Written by Capt Rajeev Jassal on April 10, 2016

If you have the experience of dry docking of a ship, you would


agree that dry docking is a great experience.

I personally love to be on a ship due for dry dock. After all, you
get to see things which you don’t see during routine operation
of the ship.
I was lucky enough to get a chance to be in dry dock in each
rank I have served on. I was even lucky to experience the
double-hull conversion of a tanker during dry dock.

But if you have not been to a dry dock, there would be one
thing that might come to your mind on hearing the word Dry
Dock. And that is dry dock calculation that we read in ship
stability, probably during our Mate’s exams.

That’s purely theory part. And I believe theory without practical


experience is just a theory.

So here I am going to write about the practical aspect of taking


a ship to dry dock.

But before I proceed, in layman’s terms I will summarize what


we had read about dry docking in ship stability.

We read and understood these things

 The time from “when Stern touches the blocks” to when “full
ship is on the blocks” is the critical period.

 During the critical period, the vessel’s GM reduces. This is


because vessel’s ‘Gravitational center G moves upwards when
Stern touches the blocks.
 It is required and a good practice to have the least trim while
docking so that the critical time is minimal.

Preparing for Dry Dock

Well, I am not going to the company specific parts of dry


docking, like preparing repair specifications.

I will specifically be talking about taking the ship into the dock
and making it sit on the blocks.

And then, of course, bringing the ship out of dry dock.

Days before the planned dry dock, Dock master will make the
first contact with the ship. He can do so either directly or
through the company representative such as superintendent.

The dock master has a huge responsibility of calculating the


stresses on the dock as well as the ship’s structure. Any
miscalculation can lead to serious accidents resulting in huge
damages. These damages can be to the ship as well as dock
itself.
The dock master is trained for block arrangement and
stability during dry docking. For all these calculations, dock
master needs certain information from the ship. Among other
things, he will ask for
 a copy of Vessel’s Docking plan
 Arrival Stability conditionPre-docking condition

 Pre-docking condition

Some of the content of his email might look something like this

From the docking plan, dock master wants to know

1) Hull structure so that he can arrange the blocks to support


the ship’s hull.

2) locations of transducers for log and echo sounders so that


these do not come beneath the blocks.

3) Location of sea chests and drain plugs for the same reason.
Based on the docking plan provided by the ship, dock master
prepares his own docking plan for the ship. Below are some of
the sections of actual docking plan prepared by dock master for
s ship arriving for dry dock.

As you can see, dock master has planned which blocks he


needs to remove and where he needs to put blocks. He also
has specifically marked the location of echo sounder and speed
log.

Have a look at the more closer view below, which is again from
same docking plan prepared by dock master.
I think the above image make it more clear about what dock
master is trying to achieve from the docking plan. If you want
to see the stern view too. Here is it.
And this is no theory. This is an actual docking plan prepared
by dock master for a ship arriving at dry dock.

I know I am kind repeating myself but I can’t say it enough.


That is because I get excited to see real thing than just theory.
Stability condition and weight distribution

Apart from docking plan, dock master would ask arrival weight
distribution of the ship.

There can be up to 4 stages for which stability calculations are


required. These stages are

 Arrival Dry docking port

 Pre-docking condition

 Ship sitting on the blocks but dock not yet empty (also called
wet condition by dock master)

 Ship on the blocks and dock empty (called Dry condition by


docking master

Let’s discuss each of this condition

Arrival Dry docking port

On arrival dry docking port, you need to have least possible


ballast. By least possible I mean, propeller should be
immersed. And also you should be complying with all stability
requirements.
Pre-docking stability condition

So we know that we cannot arrive with zero ballast as our


propeller need to be immersed and the ship needs to be stable.

But what is the logic behind having other three conditions?


Why can’t we just remove all the ballast and go inside the
dock?

Let’s understand the logic behind these conditions

Docking with zero ballast is the ideal condition. But most of the
times this would not be possible. That is because docking
master would limit you for the maximum trim that you can
have. In zero ballast condition, your trim may be more than 2
meters.

