Sekar Pamen
Divisi Kontraktor
Cluster Type 36 (Standar
PEMBAYARAN PEKERJAAN / M
Blok D.17
Nilai Kontrak
No. URAIAN PEKERJAAN SAT.
Harga Sat. Jumlah Harga
Vol.
Rp. Rp.
A
1 Pasang Bouplank ls 1 260,000 260,000
2 Galian Tanah + urugan m3 23 30,000 690,000
3 Pasangan Pondasi Batu Kali m3 16 80,000 1,280,000
4 Pekerjaan Sloof m' 80 10,000 800,000
5 Pasangan Bata Ringan m2 277 15,000 4,155,000
6 Pekerjaan Kolom, Balok, Plat dan Ring m' 330 10,000 3,300,000
7 Pekerjaan Plesteran Acian + rabat lantai m2 280 15,000 4,200,000
8 Pekerjaan Benangan m' 200 12,000 2,400,000
9 Pasang Genteng + Bubungan m2 87 15,000 1,305,000
10 Pekerjaan Instalasi Air + Resapan ls 1 500,000 500,000
11 Pasang Paving Carport + T. Nomer m2 15 25,000 375,000
PEMBAYARAN PEKERJAAN / M
Blok D.18
Nilai Kontrak
No. URAIAN PEKERJAAN SAT.
Harga Sat. Jumlah Harga
Vol.
Rp. Rp.
A
1 Pasang Bouplank ls 1 260,000 260,000
2 Galian Tanah + urugan m3 23 30,000 690,000
3 Pasangan Pondasi Batu Kali m3 16 80,000 1,280,000
4 Pekerjaan Sloof m' 80 10,000 800,000
5 Pasangan Bata Ringan m2 277 15,000 4,155,000
6 Pekerjaan Kolom, Balok, Plat dan Ring m' 330 10,000 3,300,000
7 Pekerjaan Plesteran Acian + rabat lantai m2 280 15,000 4,200,000
8 Pekerjaan Benangan m' 200 12,000 2,400,000
9 Pasang Genteng + Bubungan m2 87 15,000 1,305,000
10 Pekerjaan Instalasi Air + Resapan ls 1 500,000 500,000
11 Pasang Paving Carport + T. Nomer m2 15 25,000 375,000
AN PEKERJAAN / MC.0
Blok D.17
Jumlah Pembayaran
S/D Minggu lalu Minggu ini S/D Minggu depan
Keterangan
Bobot Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga
% Rp. % Rp. % Rp.
0% 0%
0% 0%
0% 0%
0% 0%
0% 0%
5,006,250 6,470,250
AN PEKERJAAN / MC.0
Blok D.18
Jumlah Pembayaran
S/D Minggu lalu Minggu ini S/D Minggu depan
Keterangan
Bobot Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga
% Rp. % Rp. % Rp.
0% 0%
0% 0%
0% 0%
0% 0%
0% 0%
4,590,750 6,348,000
PT. Sekar Pam
Divisi Kontrak
Cluster Type 36 (Sta
1 - -
20 27,600 560,901
7 13,230 89,622
17 84,614 1,421,520
3 42,114 115,397
- Jumlah II 2,187,440
- - -
20 - -
24 - -
196 - -
6 - -
1 - -
18 - -
91,541,960
67,741,050
Standard
KETERANGAN
1 rit = 3 m3 - Engkel
Re-Cutting
1 dus = 25 kg
1 dus = 20 kg
1 lbr = 3 m
1 gal = 5 kg
0.83
0.12
REKAPITULASI
PERHITUNGAN PEKERJAAN TAMBAH KURANG / CCO
91,541,960 100.00
ANG / CCO
Pekerjaan Tambah
KETERANGAN
Jumlah
PT. S
Nilai
No. Uraian Kavling 1 2
Kontrak Pembayaran
(20/08-01/09) (02 - 08/09)
Opname 48,935 2,197,013
Blok D.17 23,760,000
Kumulatif 48,935 2,245,948
1 Tenaga Kerja
Opname 48,935 2,197,013
Blok D.18 23,760,000
Kumulatif 48,935 2,211,918
Opname 140,341 6,300,874
Blok D.17 68,141,960
Kumulatif 140,341 6,441,215
2 Material
Opname 140,341 6,300,874
Blok D.18 68,141,960
Kumulatif 140,341 6,441,215
Opname
Blok D.17
Kumulatif
3 Peralatan 1,000,000 1,000,000
Opname
Blok D.18
Kumulatif
2.
