Você está na página 1de 6

1

Meshed vs. Radial MV Distribution Network in


Presence of Large Amount of DG
G. Celli, Member, IEEE, F. Pilo, Member, IEEE, and G. Pisano, Student Member, IEEE
V. Allegranza, R. Cicoria, and A. Iaria

govern local cells, to control generated and absorbed power,


Abstract—Until now, distribution networks are regarded as a to manage congestions and prevent propagation of overloads
passive termination of the transmission network, with a radial and faults by isolating the affected part of the network.
structure, unidirectional power flows, and a simple and efficient Of course, in order to perform a so drastic and
protection scheme. In presence of a large amount of Distributed revolutionary development, drives and political decisions are
Generation (DG), distribution networks will gradually, but
necessary to convince people to change. Among all these
ineluctably, change towards a new kind of active networks. The
most revolutionary change, needed to efficiently allocate so much drastic changes, certainly one of the most revolutionary is
DG, could be represented by the adoption of a meshed network represented by the changing from radial to meshed
architecture. For this reason, in the paper new possible architectures and, for this reason, in the paper new possible
arrangements for distribution networks have been deeply arrangements for distribution networks have been deeply
investigated and compared with the radial scheme. Steady state investigated. In particular, it has been highlighted the impact
and dynamic simulations have been performed, considering a of the meshed arrangement on the exploitation of DG
portion of the real Italian distribution network, and voltage considering different types of meshed distribution networks
profile, power losses, short circuit currents and grid reliability
have been analyzed.
(closed loop trunk feeders, closed loop laterals,
interconnection between different feeders, etc.). For each type
Index Terms—Distributed Generation, distribution network examined, steady state and dynamic simulations have been
planning, meshed and radial network schemes. performed in order to analyze the voltage profile, to asses the
short circuit level, to evaluate losses and avoided costs for
I. INTRODUCTION network upgrading and, finally, to asses grid reliability.
Examples derived from real world cases have been presented
T HE continuous progress of technology, the congestion
concern of the transmission system and the environmental
drive are making very likely a future scenario characterized by
and discussed in order to highlight potential advantages (and
disadvantages) of the possible new practice of distribution
a massive penetration of Distributed Generation (DG), grid.
allocated in the MV distribution networks. This eventuality
will inevitably lead to a new approach in the Distribution II. RADIAL AND MESHED NETWORKS
System. Until now, distribution networks are regarded as a For many years, the MV distribution system has been
passive termination of the transmission network, having the planned, built and operated always in the same way. But in the
goal of supplying reliably and efficiently end users. According last decade, the first signs of changes have appeared due to
to this scheme, distribution network are radial, with the liberalization of the electricity market, the governmental
unidirectional power flows and with a simple and efficient drive to reduce number and duration of long interruption and
protection scheme. the growing presence of DG. In particular, if DG penetration
A greater penetration of DG will change completely this reaches a high level, as predicted by many authors,
well consolidated environment: definitely, distribution distribution utilities will probably have to dismiss the
networks will be no longer passive and it has been foreseen a traditional radial network operation, adopting a more flexible
gradual, but ineluctable, changing towards a new kind of meshed structure.
active networks. Active networks will be strongly For this reason, this paper has the aim of investigating the
interconnected (no radial scheme, no unidirectional power effects of the migration from radial to meshed arrangement of
flow) and subdivided into small cells, locally managed by a distribution network, particularly referring to the impact that
power controller, which superintends power flow among local this change could have on the growth and development of DG.
generators, loads and adjacent cells. Automation, control Generally, it is very difficult to obtain from specific
systems and ICT will be widely used in active networks to examples wide-ranging conclusions valid in any case, because
the effect of DG on a distribution network strictly depends on
the generators allocation, the network configuration and the
G. Celli, F. Pilo and G. Pisano are with the Department of Electrical and
nature of loads. However, it is possible to outline the main
Electronic Engineering of the University of Cagliari, Piazza d’Armi, 09123
Cagliari, Italy (email: celli@diee.unica.it, pilo@diee.unica.it). guiding principles useful to understand macroscopically the
V. Allegranza, R. Cicoria and A. Iaria are with CESI, via Rubattino 54, effects of a meshed network operation in presence of DG.
20154 Milan, Italy (e-mail: cicoria@cesi.it).
2

