Você está na página 1de 8

128

Rachel Mitchell Design of Aberdeen Channel


Assistant Group
Engineer Bridge, Hong Kong
Highways &
Transportation
Abstract
Atkins
Aberdeen Channel Bridge will form part of the new South Island Line (East)
of Hong Kong’s Mass Transit Railway (MTR). The 225m long post tensioned
David A Smith
concrete box girder bridge will cross the Aberdeen Channel linking a section
Service Director of viaduct on Hong Kong Island to a tunnel on Ap Lei Chau Island. The local
Structures
topography and the presence of existing infrastructure tightly constrained
Highways & the arrangement of the bridge. This paper describes some of the challenges
Transportation
in designing a durable structure which fits into the local environment.
Atkins To reduce maintenance requirements bearings were eliminated from the
pier tops by providing split integral piers. The bridge is to be cast in situ
as balanced cantilevers; during this construction stage the split piers will
Claire Seward
need to be braced. A number of measures were taken to ensure the long
Senior Group Engineer term durability of these piers, including adopting Eurocode crack width
Highways & requirements, installing cathodic protection from the outset and specifying
Transportation higher performance, marine environment grade concrete. The bridge is in
Atkins a heavily populated area and to reduce the local impact full enclosure noise
barriers are to be provided. These increase the wind loads on the structure and
this, combined with a short back span required to meet site constraints, led to
large uplifts at the abutments. Measures taken to reduce this are outlined. The
overall sustainability of the design was assessed using a recently developed
in-house bridge sustainability index tool. The methodology and results of this
tool are discussed.
Keywords: Post- tensioned concrete, balanced cantilever, sustainability

Introduction
The proposed Aberdeen Channel Ap Lei Chau Island side the line will
Bridge (Figure 1) is a 225m long run directly into a tunnel on leaving
post tensioned concrete box girder the bridge, under the rocky outcrop
bridge forming part of the South and existing tower blocks.
Island Line (East) Mass Transit Railway
The detailed design of the bridge
(MTR) extension in Hong Kong. The
was undertaken by Atkins as part of
new MTR line is approximately 7km
a traditional contract covering the
long and will link South Horizons
bridge, sections of viaduct works
on Ap Lei Chau Island to the south
and certain stations for the Client,
with Admiralty station on the north
MTR Corporation. The construction
side of Hong Kong Island. The line
contract was put out to tender in
extension comprises a mix of tunnels
summer 2010 with construction of
and viaducts. The railway will cross
the bridge programmed to begin in
Aberdeen Channel onto Ap Lei Chau
2011.
Island to the south adjacent to the
existing Ap Lei Chau highway bridge
Form of bridge
Structures

on the west side. The existing bridge


was constructed in 1978 with a
second parallel crossing added to The bridge consists of three
widen the road in 1992. On the continuous spans of lengths 58.5m,
Hong Kong Island side to the north, 115m and 73m (Figure 2). At the
the new bridge will connect to south abutment the bridge leads
viaducts on a rocky outcrop. On the straight into a tunnel, at the north
73
abutment the deck rests on a short
abutment shared with the viaducts.
The two intermediate piers are
aligned with the existing Ap Lei Chau
Bridge piers to minimise disruption
to the sea channel and for aesthetic
reasons. The bridge is required to
clear the navigation channel, which
is 70m wide and 14m high above
sea level in the main span. Due to
the sloping vertical alignment of
the tracks, the south pier is 13m
tall and is founded on a pile cap
to be constructed on the existing
sea wall. The north pier is 17m tall
and founded on a pile cap in the
sea channel. The main span to side
span ratio, particularly for the south
span is larger than would have been
preferable to maximise the efficiency Figure 1. Proposed new Aberdeen Channel Bridge
of the bridge, but could not be
altered due to the topological and
maintenance liability of bearings at included a cable-stayed bridge, a
aesthetic constraints.
the top of the piers which would fin-back bridge and an extra-dosed
The deck is an internally post- be difficult to inspect and replace. bridge. The post tensioned concrete
tensioned single cell concrete box The integral connection is also more box option was selected as it was
girder. Two MTR tracks cross the stable for the construction of the viewed to harmonise with the
bridge deck which is 10.8m wide. A balanced cantilevers, reducing the existing bridge, which has a similar
single cell box section was selected need for temporary works at the pier form, and was the most economical
(Figure 3) as the deck is relatively heads. option.
narrow. The box girder varies in
At the initial design stage options
depth from 6.5m at the piers to
considered for the bridge form
3.0m at midspan and abutments,
with a parabolic curved soffit. A
simple uniform cross section was
selected for ease of construction.
The noise assessment for the scheme
has identified the need for full
enclosure noise barriers in some
locations. A continuous upstand for
the anchorage of noise barriers is
provided on each deck outstand over Figure 2. Bridge elevation
the length of the bridge. The full
height noise barriers will not initially
be installed on the full length of the
bridge, but the design was required
to allow for any possible retro-fitting.
The bridge is to be cast in situ using
the balanced cantilever construction
method.
Figure 4. Widened abutment diaphragms
The bridge is integrally connected to minimise uplift at bearings
to the two intermediate piers
with bearings only provided at
the two end abutments. The Figure 3. Typical cross section
integral connection at the pier
tops was provided to eliminate the
74
128 Design of Aberdeen Channel Bridge, Hong Kong

