Você está na página 1de 82

SARAWAK ENERGY BERHADVOLUME 1 - PART C: SECTION 3 - BILL NO.

3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project

PART C : SECTION 3 - BILL NO. 3

SUMMARY OF PRICE
TOTAL Amount
SECTION DESCRIPTION (RM)TOTAL Amount
(RM)
Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project

01 Site Clearing & Grubbing Works 7,183.46

Piling 1,474,625.00

04 132 kV Control Building 1,852,154.00

04 33 kV Control Building 1,019,912.24

05 Outdoor Foundation, trenches & Oil Interceptor 2,097,770.30

06 Infrastructure Works 2,466,181.42

07 Water Supply Works 108,134.33

08 Any Other Miscellaneous Works (Provisional) 200,000.00

SUMMARY OF PRICE FOR BILL NO. 3 : 9,225,960.75


CARRIED FORWARD TO SUMMARY OF TENDER

Note: LS means Lump Sum Price not subject to remeasurement.


Bill 3 - BILL SUM : 1/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

SECTION 01 - SITE CLEARING & GRUBBING WORKS (ALL PROVISIONAL)

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

1.0 SURVEY AND SETTING OUT WORKS

SGCW010101 Survey and setting out of the works by Licensed Surveyor


engaged by Contractor to be approved by S.O. HA 2 3,591.73 7,183.46

SGCW010304 Compliance with other Terms and Conditions of Contract not


covered by any item in the Summary of Tender.
i)
ii)

TOTAL AMOUNT OF SECTION 01: 7,183.46


CARRIED FORWARD TO SUMMARY OF PRICE

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S01 : 2/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 132kV Substation


SECTION 04 - 132kV CONTROL BUILDING
BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
1.0 WORK BELOW LOWEST FLOOR FINISHES
Excavate, Get Out, Part Return, Fill In, Well Compacted And
Level, Grade, Ram And Trim Bottom And Sides of Excavation;
Including Planking And Strutting, Working Around Piles With
Care

Ground Slabs; Commencing From Existing Ground Level To


Reduced Level

SGMCW040101 Maximum depth not exceeding 0.25m. m3 45 443.74 19,968.30


Pile Caps; Commencing From Reduced Level; Having Both Plan
Dimensions Not Exceeding 1.25m (All Provisional)
SGMCW040102 Maximum depth not exceeding 2.00m. m3 45 443.74 19,968.30
Pile Caps; Commencing From Reduced Level; Having Both Plan
Dimensions Exceeding 1.25m (All Provisional)
SGMCW040103 Maximum depth not exceeding 2.00m. m3 45 458.42 20,628.90
Ground Beams; Commencing From Reduced Level
SGMCW040104 Maximum depth not exceeding 1.00m. m3 56 458.42 25,671.52
Cable Tench; Commencing From Reduced Level
SGMCW040105 Maximum depth not exceeding 2.00m. m3 90 25.87 2,328.30
Disposal of Surplus Excavated Materials
SGMCW040106 Load and cart away from site all surplus excavated materials to
Contractor's own dump site. (Provisional) m3 250 21.73 5,432.50
Waterproofing System
Single Layer 0.2mm Thick Translucent Polythene Damp Proof
Membrane; With Minimum 150mm Lap At Joint And Tapped
With Approved Double Sided Tape (Measured Nett And No
Allowance Made For Laps)

SGMCW040107 To all soffit of ground slabs. m2 426 8.40 3,578.40

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 3/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Approved Cementitious Water Proofing System And Protective
Coating; Works To Be Carried Out By Qualified Installer And
Approved Applicator To Waterproofing Producer's Details And
Instructions

SGMCW040108 To ground slabs. m2 10 56.00 560.00


SGMCW040109 Upturn to sides of wall; 0.35m high. m2 5 56.00 280.00
SGMCW040110 Upturn to sides of wall; 1.80m high. m2 12 56.00 672.00
Prepare And Apply Approved Waterproofing System All In
Accordance With The Manufacturer'S Instructions And
Recommendation

SGMCW040111 To external surfaces of cable trench wall, base and ramp slab.
m2 120 56.00 6,720.00
Anti-Termite Treatment
Approved Anti-Termite Treatment To Be Executed In Accordance
With Manufacturer's Instructions Including Provision of Two (2)
Years Warranty From The Date of Practical Completion

SGMCW040112 To total area of ground floor, perimeter drain and extending


1.00m beyond the perimeter drain all around the building. m2 920 11.20 10,304.00
(measured flat on plan)

Concrete Works
Note:
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where
required.

Lean Concrete Grade 15; Not Exceeding 100mm Thick


SGMCW040113 Blinding under pile caps. m3 4 18.59 74.36
SGMCW040114 Blinding under ground beams. m3 6 18.59 111.54
SGMCW040115 Blinding under ground slabs. m3 30 18.59 557.70
SGMCW040116 Blinding under cable trench. m3 4 18.59 74.36
Vibrated Reinforced Concrete Grade 30
SGMCW040117 Pile caps. m3 40 443.74 17,749.60
SGMCW040118 Stumps. (Provisional) m3 5 443.74 2,218.70

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 4/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040119 Ground beams. m3 60 458.42 27,505.20
SGMCW040120 Ground slabs; exceeding 150mm but not exceeding 300mm
thick. m3 140 458.42 64,178.80

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 5/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040121 Cable trench. m3 40 458.42 18,336.80
Mass Concrete Grade 20
SGMCW040122 Topping-up slab; not exceeding 100mm thick. m3 2 384.72 769.44
SGMCW040123 Ramp slab; exceeding 100mm but not exceeding 150mm thick.
m3 2 384.72 769.44
SGMCW040124 Forming groove lines on surface of ramp slab; including making
good all works disturbed. m 40 5.60 224.00
Reinforcement Works
High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2
Pile Caps
SGMCW040125 10mm Diameter bar; as loops. kg 380 4.37 1,660.60
SGMCW040126 12mm Diameter bar. kg 110 4.37 480.70
SGMCW040127 16mm Diameter bar. kg 2,500 4.14 10,350.00
Stumps (Provisional)
SGMCW040128 10mm Diameter bar; as links. kg 260 4.37 1,136.20
SGMCW040129 16mm Diameter bar. kg 450 4.14 1,863.00
SGMCW040130 20mm Diameter bar. kg 250 4.14 1,035.00
SGMCW040131 25mm Diameter bar. kg 2,400 4.14 9,936.00
Ground Beams
SGMCW040132 10mm Diameter bar; as links. kg 1,950 4.37 8,521.50
SGMCW040133 12mm Diameter bar. kg 1,100 4.37 4,807.00
SGMCW040134 16mm Diameter bar. kg 1,800 4.14 7,452.00
SGMCW040135 20mm Diameter bar. kg 1,400 4.14 5,796.00
SGMCW040136 25mm Diameter bar. kg 4,500 4.14 18,630.00
Ground Slabs
SGMCW040137 10mm Diameter bar. kg 7,000 4.37 30,590.00
SGMCW040138 25mm Diameter bar. kg 100 4.14 414.00
Cable Trench
SGMCW040139 10mm Diameter bar; as links. kg 360 4.37 1,573.20
SGMCW040140 10mm Diameter bar. kg 500 4.37 2,185.00
SGMCW040141 12mm Diameter bar. kg 2,000 4.37 8,740.00
SGMCW040142 25mm Diameter bar. kg 1,500 4.14 6,210.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 6/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Fabric Mesh Reinforcement As Specified; Well Lapped
(Measured Nett, Rate To Include For Laps And Intersections)

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 7/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040143 BMC A8 in topping-up slab. m2 3 30.80 92.40
SGMCW040144 BMC A8 in ramp slab. m2 15 30.80 462.00
Formwork -
Formwork To Reinforced Concrete Works; Class F1 -
SGMCW040145 To sides of pile caps. m2 130 49.28 6,406.40
SGMCW040146 To sides of stumps. (Provisional) m2 60 49.28 2,956.80
SGMCW040147 To sides of ground beams. m2 370 50.62 18,729.40
SGMCW040148 To edges of ground slabs; not exceeding 250mm deep. (50mm
thick) m 10 23.18 231.80
SGMCW040149 To edges of ground slabs; not exceeding 250mm deep. (100mm
thick) m 110 23.18 2,549.80
SGMCW040150 To edges of topping-up slab; not exceeding 250mm deep.
(50mm thick) m 3 23.18 69.54
SGMCW040151 To edges of ramp slab; not exceeding 250mm deep. (150mm
thick) m 5 23.18 115.90
SGMCW040152 To sides of cable trench. m2 110 49.28 5,420.80
2.0 FRAME
Concrete Works
Note:
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where
required.

Vibrated Reinforced Concrete Grade 30


SGMCW040201 Columns. m3 45 458.42 20,628.90
SGMCW040202 Stiffeners. m3 10 458.42 4,584.20
SGMCW040203 Suspended floor beams. m3 60 465.92 27,955.20
SGMCW040204 Roof beams. m3 40 465.92 18,636.80
SGMCW040205 Corbels. m3 2 465.92 931.84
Reinforcement Works
Mild Steel Reinforcement Bar With Yield Strength of 250N/mm2

Stiffeners
SGMCW040206 10mm Diameter bar; as links. kg 610 4.37 2,665.70

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 8/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2
Columns

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 9/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040207 10mm Diameter bar; as links. kg 2,500 4.37 10,925.00
SGMCW040208 16mm Diameter bar. kg 3,600 4.14 14,904.00
SGMCW040209 20mm Diameter bar. kg 150 4.14 621.00
SGMCW040210 25mm Diameter bar. kg 510 4.14 2,111.40
Stiffeners
SGMCW040211 6mm Diameter bar. kg 150 4.37 655.50
SGMCW040212 10mm Diameter bar. kg 900 4.37 3,933.00
Suspended Floor Beams
SGMCW040213 10mm Diameter bar; as links. kg 1,700 4.37 7,429.00
SGMCW040214 12mm Diameter bar; as links. kg 100 4.37 437.00
SGMCW040215 12mm Diameter bar. kg 1,200 4.37 5,244.00
SGMCW040216 16mm Diameter bar. kg 800 4.14 3,312.00
SGMCW040217 20mm Diameter bar. kg 900 4.14 3,726.00
SGMCW040218 25mm Diameter bar. kg 3,100 4.14 12,834.00
Roof Beams
SGMCW040219 10mm Diameter bar; as links. kg 900 4.37 3,933.00
SGMCW040220 12mm Diameter bar. kg 1,200 4.37 5,244.00
SGMCW040221 16mm Diameter bar. kg 100 4.14 414.00
Corbels
SGMCW040222 10mm Diameter bar; as links. kg 40 4.37 174.80
SGMCW040223 12mm Diameter bar. kg 60 4.37 262.20
SGMCW040224 25mm Diameter bar. kg 200 4.14 828.00
Formwork
Formwork To Reinforced Concrete Works; Class F2
SGMCW040225 To sides of columns. m2 500 50.62 25,310.00
SGMCW040226 To sides of stiffeners. m2 200 50.62 10,124.00
SGMCW040227 To sides and soffit of suspended floor beams; with strutting not
exceeding 3.50m high. m2 500 50.62 25,310.00
SGMCW040228 To sides and soffit of roof beams; with strutting not exceeding
3.50m high. m2 300 50.62 15,186.00
SGMCW040229 To sides and soffit of roof beams; with strutting exceeding
3.50m but not exceeding 5.00m high. m2 10 69.10 691.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 10/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040230 To sides and soffit of corbels; with strutting not exceeding
3.50m high. m2 10 50.62 506.20
3.0 UPPER FLOORS
Concrete Works

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 11/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Note:
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where
required.