A. Passive Radial Distribution Network changes the characteristics of the existing radial networks,
Currently, MV distribution networks are always operated which are no more passive with unidirectional power flows,
with a radial arrangement, and are often subdivided into two but become active. These circumstances alter the well
different levels: trunk feeders and lateral branches. The low consolidated management procedures applied, and the effects
degree of reliability obtainable with radial network is of DG towards the network could be positive or negative
generally improved by adding emergency ties, that provide depending on the position and the size of the generators
alternative routes for power supply in case of outages or installed. Thus, it is more desirable to optimize their
scheduled interruptions: these emergency ties end with an allocation, instead of choosing randomly their connection
open switch so that radial structure is maintained during sites, like it is preferable to optimize the position of the
normal conditions. additional ties used to mesh the existing radial distribution
An important class of such networks, widely used in Italy, networks [1]. The case when a medium size generator is
are the “open loop networks”, which are usually employed in installed in a weak lateral, causing higher power losses and
urban power distribution systems. If there are no laterals virtually requiring additional resizing investment is
(“pure open loop networks”), then service restoration is emblematic.
ensured through the emergency tie that connects the ends of The same remarks can be made also for the active meshed
the feeder. An intermediate alternative, still more adopted in distribution network, even if the stronger and more flexible
rural distribution networks, is to install laterals (“spurious architecture reduces the potential negative effects of the
open loop networks”), in which top priority customers are presence of DG. If properly allocated, the main benefits
supplied through the main feeder and can be completely re- introduced by DG on the distribution networks refer to the
energized in the event of a fault. Moreover, the increased reduction of power losses, the improvement of voltage profile,
utility care about long interruptions has led to the addition of and the deferment of investment resulting from a reduced
emergency ties also for some main laterals. equipment exploitation (conductors and transformers). All
Summing up these remarks, the current MV distribution these benefits could be potentially higher for meshed
networks are already meshed and they will become more networks, because they join with the same benefits introduced
meshed in the future due to reliability reasons: thus, it is by this network arrangement. Moreover, if intentional
important to evaluate if it is still convenient to keep the radial islanding is permitted, the presence of DG suitable
operation, also considering the predicted large diffusion of coordinated with network automation can also improve the
DG, and to verify if the adoption of a different kind of supply reliability of users connected to some laterals [2]. On
operation could overcome the obstacles that limit the DG the contrary, the main negative aspects associated to the
diffusion itself. existence of DG are the increase of the short circuit currents
and the alteration of the protection system logic, which can
B. Passive Meshed Distribution Network prejudice its selectivity. For this reason, currently the majority
Meshed networks have well known advantages versus of the international Standards (including Italian ones)
radial schemes: a reduction of power losses, a better voltage contemplate the instantaneous disconnection of the generators
profile, a greater flexibility and ability to cope with the load in case of a fault, so that the existing protection system can
growth, and an improvement of Power Quality (PQ) due to work properly. On the other hand, this practice prevents the
the fault level increase at each bus. Moreover, also without adoption of the intentional islanding, deleting the relative
DG, the potential more suitable power flows sharing, benefit, and thwarts the advantage of a PQ improvement,
consequent to the passage from radial arrangement to meshed related to the fault level increase.
operation, can allow the deferment of investment needed to At the end of these comments, it is important to notice that
meet with the growing energy demand. all the benefits considered will turn to disadvantages if the DG
It is prominent to observe that these advantages can be penetration level becomes significantly high. In this case, the
maximized only optimizing number and position of the power losses resume to rise, the voltage profile worsens and
emergency ties. Without careful planning strategies, the the equipment could be again heavily overworked. However,
adoption of a meshed scheme can also worsen some technical as it will be shown in the next sections, meshed arrangement
aspect of the network operation: for example, if a weak lateral seems to be more suitable to accommodate a massive
(generally having smaller sections) is involved in a meshed penetration of DG.
route, it could turn to a status of excessive exploitation.
Obviously, compared to radial arrangement, a meshed III. HOW THE COMPARISON HAS BEEN MADE
network presents also some drawbacks: a more complex In order to compare the performance of the radial and
planning and operation, that consequently involves a higher meshed arrangements in presence of DG, a small portion of
cost, and a rising of short circuit current in each node, that the Italian MV distribution network has been simulated (Fig.
could implies the substitution of the existing circuit breakers, 1). It is mostly settled in a rural and extra-urban area of about
due to the overcoming of their interrupting capacity (12.5 kA 1700 km2, with a predominance of overhead lines (only 10%
for rural and 16 kA for urban Italian distribution networks). of the network extension is made by buried cables). The
C. Active Radial and Meshed Distribution Network network is energized by 4 HV/MV primary substations (two
The presence of DG on the Distribution System drastically of which with two separated MV busbars, for a total of 6
3