Deck design
Design standards
The bridge was designed to MTR’s
in-house design standards1. These
standards are based on the Structures
Design Manual for Highways and Figure 5. Balanced cantilever construction prior to stitching to adjacent deck sections
Railways (SDMHR) published by the
Hong Kong Highways Department2. installed (Figure 5). At this point In the final design the uplift at the
The SDMHR is largely based on the wind loading can generate large north abutment was eliminated
BS 54003 but with modifications transverse forces at the piers and any and uplift bearings do not need
appropriate to local conditions in out of balance construction loading to be provided here. At the south
Hong Kong. For some aspects of the can generate large moments in the abutment where the side span is
design, reference was also made to piers. The out of balance construction shorter due to the need to link into
the new Eurocode BS EN 1992-2 loading considered was a Uniformly the adjacent tunnel, uplift could
Design of Concrete Bridges4. Distributed Load (UDL) on one side not be eliminated and special uplift
of the deck representing either the bearings will need to be provided. At
Global analysis concrete pours out of balance or both locations the transverse loads
The global analysis of the bridge was the temporary formwork out of from the wind at the deck ends can
carried out using a 3-D space frame balance, but not both. Other out of become very high and so a separate
line beam model. A separate shear balance effects such as unintentional longitudinal guide bearing is provided
flexible grillage model was used to deviation of concrete thicknesses to resist these loads (Figure 4).
determine the distribution of load and construction surcharges/storage
effects between the two webs. The loads were also considered. Such Diaphragm design
space frame model allowed the considerations are now more formally The deck diaphragms at the piers and
construction sequence and tendon given in BS EN 1992-2, although abutments are required to transfer
stressing operations to be taken into this was not specifically used for the the loading from the box section
account and automated the creep, design of Aberdeen Channel Bridge. into bearings at the abutments or
shrinkage and loss calculations for into the piers. These elements were
the post tensioned box.
Uplift
designed using strut and tie analysis.
The short side spans meant that The checks of the compression
The train live loading on the bridge
under some loading conditions, struts, ties and nodes were carried
followed the requirements set out
uplift was generated at the bearings. out in accordance with the guidance
in the MTR design standards, which
The transverse wind loading on given in BS EN 1992-2. Limits on
are based on BS 5400 loading with
the noise barrier also generated a compressive stresses and tension at
modifications for the specific MTR
twisting at the deck end which gave ULS are given in this code. At the
trains. One of the most critical
more uplift on one side. A number Serviceability Limit State (SLS) the
load effects on the bridge was
of options to eliminate this uplift tension stress in the bars was limited
the wind loading. The Hong Kong
were investigated. Increasing the to 200MPa to ensure strains under
region is affected by typhoons and
mass of the deck at the side spans service loads and thus cracking was
the SDMHR makes allowance for
by increasing the wall thicknesses limited. “Suspension reinforcement”
this by specifying high Ultimate
and extending the solid diaphragm to transfer the shear forces from
Limit State (ULS) factors for wind
section was considered. However the box webs into the top of the
loading. The overall effect of the
this did not provide sufficient diaphragms was provided based
high wind loads was also increased
additional mass to fully eliminate the on the guidance by Leonhardt5.
by the requirement to allow for the
uplift. The uplift generated by the Separate models were developed for
presence of the noise barrier in the
eccentric transverse wind loading the maximum torsion and maximum
design. The barrier presents a greatly
was minimised by widening the shear load cases.
increased total wind area, more than
Structures

