friction, considering the horizon- of the panel arrangement at the build-
tal and vertical panel joints as failure ing corners suggests strongly that a re-
planes provides a means to insure ulti- vision is in order. The corner arrange-
mate composite action. Since it is im- ment in the proposed problem requires
portant that the precast shear wall be- the use of weld plates. Instead, con-
have as a monolithic wall in the elastic crete dimensions should be adjusted to
range, the connections selected must allow for the use of a grouted vertical
also satisfy the elastic shear distribution. panel joint.
A means for comparing the difference
in shear distribution for an ultimate and Distribution of Shears
an elastic composite approach is to re-
The determination of the shear dis-
view the behavior of a composite beam.
tribution for the 72-ft panel shear wall
The design of a composite beam by between the first and second floors is
an ultimate shear friction approach in- presented in the calculations on Sheets
sures its strength, but does not insure 1/11 C3 to 4/11 C3. Between the first
its deformation behavior. An ultimate and second floor, a total ultimate hori-
approach assumes that the shear distri- zontal wind shear of 505 kips is applied.
bution at the composite interface is uni- This distribution of 505 kips wind
form, and thus allows the connections shear will be modified by the influence
(composite stirrups) to be spaced uni- of the "flange" compression and tension
formly and independent of the shear forces in the 96-ft wall as shown on
diagram. Elastic composite design con- Sheet 2/11 C3. The assumed shear dis-
siders the shear diagram and spaces tribution is that which complies with
composite stirrups accordingly. If the the ultimate composite approach.
total number and capacity of ultimate
The elastic analysis for lateral loads
composite stirrups are first selected, and
indicates that the maximum "flange"
then located approximately according
shear at the building corner occurs near
to the beam elastic shear diagram, the
the 8th story level, and is 30.1 kips at
composite beam will behave mono-
ultimate. As discussed in the following,
lithically for practical design purposes.
and in the calculations, the connection
The use of an ultimate composite de- for composite action must also have suf-
sign method places several require- ficient strength to develop this peak
ments on the design. It requires that type force. Most probably, all connec-
the connections be stiff and at the same tions will be standard, and their capa-
time not have their capacity influenced city based on a 73.3-kip force for a B
or reduced by the volume changes in- panel shown on Sheet 3/11 C3 of the
ducing T. forces into the connections. calculations. A check of shear distribu-
Another requirement is that the con- tion at the 8th floor should be made to
nections should not be eccentric to the verify that the typical connection is
plane of the shear wall. For these rea- satisfactory.
sons, it is most undesirable to use more
structurally flexible weld plate solutions Horizontal Joint Shear
for achieving composite action between The design of the joint connections
precast wall panels. Grouted type con- to resist horizontal shear can be
nections should be used as they satisfy achieved by one of two approaches.
8/11 C3. The case illustrated in the joint must use Iarge interlocking keys
calculations is for the first floor where if a of 1.4 is to be used. The detail
,^,t
the wind pressure is 20 psf. Upper floor selected following the design is given
wind pressures of 40 psf as required by by Section E of the calculations on
the code would control. Sheets C4. A review of this Section E
As discussed in the calculations, the indicates the importance of initially se-
shear stresses between the topping and lecting panel shape and dimensions
the wall panels at ultimate are very prior to design.
small; not greater than 13 psi at ulti- Projection of the panel top above the
mate for the upper stories. A shear fric- finished floor allows for easy placement
tion approach can be used to design of grout connection as the erected floor
this connection, or the temporary erec- serves as a work platform. Also, since
tion connections can be employed to re- the A,,, reinforcement is placed in the
sist this shear. floor topping, the 4-in, top projection
allows the grouted connection to be
Vertical Joint Shear
placed adjacent to the A f reinforce-
The connection design for vertical ment.
panel joint shear is presented on Sheets A secondary consideration, yet still
8/11 C3 to 11/11 C3. A vertical joint important, is the stiffness of the panel
shear of 73.3 kips at ultimate is used for in the vicinity of the grouted connec-
this connection design in accordance tion. To prevent any torsional distor-
with the previous discussion. tions of the 6-in, flat concrete adjacent
To insure that the vertical joint shear to the panel side mullion, good design
force of 73.3 kips can be transferred
practice would require all panels to
by the panel, a preliminary check of
the panel's concrete shear capacity is have a 10-in, haunch rather than just
made. The approximate analysis shown those supporting floor tees.