Fig. 2. The different meshed configurations investigated.


existing open rings;
• C2: 1st meshed level, obtained by connecting two “adjacent”
closed loops at about half of their length (adjacent means
that they share the same HV/MV substations);
Fig. 1. The case study: a small portion of the Italian MV distribution network.
• C3: 2nd meshed level, obtained by using an additional edge
HV/MV transformers), and feeds 999 MV/LV nodes (390 of to connect two not-adjacent closed loops;
which are trunk nodes), via 18 trunk feeders and 1005 edges. • C4: 3rd meshed level, obtained by adding new edges, which
Several scenarios have been hypothesized diversifying the connect the adjacent closed loops at one quarter and three
load and the DG penetration, as summarized in Table I. quarter of their length.
More specifically, 4 different load demands have been Fig. 2 shows a schematic representation of the 8 feeders
considered, varying the equipment exploitation from 10% to considered (without the depiction of laterals) in order to
50% of loading. It is basic to remind that, due to the open highlight the different configurations investigated.
loop configuration, overhead lines, buried cables and The load flow calculations and the short circuit analyses,
transformers are loaded respectively no more than 60%, 50% for the 100 possible cases defined by the combination of all
and 65% of their capacity. Regarding DG, only 8 feeders have the scenarios considered, have been performed by using a
been used to allocate generators, but all the 18 feeders have specific software package (SPIRA), developed by CESI.
been considered in the calculations. All the 20 generators Furthermore, in order to check the DG capability to
added have been connected to lateral nodes, in order to improve PQ and supply reliability, some dynamic simulations
strengthen the effects of DG on the network. By using have been carried out, focusing the attention on the possibility
different generator sizes, 5 DG penetration levels have been to maintain generators connected to the network during faults.
employed, from 0% to 120% of the overall load of the 8 For this study, a clustered network derived from the real case
feeders interested by DG. has been simulated with the DigSilent software package.
Five different network arrangements have been
investigated and tested with all these scenarios. These IV. STEADY STATE COMPARISON
configurations have been realized by altering only the
The aim of the steady state analyses has been the
architecture of the 8 feeders considered above to allocate the
evaluation of the meshed arrangement capability to allow a
DG units:
large diffusion of DG on the Distribution System. To do this,
• C0: radial configuration (open loop network); 4 technical aspect have been investigated: the power losses,
• C1: closed loop network, obtained by closing only the the voltage profile, the equipment exploitation and the short
TABLE I
POWER OF LOAD E POWER GENERATED BY DG [MVA] circuit level.
Equipment Exploitation Scenarios A. Power Losses
10% loading Reference 30% loading 50% loading Under the same load demand and DG penetration, power
demand

Total 10.257 21.520 27.752 38.251 losses are reduced moving from radial to any meshed
Load

DG Feeders 4.899 11.648 13.794 20.069 arrangement. In particular, the more significant contribution is
provided when C1 configuration is adopted; thickening the
10% 0.45 1.10 1.45 1.95
meshes produces additional negligible benefits (Fig. 3).
penetration

30% 1.55 3.90 4.20 6.00


Power losses come down also by rising the DG penetration,
DG

70% 3.50 7.95 9.50 14.60 until the maximum integration capacity of DG on the network
120% 6.00 13.79 16.40 24.09
4