Vibrated Reinforced Concrete Grade 30


SGMCW040301 Suspended floor slabs; exceeding 150mm but not exceeding
300mm thick. m3 100 465.92 46,592.00
Reinforcement Works
High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2
Suspended Floor Slabs
SGMCW040302 10mm Diameter bar. kg 4,800 4.37 20,976.00
Formwork
Formwork To Reinforced Concrete Works; Class F2
SGMCW040303 To soffit of suspended floor slabs not exceeding 200mm thick;
with strutting not exceeding 3.50m high. m2 400 53.76 21,504.00
SGMCW040304 To edges of suspended floor slabs; not exceeding 250mm deep.
(100mm thick) m 30 -
4.0 ROOF
Roof Structure
Design, Construction And Completion of 'EcoSteel Truecore' Or
Other Approved Equivalent Proprietary Steel Truss System;
Including Purlins, battens, Screws, Connection Plates,
Accessories And Painting (Measured Nett Roof Covering Area)

SGMCW040401 To lower roof; at 15° pitch. m2 410 118.72 48,675.20


SGMCW040402 To upper roof; at 15° pitch. m2 500 118.72 59,360.00
SGMCW040403 To canopy roof; at 15° pitch. m2 30 98.56 2,956.80
Roof Covering

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 12/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
0.48mm BMT (0.54mm TCT) 'Clean Colorbond UGI Unilok' Or
Other Approved Equivalent Metal Roofing Sheet; Laid In Strict
Accordance With Manufacturer's Specifications And Instruction
Including All Necessary Fixing Accessories, Concealed Clips,
Fasteners And Screws (Measured Nett And No Allowance Made
For Laps)

SGMCW050404 To lower roof; at 15° pitch. m2 410 106.40 43,624.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 13/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW050405 To upper roof; at 15° pitch. m2 180 106.40 19,152.00
SGMCW050406 To canopy roof; at 15° pitch. m2 30 106.40 3,192.00
0.48mm BMT 'Clean Colorbond UGI' Or Other Approved
Equivalent Metal Roofing Accessories; Cut And Bent To Required
Shape And Profile, Well Lapped And Jointed; Laid In Strict
Accordance With Manufacturer's Specifications And Instruction
Including All Necessary Fixing Accessories, Fasteners, Screws
And All Necessary Brackets (Measured Nett And No Allowance
Made For Laps)

SGMCW040407 Ridge capping including notching edges to match roof profile;


457mm girth. m 50 61.60 3,080.00
SGMCW040408 Flashing; 457mm girth; one end secured into brickwall and
other end notched and dressed over roofing sheet. m 25 61.60 1,540.00
SGMCW040409 FSGMCia; 457mm girth; one end dressed over roofing sheet and
other end dressed over ceiling eave. m 110 79.52 8,747.20
SGMCW040410 Barge capping; 457mm girth; one end dressed over roofing
sheet and other end dressed over ceiling eave. m 70 61.60 4,312.00
0.48mm BMT (0.54mm TCT) 'Clean Colorbond UGI Unilok' Or
Other Approved Equivalent Metal Roofing Accessories; Cut And
Bent To Required Shape And Profile, Well Lapped And Jointed;
Laid In Strict Accordance With Manufacturer's Specifications
And Instruction; Pierced-Fix Including All Necessary Fixing
Accessories, Steel Framing, Fasteners And Screws (Measured
Nett And No Allowance Made For Laps)

SGMCW040411 Barge cladding. m2 25 135.52 3,388.00


Insulation Works

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 14/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040412 Layer of 8mm thick resilient thermal insulating air-bubble faced
with and including double sided approved fire rated aluminium
foil complete with reinforced net; laid over wire mesh
(measured separately), lapped minimum 150mm at joints and
sealed with and including adhesive jointing tape of similar m2 910 33.60 30,576.00
material. (measured nett and no allowance made for laps)

SGMCW040413 Layer of 50mm x 50mm x 2mm diameter galvanised steel wire


mesh; lapped 150mm at joint and secured to roof framing. m2 910 5.60 5,096.00
(measure nett and no allowance made for laps)

0.48mm BMT (0.53mm TCT) 'Torres Blue Clean Colorbond'


SGMCW040414 'Lysaght',
Gutter; 'UGI' Or
300mm Other Approved
x 300mm; Equivalent
fixed to fSGMCia Metal
board orSheet; Cut
secured to
And
steelBent
roof To Required Shape And Profile; Well Lapped And
truss. m 100 118.72 11,872.00
Jointed; Including All Necessary Fixing Accessories, Holders,
SGMCW040415 Hangers,
EXTRA OVER Brackets,
gutterSteel Framing,
for stop end. Supports, Fastener And No 10 39.20 392.00
Screws (Measured Nett And
uPVC Pipe Works And Fittings; NoWith
Allowance Made For
And Including AllLaps)
Necessary
Fixing Accessories, Holding Clips, Jointed With And Including
Approved Solvent; All In Accordance With The Manufacturer's
Specification And Instructions

SGMCW040416 100mm Diameter rainwater downpipe fixed to wall or column.


m 180 36.40 6,552.00
SGMCW040417 100mm Diameter rainwater downpipe embedded in reinforced
concrete slab. m 25 36.40 910.00
SGMCW040418 EXTRA OVER 100mm diameter downpipe for swan neck. No 20 16.46 329.20
SGMCW040419 EXTRA OVER 100mm diameter downpipe for 90° bend. No 20 43.34 866.80
SGMCW040420 EXTRA OVER 100mm diameter downpipe for 45° bend. No 40 43.34 1,733.60
SGMCW040421 EXTRA OVER 100mm diameter downpipe for shoes. No 20 16.46 329.20
SGMCW040422 Dome grating cover including water proofing works. No 20 11.09 221.80
5.0 STAIRCASE
Concrete Works
Note:
Prices/rates for concrete shall be deemed to include the
addition
Vibrated of super-plasticizer
Reinforced Concreteadmixture
Grade 30 at location where
required.
SGMCW040501 Staircase. m3 10 465.92 4,659.20

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 15/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Reinforcement Works
High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 16/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Staircase
SGMCW040502 12mm Diameter bar. kg 700 4.37 3,059.00
Formwork
Formwork To Reinforced Concrete Works; Class F2
SGMCW040503 To sides and soffit of landing slab.
m2 5 53.76 268.80
SGMCW040504 To soffit of staircase; sloping over 15° from the horizontal. m2 25 53.76 1,344.00
SGMCW040505 To sides of undercut riser; not exceeding 250mm high.
(168.75mm high) m 85 21.28 1,808.80
SGMCW040506 To stringer sides of staircase; exceeding 250mm but not
exceeding 500mm high; sloping over 15° from horizontal. m 30 41.55 1,246.50
(350mm high)

Handrail
Stainless Steel Handrail; Cut, Welded, Framed Together And
Fixed Into Position Including All Shop And Site Connections,
Filing Smooth All Welded Junctions, Base Plates, Anchor Bolts,
Flanges, Polishing And Etc.; Complete In Place

SGMCW040507 900mm High railing comprising of 50mm diameter vertical


support, 50mm diameter top rail and 2 rows x 50mm diameter m 20 840.00 16,800.00
intermediate rails.

Finishes
18mm Thick Internal Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

SGMCW040508 To soffit of staircase; sloping over 15° from the horizontal. m2 10 25.76 257.60
SGMCW040509 To stringer sides of staircase; exceeding 250mm but not
exceeding 500mm high; sloping over 15° from horizontal. m 10 14.56 145.60
(350mm high)

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 17/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
18mm Thick External Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

SGMCW040510 To sides and soffit of landing slab. m2 5 25.76 128.80


SGMCW040511 To soffit of staircase; sloping over 15° from the horizontal.
m2 20 25.76 515.20

SGMCW040512 To stringer sides of staircase; exceeding 250mm but not


exceeding 500mm high; sloping over 15° from horizontal. m 10 14.56 145.60
(350mm high)

'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One


Coat of Alkali Resisting Sealer And Two Coats of 'Satin Gloss' Or
Equivalent Emulsion Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Internally

SGMCW040513 To plastered soffit of staircase; sloping over 15° from horizontal.


m2 7 20.16 141.12
SGMCW040514 To plastered stringer sides of staircase; exceeding 300mm wide;
sloping over 15° from horizontal. m2 2 20.16 40.32
'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally

SGMCW040515 To sides and soffit of landing slab. m2 5 21.28 106.40


SGMCW040516 To plastered soffit of staircase; sloping over 15° from horizontal.
m2 20 21.28 425.60
SGMCW040517 To plastered stringer sides of staircase; exceeding 300mm wide;
sloping over 15° from horizontal. m2 3 21.28 63.84
20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled
Finish To A Smooth And Level Surface; Internally
SGMCW040518 To undercut riser; 168.75mm high. m 25 14.56 364.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 18/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040519 To tread; 285mm wide. m 25 14.56 364.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 19/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040520 EXTRA OVER tread tiling works for 'Kimgress' or other approved
equivalent 300mm x 75mm x 7mm thick non-slip homogeneous m 25 29.12 728.00
nosing tile.

20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled


Finish To A Smooth And Level Surface; Externally
SGMCW040521 To undercut riser; 168.75mm high.
m 60 14.56 873.60

SGMCW040522 To tread; 285mm wide. m 60 14.56 873.60


SGMCW040523 EXTRA OVER tread tiling works for 'Kimgress' or other approved
equivalent 300mm x 75mm x 7mm thick non-slip homogeneous m 60 29.12 1,747.20
nosing tile.

6.0 EXTERNAL WALLS


Brickwall
Well Burnt Clay Bricks In Cement Mortar (1:3) Reinforced With
And Including 'EXMET' Reinforcement In Every Fourth Course;
6mm Diameter x 450mm Girth Mild Steel Bonding Tie Hooked
At Both Ends With One End Cast Into Concrete Column And The
Other End Anchored Into Brickwall

SGMCW040601 125mm Thick wall. m2 750 61.60 46,200.00


SGMCW040602 125mm Thick temporary wall; to cable trench. m2 5 61.60 308.00
SGMCW040603 225mm Thick wall. m2 65 123.20 8,008.00
Bituminous Sheet Damp Proof Course; Laid On Cement And
Sand (1:3) Mortar; Well Lapped At Joints And Intersections
(Measured Nett And No Allowance Made For Laps)

SGMCW040604 125mm Wide; laid horizontally. m 90 8.40 756.00


Railing
Stainless Steel Handrail; Cut, Welded, Framed Together And
Fixed Into Position Including All Shop And Site Connections,
Filing Smooth All Welded Junctions, Base Plates, Anchor Bolts,
Flanges, Polishing And Etc.; Complete In Place

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 20/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040605 1000mm High railing comprising of 50mm diameter vertical
support, 50mm diameter top rail and 2 rows x 50mm diameter m 40 862.40 34,496.00
intermediate rails.

