1. Site leveling is the demarcation of the entire site with point of egress and
ingress to have a total control of entry and protection of materials on site
(True / False)
2. Quality control is an important operation that must be considered to ensure
that standard job is delivered in civil engineering construction
(True / False).
3. Settlement takes longer period on cohesionless soils such as gravel and
sandy soil.
(True / False)
4. The contractor should never bid for a job without first thoroughly examining
the site.
(True / False)
5. In setting – out of a building, it is not necessary to pay attention to the local
building line and town or local planning authority requirement
(True / False).
6. The reinforcement bar size in slabs is usually 10, 12 or 16 mm.
(True / False)
7. Non – load bearing walls are these wall that aside from their own – self
weights, carry imposed loads such as floors, and roofs.
(True / False)
8. In building design and construction, the combination of dead and live loads
is term design loads.
(True / False)
9. Polythene sheet is a good construction material used in construction of rigid
damp proof course.
(True / False)
10. The choice of foundation is a function of soil test / bearing capacity of the
sub – soil.
(True / False)
SECTION B: ANY FOUR (4) QUESTIONS
4. Draw the detailed diagrams for timbering of trenches of the following types of
soils:
a. Firm soil
b. Moderately firm soil
c. Weak soil
(10 marks)
6. a. In sequential order, state all the four (4) steps involve in application of 3:4:5
method of setting – out of building. (4 marks)
b. i. As an engineer, describe how you can check for accuracy of a setting – out
of building (4 marks)
ii. State two (2) disadvantage of theodolite method of setting – out (2 marks)
(10 marks)
Good luck