indicates that the 6-in, concrete thick- The A8 ,, reinforcement is required to
ness should be satisfactory. However, insure that a failure plane between the
22
topping and the back of the panel will ing the construction phase. The method
not reduce the strength of the A, No. of erection, regarding tower crane sta-
5 reinforcing bars. The ASh design is bility, can require the topping to be
based on a 4 = 1.0. A = 1.0 can be placed following the erection of a floor
assured if roughened keyways as shown level.
in Section E of the calculations on The subject of shear wall joint con-
Sheets C4 are used. nections should be reviewed in a gen-
eral sense. These connections can be
Summary achieved by bolting, welding or grout-
The design of the precast panel shear ing. Of the three types, only the grout-
wall is one of the main topics of this ed joint connection really satisfies all of
presentation. The analysis presented at- the design criteria. Bolted connections
tempts to consider all of the structural require tolerance to achieve bolting,
design considerations regarding forces, and this reduces the effective stiffness
and practicality. of the shear wall. Also, bolted connec-
An overall look at the shear wall be- tions would require location of inserts
havior reveals that it is probably much close to panel edges which is not desir-
stiffer than assumed in the lateral load able. Welded shear connections, while
analysis. The details used not only tie initially attractive, have questionable
the walls together, but also make the capacity since they attract building vol-
walls composite with the floors. Thus, ume changes restraint forces. These vol-
regarding stiffness, the shear wall ume changes or T,,, forces can, over
should be considered to have flanges at a period of time, reduce the connec-
each floor level when realistically de- tion's ultimate capacity. Moreover, the
termining the deformation characteris- anchorage of plates into the precast
tics of the building as a whole. Perhaps panels suffers the same problems as
a second lateral load analysis would be bolted connections in that anchors are
in order to evaluate what influence the located near the free edges of the panel
composite floors have on the shear wall requiring the use of partial shear cones.
force distribution. Lastly, welded connections result in
A practical consideration regarding T,,, shear loading towards the free edge
the details used is the effect the 1/z -in. of the panel (see Sheet 10/11 C3 of
coil rods have relative to topping sepa- the calculations). The determination of
T,, forces is at best, only a rough ap-
ration. Grout keys in the panel at the
panel-to-topping interface prevent top- proximation.
ping separation. Topping separation is The use of grouted vertical shear
further prevented from occurring due connections provides for volume move-
to the erection connections shown in ment, and if A,, f reinforcement yields, it
Sections F1 and F2 of the calculations does not impair the connection capa-
on Sheets C4. The selection of these city. Grouted vertical joint connections
erection connections also must consider also provide for excellent field toler-
ance. The most important aspect of the
the prevention of topping separation by
grouted vertical joint connections is the
their number and location.
final field accomplishment of the detail.
Important to the structural design of The final details selected such as pump-
the building is the time of topping ing grout, vent tubes, and grout tubes
placement. It would appear that the should be made only after extensive
topping should be placed at least two discussions with contractors that will be
stories below the level of erection dur- making these connections in the field.
24
tions, windows, shear to columns, axial that a review is not necessary. An item
loads to beams, and Tu forces to con- that temperature movement may influ-
nections. ence is the panel connections at the
The calculations on Sheets F present building corners where the two perpen-
an analysis of the creep behavior of dicular elevations under temperature
Panel WIA (see Sheet 1/3 B) sub- movement could create additional ver-
ject to a large load at the center tical joint shears. Volume change de-
mullions, and much smaller loads to the formations of the building as a whole
side mullions. The greatest creep de- probably will not affect the glass or
formation occurs at the upper stories partitions. Again, relative to the parti-
due to creep accumulation. The analy- tions, a prudent design may suggest the
sis indicates that a % in. relative move- use of partition details that allow for
ment could occur between the center accumulated movements in the upper
and side mullions for Panel WIA at stories.
the 23rd story. This analysis is con-
sistent with the initial assumption that
PANEL STRIPPING DESIGN
all panel loads are carried by the mul-
lions directly, and not influenced by Normally, the engineer of record is
truss action.
not concerned with the production and
As discussed, and illustrated in the erection, or general handling design of
calculations on Sheets F, the assump- a precast panel. Rather, he designs for
tion that mullions carry load directly is in-place conditions, and leaves the han-
not correct. The actual relative creep dling design to the wall panel producer.
deformation between center and side During the preliminary design phase,
mullions will be considerably less, if at such as discussed in this presentation,
all. Loads applied to center mullions it is most desirable to know whether or
will tend to be transferred to the side not the shape of panel, which satisfies
mullions by Vierendeel truss behavior in-place loadings, is satisfactory from a
of the panels. That portion of the center practical production standpoint. In
mullion load not transferred by truss short, is the panel a "boat in the base-
action will in time, be transferred to ment" or an extremely uneconomical
the side mullions by the axial creep shape to produce because of excessive
behavior of the panel under axial load. or very special handling requirements?