SGMCW040606 1000mm High removable railing comprising of 50mm diameter


vertical support, 50mm diameter top rail and 2 rows x 50mm m 5 896.00 4,480.00
diameter intermediate rails.

Sundries
Precast Concrete Grade 30; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar;
Including All Necessary Fixing Accessories, Plastering And
Painting; Complete In Place

SGMCW040607 Hood on top of windows and doors. (measured horizontal


length on elevation) m 130 58.24 7,571.20
7.0 INTERNAL WALLS AND PARTITIONS
Brickwall
Well Burnt Clay Bricks In Cement Mortar (1:3) Reinforced With
And Including 'EXMET' Reinforcement In Every Fourth Course;
6mm Diameter x 450mm Girth Mild Steel Bonding Tie Hooked
At Both Ends With One End Cast Into Concrete Column And The
Other End Anchored Into Brickwall

SGMCW040701 125mm Thick wall. m2 160 56.00 8,960.00


SGMCW040702 225mm Thick wall. m2 40 106.40 4,256.00
Bituminous Sheet Damp Proof Course; Laid On Cement And
Sand (1:3) Mortar; Well Lapped At Joints And Intersections
(Measured Nett And No Allowance Made For Laps)

SGMCW040703 125mm Wide; laid horizontally. m 35 8.40 294.00


Railing
Stainless Steel Handrail; Cut, Welded, Framed Together And
Fixed Into Position Including All Shop And Site Connections,
Filing Smooth All Welded Junctions, Base Plates, Anchor Bolts,
Flanges, Polishing And Etc.; Complete In Place

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 21/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040704 1000mm High railing comprising of 50mm diameter vertical
support, 50mm diameter top rail and 2 rows x 50mm diameter m 55 862.40 47,432.00
intermediate rails.

SGMCW040705 1100mm High removable railing comprising of 50mm diameter


vertical support, 50mm diameter top rail and 2 rows x 50mm m 10 929.60 9,296.00
diameter intermediate rails.

8.0 EXTERNAL DOORS AND WINDOWS


External Doors
Solid (Grade A Hardwood) Weather Proof Swing Doors;
Complete With And Including Belian Door Frame, 1.2mm Thick
Mild Steel Door Jamb, Ironmongeries, Fixing Cramp, Palmet,
Architrave, Beading, Varnishing And Painting; Complete In Place

SGMCW040801 Single leaf door; overall size 900mm x 2100mm high; Type D1.
No 5 772.80 3,864.00
Fire Rated Doors; Complete With And Including Door Frame,
Ironmongeries, Panic Bar, Fixing Cramp, Palmet, Architrave,
Beading, Glazing Work, Varnishing And Painting; Complete In
Place And To BOMBA Requirement

SGMCW040802 Single leaf one hour fire rated door; overall size 900mm x
2100mm high; Type FD1. No 10 1,030.40 10,304.00
Proprietary Aluminium Roller Shutter Door; Complete With
Framing And All Standard Accessories To Be Installed In Strict
Compliance To Manufacturer's Instructions; Complete In Place

SGMCW040803 Motorised operated roller shutter; overall size 4000mm x


5000mm high in single panel; Type RS. No 1 10,304.00 10,304.00
SGMCW040804 Manual operated roller shutter; overall size 2500mm x 3000mm
high in single panel; Type RS1. No 1 2,464.00 2,464.00
Precast Concrete Grade 30 Lintel; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar

SGMCW040805 125mm x 200mm high lintel. m 15 64.96 974.40

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 22/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
External Windows

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 23/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
White Powder Coated Aluminium Framed Casement Windows;
Including Frames, Transomes, Mullions, Fixing Cramps, Gaskets,
Weatherstrips, Sealant, Glazing Beads, Brackets, Straps, Mastic,
Palmet, Fittings, Locks, Fasteners, Stays, Ironmongeries, 4mm
Thick Dark Green Tinted Glass, Fixing Accessories And All
Associated Works And Materials; Complete In Place

SGMCW040806 Overall size 1200mm x 600mm high; consisting of 2 nos. 600mm


x 600mm high top hung panels; Type W1. No 20 380.80 7,616.00
SGMCW040807 Overall size 1200mm x 1200mm high; consisting of 4 nos.
600mm x 600mm high top hung panel; Type W2. No 15 761.60 11,424.00
White Powder Coated Aluminium Louvre Windows; Consisting
of Aluminium Blades Fixed On And Including Louvre Holders,
Frame, All Necessary Fixing Accessories And Finishing; Complete
In Place; All As Shown And As Specified

SGMCW040808 Overall size 2400mm x 1000mm high; consisting of 4 nos.


600mm x 1000mm high fixed louvres portion; Type L1. No 5 627.20 3,136.00
SGMCW040809 Overall size 1200mm x 600mm high; consisting of 2 nos. 600mm
x 600mm high fixed louvres portion; Type L2. No 5 190.40 952.00
SGMCW040810 Overall size 600mm x 600mm high; consisting of 1 no. 600mm x
600mm high fixed louvres portion; Type L3. No 5 100.80 504.00
Hot Dipped Galvanised Window Grill; Complete With And
Including Frames; Complete In Place
SGMCW040811 To suit opening size 1200mm x 600mm. No 30 324.80 9,744.00
SGMCW040812 To suit opening size 1200mm x 1200mm. No 15 649.60 9,744.00
SGMCW040813 To suit opening size 2400mm x 1000mm. No 1 1,086.40 1,086.40
SGMCW040814 To suit opening size 600mm x 600mm. No 10 168.00 1,680.00
Sliding Aluminium Insect Screen; Including Frames, Netting And
All Necessary Fixing Accessories; Complete In Place
SGMCW040815 To suit opening size 1200mm x 600mm. No 25 61.60 1,540.00
SGMCW040816 To suit opening size 1200mm x 1200mm. No 15 123.20 1,848.00
SGMCW040817 To suit opening size 2400mm x 1000mm. No 5 206.08 1,030.40
SGMCW040818 To suit opening size 600mm x 600mm. No 5 31.36 156.80

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 24/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Glass Block Window
SGMCW040819 Overall size 2400mm x 1000mm. No 25 672.00 16,800.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 25/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Precast Concrete Grade 30 Lintel; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar

SGMCW040820 125mm x 200mm high lintel. m 30 64.96 1,948.80


Internal Windows
White Powder Coated Aluminium Louvre Windows; Consisting
of Aluminium Blades Fixed On And Including Louvre Holders,
Frame, All Necessary Fixing Accessories And Finishing; Complete
In Place; All As Shown And As Specified

SGMCW040821 Overall size 600mm x 600mm high; consisting of 1 no. 600mm x


600mm high fixed louvres portion; Type L3. No 1 100.80 100.80
Hot Dipped Galvanised Window Grill; Complete With And
Including Frames; Complete In Place
SGMCW040822 To suit opening size 600mm x 600mm. No 1 168.00 168.00
Sliding Aluminium Insect Screen; Including Frames, Netting And
All Necessary Fixing Accessories; Complete In Place
SGMCW040823 To suit opening size 600mm x 600mm. No 1 31.36 31.36
Precast Concrete Grade 30 Lintel; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar

SGMCW040824 125mm x 200mm high lintel. m 1 64.96 64.96


9.0 INTERNAL DOORS
Solid (Grade A Hardwood) Weather Proof Swing Doors;
Complete With And Including Belian Door Frame, 1.2mm Thick
Mild Steel Door Jamb, Ironmongeries, Fixing Cramp, Palmet,
Architrave, Beading, Varnishing And Painting; Complete In Place

SGMCW040901 Single leaf door; overall size 900mm x 2100mm high; Type D1.
No 3 772.80 2,318.40
SGMCW040902 Single leaf door; overall size 800mm x 2100mm high; Type D2.
No 2 358.40 716.80

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 26/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Fire Rated Doors; Complete With And Including Door Frame,
Ironmongeries, Panic Bar, Fixing Cramp, Palmet, Architrave,
Beading, Glazing Work, Varnishing And Painting; Complete In
Place And To BOMBA Requirement

SGMCW040903 Single leaf one hour fire rated door; overall size 900mm x
2100mm high; Type FD1. No 2 1,030.40 2,060.80
SGMCW040904 Double leaf equal panels one hour fire rated door; overall size
1800mm x 2100mm high; Type FD2. No 1 2,587.20 2,587.20
Precast Concrete Grade 30 Lintel; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar

SGMCW040905 125mm x 200mm high lintel. m 15 64.96 974.40


Precast Concrete Grade 30 Heel Stone; Including All Formwork,
Reinforcement; Setting In Position And Bedding In Cement (1:3)
Mortar

SGMCW040906 125mm x 125mm x 150mm high heelstone cast to suit profile of


door frame with and including steel dowel, one end cast into No 4 54.88 219.52
concrete and the other into foot of door frame.
10.0 INTERNAL WALL FINISHES
18mm Thick Internal Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

SGMCW041001 To sides of walls and columns, sides and soffit of associated


beams. m2 1,110 28.00 31,080.00
18mm Thick Cement And Sand (1:3) Screed
SGMCW041002 To sides of walls and columns, sides and soffit of associated
beams; to receive ceramic tiles (measured separately). m2 45 28.00 1,260.00
SGMCW041003 To sides of walls and columns, sides and soffit of associated
beams; to receive non-slip homogeneous tiles (measured m2 400 28.00 11,200.00
separately).

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 27/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
300mm x 300mm x 6mm Thick 'Kimgress' Or Other Approved
Equivalent Ceramic Wall Tiles of Approved Colour; Cut And Laid
To Approved Pattern; Bedded In Cement And Sand (1:3) Mortar
And Cement And Sand (1:3) Screed (Measured Separately);
Pointed In Neat Matching Colour Cement -

SGMCW041004 To sides of walls and columns, sides and soffit of associated


beams. m2 45 81.76 3,679.20
300mm x 300mm x 7mm Thick 'Kimgress' Or Other Approved
Equivalent Homogeneous Wall Tiles of Approved Colour; Cut
And Laid To Approved Pattern; Bedded In Cement And Sand
(1:3) Mortar And Cement And Sand (1:3) Screed (Measured
Separately); Pointed In Neat Matching Colour Cement -

SGMCW041005 To sides of walls and columns, sides and soffit of associated


beams. m2 400 90.72 36,288.00
'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of 'Satin Gloss' Or
Equivalent Emulsion Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Internally -

SGMCW051006 Plastered sides of walls and columns, plastered sides and soffit
of associated beams. m2 1,200 20.16 24,192.00
11.0 INTERNAL FLOOR FINISHES
20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled
Finish To A Smooth And Level Surface -
SGMCW041101 To floor. m2 410 28.00 11,480.00
SGMCW041102 EXTRA OVER tread tiling works for 'Kimgress' or other approved
equivalent 300mm x 75mm x 7mm thick non-slip homogeneous m 10 29.12 291.20
nosing tile.