diaphragm at the bearing location


doubling the transverse wind loads. Tendon arrangement
(Figure 4). This both increased the
During the construction of the total dead load and increased the The post-tensioning tendons are
bridge, the most critical stage is spacing of the bearings, thereby arranged in the box in accordance
when the majority of the balanced increasing the lever arm for the with the guidance in Appendix D of
cantilever decks have been cast but bearing reactions, reducing the final BS 5400 Part 4. In order to simplify
the midspan stitch has not yet been uplift force. the construction process, as much
75
repetition of detailing as possible
was adopted. The box section
requires a significant amount of post
tensioning to be installed. Ensuring
that the tendons were arranged
to minimise curvature (to minimise
losses) and ensuring sufficient cover
is always provided to prevent any
pull out failures, required careful
consideration of the 3–dimensional
layout of the tendons. An existing
in-house clash detection software
package was modified to ensure the
optimum layout of the tendons. The
3-dimensional box dimensions and
the tendon layouts were input into a
model and the software checked that
the limits in Appendix D were met for
every tendon at every location along
its length. Figure 6 and 7 show Figure 6. Clash detection for tendon geometry including minimum spacing
the visual output from this clash
detection software.

Pier and foundation


design
Split pier arrangement
The piers are integrally connected
to the deck without bearings. This is
intended to reduce the maintenance
costs of the bridge in service, but
generates issues for the pier design.
Expansion and contraction of the
deck due to temperature changes,
generate longitudinal forces at the
top of the piers as the piers deflect.
The size of these forces depends on
the stiffness of the piers. Rigid piers
Figure 7. Clash detection for tendon geometry including minimum spacing
will restrain the deck from changing
length and so will generate very large separated leaves have considerably is in operation. Rather than design
longitudinal forces at the top (and less longitudinal stiffness than a the split piers to resist these critical
bottom) of the piers. More flexible single pier, whilst retaining a similar short-term, temporary construction
piers will provide reduced restraint, effective strength. forces, temporary bracing of the piers
thereby reducing the longitudinal was specified during the construction
loads generated in the piers Piers during construction phase. By temporarily connecting
Initial design checks showed that During the construction of the bridge the split leaf piers their stiffness
a single pier design, either solid the most critical stage for the piers is increased and the second order
or hollow that provided sufficient will be once the majority of the deck moments generated in the piers
strength for most load combinations has been cast, but before the two are reduced. Consequently the final
would be too rigid, generating a balanced cantilevers have been joined reinforcement quantities required in
greater longitudinal force at the by the stitch in the main span. The the piers are also reduced.
top of pier than could easily be moment and shear forces exerted on
resisted in bending. A split leaf pier the pier at this stage greatly exceed
design was thus proposed. The two those experienced whilst the bridge

