COMMISSIONING INSPECTION SHEET

SETE ENERGY SAUDIA FOR INDUSTRIAL PROJECTS LTD.

QUALITY CONTROL DEPARTMENT CONTRACT NO. 7200012306 - INSTALLATION OF


48,000 M³/DAY INDUSTRIAL WASTE WATER
Site Acceptance Testing (S.A.T) TREATMENT PLANT

INSPECTION CHEKLIST: ANOXIC BASIN MIXER


(Equip. Tag No. 12-125 A-F & M12-125 A-F )
1.0] ITEM DESCRIPTION: Anoxic Basin Mixer (12-125 A-F) for Pre-Denitrification Basin inclusive of
Mixer Motor (M12-125 A-F) .
1.1] Construction Category : 1.2] Process Location/Component ID No :

1.3] Contractor : 1.4] Documents Defining Quality Requirements :

Not
2.0] ITEM ACCEPT REJECT
Applicable
A- GENERAL :
(i) Review required Material Specifications and condition for that equipment
(ii) To the Item: Recording of items Received, Spares Received and checking for that
equipment model, type and source check.
B- OVERALL EXAMINATION :
(i) Examination of system Materials, and check for certificates for F.A.T for the equipment.
(ii) Check for transportation Damage caused or storage damage for Complete
system and parts.
(iii) Check For Mixer Body for Matching specifications and Securation to the shaft) .
(iv) Check for over all mixer Body, Wear and tear and check against corrosion. (all inclusive)
(v) check for shaft, and motor material, length, Diameter and Fixation according to
data sheet, and ( P& I.D no. 12306-PP-A1-135 ) for all 6 mixers.
C-INSTALLATION AND ASSEMBLY
(i) Installation according to the submitted drawings. (p& I.D no. 12306-PP-A1-135)
(ii) Check for Level, Plumb and angle of mounting flange.
(iii) Check for Level, Plunge and angle of Mixer before fixation
(iv) Check for Straightness of Shaft and if it can turn freely.
(v) Final Cold Allignment to manufacturer's Tolerance.
(v) Driver Checked for correct Rotation.
(vi) Gear Unit Checked (when Applicable)
(vii) Bearing Housing Flushed and Re-Lubricated.
(viii) Lubricator filled and checked for operatability.
(ix) Mechanical Seal and Packing Installed Type .
(x) Belt or Coupling is correctly Installed and secured.
(xi) Driver Doweled (only when specified)
(xii) Check for installation of bottom guide bushing was performed properly and Aligned
as described with the shaft.
(xiii) Check that the shear Ribs were installed properly.

D-OPERATION
(i) check for performance of the equipment against the designed thickenss of sludge, and
REV. No. 0 - 10/15/2018 SETE-CIS-IWTP-II-**** PAGE NO. 1
COMMISSIONING INSPECTION SHEET

SETE ENERGY SAUDIA FOR INDUSTRIAL PROJECTS LTD.

QUALITY CONTROL DEPARTMENT CONTRACT NO. 7200012306 - INSTALLATION OF


48,000 M³/DAY INDUSTRIAL WASTE WATER
Site Acceptance Testing (S.A.T) TREATMENT PLANT

INSPECTION CHEKLIST: ANOXIC BASIN MIXER


(Equip. Tag No. 12-125 A-F & M12-125 A-F )
1.0] ITEM DESCRIPTION: Anoxic Basin Mixer (12-125 A-F) for Pre-Denitrification Basin inclusive of
Mixer Motor (M12-125 A-F) .
1.1] Construction Category : 1.2] Process Location/Component ID No :

1.3] Contractor : 1.4] Documents Defining Quality Requirements :

Not
2.0] ITEM ACCEPT REJECT
Applicable
speed test (roration per minute).
(ii) check data sheet and corresponding test results from running equipment on site.

3.0] DESCRIPTION OF DEFICIENCIES NOTED :

4.0] ACTION TAKEN ON NOTES DEFICIENCIES :

SUB-CONTRACTOR
CHECKED BY: PREPARED BY SETE QA/QC MARAFIQ
QA/QC

NAME:

SIGNATURE:

DATE:

REV. No. 0 - 10/15/2018 SETE-CIS-IWTP-II-**** PAGE NO. 2