18mm Thick Cement And Sand (1:3) Screed


SGMCW041103 To floor; to receive non-slip homogeneous tiles (measured
separately). m2 70 24.64 1,724.80

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 28/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041104 To drop; 50mm high; to receive non-slip homogeneous tiles
(measured separately). m 2 12.32 24.64
SGMCW041105 To floor; to receive polyvinyl tiles (measured separately). m2 200 24.64 4,928.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 29/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041106 To drop; 100mm high; to receive polyvinyl tiles (measured
separately). m 5 12.32 61.60
SGMCW041107 To skirting; 100mm high; to receive polyvinyl tiles (measured
separately). m 90 12.32 1,108.80
SGMCW041108 To floor; to receive epoxy paint (measured separately). m2 190 24.64 4,681.60
SGMCW041109 To drop; 100mm high; to receive epoxy paint (measured
separately). m 1 12.32 12.32
300mm x 300mm x 7mm Thick 'Kimgress' Or Other Approved
Equivalent Non-Slip Homogeneous Floor Tiles of Approved
Colour; Cut And Laid To Approved Pattern; Bedded In Cement
And Sand (1:3) Mortar And Cement And Sand (1:3) Screed
(Measured Separately); Pointed In Neat Matching Colour
Cement

SGMCW041110 To floor. m2 70 105.28 7,369.60


SGMCW041111 To drop; 50mm high. m 2 26.88 53.76
'Armstrong' Or Other Approved Equivalent Polyvinyl Tiles; 2mm
Thick With And Including Adhesive, Self-Levelling Compound
And Heat Welding All Seams And Joints With Welding Rod; All
To Manufacturer's Details And Specification

SGMCW041112 To floor. m2 200 201.60 40,320.00


SGMCW041113 To drop; 100mm high. m 5 22.40 112.00
SGMCW041114 To skirting; 100mm high. m 90 22.40 2,016.00
Approved Epoxy Paint Floor Finish In Accordance To
Manufacturer's Details And Specification
SGMCW051115 To floor. m2 190 33.60 6,384.00
SGMCW051116 To drop; 100mm high. m 1 16.80 16.80
12.0 INTERNAL CEILING FINISHES
18mm Thick Internal Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 30/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041201 To soffit of suspended slab, sides and soffit of associated
beams; not exceeding 3.50m high. m2 430 28.00 12,040.00
600mm x 600mm x 9.5mm Thick Gypsum Board Ceiling; On And
Including Suspended Aluminium 'T' Frame -

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 31/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041202 To Ceiling; not exceeding 3.50m high. m2 240 64.96 15,590.40
'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of 'Satin Gloss' Or
Equivalent Emulsion Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Internally

SGMCW041203 Plastered soffit of suspended slab, sides and soffit of abutting


beams; not exceeding 3.50m high. m2 430 20.16 8,668.80
SGMCW041204 Surfaces of gypsum board ceiling; not exceeding 3.50m high.
m2 240 20.16 4,838.40
13.0 EXTERNAL FINISHES
External Wall Finishes
18mm Thick External Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

SGMCW041301 To sides of walls and columns, sides and soffit of associated


beams. m2 1,200 29.12 34,944.00
'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally

SGMCW041302 Plastered sides of walls and columns, plastered sides and soffit
of associated beams. m2 1,200 21.28 25,536.00
External Floor Finishes -
20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled
Finish To A Smooth And Level Surface; Externally
SGMCW041303 To floor. m2 250 28.00 7,000.00
SGMCW041304 To drop; 100mm high. m 130 14.56 1,892.80
External Ceiling Finishes

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 32/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
18mm Thick External Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 33/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041305 To soffit of suspended slab, sides and soffit of associated
beams; not exceeding 3.50m high. m2 70 29.12 2,038.40
0.48mm BMT (0.54mm TCT) 'Clean Colorbond Presta-C' Panel
Ceiling Or Other Approved Equivalent Metal Strip Ceiling;
Complete With 'Truecore' Or Other Approved Equivalent Steel
Support Framings And Subframes; Including All Necessary Fixing
Accessories, Connection Accessories, Fasteners And Screws;
Laid In Strict Accordance With Manufacturer's Specifications
And Instruction

SGMCW041306 To Ceiling; 5.80m high. m2 100 188.16 18,816.00


SGMCW041307 To Ceiling; at 15° pitch; 6.575m to 8.357m high. m2 40 188.16 7,526.40
SGMCW041308 To Ceiling; 13.50m high. m2 140 188.16 26,342.40
SGMCW041309 To Ceiling; at 15° pitch; 14.275m to 15.789m high. m2 60 188.16 11,289.60
'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally

SGMCW051310 Plastered soffit of suspended slab, sides and soffit of abutting


beams; not exceeding 3.50m high. m2 70 21.28 1,489.60
14.0 SANITARY FITTINGS
Sanitary Ware And Fittings Including All Fixing Accessories,
Sorting, Assembling, Bedding, Plugging, Screwing, Cutting And
Pinning, Jointing And Making Good Disturbed Area And -
Connecting To Services Inlet/Outlet

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 34/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041401 'Claytan' or other equal and approved pedestal water closet
flush valve suites; white vitreous China pan; complete with light
duty seat and cover, flush valve system without pump, push
button, vacuum breaker, elbow flush connection, adjustable
tailpiece, dual filtered, one flush depress and hold feature,
exposed parts hard chrome plated pan with S or T trap No 1 675.36 675.36
conversion bend; setting pan in tiled concrete floor.

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 35/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041402 'Claytan' or other equal and approved wash hand basins, white
glazed vitreous china complete with 12mm diameter chrome
plated "elbow action" tap, one blank tap hole stopper, 31mm
diameter chromium plated waste outlet fitting with plug, chain
& stay, 31mm diameter bottle trap with 75mm deep seal
including jointing outlet to waste pipe 560mm x 410mm fixing No 2 398.72 797.44
brackets with screws, sealing at back with mastic sealant.

SGMCW051403 Chromium plated inclined shower fittings for cold water only,
comprising 13mm diameter stop cock in chrome plated with
wall flanged, 15mm diameter riser pipe with 100mm diameter
shower rose pipe swivel joint and fixed to tile wall. No 1 109.76 109.76

SGMCW051404 100mm Diameter uPVC floor trap with openable grating and
frame set into concrete floor and finish flush with floor finish. No 5 23.52 117.60

SGMCW041405 'Claytan' or other equal and approved paper holder complete


with roller fixed to and including forming recess in tiled wall. No 1 31.36 31.36

SGMCW041406 500mm x 750mm glass mirror with bevelled edge; mounted on


and fixed with and including 6mm thick waterproof plywood
backing, 12mm x 12mm natural anodised aluminium angle
framing all round and chromium plated dome head fixing No 1 201.60 201.60
screws and cork washes.

Testing
SGMCW041407 On completion of the installation of sanitary fittings, test all the
apparatus, piping and fittings and make good any defects and
leave the whole in perfect working order to the satisfaction of Item - 2,240.00
the Architect or Engineer.

15.0 SUNDRIES
Anti-Intrusion Security Grill; made of 16mm Diameter Mild
Steel Bars All Welded Together At 40mm c/c; Cast Into Concrete
Slab

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 36/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041501 To cable trench. m2 5 302.40 1,512.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 37/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Metal Edging On Concrete Slab To Receive Chequer Plate Cover
(Measured Separately)
SGMCW041502 50mm x 50mm x 3mm Thick x 2.33kg/m galvanised angle with
25mm x 3mm fishtail plate welded to angles at 300mm c/c. m 140 56.00 7,840.00

Galvanised Mild Steel Chequer Plate Cover -


SGMCW041503 380mm Wide x 6mm thick; complete with 8mm diameter
galvanised mild steel lifting lug. m2 10 739.20 7,392.00
SGMCW041504 480mm Wide x 6mm thick; complete with 8mm diameter
galvanised mild steel lifting lug. m2 20 739.20 14,784.00
SGMCW041505 580mm Wide x 6mm thick; complete with 8mm diameter
galvanised mild steel lifting lug. m2 5 739.20 3,696.00
SGMCW041506 Logo & Lettering. Item - 11,200.00 11,200.00
16.0 CAT LADDER
SGMCW041601 Galvanised cat ladder cum safety cage and maintenance
platform; 11.9m high; including all necessary fixing accessories;
all welded and bolted together including shop and site works,
fabrication, transportation, erection, welding, filling smooth kg 5,000 15.00 75,000.00
junction as specified.

17.0 BUILDER'S WORK IN CONNECTION WITH SERVICES -


SGMCW041701 Allow for all necessary builder's works in connection with
mechanical and electrical services which shall include, but not
limited to; forming openings through walls, floors and roof for
mechanical and electrical fittings and services; provision pipe
sleeves; patching up and making good all affected areas to the Item - 33,600.00 33,600.00
satisfaction of the S.O., all as shown and/or specified in
Mechanical and Electrical drawings.

18.0 GANTRY CRANE SUPPORT STRUCTURE -


SGMCW041801 Rolled mild steel in universal beams, plates, etc. including
cutting, drilling, assembling, welding, rivetting, bolting etc. kg 3,000 10.304 30,912.00

Supply and fix the following mild steel bolts complete with nuts
and washers:-

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 38/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041802 12mm to 20mm (Grade 8.8) kg 50 17.36 868.00
SGMCW041803 Compliance with other Terms and Conditions of Contract not
covered by any item in the Summary of Tender.
i) -
ii) -
iii) -
TOTAL AMOUNT OF SECTION 04: 1,852,154.00
CARRIED FORWARD TO SUMMARY OF PRICE

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S04 : 39/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 33kV Substation


SECTION 04 - 33KV CONTROL BUILDING

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
1.0 WORK BELOW LOWEST FLOOR FINISHES
SGMCW040101 Excavate, Get Out, Part Return, Fill In, Well Compacted And
Level, Grade, Ram And Trim Bottom And Sides of Excavation;
Including Planking And Strutting, Working Around Piles With
Care for pilecaps, stumps,cable sumps and other related works. m3 135 25.87 3,492.45

SGMCW040102 Load and cart away from site all surplus excavated materials to
Contractor's own dump site. LS 120 21.73 2,607.60
Waterproofing System
Single Layer 0.2mm Thick Translucent Polythene Damp Proof
Membrane; With Minimum 150mm Lap At Joint And Tapped
With Approved Double Sided Tape (Measured Nett And No -
Allowance Made For Laps) to all soft fit of ground slabs

Approved Cementitious Water Proofing System And Protective


Coating; Works To Be Carried Out By Qualified Installer And
Approved Applicator To Waterproofing Producer's Details And -
Instructions:-

SGMCW040103 To ground slabs. m2 125 8.40 1,050.00


SGMCW040106 Prepare And Apply Approved Waterproofing System All In
Accordance With The Manufacturer'S Instructions And
Recommendation to external surfaces of cable trench wall, base m2 61 -
and ramp slab.

Concrete Works
Note:

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 40/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where -
required.

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 41/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040107 Lean Concrete Grade 15; Not Exceeding 100mm Thick Blinding
under pilecaps, ground beams, ground slabs and under cable m3 35 18.59 650.65
trench.