76
128 Design of Aberdeen Channel Bridge, Hong Kong

Serviceability design of piers open and close quickly under peak durability of the piers, especially with
service loading will have little time their inherent difficult access.
Initial crack width calculations for
to affect durability. A crack which
the piers indicated that design crack An impressed current cathodic
is permanently open however does
widths may exceed the simple limits protection system was therefore
provide a sustained path to the
specified in BS5400. This could chosen as the preferred option for
reinforcement.
have been solved by providing the piers on the Aberdeen Channel
extra reinforcement in the face of The limit on crack width for Bridge. This system can be installed at
the piers. However the piers were appearance reasons are based the time of original construction and
already heavily reinforced and on studies that have shown that consists of ribbon anodes installed
there was a concern that additional members of the public are generally on top of the reinforcement cages in
reinforcement, although allowing unaware of crack widths of 0.3mm the piers and pilecaps using isolating
the design to meet the code and below, but start to notice larger clips. Cabling for a data monitoring
requirements, would actually reduce cracks. This is based on a viewing system and power supply system
the durability of the structure due to distance of 3 metres. A value of will also be installed in the piers
the adverse effect such congestion 0.3mm has therefore been taken as with junction boxes in the hollow
may have on placing the concrete, the upper bound to acceptable crack box girder deck at the pier locations.
with perhaps a reduced quality of widths where the concrete surface Data about the condition of the
concrete and cover. is visible, irrespective of durability reinforcement will be collected and
requirements. monitored, using a suitable interface
The new Eurocodes take a
system to detect the onset of
different approach to BS5400 in It is recognised that additional
corrosion at an early stage. The low
the consideration of crack widths measures such as special coatings
powered current supply to the ribbon
in design. Larger peak crack or cathodic protection need to be
anodes would then be switched on
widths under short-term loading taken to enhance durability for some
to actively prevent corrosion of the
are permitted, even in aggressive situations. Horizontal surfaces subject
reinforcement. This system has a
environments and crack width to de-icing salts is a clear example
design life of 120 years, and when
limits are considered only under and vertical surfaces subject to salt
installed at the construction phase
quasi-permanent loads (i.e. the water spray such as the piers on
of a structure, does not significantly
time-based average bridge loading). Aberdeen Channel Bridge close to
increase overall costs as it is relatively
There are a number of reasons for the tidal splash zone also require
easy to install.
these differences. Crack widths are further consideration. In conjunction
limited in structures for three main with the Client, it was decided Additionally, marine grade concrete
reasons: to prevent corrosion of that cathodic protection should be was specified for the piers to further
reinforcement, to prevent unsightly provided for the piers to enhance improve the long-term durability
appearance and to prevent loss of their long term durability, despite of the structure and minimise
service, e.g. by leakage in a liquid not being strictly necessary to BS EN maintenance requirements in the
containing structure. 1992-2. difficult location.
For the piers on this bridge only the Cathodic protection system Foundations
first two of these requirements apply.
Initially, a sacrificial anode system The pier foundations are both formed
BS EN 1992-2 permits wider crack
submerged below sea level and of 4 no. 2.0m diameter piles, with
widths as research into durability
attached to the pier foundations was a rectangular pile cap. The piles are
has found that below 0.3mm the
considered. However the beneficial founded in 2.0m deep rock sockets.
width of cracks has little influence
effects would be limited by the The pile cap within the sea channel
on the durability of the structure.
height of influence above sea-level will be fitted with a fender system to
The quality of the concrete cover
that could be achieved and which protect it from ship impact and will
has the greatest influence on overall
would be limited to approximately be cast above highest water level to
durability. Eurocode 2 bases its crack
2m. Another solution was to embed ensure it is visible from sea channel
width requirements on the quasi-
sacrificial anodes in the concrete vessels. The bridge was designed
permanent load combination as they
piers. However their effective life is to resist ship impact, however the
Structures