Nevertheless, it is proper design pro- A preliminary review of panel strip-
cedure to recognize that some differen- ping requirements is presented in the
tial creep behavior may occur in the calculations on Sheets S. The analysis
panel. Additional nominal reinforce- presented deals only with the initial
ment should be added to the panel as stripping. In order to make the analysis
illustrated in the calculations on Sheet it is necessary to determine the section
5/5F. Likewise, good design practice properties and weights of each cross
would indicate that the side mullion section as illustrated. The key factor is
column reinforcement should be similar the calculation of bending stresses to
to the center mullion reinforcement insure that the panel does not crack
when considering the two side mullions when being stripped. Reinforcement is
together.
selected to further control, or eliminate
No analysis is made for the effects of the possibility of cracking, which can
temperature and shrinkage behavior of be the cause for rejection of a panel.
the wall panels. This does not imply The procedure illustrated in the calcu-
26
LOADS AND DESIGN CRITERIA SHEET 1/2 A
Design Requirements
1. Uniform Building Code
2. PCI Design Handbook
,
12 Mullions = 7(6)4(10) 110 = 1283 lb
^^ 144
f fl
Flat = (12)(10)(6/12)(110) = 6600 lb.
28
GRAVITY LOADS TO W1 PANEL SHEET 1/3 B
SYMMETRICAL
END WALL
120"
TYPICAL
•ҟ
NOTE: WIA OR WIB
p Q a wҟPANEL BASE LOCATED
Np
Q U
U .. m W LL APPROX. 15 FT. ABOVE
GROUND FLOOR
ODD
EVEN
FLR.T LR
-COL. BE
BEAM 30 BEAM
0 o a SPAN
^^ ODD ?ca
m REFER TO SHEETS I/2A
N FLR. L?
TO 2/2A FOR LOADS
SIDE WALL
WIB ( 24' BEAM
BEAM SPAN
) BEAM.)
EVEN ODD
f
R FLR.
N W
- p co Z
W J
Q LL \
wLLEN
SEE -'--4. -W I A
SHEET I/5 C
50'-0.1
FLOOR PLAN
Even Floors
Concentrated beam load (use W 2 load)
Panel loads
12
CENTERҟSIDE
MULLION
MULLIONҟ
30
GRAVITY LOAD TO W1 PANEL (coNT,) ḏ
SHEET 3/3 B
PANEL
MULLION
SI
MUL
1ST FLOOR
VGY 1 CR
MULLION
RI R2 R3
75.6 K 577.2 K 78.3 K DEAD LOAD
6.3 K 85.8 K 6.9 K LIVE LOAD
81.9 K 663.0 K 85.2 K TOTAL LOAD
oddḏ odd
mullion unif.DLḏ unif.LLḏ DLḏ LL
Rl = 45.0 + (61.0/2) + (12.7/2) = 75.6 + 6.3 = 81.9 kips
evenḏ even
mullion unif.DLḏ unif.LLḏ DLḏ LL
R3 = 45.0 + (66.5/2) + (13.8/2) = 78.3 + 6.9 = 85.2 kips
Lateral load forces are obtained from Paper 2. Data for loads
applied at first story level is summarized on Sheets 2/3 Bl
and 3/3 Bl.
32
PANEL LATERAL LOAD SHEET 2/3 Bl
2-
WIND
FORCE
0.55°
20 SIDE
WALL 72
END
WALL 48'
15 END WALL/
VERTICAL FORCE
r SIDE WALL
SHEAR j DEFLECTION
1-10 CURVE
SIDE WALL / /f
• VERTICAL / I /
FORCE
5 /
SIDE WALL
MOMENT
/ /;
'358K 1(
"310K 361 K BUILDING DEFLECTION, IN.
G I I .
TENSION / END
18,5 1 0 FT. KIPS WALL
IST FLOOR
I8 AS
oIU D STRIBUTTION
0 361 K SIDE ba
in ? WALL OF 310 K 8 358 K
FORCES
0
72 REACTION=668 K
NEAR CORNER
GRAVITY
BEAM DEAD LOAD
DEAD LOAD
24 FT. PROBABLE
EFFECTIVE FLANGE
WIDTH.