Dock master would want you to reduce the trim to around 0.5
meters. This depends on the dock on how much trim you can
have before docking.

We have already discussed the reason for the need of least


trim while docking. This is to have the least critical period.
More trim we have more will be the time required to bring the
vessel from stern on the block to full ship on the block. And this
is the critical period with least GM value. We do not want to
have the ship in the critical period for longer time.
Most of the ships will have considerable stern trim in light
weight condition. So most ships will need to have some ballast
forward in Pre-docking condition.

The amount of ballast would depend on how much trim dock


master has advised you to have.

Stability condition while ship on blocks but


dock not empty

When the ship is on the blocks, you have already passed the
critical period. Dock master will tell you to start deballasting.
The only concern dock master will have is the ship should not
refloat.

The ship can refloat if dock deballasting cannot compensate for


the decrease in the draft because of deballasting.

The condition is monitored by the dock master and he would


tell you on how much ballast you can remove in this condition.

But the question is why the dock master need the vessel to
remove the ballast concurrently when he empties the dock?

This is because dock water does not want to have more weight
on the blocks. When the ship is sitting on the blocks but has
water inside the dock, there is a certain amount of buoyancy
ship has. This buoyancy acts like upthrust which reduces the
effective weight acting on the blocks.

This condition will be discussed by the dock master and he will


advise when and how much ballast you can remove.

As I said earlier, dock master bases his calculations on not to


allow the ship to refloat.

Ship on the blocks and dock empty

When the ship is on the blocks and there is no danger of ship


re-floating, dock master will tell to take out all ballast.

Dock masters sometimes call this condition as the Dry


condition.
Procedures for taking the ship to dry dock

Now that we know about the stability part, let’s look into each
stage of taking the ship to the dry dock.
Arrival to dry docking port

As I mentioned, you would arrive with least ballast. That would


be arrival dry docking port condition. Even though the ship will
be complying with draft and stability requirements, but the ship
will be light. Lighter than usual ballast condition. So before you
arrive at this condition, it is important to scan the weather
reports. You would not want to arrive in light condition if the
weather prediction is rough.

Most of the time, the ship is taken to the lay-up berth before
going into the dry dock. If not, vessel needs to be at anchor for
deballasting to arrive at the Pre-docking condition.

While at anchor, dock safety inspector will board the vessel. He


will do the gas check of all the compartments to make sure that
vessel is gas free. He will then issue a gas free certificate. He
will also give safety booklet of the dock which will have all the
safety regulations of the dock.

Docking of the vessel

The vessel will dock when it has achieved the pre-docking


condition. In this condition, vessel will have least ballast to
achieve the required trim.
Before docking, dock master will board the vessel. He
will discuss the docking procedures with master and chief
officer. He will give the mooring arrangement plan while
docking. He will specify the Panama leads from where the
moorings will be passed.

Apart from this, he will also discuss the ballast condition at


each stage.

For shifting to the dock, the pilot will board the vessel. As the
ship’s engine will not be available, the ship will have a number
of tugs to move the ship to dry dock. The number of tugs
would depend on how big the ship is and how powerful the tugs
are. In any case, all ships can expect 5 tugs or more.

Out of these 5 tugs usually, 2 will only be assisting for pushing.


Different docks can have different arrangements for making
fast the tugs. It will all depend upon the location, tidal current,
and local factors.

One of such arrangement can be two tugs made fast forward,


one made fast aft and two tugs standby. The one tug made fast
aft will have one line on each side of the poop deck to have
better control in handling the ship.

Depending upon the dock, the ship will either enter stern in or
bow in.
The pilot will bring the ship parallel to the dock. When the stern
(or bow whichever is entering first) is close to the dock
knuckle, docking master will take over from the pilot. Docking
Master is different from dock master. Docking Master may not
board the vessel and will be giving instructions to the tugs from
the dock itself.