SGMCW040108 Vibrated Reinforced Concrete Grade 30 for Pilecaps, Ground


Beams, Ground Slabs not exceeding 150mm and cable trenches m3 132 443.74 58,573.68

Stumps. (Provisional)
SGMCW040109 Mass Concrete Grade 20 for stumps. m3 8 384.72 3,077.76
Formwork to Stump m2 24 49.28 1,182.72
Reinforcement Works
High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2 for pile caps, ground beams, ground slabs and LS
cable trench

Stumps (Provisional)
SGMCW040110 10mm Diameter bar; as links. kg 120 4.37 524.40
SGMCW040111 16mm Diameter bar. kg 200 4.14 828.00
SGMCW040112 20mm Diameter bar. kg 95 4.14 393.30
SGMCW040113 25mm Diameter bar. kg 1,200 4.14 4,968.00
Formwork
SGMCW040114 Formwork To Reinforced Concrete Works; Class F1 to sides of
pile caps, to sides of ground beams, to edges of ground slabs;
not exceeding 200mm deep. (50mm thick),to edges of topping-
up slab; not exceeding 250mm deep. (50mm thick) and to sides m2 970 49.28 47,801.60
of cable trench.

33/11kV Cable Sleeves and Earthing Pipe Sleeves


Supply and deliver to store/pipe dumps on site pipes including
all related works for pipes HDPE Pipes (red marking).

SGMCW040115 110mm OD HDPE Pipe PN 8 m 250 20.16 5,040.00


SGMCW040116 160mm OD HDPE Pipe PN 8 m 200 23.18 4,636.00
SGMCW040117 160mm OD HDPE Pipe PN 10 m 150 23.18 3,477.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 42/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
2.0 FRAME
Concrete Works
Note:

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 43/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where
required.

SGMCW040201 Vibrated Reinforced Concrete Grade 30 for column, stiffeners,


suspended floor beams and roof beams m3 90 458.42 41,257.80
Reinforcement Works
SGMCW040202 Mild Steel Reinforcement Bar With Yield Strength of 250N/mm2
for Stiffeners kg 200 4.37 874.00
SGMCW040203 High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2 for columns, Stiffeners, suspended floor beams kg 13,100 4.37 57,247.00
and roof beams

Formwork
SGMCW040204 Formwork To Reinforced Concrete Works; to sides of column, to
sides of stiffeners, to sides and soffit of suspended floor beams;
with strutting not exceeding 3.50m high, to sides and soffit of
roof beams; with strutting not exceeding 3.50m high. m2 2,000 50.62 101,240.00

3.0 UPPER FLOORS


Concrete Works
Note:
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where -
required.
SGMCW040301 Vibrated Reinforced Concrete Grade 30 for suspended floor
slabs; exceeding 50mm but not exceeding 150mm thick. m3 56 53.76 3,010.56

Reinforcement Works
SGMCW040302 High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2 in suspended Floor Slabs kg 5,000 4.37 21,850.00
Formwork

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 44/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040305 Formwork To Reinforced Concrete Works; Class F2To soffit of
suspended floor slabs not exceeding 200mm thick; with
strutting not exceeding 3.50m high, to edges of suspended floor m2 600 53.76 32,256.00
slabs; not exceeding 250mm deep. (125mm thick)

4.0 ROOF

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 45/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Roof Structure
SGMCW040401 Design, Construction And Completion of 'EcoSteel Truecore' Or
Other Approved Equivalent Proprietary Steel Truss System;
Including Purlins, battens, Screws, Connection Plates, m2 670 118.72 79,542.40
Accessories And Painting .

Roof Covering
SGMCW040402 0.48mm BMT (0.54mm TCT) 'Clean Colorbond KLIP LOK' Or
Other Approved Equivalent Metal Roofing Sheet; Laid In Strict
Accordance With Manufacturer's Specifications And Instruction
Including All Necessary Fixing Accessories, Concealed Clips, m2 670 106.40 71,288.00
Fasteners And Screws.

Insulation Works
SGMCW040404 Layer of 8mm thick of Polynum Big resilient thermal insulating
or approved equivalent air-bubble faced with and including
double sided approved fire rated aluminium foil complete with
reinforced net; laid over wire mesh, lapped minimum 150mm at m2 800 33.60 26,880.00
joints and sealed with and including adhesive jointing tape of
similar material.

SGMCW040405 Layer of 50mm x 50mm x 2mm diameter galvanised steel wire


mesh; lapped 150mm at joint and secured to roof framing. m2 800 5.60 4,480.00
(measure nett and no allowance made for laps)

0.48mm BMT (0.53mm TCT) 'To match existing building'


'Lysaght', 'UGI' Or Other Approved Equivalent Metal Sheet; Cut
And Bent To Required Shape And Profile; Well Lapped And
Jointed; Including All Necessary Fixing Accessories, Holders,
Hangers, Brackets, Steel Framing, Supports, Fastener And
Screws (Measured Nett And No Allowance Made For Laps)

SGMCW040406 Gutter; 300mm x 300mm; fixed to fascia board or secured to


steel roof truss. m 37 118.72 4,392.64

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 46/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040407 EXTRA OVER gutter for stop end. no 3 39.20 117.60
UPVC Pipe Works And Fittings; With And Including All
SGMCW040408 Necessary Fixing Accessories,
100mm Diameter Holding encased
rainwater downpipe Clips, Jointed With And
in columns. no 203 41.44 8,412.32
Including Approved Solvent; All In Accordance With The
SGMCW040409 EXTRA OVER 100mm
Manufacturer's diameterAnd
Specification downpipe for swan neck.
Instructions no 10 16.46 164.60
SGMCW040410 EXTRA OVER 100mm diameter downpipe for 90° bend. no 25 20.16 504.00
SGMCW040411 EXTRA OVER 100mm diameter downpipe for 45° bend. no 50 20.16 1,008.00
SGMCW040412 EXTRA OVER 100mm diameter downpipe for shoes. no 11 22.40 246.40
SGMCW040413 Dome grating cover including water proofing works. no 13 42.56 553.28
Extra over roofing sheet shelf to exhaust fan no 10 42.56 425.60
5.0 STAIRCASE
Concrete Works
Note:
Prices/rates for concrete shall be deemed to include the
addition of super-plasticizer admixture at location where
required.

SGMCW040501 Vibrated Reinforced Concrete Grade 30 for Staircase m3 4 465.92 1,863.68


Reinforcement Works
SGMCW040502 High Tensile Deformed Reinforcement Bar With Yield Strength
of 460N/mm2 for Staircase kg 568 4.37 2,482.16
Formwork
SGMCW040503 Formwork To Reinforced Concrete Works; Class F2 To sides and
soffit of landing slab, to soffit of staircase; sloping over 15° from
the horizontal. to sides of undercut riser; not exceeding 250mm m2 74 53.76 3,978.24
high, to stringer sides of staircase; exceeding 250mm but not
exceeding 500mm high; sloping over 15° from horizontal.
(350mm high)
Handrail
Stainless Steel Handrail; Cut, Welded, Framed Together And
Fixed Into Position Including All Shop And Site Connections,
Filing Smooth All Welded Junctions, Base Plates, Anchor Bolts,
Flanges, Polishing And Etc.; Complete In Place

SGMCW040504 900mm High railing comprising of 50mm diameter vertical


support, 50mm diameter top rail and 2 rows x 50mm diameter m 30 840.00 25,200.00
intermediate rails.

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 47/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Finishes

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 48/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040506 18mm Thick External Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On to sides and soffit of landing slab, To soffit of staircase;
sloping over 15° from the horizontal, To stringer sides of m2 72 28.00 2,016.00
staircase; exceeding 250mm but not exceeding 500mm high;
sloping over 15° from horizontal.

SGMCW040508 'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One


Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally m2 42 20.16 846.72

SGMCW040509 20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled
Finish To A Smooth And Level Surface m2 167 21.28 3,553.76
6.0 EXTERNAL WALLS
Brickwall
SGMCW040601 Well Burnt Clay Bricks In Cement Mortar (1:3) Reinforced With
And Including 'EXMET' Reinforcement In Every Fourth Course;
6mm Diameter x 450mm Girth Mild Steel Bonding Tie Hooked
At Both Ends With One End Cast Into Concrete Column And The m2 396 61.60 24,393.60
Other End Anchored Into Brickwall

SGMCW040602 Bituminous Sheet Damp Proof Course; Laid On Cement And


Sand (1:3) Mortar; Well Lapped At Joints And Intersections m 49 10.08 493.92
Sundries
Aluminium air con grill kg 150 15.00 2,250.00
7.0 INTERNAL WALLS AND PARTITIONS
Brickwall

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 49/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040701 Well Burnt Clay Bricks In Cement Mortar (1:3) Reinforced With
And Including 'EXMET' Reinforcement In Every Fourth Course;
6mm Diameter x 450mm Girth Mild Steel Bonding Tie Hooked
At Both Ends With One End Cast Into Concrete Column And The m2 583 56.00 32,648.00
Other End Anchored Into Brickwall

SGMCW040702 Bituminous Sheet Damp Proof Course; Laid On Cement And


Sand (1:3) Mortar; Well Lapped At Joints And Intersections m 49 10.08 493.92

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 50/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
8.0 DOORS AND WINDOWS
Doors
SGMCW040801 Solid (Grade A Hardwood) Weather Proof Swing Doors;
Complete With And Including Belian Door Frame, 1.2mm Thick No 20 772.80 15,456.00
Mild Steel Door Jamb, Ironmongeries, Fixing Cramp, Palmet,
Architrave, Beading, Varnishing And Painting; Complete In Place
SGMCW040802 Proprietary Aluminium Roller Shutter Door; Complete With
Framing And All Standard Accessories To Be Installed In Strict
Compliance To Manufacturer's Instructions; Complete In Place No 5 10,304.00 51,520.00

SGMCW040803 Precast Concrete Grade 30 Lintel; Including All Formwork,


Reinforcement, Dowel Bars; Hoisting And Fixing In Position;
Bedding, Jointing And Pointing In Cement (1:3) Mortar m 8 64.96 519.68

SGMCW040804 Precast Concrete Grade 30 Heel Stone; Including All Formwork,


Reinforcement; Setting In Position And Bedding In Cement (1:3) no 30 54.88 1,646.40
Mortar

External Windows
SGMCW040804 White Powder Coated Aluminium Framed Casement Windows;
Including Frames, Transomes, Mullions, Fixing Cramps, Gaskets,
Weatherstrips, Sealant, Glazing Beads, Brackets, Straps, Mastic,
Palmet, Fittings, Locks, Fasteners, Stays, Ironmongeries, 4mm
Thick Dark Green Tinted Glass, Fixing Accessories And All No 25 761.60 19,040.00
Associated Works And Materials; Complete In Place

SGMCW040806 White Powder Coated Aluminium Louvre Windows; Consisting


of Aluminium Blades Fixed On And Including Louvre Holders,
Frame, All Necessary Fixing Accessories And Finishing; Complete No 11 627.20 6,899.20
In Place; All As Shown And As Specified

SGMCW040807 Hot Dipped Galvanised Window Grill; Complete With And


Including Frames; Complete In Place to suit all openings No 36 649.60 23,385.60

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 51/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040808 Sliding Aluminium Insect Screen; Including Frames, Netting And
All Necessary Fixing Accessories; Complete In Place to suit all No 36 206.08 7,418.88
openings

SGMCW040809 All Glass Block Windows as per drawings No 36 672.00 24,192.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 52/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW040810 Precast Concrete Grade 30 Lintel; Including All Formwork,
Reinforcement, Dowel Bars; Hoisting And Fixing In Position; m 29 64.96 1,883.84
Bedding, Jointing And Pointing In Cement (1:3) Mortar
9.0 INTERNAL WALL FINISHES
SGMCW040901 18mm Thick Internal Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On to sides of walls and columns, sides and soffit of m2 714 28.00 19,992.00
associated beams.