feeders have many generators (i.e. wind generators during the


night), voltage rise, exalted by the tap-changer, can be the
major concern.
Thus, to overcome all these problems, in case of a massive
DG penetration it will become necessary to allow generators
taking part of the reactive power market, probably admitting
an economic recompense to the voltage regulation service
provided (Ancillary Service).
C. Equipment Exploitation
In order to assess the influence of DG and meshed
operation on the equipment exploitation, all the elements that
presented an utilization degree higher than the limits
previously mentioned in Section III for lines and transformers,
have been checked. The overcoming of these thresholds
involves investment for the network reinforcement.
First of all, it can be noticed that the meshed arrangement
alone allows reducing the exploitation, due to the alternative
supply paths provided. This benefit is as much higher as more
additional edges are present (moving from C0 to C4
configuration).
Also the reliability of the network takes advantage from
this circumstance, and the exploitation thresholds can be
Fig. 3. Power losses as a function of DG penetration level, varying network raised due to the presence of alternative paths in emergency
configuration and equipment exploitation.
conditions. Obviously, this benefit is verified only from C2
is reached. After that, they start to grow, more rapidly on a configuration, because from this point of view C1 and C0 are
radial configuration. This point of inversion would seem to equal. The presence of DG concurs to reduce the network
happen for a higher DG penetration level on a meshed loading, with increasing effects when raising meshed degree.
network, but this is not a general result because it strictly However, the presence of big size generators could cause
depends on the position of generators and additional edges. critical situations if they are installed on weak or already
The adoption of meshed operation is always advantageous heavily loaded laterals. It is noticeable to remark that a higher
on lightly load cases; instead, with heavily load conditions, meshed level does not permit reducing criticalities on some
the additional edges must be optimized to avoid possible edges when they are part of laterals not included in the
worsening. meshed paths. Thus, also in this case it is fundamental to
perform a network optimization that finds the best
B. Voltage Profile arrangement for additional ties connection and DG units
Also for this technical aspect, the meshed operation has allocation.
been demonstrated to be positive. The presence of DG Finally, regarding transformer exploitation, there is a
commonly improves the situation, due to the compensation of benefit with both the increasing DG penetration and the
the resistive voltage drop of the lines. It has instead little passage from C0 to C1 configuration. Additional mesh links
influence on the reactive part, because usually the generators do not ameliorate the transformer working conditions.
are not involved in the voltage regulation (in Italy they have to
work with constant power factor). Taking into account this D. Short Circuit Level
way of operation, the allocation of big size DG units (some As general remark, it can be observed that the meshed
MW) on weak laterals could deteriorate the voltage profile, operation determines the biggest three phase short circuit
with also some cases of limit violation due to excessive current (Isc) increment also in case of passive network (no
overvoltage. DG). This increment is particularly relevant in the points of
During these studies, some problems have appeared to mesh links connection (Fig. 4).
correctly interpret the results, because the non unidirectional The presence of DG raises itself the Isc but less than the
power flow, caused by the presence of DG and the meshed mesh structure of the network. If the DG unit is connected to
arrangement, alters the correct operation of the transformer the network through an inverter, its influence on the short
tap-changer controller. In fact, the regulator measures the circuit current become negligible. However, in case of a
current through the transformer, and reduces the voltage at massive penetration of DG it would be possible to cause
the MV busbar when this current is low. By so important growth of the Isc. Moreover, the lower effect of DG
with respect of the meshed operation is also due to the chosen
doing, a passive feeder connected to the same busbar can position of the generators on weak laterals, with initial low
suffer of excessive voltage drops. short circuit power and consequently small influence on the
In some other cases, particularly when load is low and other nodes of the network. In fact, positioning a big size
5