^I II I 11 I
,- WIND+GRAVITY
i__^_____ DEAD LOAD -
NO TENSION, ALL
COMPRESSION
34
DETERMINE PANEL MULLION SIZE REQUIRED ḏ
SHEET 1/5 C
LOAD DATA
Mullion size of panels will be controlled by:
1. Dead plus live load of center mullion of
Panel W1A which supports concentrated beam
reactions (1.4 D + 1.7 L at ultimate)
36
PANEL MULLION SIZE SHEET 3/5 C
28.5"
r1
4—POINTS FOR COMPUTER
N
tḏ 0 AREA DETERMINATION
3ḏ
^ḏ ^
TYPICAL
^7ḏ61
4° 2 ḏ I 6"
16.5"ḏ
I
Determine capacity by Section 6.1.6 PCI Design Handbook
(use Eq. 6-11)
Use T u /V u = 0
1/3Cr T u /V u = 0
= Cr
f buḏ ) (S/W
4) 70 f' = 1 for
P u = (303/1000)(2870) + 2(0.79) 60
= 870 + 95 = 965 kips (grout area capacity at ultimate)
This value is satisfactory since it is greater
than 954 kips.
Therefore, 6000-psi grout is satisfactory.
ARCHITECTURAL PROGRAM N1
ARCHITECTURAL PROGRAM •1
X s 14.2500 Y = 8.11199
SECTION PROPERTIES ABOUT THE Y-Y AXIS THRU THE CENTER- OF- GRAVITYU
38
PANEL MULLION SIZE SHEET 5/5 C
DESIGN SUMMARY
II'-IIh/2"
P6 P5 B
-1N
O
h
P2 P4
Ao
^ O
PI P3
L
II SECTIONS PI TO P8
P7 PR
-
SEE SHEET 2,'I0S
ELEVATION -TYPICAL WI TYPE PANEL
(PANEL WT. = 8260 LBS. AT 110 PCF)
SECTION A
40
SHEET 2/2 C1
PANEL SHAPE & DIMENSIONS ḏ
PING
H MESH
12"
SECTION B
(ALSO SHOWS RELATION
OF PANEL TO STRUCTURE)
DL floor = 77 psf
LL floor = 40 psf (non-reduced)
117 psf
The haunch depth should not project below the bottom of the
beam framing into the wall panels. Also the practical size
would be 8 to 10 in. Haunch depth will also be partly deter-
mined by considering the beam-to-panel connection. Try a
depth equal to 10 in. as shown on Sheet 2/2 Cl.
r—I'CLEAR
Check ultimate shear stress
Effective width
b = 6 + 6 + 3.75 = 16 in.
10,530ḏ
(Note: 8.7 in. is the
estimated depth d
uḏ
16x8.7ḏ pḏ )ḏ HAUNCH' S AS UME
=ḏ
76 psi at ultimateḏ
PLAN VIEW-HAUNCH
Since this stress is less than 800 psi, the section is
satisfactory. Therefore, for design purposes use a
10-in. depth.
42
FLOOR SUPPORT CONNECTIONS SHEET 2/4 C2
u
This is the minimum value for the ratio T/V u = 0.2.
Select Avf
Note that "5.5" reflects the Table 6.2.5 value for 53.3 kips.
The concrete strength "6000 psi" is used to modify width "b."
_ 53,100
= 590 psi
fb (4/3)(1.5)(45)
A 3/8-in, bearing pad will be satisfactory.,
44
FLOOR SUPPORT CONNECTIONS SHEET 4/4 C2
F
TYPICAL DETAIL E60
„ҟ
STRUCTURAL
ERECTION I/ TEE OR
DETAIL
'2 "PLATE
3/"NEOPRENE
BEARING PAD
3/8"PLATE 6"X I4" 50 DURO
•
CT X 12.25
•
1T
I/2 X 4 H.S. A
2••
E60 LEDGER
II/2 BEAM
6
^ 10I I ST
361K
72'ḏ
wT
46
LATERAL LOAD CONNECTIONS SHEET 2/11 C3
WAND
END WALL
II
Iҟ
SIDEҟ 231'±
1
WALLҟ
II
358K %
(TENSION)ҟ
^
361 K (^p8 K
310K
(TENSION) SEE ASSUMED DISTRIBUTION
310 K
3
(COMP.)ҟ (SHEET 3/3 BI)
2NDҟ 1.4(358 )_
21.8 K AT ULTIMATE
10^ 21.8 KI 23ҟ
DISTRIBUTED OVER 23 STORIES
6^ҟ
1STҟ ^505Kҟ6'
1.4(310) ,18.9K
{8.9 Kҟ
72 ҟ 23 AT ULTIMATE
Find Force F
1
42.1 84.2 84.2ҟ
84.2 84.2 84.2 42.1 j-2 ND FLOOR
^jr&3
1
110, M
54.4 KI 54.4 K
F- r 373.