recognise that it is not the widest


relatively short (approximately 10 vessels in the channel are of limited
crack that opens during service of a
years), and they would then need size and so this was not generally
structure, rather the time averaged
to be replaced by breaking out the found to be a critical global load
mean crack width. This means that
surrounding concrete and then case.
for road and rail bridges no traffic
repairing it. This in itself is expensive
loading is included when crack As the rock head level in the
and would affect the long-term
widths are checked. Cracks that vicinity of the foundations for the
77
piers is relatively shallow, various provides the end supports and shared A relatively small bank seat
construction options were considered interface structure for the Aberdeen arrangement is used in this location
for the marine pier. Spread Channel Bridge and the adjacent due to the topography. A bearing
foundations were considered at the viaducts. The articulation of both shelf with discrete bearing plinths
feasibility stage, constructed either by structures requires free mechanical is included to accommodate the
de-watering a temporary cofferdam bearings at this abutment, therefore mechanical bearings and jacking
and excavating to acceptable bed- two sets of bearing shelves are positions to allow for future bearing
rock, or using precast caissons, sunk needed to locate the bearings and replacement. A suitable gap and
onto the seabed with in situ mass jacking positions for future bearing expansion joint is designed to allow
concrete. The former option was replacement. A suitable gap and for the movement of the bridge. The
used for the adjacent Ap Lei Chau expansion joint was designed to abutment will also have an inspection
Highway Bridge pier foundations, so allow for the relative movements of gallery as required by the HKDSM
this solution has already been trialled both structures. with a curtain wall behind to support
successfully in this location. the earthworks at the back of the
A relatively small bank seat
abutment. The rock head in this
Various construction methods arrangement is used in this location
location is at the approximate level
for a piled solution for the pier due to the topography. The rock
of the abutment foundation but also
foundations were also investigated. head is relatively close to ground
dips down steeply in the transverse
Options including construction of level but falls steeply in the transverse
direction. Therefore to minimise
a temporary island, construction of direction. Therefore a spread
excavation, a spread foundation
a temporary cofferdam or using a foundation, 3m deep to account for
3m deep has been designed for this
barge or jetty were considered. The the dipping rock head, was designed
location.
final construction method proposed for this location.
for the detailed design was to use
A requirement of the Hong Kong Fire Sustainability
a temporary cofferdam to create a
Department is to provide emergency
piling platform, which also provides a
access off the Aberdeen Channel
dry area for constructing the pilecap. The Atkins sustainability index
Bridge. Generally, MTR evacuation
This option minimises disturbance to
routes are from the end of the train
tool
the seabed and the plan area of the
carriages between the rails of the Atkins has recently developed an
construction works for the marine
track, keeping the deck cross-section in-house tool to determine and
pier foundation in the sea channel.
relatively narrow. However it was measure various sustainability aspects
The south pier is located to ensure agreed with the Hong Kong Fire for bridge schemes. The objective is
that the main span of the new bridge Department that the route off the to use the tool during both outline
is in line with the existing highway bridge will be accommodated by and detailed design phases of a
bridge main span. This places the widening the deck at the north end scheme to understand the effects
foundation for the south pier on to provide an emergency walkway on of changing different aspects of a
top of the existing seawall. During one side of the tracks. This walkway structure on its overall sustainability.
construction of the south pier and leads to a set of stairs at the north The Sustainability Index raises
foundations, the seawall will need abutment that connects to the awareness of sustainable aspects of
to be temporarily removed and a existing adjacent highway bridge, design and construction of a scheme
piling platform constructed over the which is at a lower elevation at this to all members of the team, including
foundations of the seawall. Once the location. Emergency access steps the Client.
piles and pilecap are cast, the seawall from the highway parapet to the
Aspects considered by the
will be rebuilt in the same location pedestrian walkway on the highway
Sustainability Index Tool include:
and the rock revetments will be bridge will also need to be installed
reinstated to the same extent in the to complete the emergency access • Economy (Initial Cost, Whole
sea channel. route. Life Cost, User delay during
construction)
South abutment
Abutment and • Environment (Extent of loss
The south abutment is located on
foundation design the steep slopes of the rocky outcrop
of habitat, Noise during
construction, Noise during service)
with the Sham Wan Towers building
North abutment on top. It provides the end supports • Society (Aesthetics, User delay
The north abutment is located on and shared interface structure for the during construction)
the steep slopes of the rocky outcrop Aberdeen Channel Bridge and the • Resources (Use of recycled
with the Seminary building on top. It tunnels of the adjacent contract. material, Consumption of natural
78
128 Design of Aberdeen Channel Bridge, Hong Kong