Nilai
No. Uraian Kavling 1 2
Kontrak Pembayaran
(20/08-01/09) (02 - 08/09)
Tukang 1,100,000 2,200,000
Blok D.17 23,760,000
Kumulatif 1,100,000 3,300,000
1 Tenaga Kerja
Tukang 1,700,000 1,200,000
Blok D.18 23,760,000
Kumulatif 1,700,000 2,900,000
MATERIAL 357,750 4,287,581
Blok D.17 68,141,960
Kumulatif 357,750 4,645,331
2 Material
MATERIAL 337,750 4,271,515
Blok D.18 68,141,960
Kumulatif 337,750 4,609,265
2. ACTUAL on SITE
Minggu (Starting : 20 Agustus 2018). (Rp.)
3 4 5 6 7 8 9
(09 - 15/09) (16 - 22/09) (23 - 29/09) (30 -06/10) (07 -13/10) (14-20/10) (21-27/10)
960,000 1,350,000 2,450,000 2,100,000
4,260,000 5,610,000 8,060,000 10,160,000
970,000 1,650,000 2,750,000 2,200,000
3,870,000 5,520,000 8,270,000 10,470,000
7,327,661 1,000,000 7,360,411 3,133,081
11,972,992 12,972,992 20,333,403 23,466,484
6,499,447 600,000 8,311,250 2,936,447
11,108,712 11,708,712 20,019,962 22,956,409
10 11 12 Retensi
(28/10-03/11)
0
PT. Sekar Pamenang
Divisi Kontraktor
Pembangunan Cluster
Kebutuhan Material untuk Type 36 + 45 Standard
PLANNING
VOLUME HARGA
NO BARANG T.36
SAT
T.45 Rencana Aktual Rencana
1 unit 2 unit
JUMLAH TOTAL
enang
or
er
36 + 45 Standard
NNING
HARGA JUMLAH
KETERANGAN
Rencana Aktual
Aktual
1 unit 2 unit
### ###
Material Schedu
Type 36 Standard
Minggu
NO TGL
1 ( start 20 - 27 Agustus ) 2 ( 27/agu
Material Satuan Volume Harga Jumlah harga Material
1 8/21/2018 Bendrat kg 1 18,000 18,000 batu kali
2 8/21/2018 Benang nilon (kenur) ikat 2 4,000 8,000 pasir
3 8/21/2018 paku 5" kg 1.5 16,500 24,750 semen
4 8/21/2018 paku 7" kg 1.5 16,500 24,750 Tang catut
5 8/21/2018 kaso usuk speck glugu btg 50 20,000 1,000,000Gergaji besi
6 8/26/2018 pvc wafin 4" biji 2 ### 294,000 Bendrat
7 8/26/2018 pvc wafin 3" biji 2 ### 210,000 Pacul
8 8/26/2018 Begel 8 x 15 (20kg) duz 1 ### 350,000
Tang tekuk besi di.8
9 8/26/2018 Begel 8 x 10 (25kg) duz 1 ### 437,500
Pentangan gergaji
10 8/26/2018 Besi uk 8" biji 54 46,000 2,484,000 Batu koral
11 8/26/2018 Pasir (engkel) rit 1 ### 325,000 Papan cor
12 8/26/2018 Semen holcim sak 10 42,000 420,000 Hebel
13 8/27/2018 Benang nilon (kenur) ikat 2 4,000 8,000
14 8/27/2018 Paku 7" kg 2 16,500 33,000
15 8/27/2018 Batu belah(kali) dump rit 1 ### 800,000
TOTAL 3,310,000
September) 4 ( 10 - 17 September) 5 ( 17 - 24 September)
Jumlah Harga Material Satuan Volume Harga Jumlah Harga
Material Satuan Volume
- 24 September) 6 ( 24/sept - 01/okt) 7 ( 01 - 08 oktober )
Harga
Jumlah Harga
Material Satuan Volume Harga Jumlah Harga
Material Satuan Volume
1 - 08 oktober ) 8 ( 08 - 15 Oktober)
Harga Jumlah Harga
Material Satuan Volume Harga Jumlah Harga