SGMCW040902 18mm Thick Cement And Sand (1:3) Screed To sides of walls and
columns, sides and soffit of associated beams; to receive
ceramic tiles (measured separately), and to sides of walls and
columns, sides and soffit of associated beams; to receive non- m2 54 28.00 1,512.00
slip homogeneous tiles.

SGMCW040903 300mm x 300mm x 6mm Thick 'Kimgress' Or Other Approved


Equivalent Ceramic Wall Tiles of Approved Colour; Cut And Laid
To Approved Pattern; Bedded In Cement And Sand (1:3) Mortar
And Cement And Sand (1:3) Screed (Measured Separately);
Pointed In Neat Matching Colour Cement to sides of walls and m2 22 81.76 1,798.72
columns, sides and soffit of associated beams.

SGMCW040904 300mm x 300mm x 7mm Thick 'Kimgress' Or Other Approved


Equivalent Homogeneous Wall Tiles of Approved Colour; Cut
And Laid To Approved Pattern; Bedded In Cement And Sand
(1:3) Mortar And Cement And Sand (1:3) Screed (Measured m2 63 90.72 5,715.36
Separately); Pointed In Neat Matching Colour Cement

SGMCW040905 'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One


Coat of Alkali Resisting Sealer And Two Coats of 'Satin Gloss' Or
Equivalent Emulsion Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Internally m2 595 20.16 11,995.20

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 53/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
10.0 INTERNAL FLOOR FINISHES

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 54/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041002 18mm Thick Cement And Sand (1:3) Screed to floor; to receive
non-slip homogeneous tiles, to drop; 50mm high; to receive
non-slip homogeneous tiles, to floor; to receive polyvinyl tiles,
to drop; 100mm high; to receive polyvinyl tiles, to skirting;
100mm high; to receive polyvinyl tiles, to floor; to receive m2 32 18.48 591.36
epoxy paint and to drop; 100mm high; to receive epoxy paint

SGMCW041003 300mm x 300mm x 7mm Thick 'Kimgress' Or Other Approved


Equivalent Non-Slip Homogeneous Floor Tiles of Approved
Colour; Cut And Laid To Approved Pattern; Bedded In Cement
And Sand (1:3) Mortar And Cement And Sand (1:3) Screed ;
Pointed In Neat Matching Colour Cement, to floor and to drop; m2 25 105.28 2,632.00
50mm high.

SGMCW041005 Approved Epoxy Paint Floor Finish In Accordance To


Manufacturer's Details And Specification to floor and to drop. m2 333 33.60 11,188.80

SGMCW041006 Cement screed (Power Float Finish) for Cable compartment,


building apron slab, and all other areas which are not specified m2 520 20.16 10,483.20
above.

11.0 INTERNAL CEILING FINISHES


SGMCW041101 18mm Thick Internal Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key On To soffit of suspended slab, sides and soffit of associated m2 534 28.00 14,952.00
beams; not exceeding 3.50m high

SGMCW041102 600mm x 600mm x 9.5mm Thick Gypsum Board Ceiling; On And


Including Suspended Aluminium 'T' Frame To Ceiling; not m2 365 64.96 23,710.40
exceeding 3.50m high.

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 55/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041103 'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One
Coat of Alkali Resisting Sealer And Two Coats of 'Satin Gloss' Or
Equivalent Emulsion Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Internally m2 712 20.16 14,353.92

12.0 EXTERNAL FINISHES

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 56/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
External Wall Finishes
SGMCW041201 18mm Thick External Plastering Consisting of Two Coats of
Cement And Sand (1:3) Finished With Steel Float And Including
Raking Out Joints of Brickwall Or Hacking Concrete Surfaces For
Key to sides of walls and columns, sides and soffit of associated m2 355 29.12 10,337.60
beams.

SGMCW041202 'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One


Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally m2 383 21.28 8,150.24

External Floor Finishes


SGMCW041204 20mm Thick Cement And Sand (1:3) Screed; Steel Trowelled
Finish To A Smooth And Level Surface; Externally to floor and to m2 134 33.60 4,502.40
drop

External Ceiling Finishes


SGMCW041206 0.48mm BMT (0.54mm TCT) 'Clean Colorbond Presta-C' Panel
Ceiling Or Other Approved Equivalent Metal Strip Ceiling;
Complete With 'Truecore' Or Other Approved Equivalent Steel
Support Framings And Subframes; Including All Necessary Fixing
Accessories, Connection Accessories, Fasteners And Screws;
Laid In Strict Accordance With Manufacturer's Specifications m2 87 188.16 16,369.92
And Instruction

SGMCW041207 'ICI', 'Kansai', 'Nippon' Or Other Approved Equivalent Paint; One


Coat of Alkali Resisting Sealer And Two Coats of Weather
Resistance Acrylic Paint Including Surface Preparation; All In
Strict Compliance To Manufacturer's Instruction; Externally m2 18 21.28 383.04

13.0 SANITARY FITTINGS

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 57/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
Sanitary Ware And Fittings Including All Fixing Accessories,
Sorting, Assembling, Bedding, Plugging, Screwing, Cutting And
Pinning, Jointing And Making Good Disturbed Area And
Connecting To Services Inlet/Outlet

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 58/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041301 Claytan' or other equal and approved pedestal water closet
flush valve suites; white vitreous China pan; squat type, flush
valve system without pump, flexible hose, swivel wall tap, soap
holder, flush lever, vacuum breaker, flushes, squat pan; setting no 1 675.36 675.36
pan in tiled concrete floor.

SGMCW041302 Claytan' or other equal and approved wash hand basins, white
glazed vitreous china complete with 12mm diameter chrome
plated "elbow action" tap, ceramic soap holder, one blank tap
hole stopper, 31mm diameter chromium plated waste outlet
fitting with plug, chain & stay, 31mm diameter bottle trap with
75mm deep seal including jointing outlet to waste pipe 560mm no 1 398.72 398.72
x 410mm fixing brackets with screws, sealing at back with
mastic sealant.

SGMCW041303 100mm Diameter uPVC floor trap with openable grating and
frame set into concrete floor and finish flush with floor finish. no 4 23.52 94.08

SGMCW041304 Kimware' or other equal and approved paper holder complete


with roller fixed to and including forming recess in tiled wall. no 1 31.36 31.36

Testing
SGMCW041306 On completion of the installation of sanitary fittings, test all the
apparatus, piping and fittings and make good any defects and
leave the whole in perfect working order to the satisfaction of LS - 2,000.00 2,000.00
the Architect or Engineer.

14.0 SUNDRIES
SGMCW041401 Anti-Intrusion Security Grill; made of 16mm Diameter Mild
Steel Bars All Welded Together At 40mm c/c; Cast Into Concrete m2 4 302.40 1,209.60
Slab to cable trench.

SGMCW041402 "Sarawak Energy" Logo with painted finish as shown in Tender


Drawing and Specifications No 1 10,000.00 10,000.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 59/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041403 Substation name with painted finish as shown in Tender
Drawing and Specifications No 1 -

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 60/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)
SGMCW041404 Supply one (1) unit of writing table (model PB 1570: dimension
WxDxH 1500mmx700mmx750mm; grey colour), fixed pedestal
(model: PB FP [3D]: dimension WxDxH:
396mmx496mmx480mm; grey colour), and medium black chair
(model: GI 280E) or equivalent to be allocated in the control No 1 -
room.

Six (6) nos. of stainless steel room signage as shown in Tender


Drawings:-
SGMCW041405 One (1) no for Cable Compartment No 1 100.00 100.00
SGMCW041406 One (1) no for 11kV Switchgear room No 1 100.00 100.00
SGMCW041407 One (1) no for 33kV Switchgear room No 1 100.00 100.00
SGMCW041408 One (1) no for Control Room No 1 100.00 100.00
SGMCW041409 One (1) no for Battery Room No 1 100.00 100.00
SGMCW041410 One (1) no for for toilet No 1 100.00 100.00
15.0 BUILDER'S WORK IN CONNECTION WITH SERVICES
SGMCW041501 Allow for all necessary builder's works in connection with
mechanical and electrical services which shall include, but not
limited to; forming openings through walls, floors and roof for
mechanical and electrical fittings and services; provision pipe
sleeves; patching up and making good all affected areas to the LS -
satisfaction of the S.O., all as shown and/or specified in
Mechanical and Electrical drawings.

SGMCW041502 Compliance with other Terms and Conditions of Contract not


covered by any item in the Summary of Tender.
i) -
ii) -
iii) -
TOTAL AMOUNT OF SECTION 04: 1,019,912.24
CARRIED FORWARD TO SUMMARY OF PRICE

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S0433kv : 61/82
PLS-140032
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 33kV Substation


SECTION 05 - OUTDOOR FOUNDATION, TRENCHES & OIL INTERCEPTOR (ALL PROVISIONAL)
BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

1.0 WORK BELOW LOWEST FLOOR LEVEL (ALL PROVISIONAL)

EXCAVATE, GET OUT, PART RETURN, LEVEL, GRADE AND RAM


BOTTOM, TRIM SIDES AND INCLUDING PLANKING AND STRUTTING

Commencing from platform level


SGMCW050101 Excavate for switch yard equipment foundations with maximum m3 110 22.96 2,525.60
depth not exceeding 1.50m deep
SGMCW050102 Excavate for trench base with maximum depth not exceeding 1.5m m3 600 22.96 13,776.00
deep
SGMCW050103 Excavate for trench base with maximum depth not exceeding 2.0m m4 460 25.87 11,900.20
deep
SGMCW050104 Excavate for transformer base with maximum depth not exceeding m3 260 25.87 6,726.20
2.0m deep
SGMCW050105 Excavate for oil interceptor and oil interceptor sump with maximum m3 180 25.87 4,656.60
depth not exceeding 3.00m deep
SGMCW050106 Excavate for switchyard equipment foundation with maximum m3 1050 25.87 27,163.50
depth not exceeding 2.5m deep
SGMCW050107 Excavate for earth mast and gantry foundation with maximum m3 610 25.87 15,780.70
depth not exceeding 2.5m deep
Commencing from reduced level

DISPOSAL OF SURPLUS EXCAVATED MATERIAL


SGMCW050108 Load and cart away from site to Contractor's own dump m3 1100 21.73 23,903.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S05 : 62/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

LEAN CONCRETE GRADE 15 BLINDING WITH SURFACE FINISHED


LEVEL TO RECEIVE CONCRETE INCLUDING WHERE NECESSARY
TRIMMING BASE OF EXCAVATION

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S05 : 63/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