resources, ease of modification or Bridges Sustainability Index - Output


demolition) Project MTR - South Island Line (East)
Structure: Aberdeen Channel Bridge
• Climate Change (Carbon footprint
(construction), Carbon footprint Attribute Measure Grade
(maintenance))
Economy
The tool allows the user to calculate Initial cost <2500, >2250 (£/m2) 6
a weighted score of between 1 and
Whole life cost <3250, >2750 (£/m ) 2
4
10 for each aspect of sustainability
listed above, with the lowest score User delay during construction 1 out of 13 1
being most favourable. The overall Environment
score for the bridge is the total score
Extent of loss of habitat 3 out of 16 2
from the sum of the scores of each
aspect, with the lowest overall score Noise during construction 7 out of 10 7
being most favourable. The scores Noise during service -1 out of 4 0
for each aspect are also represented Society
visually by the tool using a ‘spider
chart’ to highlight aspects with Aesthetics 7 out of 14 5
relatively high scores. User delay during construction 1 out of 13 1
The use of the tool depends on Resources
assumptions made by the user based Use of recycled materials 7 out of 11 7
on best information available at the Consumption of Natural resources >2.50 (tonnes/m ) 2
10
time of undertaking the sustainability
Ease of modification, demolition 6 out of 10 6
assessment. The score can be
adjusted to match the more accurate Climate change
information available as the scheme Carbon footprint (constructive) <3, >1.5 (tonnes C02 /m2) 8
progresses.
Carbon footprint (maintenance) <0.05 (tonnes C02 /m2) 0
Use of the sustainability index Overall index score = 0.427
tool for Aberdeen Channel
Bridge
The sustainability index tool was
used during the detailed design
of the Aberdeen Channel Bridge
to understand the implications of
decisions on design aspects and
construction methods, some of
which could be varied, while other
choices were required due to either
physical or client requirements.
Figure 8 shows the completed
Sustainability Index for Aberdeen
Channel Bridge.
Sustainability aspects that are
influenced by the design process
include the use of natural resources,
which has a high score for this
structure. This is due in part to a
Structures

heavy concrete deck profile relative


to the area of the deck, as the bridge
is relatively narrow but has relatively
deep sections. Another aspect relates Figure 8. Bridges sustainablity index ouput for Aberdeen Channel Bridge
to the extensive use of prestress
in design, making demolition or
modification of the structure complex
79
in the future. The initial cost of so it is assumed that only a limited a high score for this aspect. This
construction of the bridge is relatively amount will be used demonstrates how the construction
modest based on the deck area and process can improve the sustainability
• Distances to be travelled by
this keeps the score for this aspect of a scheme further by choices of
materials have been conservatively
at a moderate level. The design material types and sources and
assumed
choices for the structural form will methods of working.
keep maintenance requirements to • There will be a high use of natural
Continually using the Sustainability
a minimum, thereby achieving a low resources
Index tool throughout the design of
score for this aspect of sustainability
• Relatively large amounts of Aberdeen Channel Bridge highlighted
too.
excavation will be required with that a low maintenance, economical
As this scheme uses a traditional associated removal of waste structure that did not adversely affect
form of contract, where the detailed materials the environment was developed. It
design is completed and then also highlighted how the choice of
• Night working will be used which
contractors will tender to construct materials and construction processes
may affect local residents and
the bridge, various assumptions were are important and affect the overall
businesses.
made in relation to construction sustainability of the bridge.
aspects. The main assumptions are These assumptions are generally
given below: conservative, and they particularly
affect the carbon footprint of the
• I t is unknown if recycled materials
scheme during construction, giving
will be used during construction

Acknowledgements
This paper is submitted with the approval of the Hong Kong MTR Corporation. The authors would also like to thank
Atkins’ design management team led by Douglas Simmons and Bruce Gillespie for their crucial role in coordinating
all aspects of the detailed design, including Client liaison, architectural input and interfaces with other third party
consultants and stakeholders.
This paper was first published in Proceedings fib Symposium Prague 2011.

References
1. MTR Corporation Limited, New Works Design Standards Manual – Section 4 Civil Engineering, MTR
Corporation Limited, Hong Kong, April 2009.
2. The Government of the Hong Kong Special Administrative Region, Structures Design Manual for Highways and
Railways, 3rd Edition, HKSAR, Hong Kong, August 2006.
3. British Standards Institution. Steel, Concrete and Composite Bridges, Part 4 – Code of practice for design of
concrete bridges. BSI, London, 1990, BS5400.
4. British Standards Institution. Eurocode 2: Design of Concrete Structures – Part 2-2: Concrete bridges – Design
and detailing rules. BSI, London, 2005, BS EN 1992-2.
5. Leonhardt, F, Koch, R and Rostasy, F.S, Suspension reinforcement for indirect load application to prestressed
concrete beams: test report and recommendations, Beton und Stahlbetonbau, 1971, Vol. 66, Issue 10, pp.
233-241.

80

Você também pode gostar