When the ship is inside the dock, ship’s crew need to pass the
mooring lines as per the agreed mooring arrangement. Usually
forward and aft will have two lines on each side. Out of two
lines on each side, one on each side can be shore line. But this
can be different and mooring arrangements will be advised by
the dock master.

When the ship is made fast with the moorings, docking master
will sign off and dock master will take over.

Vessel on the blocks

Before dock master starts to remove dock water, a diver will


make an underwater inspection. The diver will ensure that echo
sounder and log sensors are clear and not sitting under the
blocks. He will also ensure physically that vessel’s centerline is
in line with the blocks. It is a good practice to switch off the
echo sounder and speed log now.
After the diver has made his inspection, dock master will start
pumping out dock water.

Dock master will let the vessel know when Stern has touched
the blocks and when the ship is on the blocks.

After the ship is on the blocks, dock master will tell to start
pumping out ballast to arrive at the wet condition.

As the dock water is being pumped out, at one point the water
will go down from the generator cooling water sea chest.

After this point ship will get power supply from shore.

A shore electrician will board the ship (Through basket and


shore crane) and make arrangement to connect the shore
power. Ship’s Electrician should coordinate with him to have
the shore power connected.

You should check if shore power will be enough for running the
ballast pump and mooring winches. If not, this should be
discussed with dock master in advance. He will then ensure
that water level does not go below sea chest until you have
pumped out required ballast.
Once on shore power, dock master would continue to dry the
dock. He will tell you to take out all ballast accordingly. You
may do so with gravity as same might be more effective.

Once the dock is dry and ship sitting on the blocks, you can line
up to deballast all ballast tanks by gravity. This is to let all the
water drain whatever is left in the ballast tanks.

So now you have already brought the ship to the dry dock. It is
a wonderful view to see the ship out of the water. You should
not wait to go down in the dock and have a look at her.

Removing the Drain plugs

The Ship repair manager will now request the chief officer to
witness the removal of the bottom plugs.

As you know, each tank which forms part of the hull has a
bottom plug to drain the water in dry dock.

Removing bottom plugs ensure that the tanks are empty and
dry. As bottom plug of each tank is removed, it is important to
label it. This will ensure that bottom plugs are not interchanged
while fitting back.
Though plugs of all the ballast tanks are of the same size, it is
best practice to fit back plugs which belong to each tank.

If you wish to experience how we remove the bottom plugs,


watch this video.

Departure from Dry Dock

After few hectic days in dry dock, it would be time to leave dry
dock. We need to be equally attentive in leaving the dry dock
as we were while coming into the dry dock.

Before dock master floods the dry dock, all the underwater
things need to be in order. This includes sea chests, ICCP
system, echo sounder sensors, log sensors and drain plugs.

Echo sounder, log and drain plugs are tested for air and
water tightness. Testing involves first putting soap solution
around the drain plug. Then we create the vacuum around
drain plug and look for any bubbles.

If you have never experienced this testing before, here is a


video of testing of the drain plug.

After all these integrity tests are complete, it is time to leave


the dry dock.
The best approach of leaving the dry dock is to follow exactly
how the ship came into the dry dock.

It would involve

1. Filling the ballast to bring the ship to wet condition.

2. passing the lines as was in the arrival condition

3. Flooding the dock

4. Filling the ballast to pre-dry dock condition

5. Flooding the dock up to the level where the ship is fully afloat.

6. Disconnecting the shore supply and taking ship’s generators on


load

7. Taking the ship out of the dock with the help of tugs.

Finally to summarize the process of bringing a ship to the dry


dock, here is an Infographic
Conclusion

Dry docking is a great experience for those who do not want to


stop learning. The special thing about dry docking is that there
are plenty things that a seafarer can learn each time he
attends a dry dock.

While it might seem to be a difficult process but if we view the


whole process logically, it would seem a routine.

If you are going to a dry dock, Enjoy the learning process. And
let me know in the comments below if there was anything that
should form a part of this guide.