SGMCW050109 Not exceeding 50mm thick under switchyard equipment plinth m2 1050 18.59 19,519.50

SGMCW050110 Not exceeding 50mm thick under trench base m2 800 18.59 14,872.00

SGMCW050111 Not exceeding 50mm thick under transformer base m2 90 18.59 1,673.10

SGMCW050112 Not exceeding 50mm thick under oil interceptor and sump base m2 80 18.59 1,487.20

SGMCW050114 Not exceeding 50mm thick under earth mast and gantry foundation m2 300 18.59 5,577.00

VIBRATED REINFORCED CONCRETE GRADE 25 AS DESCRIBED IN

SGMCW050115 Transformer Base Slab not exceeding 250mm thick m3 8 428.85 3,430.80
VIBRATED REINFORCED CONCRETE GRADE 30 AS DESCRIBED IN
SGMCW050116 Cable Trench wall and base. m3 130 458.42 59,594.60
SGMCW050117 Transformer Foundation, Base, column, Beam and Wall m3 130 458.42 59,594.60
SGMCW050118 Oil Interceptor base, wall, sump base and sumo wall m3 20 458.42 9,168.40
SGMCW050121 Switchyard Equipment Foundation m3 700 458.42 320,894.00
SGMCW050129 Earth mast and Gantry Foundation m3 600 458.42 275,052.00
Cable Trench Cover m3 20 458.42 9,168.40
HIGH TENSILE DEFORMED STEEL REINFORCEMENT (460N/MM2)
TO CONCRETE WORK AS DESCRIBED
SGMCW050130 Switchyard Equipment Foundation kg 27133 4.37 118,571.21
SGMCW050131 Cable Trenches Wall and Base kg 115049 4.37 502,764.13
SGMCW050132 Transformer Wall, Base, Beam and Column kg 13400 4.37 58,558.00
SGMCW050133 Oil Interceptor Wall, Base and Sump kg 4500 4.37 19,665.00
SGMCW050134 Earth Mast and Gantry kg 13500 4.37 58,995.00
Cable Trench Cover kg 6240 4.37 27,268.80
FORMWORK CLASS F1 AS DESCRIBED TO REINFORCED CONCRETE
WORK

SGMCW050151 Earth Mast Plinth and Gantry m2 680 49.28 33,510.40

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S05 : 64/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

SGMCW050152 Switchyard Equipment Foundation m2 300 49.28 14,784.00


FORMWORK CLASS F2 AS DESCRIBED TO REINFORCED CONCRETE
WORK
SGMCW050155 Cable Trench Wall m2 1400 49.28 68,992.00
SGMCW050156 Transformer Foundation, Base, column, Beam and Wall m2 3500 49.28 172,480.00
SGMCW050157 To sides of Oil Interceptor,Oil Interceptor Sump Wall, Base and soffit m2 25 49.28 1,232.00
of oil interceptor slab
Cable Trench Cover (concrete mould) m2 86 49.28 4,238.08
PREPARE AND APPLY APPROVED WATERPROOFING SYSTEM ALL IN
ACCORDANCE WITH THE MANUFACTURER'S INSTRUCTIONS AND
RECOMMENDATION

SGMCW050163 To cable trench wall and base m2 700 56.00 39,200.00


SGMCW050164 To oil interceptor wall and Base m2 25 56.00 1,400.00
SGMCW050166 To transformer base slab m2 30 56.00 1,680.00
SUNDRIES
Approved gravel stone as described, spread, levelled, well
rammed, consolidated and watered as described
SGMCW050168 To transformer plinth m3 30 115.02 3,450.60
One brickwall in common bricks in cement mortar (1:3) with
plaster and paint finish on both sides as specified.
SGMCW050169 Transformer Base Brick Wall m2 24 98.34 2,360.16
Miscelleanous Works for Oil Interceptor Including Supply Deliver
and Install of Materials as described:
SGMCW050170 100mm diameter G.I Vent Pipe complete with insect screen m 4 33.60 134.40
Miscelleanous Works for Oil Interceptor Sump Including Supply
Deliver and Install of Materials as described:
SGMCW050171 50mm diameter PVC weepholes with 38mm diameter crushed no. 4 29.12 116.48
stone and wrapped with approved geotextile
Hot Dip Galvanised Steel Angle Frame for Trench Cover including
cutting, drilling, assembling and welding as described:

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S05 : 65/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

45mm x 45mm x 3.38kg/m steel angle kg 13924 5.38 74,911.12


Hot Dip Galvanised Mild Steel Chequered Plate Cover including
cutting, drilling, assembling, welding, rivetting, bolting complete
with mild steel handle as described:

SGMCW050176 880mm x 880mm x 12mm Cover for Oil Interceptor opening cover NO 2 683.20 1,366.40
SGMCW050177 1380mm x 1380mm x 12mm Cover for Oil Interceptor opening NO 2 1,680.00 3,360.00
cover
UPVC pipe weepholes including supply, install and fix to trench
wall
SGMCW050178 150mm ND m 1 51.52 51.52
Galvanised iron step
SGMCW050179 Overall girth 550mm long x 25mm diameter mild steel galvanised No 11 201.60 2,217.60
iron step once bent to shape as step cast 150mm deep into
reinforced concrete wall at 300mm centres complete with approved
painting system and cement grouting

SGMCW050180 Compliance with other Terms and Conditions of Contract not


covered by any item in the Summary of Tender.

i) 0.00

ii) 0.00

iii) 0.00

TOTAL AMOUNT OF SECTION 05:


CARRIED FORWARD TO SUMMARY OF PRICE 2,097,770.30

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S05 : 66/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 33kV Substation


SECTION 06 - INFRASTRUCTURE WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

1.0 ROAD WORKS

Within Site Boundary

ASCW060101 Prepare, grade to fall and compact subgrade in suitable


materials. m2 2,325 3.20 7,440.00

ASCW060102 Supply, lay, spread, grade and compact subbase including


200mm thick continuous subbase layer. m3 465 109.76 51,038.40

ASCW060103 Supply, lay, spread, grade and compact roadbase including


200mm thick continuous roadbase layer. m3 465 112.00 52,080.00

ASCW060104 Supply and spray bituminous prime coat m2 2,325 3.92 9,114.00
ASCW060105 Supply and spray bituminous tack coat m2 2,325 3.14 7,300.50
ASCW060106 Supply, lay and compact 50mm binder course m3 116 672.00 77,952.00
ASCW060107 Supply, lay and compact 50mm wearing course m3 116 683.20 79,251.20
ASCW060108 Non-woven geotextile TS-20 or other equal and approved
equivalent geotextile filter m2 3075 28.78 88,498.50
Gravel Road All Provisional

ASCW060110 Supply and lay 150mm thick gravel surface road as per General
Spec. m2 60 112.00 6,720.00

2.0 SWITCHYARD GRAVEL TOPPING (ALL PROVISIONAL)

ASCW060201 Supply and lay 200mm thick gravel topping as per Particular
Spec. m3 1,000 112.00 112,000.00

3.0 SURFACE WATER DRAINAGES INCLUDING SUMPS AND


CAST IN-SITU CULVERTS (ALL PROVISIONAL)

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 67/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

EXCAVATE, GET OUT, PART RETURN, LEVEL, GRADE AND RAM


BOTTOM, TRIM SIDES AND INCLUDING PLANKING AND
STRUTTING

Commencing from platform level

ASCW060301 450mm drain m3 360.00 25.87 9,313.20


600mm open drain m3 150.00 25.87 3,880.50
LEAN CONCRETE GRADE 15 BLINDING WITH SURFACE
FINISHED LEVEL TO RECEIVE CONCRETE INCLUDING WHERE
NECESSARY TRIMMING BASE OF EXCAVATION

450mm open drain m2 550.00 18.59 10,224.50


600mm open drain m2 415.00 18.59 7,714.85
VIBRATED REINFORCED CONCRETE GRADE 30 AS DESCRIBED IN

ASCW060302 450mm open drain m3 200.00 404.21 80,842.00


ASCW060303 600mm open drain m3 450.00 404.21 181,894.50
HIGH TENSILE DEFORMED STEEL REINFORCEMENT
(460N/MM2) TO CONCRETE WORK AS DESCRIBED
450mm open drain kg 4,000.00 4.37 17,480.00
600mm open drain kg 2,500.00 4.37 10,925.00
FORMWORK CLASS F1 AS DESCRIBED TO REINFORCED
CONCRETE WORK
450mm open drain m2 2,000.00 49.28 98,560.00
600mm open drain m2 1,500.00 49.28 73,920.00
Rip-Rap

ASCW060310 Supply and lay 225mm thick blockstone rip rap with 1:3 m2 2 442.40
884.80
cement sand mortar
Subsoil Drain

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 68/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

ASCW060311 Provide and lay subsoil 160 diameter HDPE perforated pipe type m 670 58.46
A wrapped in Geotextile with minimum 400x600mm earth 39,168.20
trenches

ASCW060312 Provide and lay subsoil 160 diameter HDPE pipe m 80 78.40 6,272.00

Hot Dip Galvanized Mild Steel Gratings for all drains and sumps,
including supply, delivery, handle, cutting, bending, fabrication kg 0.00
and installation on site.
ASCW060313
450mm drain
kg 41,000 15.90 651,900.00
ASCW060314 600mm drain kg 27,100 15.90 430,890.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 69/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

4.0 FENCING AND GATE (ALL PROVISIONAL)

ASCW060317 Chain link fencing consisting of 62mm x 62mm x 6mm painted m


steel angle post at 3.00m centres with bottom end embedded
in concrete (Grade 25) and including 3mm x 55mm square
mesh PVC coated chain-link fence, 3 rows of 2.4mm PVC coated
barbed wire, 4 rows of 3mm PVC coated lines wires, all with
galvanised iron wire as core wire and 50mm x 50mm x 6mm 630 224.00 141,120.00
painted steel angle corner struts with bottom end embedded in
concrete (Grade 25).

ASCW060318 Brickwall Fencing consisting of brickwall c, r.c. (Grade 30) m


Beams, r.c pillars and foundation c/w concrete and approved 187 580.16 108,489.92
paint finish in both sides.
ASCW060319 R.c. Retaining wall under brickwall where required m 20 728.00 14,560.00
ASCW060320 Provide and supply sliding gate at the front entrance in
accordance in the drawings including all necessary foundation, nos 1 26,880.00 26,880.00
approach slabs, capping and masonry.