service after three-phase short circuits in lines or


busbars cleared in standard time (300ms). Faster SGs
(H=2s) connected near to the fault must be disconnected
in a shorter time (CCT=220ms), but this time rise in
meshed network ;
− in radial networks all the SGs (slow and fast) connected
to healthy lines could remain in service for three-phase
short circuits followed by a high-speed successful
reclosure; in meshed networks all slow SGs and the fast
ones connected far enough from the faulted point could
remain in service.
− in radial or meshed networks all the SGs connected to
faulty lines must be disconnected to avoid re-
Fig. 4. Short circuit current increment in each trunk node of a closed loop energization of SGs out of synchronism;
feeder, referred to the Isc of the radial arrangement.
− in radial or meshed networks, for 3-phase short circuits
generator on a trunk node, it has been noticed an increment followed by a high-speed unsuccessful reclosure, all
percentages similar to those obtained with the C1 passive generators must be disconnected.
configuration. An additional result verified has been that, It is worth to notice that stability increases in meshed
once a mesh configuration is adopted, an increment on the networks and this fact gives enough time to detect and
DG penetration level does not provoke significant growth of isolated the faulted area leaving in service the majority of
the Isc. generators.
In conclusion, both the presence of DG and the adoption of
a meshed arrangement increase the three phase short circuit VI. DISCUSSION AND CONCLUSIONS
current (Isc) in each node. The potential overcoming of the
Jenkins et al. have noticed that many of the issue related to
interrupting capacity of the existing circuit breakers and the
the huge diffusion DG like voltage rise, power quality, short
lose of coordination of the system protection are both the
circuit level increase, and islanding can be solved with
main issues related to short circuit. But, whereas the rise in
innovative Dynamic Management Systems (DMS) [7]. They
short circuit level due to DG is not really common and may be
have delineated three steps for the development of such a
controlled by using power converters, the problem of
revolutionary distribution network: initially only simple DMS
protection coordination is becoming more and more urgent
to control few generators, then a dynamic control of the
and would require to change the protection system relatively
network and finally a complete active network, meshed with
soon. This fact would provoke a huge investment needed to
short circuit current limiters. Roberts and Van Overbeek have
substitute the whole system protection, with a complete
pointed out the possible final realization of active networks
revision of the coordination logics and a massive use of new
[8],[9]. Distribution networks will supply connectivity (they
kind of controller devices, characterized by a large use of
will provide connectivity between points of supply and
ICT.
consumption). They have envisaged a future system
This conclusion is important, because even if the meshed
characterized, among many other interesting features, by
arrangement is not accepted, the huge investment on the
interconnection (in opposition to current radial schemes) to
replacement of the actual system protection will be in any
take advantage of all possibilities offered by ICT, network
case ineluctable.
automation and power electronics. All these papers deal with
the distribution network evolution, and they attribute to the
V. DYNAMIC BEHAVIOR
interconnection a key role for the development and the
The dynamic behavior of Synchronous Generators (SG) implementation of DG. Furthermore all of them consider that
has been evaluated to assess the possibility of maintain in the changing from radial to meshed networks will be a
service some generators during fault conditions in meshed consequence of the implementation of new DMS, that deeply
networks (similar analysis have been carried out in [3]-[4] involve ICT, control capabilities and automation that are
showing the dynamic behavior of DG in radial networks). The practically absent in current distribution networks. The idea of
following data have been used for the simulations: Pn=1 MW, this paper is to show that meshed network can be important to
cosφn=0.9, Vn=0.4kV, X’d=0.29p.u., round rotor. Two create the conditions to develop a new distribution system,
different inertia constant (H=2s and H=4s) have been also and avoid and eliminate most of the barriers, that still limit the
considered for their impact on the Critical Clearing Time diffusion of DG, before adopting complicated and innovative
(CCT). Greater details on simulations and results can be control systems. Furthermore, it should be noticed that this
found in [5]. By hypothesizing, according to [6], that the zone changing in most cases do not require building new lines
where a fault occurred could be located and isolated by because of distribution networks are already meshed but
protections, the followings are the most important results: radially managed so few physical modifications to the net are
− in radial or meshed networks slow SGs (H=4s) to be expected.
connected to faulty or healthy lines could remain in The comparisons among different situations derived from a
6