73• •3 73.3L 7
703.31 73.3 3r ®
42.1 84.2 84.2ҟ 84.2 ҟ I ST FLOOR
18.9 K 18.9K
SUMMARY OF APPLIED LOADS
48
LATERAL LOAD CONNECTIONS SHEET 4/11 C3
FH
42.1 K FH = 42.1 - 94.6 = 9.5 KIPS
10
54.4 KI 54.4 K
32.6K AT ULTIMATE
42.1 K
FH 54.4K AT ® 54.4K AT
ULTIMATE ULTIMATE
NECESSARY
FOR EQUIL. Ir-
JOINT SHEAR FORCES 32.6 K AT ULTIMATE
AT ULTIMATE FOR
DESIGN PANEL
FH
842K 7-M=O?
84.2(10) -73.3(12) = 842 -879.6=
-37.6 FT. KIPS NOT BALANCED
73.3K 173.3K VERTICAL JOINT SHEARS CAN NOT
CHANGE AS DISCUSSED ABOVE- FIND
CORRECTED HORIZONTAL SHEAR.
84.2 K
s FH FH = 37.6 -3.8 K
NECESSARY) 10 88.0 K AT ULTIMATE
FOR EQUIL.
73.3 K ® 147T3. K
AT ULT. ULT.
JOINT SHEAR FORCES
AT ULTIMATE FOR 88.0 K AT ULTIMATE
DESIGN PANEL
50
LATERAL LOAD CONNECTIONS SHEET 6/11 C3
Design Criteria
1. Design for shear applied to the side wall at the
first story, V u = 505 kips (see Sheet 2/11 C3).
DESIGN SUMMARY
Design Criteria
The shear force per side wall at the first floor is:
(20/100)(10.042)(96/2) = 9.64 kips (working)
52
LATERAL LOAD CONNECTIONS SHEET 8/11 C3
DESIGN SUMMARY
2.ḏ
Temporary erection connections such as Section Fl on Sheet
5/5 C4 provides sufficient A ḏ reinforcement for the floor
diaphragm shear.
88K-„"
2ND
Approximately the same shear forces are
obtained by:
73.3Kḏ 73.3 K (505/6) = 84.2 kips per 12-ft panel
ḏ (10/12)(84.2) = 70.2 kips vertical shear
1ST
ḏ Note that the "6 ® 'above represents the
88 K number-of panels per side wall.
SEE SHEET
4 /II C3
= 2(0.85)
2jḏ föö
0 = 132 psi (ok, greater than 125 psi)
_ (v u - v c ) b w sḏ
Eq.(11-13) of ACI 318-71
A Vfy
54
LATERAL LOAD CONNECTIONS SHEET 10/ll C3
Vu = V ḏ
73.3 kips at ultimate
Determine A vf Required
DETERMINE A sh REINFORCEMENT
Try using 1/2-in, coil rods into inserts cast in the panel shown
in Section F, Sheet 4/5 C4.
DESIGN SUMMARY
56
TYPICAL PANEL CONNECTIONS SHEET U5 C4
I,
2NC
1ST
PANEL WIDTH.
IK"
'COIL ROD
ON-SHRINK GROUT
f^ = 6000 PSI )
NOTE:
NO GROUT
IN JOINT CLOSED CELL BACK-UP
I/2..
CAUL
TOP OF TOPPING
SECTION B - TYPICAL
58
TYPICAL PANEL CONNECTIONS SHEET 3/5 C4
GI
'(CAL
GROUT /'a^
PL ACEME NT-. NON-SHRINK GROUT
DUCT (f':s000po/)
Avfnsm
a'to
IJ
L.
^
ҟ
SECTION E -TYPICAL VERTICAL D ETA |L
JOINT SHEAR CONNECTION
AVfRNҟ
::6
"2"COIL RODS ^
MESHҟ)
OIL INSERT
DPTIONAL SPACED KEYS
To INCREASE ^=/.o^
.
|a
12" \ TOP I^^yNG2
^Aoh nomp
I4" NEOPRENE'
asxmwsp^o
60
TYPICAL PANEL CONNECTIONS SHEET 5/5 C4
5X3 L(LLH)WITH
DEFORMED STUD 8
HEADED STUD
4 STRUCTURALSTEEL
LOCATED AT STEM;
°T°WITH HEADED STUDS
12°
SECTION Fl - ERECTION
CONNECTION AT PANEL
BEARING CONNECTION
(REMAINDER-SECTION F)
1
'2"COIL ROD
BEYOND Avf REINF
MESH
12"
SECTION F2-ERECTION
CONNECTION AT NON FULL SLAB
BEARING PANEL WIDTH E7015 OR
(REMAINDER - SECTION F) E7016