Concertina Barbed Wire

ASCW060321 Concertina barbed wire m 240 22.40 5,376.00


Support Structure for Noise Barrier

Hot Dip Galvanized Mild Steel Gratings for Steel Structure


Support for Noise Barrier, including supply, delivery, handle,
cutting, bending, fabrication and installation on site. kg 670 15.90 10,653.00

Lean Concrete grade 15 blinding with surface finished level to


receive concrete including where necessary trimming base of m2 5 18.59 92.95
excavation

Supply, deliver handle and install BMC A8 Steel Wire Mesh for
Support Structure Foundation m2 20 30.80 616.00
Formwork class f1 as described to reinforced concrete work m2 19 49.28 936.32
Vibrated reinforced Concrete Grade 30N/mm Works for Steel
Support Structure Foundation. m3 2 443.74 887.48

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 70/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

5.0 SEWERAGE

ASCW060322 Supply and install 150mm outer diameter DICL Pipe including m 6
excavation, backfill, compaction and cart away and Grade 25
concrete surround c/w rebar. 3,360.00 20,160.00

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 71/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

ASCW060324 900 x 900mm Manholes complete with benching, glazed No 4


channel and heavy grade manhole covers 3,326.40 13,305.60

ASCW060325 Supply and Lay HDPE Ecosept (ES-5)or equivalent spetic tank No 1
inclusive of excavate, backfill, compact, cart away, cast iron
cover for septic tank and manhole come with cast irom frame,
effluent pipe with concrete encasement to drain all as per detail 7,840.00 7,840.00
in drawing

ASCW060326 Compliance with other Terms and Conditions of Contract not


covered by any item in the Summary of Tender. 0.00

i)
0.00

ii)
0.00

iii)
0.00

TOTAL AMOUNT OF SECTION 06: 2,466,181.42


CARRIED FORWARD TO SUMMARY OF PRICE

Note: LS means Lump Sum Price not subject to remeasurement. BILL 3 - (A) S06 : 72/82
PLS-120064
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 33kV Substation


SECTION 07 - WATER SUPPLY WORKS
TOTAL AMOUNT
BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) (RM)
1.0 EXCAVATION WORKS
Important note: Contractor is required to refer with all general
notes, specification, drawings, detailing, site visit and all
information in the tender document prior to pricing this tender
and acquiring the material or execute works at the site. This note
referred to all section in the BQ in this Contract. Important note:
Contractor is required to refer with all general notes, specification,
drawings, detailing, site visit and all information in the tender
document prior to pricing this tender and acquiring the material
or execute works at the site. This note referred to all section in the
BQ in this Contract. Important note: Contractor is required to refer
with all general notes, specification, drawings, detailing, site visit
and all information in the tender document prior to pricing this
tender and acquiring the material or execute works at the site.
This note referred to all section in the BQ in this Contract.
Important note: Contractor is required to refer with all general
notes, specification, drawings, detailing, site visit and all
information in the tender document prior to pricing this tender
and acquiring the material or execute works at the site. This note
referred to all section in the BQ in this Contract.

Trench Excavation
Excavate trench in all materials, refilling of trenches with approved
selected excavated materials, compaction, disposal of surplus,
restoration surfaces and to include all as specified to a depth not
exceeding 2.0m for

SGMCW070101 160mm ND pipes and specials M 45 25.87 1,164.15


SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

2.0 SUPPLY AND INSTALL PIPES, SPECIALS, FITTINGS, VALVES


Contractor shall ensure all material must comply with the
approved list by SPAN, Pihak Berkuasa Air Negeri and other
relevant authorities. Please refer to all requirements stated in the
specification, drawings and others document.

Supply and delivery of pipes and fittings with flanges shall includes
hot dipped galvanized steel bolts, nuts, washers and rubber
gasket. Collect from store or pipes dumps on site for pipes,
specials, joints, fittings and valves. All flanges to include
installation of bolts, nuts and gasket.

HDPE PIPES
Straight Pipes
SGMCW070201 160mm OD HDPE Pipe (PN 10) m 160 78.40 12,544.00
HDPE FITTINGS AND SPECIALS
MISCELLANEOUS

SGMCW070202 Electrofusion Tapping Tee c/w Underport nos 2 134.40 268.80


DUCTILE IRON FITTINGS AND SPECIALS

Bend
Ductile Iron > 0.6m Long and ≤ 1m Long DF Short Piece K12,
including Rubber Gasket.
100mm ND Nos 2 349.66 699.32
SGMCW070203 150mm ND nos 4 349.66 1,398.64
Ductile Iron > 1.0m Long and ≤ 2m Long DF Short Piece K12,
including Rubber Gasket.
SGMCW070204 150mm ND nos 4 466.95 1,867.80
D.I. Pipe Ductile Iron 6.0m Long DF K12, including Rubber Gasket.

SGMCW070205 150mm ND nos 2 917.75 1,835.50


SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

SGMCW070206 150mm ND double flange ended x 90 degrees150mm ND double


flange ended x 90 degrees150mm ND double flange ended x 90 nos 6 246.40 1,478.40
degrees

Tee
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

SGMCW070207 150mm x 150mm x 150mm ND all flange nos 1 320.49 320.49


Sluice Valve
SGMCW070208 150mm dia. double flanged sluice valve. nos 6 620.22 3,721.32
Washout
SGMCW070209 100mm dia. double flanged sluice valve. nos 2 425.71 851.42
SGMCW070210 100m dia Flap gate. nos 2 188.16 376.32
150mm x 150mm x 100mm ND all flange nos 1 300.00 300.00
100mm O.D. Hot dip galvanised steel bolts, nuts, washer and
gasket, to suit. nos 2 300.00 600.00
Blank Flange
SGMCW070211 Blank flange for 150mm ND pipes and specials. nos 8 140.00 1,120.00
Single Air Valve including Tapping Saddle Piece
SGMCW070212 25mm single orifice air valve nos 3 117.60 352.80
Hydrant (Sluice Valve Measured Seperately)
SGMCW070213 100 mm x 90 deg. Duck foot Bend NO. 1 89.60 89.60
SGMCW070214 100 mm dia. Heavy Duty Std Pillar Hydrant NO. 1 3,360.00 3,360.00
PIPE JOINTING FOR HDPE PIPES
PIPE JOINTING FOR HDPE PIPES

SGMCW070213 160mm O.D plain ended pipes/stub end by Automatic Butt Fusion
nos 40 67.20 2,688.00

PIPE JOINTING FOR DUCTILE IRON PIPES AND HDPE PIPES


SGMCW070214 150mm O.D. Stud ends (long collar) complete with Ductile Iron
flanges, hot dip galvanised steel bolts, nuts, washer and gasket, to nos 10 123.20 1,232.00
suit.

PIPE JOINTING FOR DUCTILE IRON PIPES


SGMCW070215 150mm O.D. Hot dip galvanised steel bolts, nuts, washer and
gasket, to suit. nos 26 70.56 1,834.56

3.0 SYSTEM TEST, STERILISING & FLUSHING


SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Note : Pressure and leakege test must be carried out at every


maximum of 1000m. All payment for the trench excavation, supply
and layof pipe to be made only to the length of tested pipe and
passed. All payment subject to the satisfactory of work done by
the Engineer

Sectional and System Test

Sectional and system testing for the pipeline including


overcrossing pipes and specials. Rate to include supply of clean
water for

SGMCW070301 160mm ND pipeline LS 201.60 201.60


Sterilising and Flushing

Sterilising and Flushing for the pipeline including overcrossing


pipes and specials. Rate to include supply of clean water,
chemicals, equipments and finally flush with treated water for :

SGMCW070302 160mm ND pipeline LS 274.68 274.68


Laboratory Test

SGMCW070303 Provide bacterialogical tests and residual chlorine test by an


accredited laboratory. Location 1 1,344.00 1,344.00

4.0 PIPE TRENCH, CHAMBER, CONCRETE WORKS AND


MISCELLANEOUS

Precast Chamber
Supply, transport to sites, store, haul, handle and install complete
set of precast chamber. Rate to include excavation, campacted
sand fill, reinstatement, painting, heavy duty surface box, etc as
shown in the drawing. Each set of chamber consists of one (1) no.
of bottom section, at least three (3) no. of middle sections (with
reference to the stated depth, contractor to check the exact no.
required per chamber) and one (1) no. of top section. The
chambers shall be obtained from approved supplier or sources for
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

SGMCW070401 Internal dimension of 800mm x 900mm to average depth of


1500mm deep, SV chamber nos 8 705.60 5,644.80
SGMCW070402 Internal dimension of 750mm x 850mm to average depth of
1500mm deep, WO chamber nos 1 548.80 548.80
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Mass Concrete
SGMCW070403 In thrust block haunches, support blocks, and surround for pipes
and valves. m3 1 470.40 470.40

Reinforcement and Formwork


Unless rate for reinforcement and formwork not included or
measured as individual items, the rate and quatities below shall
apply for footings, thrust or anchor blocks, pipe supports and
saddles, tail bay, chamber.

SGMCW070404 BMC A7 sq.m 16 23.52 376.32


SGMCW070405 Class F1 formwork sq.m 9.6 49.28 473.09

Lean Concrete
SGMCW070406 50mm thk Lean concrete sq.m 8 18.59 148.72

Marker Post

Supply and erect precast concrete Grade 25 marker post complete


with embossed symbols and numbers as shown in the Drawings.
Rate to include excavation, reinforcement, concrete base and
painting for
SGMCW070407
Pipe marker post (at maximum 250m interval) nos 2 78.40 156.80
SGMCW070408
Sluice valve marker post nos 3 78.40 235.20
SGMCW070409
Washout marker post nos 2 78.40 156.80
6.0 CONNCETION WORKS TO EXISTING WATERMAIN (ALL
PROVISIONAL)
Connection works to the existing watermain including Capital
Contribution and the supply, deliver and install of bulk meter. LS 1 60,000.00 60,000.00

Compliance with other Terms and Conditions of Contract not


covered by any item in the Summary of Tender. 0.00

i) 0.00
ii)
0.00
iii) 0.00
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

TOTAL AMOUNT OF SECTION 07:


CARRIED FORWARD TO SUMMARY OF PRICE 108,134.33
SARAWAK ENERGY BERHAD VOLUME 1 - PART C: SECTION 3 - BILL NO.3: CIVIL WORKS

Tender for Sg. Merah 132/33kV Substation and Sg. Maaw 132kV Extension Project
PART C : SECTION 3 - BILL NO.3
SCHEDULE OF PRICE

A. New Sungai Merah 33kV Substation


SECTION 08 - ANY OTHER MISCELLANEOUS WORKS

BID ITEM NO. DESCRIPTION UNIT QTY RATE (RM) TOTAL AMOUNT (RM)

1.0 MISCELLANEOUS
ASCW080101 Allow for protection, repair, temporary diversion,
making good to any damages to the existing utilities,
road or structures, existing subsoil drains, relocation
of existing utility services either overhead or
underground or both or on the surface, and private
properties. If making good of the damages to the
original condition is not possible or not to the LS 1 40,000.00 40,000.00
satisfaction of the Engineer, the Contractor shall
replace it by the new one.

ASCW080102 Construction of safety barricade as per the tender drawings,


specification or as per authority requirements. LS 1 40,000.00 40,000.00
ASCW080103 Provision for the relocation of existing utilities LS 1 40,000.00 40,000.00
ASCW080104 Provision for the interfacing works with the existing facilities
including all coordination works LS 1 40,000.00 40,000.00
ASCW080105 Allow for items/works deemed necessary for the
completion of the Works but not listed elsewhere (Tenderer to
specify) LS 1 40,000.00 40,000.00

TOTAL AMOUNT OF SECTION 08:


CARRIED FORWARD TO SUMMARY OF 200,000.00
PRICE