real world case study have highlighted that weakly meshed VIII. REFERENCES
network have the potentialities to accommodate much more [1] G. Celli and F. Pilo, “Optimal Distributed Generation Allocation in MV
generation than radial nets. The main advantages of weakly Distribution Networks”, in Proc. 2001 PICA Conf., pp. 81-86.
meshed networks consist in a more uniform power flow, that [2] G. Celli, S. Mocci, F. Pilo, “Improvement of reliability in active networks
with intentional islanding”, in Proc. 2004 DRPT Conf.
allows improving voltage profile, reducing power losses, [3] S. K. Salman, I. M. Rida, “Investigating the Impact of Embedded
limiting, and balancing the exploitation of lines and Generation on Relay Settings of Utilities’ Electrical Feeders ”, IEEE
transformers. Another important result that can be pointed out Trans. Power Delivery, vol. 16, pp., April 2001.
by the studies performed is that the changing from open loop [4] F. M. Gatta, F. Iliceto, S. Lauria, P. Masato, “Behaviour of Dispersed
Generation in Distribution Networks During system Disturbances.
to closed loop networks is generally always positive from the Measures to Prevent Disconnection”, in Proc. 2003 International
DG diffusion point of view. On the other hand, more thicken Conference on Electricity Distribution – CIRED, Session 4, paper n°79.
meshes can not be chosen randomly and they have to be [5] F. Pilo et al., “Meshed Distribution Networks to Maximize the
Exploitation of Embedded Generation”, presented at the Distribution
carefully planned on the basis of the load and generation
Europe 2004 Conference, Amsterdam, 28-29 April, 2004.
location. Particular important is the capability of meshed [6] S. Brahma, A. Girgis, “Development of Adaptive Protection Scheme for
network to withstand severe contingencies: in this case the Distribution systems With High penetration of Distributed Generation”,
more thicken the mesh network the more it can withstand to a IEEE Trans. Power Delivery, vol.19, pp.56-63, January 2004.
[7] T. Bopp, A. Shafu, I. Cobelo, I. Chilvers, N. Jenkins, G. Strbac, H. Li, P.
fault in the network. Crossley, “Commercial and Technical integration of Distributed
Short circuit level, voltage regulation, and protection Generation into Distribution Network”, in Proc. 2003 International
coordination are the main issues in meshed distribution Conference on Electricity Distribution – CIRED, Sess.4.
network. Short circuit level can increase to intolerable values [8] G. C. Schoonenberg, A. R. A. Pikkert, F. Van Overbeeke, C. Spoorenberg,
“Future Concepts for Medium voltage Distribution Networks: a New
and this fact can lead to change many switchgears in the Philosophy”, in Proc. 1999 International Conference on Electricity
network (it should be noticed that even of less gravity, this Distribution – CIRED, Sess. 5, paper n°2.
problem could arise also in radial system with much DG). A [9] F. Von Overbeeke, V. Roberts, “Active Networks as facilitators for
solution to avoid changing all switches may be to resort to embedded generation”, in Proc. 2002 IQPC Conf. on Embedded
Generation within Distribution Networks.
short circuit current limiters [10]. Voltage regulation via the [10] I. Chilvers, N. Jenkins, P. Crossley, “Development of Distribution
transformer tap-changer should be revised because generators Network Protection Schemes to Maximise the Connection of Distributed
modify power flows and this fact may be erroneously Generation”, in Proc. 2003 International Conference on Electricity
interpreted by the control system. Meshed networks try to Distribution – CIRED, Session 4, paper n°46.
equalize voltage along feeders and this may be useful to
achieve an acceptable voltage regulation. Anyway, in order to IX. BIOGRAPHIES
have a better voltage regulation each generator should Gianni Celli graduated in Electrical Engineering at the University of
Cagliari in 1994. He became Assistant Professor of Power System in 1997.
contribute to regulation and voltage regulator should be Current research interests are in the field of MV distribution network planning
modified. Protection coordination is the last issue to solve. optimization, Power Quality and neural networks. He is author of several papers
There are many papers dealing with protection coordination in published on international journals or presented in various international
weakly meshed networks, but there is a lack of studies on conferences. He is IEEE and AEI member.
protection coordination in non radial networks with DG. Fabrizio Pilo graduated in Electrical Engineering at the University of
Cagliari in 1992 and earned the Ph.D. from the University of Pisa in 1998. He
Girgis et al. have proposed an adaptative protection that became Associate Professor of Electrical Power Systems in 2001. His research
allows protecting a distribution system with DG [6]. This kind activity is focused on electrical power systems, network planning and
of protection system can be easily implemented in a network, optimization and neural networks. He is author of several papers published on
but it requires a tremendous effort to modify a well international journals or presented in various international conferences. He is
IEEE, AEI, and CIRED TC member,.
consolidated operation practice.
Giuditta Pisano graduated in Electrical Engineering at the University of
Summing-up, closed-loop networks can be quite easily
Cagliari in 2001 and currently is a Ph.D. student. Her research activity is
implemented but, to have the maximum benefit, it is essential focused on DG and its impact on Power Quality. She is AEI member and IEEE
that some modifications in protection coordination were student member.
performed, short circuit currents will be limited and a new Vittorio Allegranza received his Doctor of Electrical Engineering Degree
voltage control will be applied. In other words meshed in 1999 from Politecnico of Turin. He joined CESI in 2001, where he currently
works for the T&D Network Unit. His main research interests include HV and
networks may be a valid option to improve the capability of
MV planning and operation and power system dynamics. He is author of papers
networks to accommodate generation but their development presented in various international conferences.
have to accompanied by revolutionary change in distribution Rocco Cicoria received the Doctor degree in Electrical Engineering from
that could be considered the first step to real active networks. the Politecnico of Turin in 1974. From 1976 to 1999 he was research engineer in
ENEL-Electrical Research Center and joined CESI in 2000. His main research
interests include electrical power systems, network planning and optimization.
VII. ACKNOWLEDGMENT
He is author of several papers published on international reviews or presented in
This work has been supported by the Italian MAP various international conferences
(Ministry for Productive Activities) in the frame of the Public Adriano Iaria received his Doctorial Degree in Electrical Engineering from
Interest Energy Research Project named “Ricerca di Sistema” University of Pavia, in 2002. He joined CESI in 2002 where he is engaged in
Network Study Unit. His main research interests include power system planning
(MAP Decree of February, 28th 2003). and system modeling.

Você também pode gostar