CÁLCULO DEL CAUDAL MÁXIMO DE LA


CUENCA DEL RÍO TARAY
PRÁCTICAS DE IRRIGACIONES
Docente:
Ing. John Zapata Gutiérrez
Integrantes:
 Cornejo Mayhua, Franklin
 Corrales Cusi, Vladimir
 Huamani Fred
 Pinares Ledesma, José Luis
 Suma De La Colina, Rodolfo Eliot
Fecha de entrega:
Martes ,02 de octubre del 2018

CUSCO – PERÚ
2018
UNIVERSIDAD ANDINA DEL CUSCO
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
PRÁCTICAS DE IRRIGACIONES

1. COEFICIENTE DE ESCORRENTIA
CALCULO DE LA PENDIENTE PROMEDIO
INCLINACION
PONDERACION
N° PROMEDIO % MAXIMO AREA (a)x(b)
MINIMO % (b)
(a) %
1 0 1.39 2.77 8650949.34 9.81% 0.13590091
2 2.77 4.58 6.38 4303890.47 4.88% 0.22333723
3 6.38 9.18 11.98 5004218.25 5.68% 0.52106
4 11.98 21.59 31.19 18434351.3 20.91% 4.51324309
5 31.19 38.41 45.63 19018164.6 21.57% 8.28555726
6 45.63 51.81 57.98 13620156.8 15.45% 8.0031803
7 57.98 65.83 73.67 10916789.5 12.38% 8.15069455
8 73.67 230.03 386.39 8215459.43 9.32% 21.435082
SUMA 88163979.7 100.00%

Escorrentía
PROMEDIO PONDERADO
Coeficiente de Escurrimiento (Ce) (pm): 51.27 %

MEDIANTE EL USO DE TABLAS

Ce  C1  C 2  C3
VEGETACION
SUELO TOPOGRAFIA
COBERTURA C1 C2 C3
TEXTURA PENDIENTE (%)
(%)
100 0.08 Arenoso 0.08 0.0-0.2 0.04
80-100 0.12 Ligera 0.12 0.2-0.5 0.06
50-80 0.16 Media 0.16 0.5-2.0 0.06
20-50 0.22 Fina 0.22 2.0-5.0 0.10
0-20 0.30 Rocosa 0.30 5.0-10.0 0.15

C1= Esta en funcion de la cobertura vegetal


C2= Esta en funcion de la textura del suelo
C3= Esta en funcion de la topografia del terreno

CODIGO DE C para Mac𝐶1 = 0.12


Mach
Ce
CUENCA C1 C2 𝐶2 = 0.30C3
C3 0.220 0.220𝐶3 = 0.15
0.150 0.590
C4 0.160 0.160
C5
𝐶 = 𝐶1
0.220
+ 𝐶2 + 𝐶3 = 0.12 +0.150
0.220
0.30
0.150
+ 0.15 =0.470
0.57
0.590

CÁLCULO DEL CAUDAL MÁXIMO DE LA CUENCA DEL RÍO TARAY 2


UNIVERSIDAD ANDINA DEL CUSCO
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
PRÁCTICAS DE IRRIGACIONES

2. PENDIENTE
AREA (HA) 8816.40 ha
COTA MAS ALTA 4250.13 msnm
COTA MAS BAJA 2999.82 msnm
COTA MEDIA 3624.97 msnm
COTA ESTACION 2863.00 Calca
RELACION 1.27
L. CAUCE 19.06 km
PENDIENTE 65.62 m/km

ANALISIS DE MAXIMAS AVENIDAS SEGUN MAC MATH


UTILIZANDO PRECIPITACION MAXIMA DE 24 HORAS

𝑄 = 10−3 × 𝐶 × 𝑃 × 𝐴0.58 × 𝐼 0.42

Donde:
 C: coeficiente de escorrentía
 P: precipitación máxima 24horas corregida (mm)
 A: Área (ha)
 I: Pendiente (m/km)

CÁLCULO DEL CAUDAL MÁXIMO DE LA CUENCA DEL RÍO TARAY 3


UNIVERSIDAD ANDINA DEL CUSCO
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
PRÁCTICAS DE IRRIGACIONES

P.MAX24 Q.MAXIMO Q.MAXIMO


P.MAX24
ITEM AÑO CORREGIDO CRONOLOGICO ORDENADO LOG(Q) (Qi-Q)^3
CRONOLOGICO
F=1.266 m3/s. m3/s.

1 1963 26.00 32.92 21.10 51.20 1.709 0.076


2 1964 17.00 21.52 13.80 45.50 1.658 0.051
3 1965 34.00 43.05 27.60 40.60 1.609 0.033
4 1966 56.00 70.90 45.50 30.40 1.483 0.008
5 1967 24.00 30.39 19.50 28.40 1.453 0.005
6 1968 30.00 37.98 24.40 27.60 1.441 0.004
7 1969 27.50 34.82 22.30 26.80 1.428 0.003
8 1970 20.00 25.32 16.20 26.80 1.428 0.003
9 1971 31.00 39.25 25.20 25.20 1.401 0.002
10 1972 20.20 25.58 16.40 24.40 1.387 0.001
11 1973 37.40 47.35 30.40 23.60 1.373 0.001
12 1974 25.20 31.91 20.50 22.70 1.356 0.000
13 1975 33.00 41.78 26.80 22.30 1.348 0.000
14 1976 27.20 34.44 22.10 22.10 1.344 0.000
15 1977 27.20 34.44 22.10 22.10 1.344 0.000
16 1978 26.00 32.92 21.10 21.90 1.340 0.000
17 1979 6.00 7.60 4.90 21.10 1.324 0.000
18 1980 1.00 1.27 0.80 21.10 1.324 0.000
19 1981 17.00 21.52 13.80 20.50 1.312 0.000
20 1987 20.50 25.96 16.70 19.50 1.290 0.000
21 1988 22.00 27.86 17.90 19.50 1.290 0.000
22 1989 50.00 63.31 40.60 19.50 1.290 0.000
23 1990 35.00 44.32 28.40 17.90 1.253 0.000
24 1991 63.00 79.77 51.20 16.70 1.223 0.000
25 1992 28.00 35.45 22.70 16.40 1.215 0.000
26 1993 29.00 36.72 23.60 16.20 1.210 0.000
27 1994 33.00 41.78 26.80 14.60 1.164 -0.002
28 1995 27.00 34.19 21.90 13.80 1.140 -0.003
29 1996 18.00 22.79 14.60 13.80 1.140 -0.003
30 1997 24.00 30.39 19.50 4.90 0.690 -0.212
31 1998 24.00 30.39 19.50 0.80 -0.097 -2.646
Nº Datos = 31.00
8816.39796
A= 6 há Suma = 39.87 -2.6800
C= 0.57 Media = 1.29 -0.086
I = 66 m/Km Stds = 0.313
Pmax. 24
P= hrs. mm Sesgo = -0.1001

Periodo de Vida 25.00 años


Riesgo permisible 30%
Periodo de Retorno (T) 70.59 años

1
𝑇=
1 − (1 − 𝑅)1/𝑛

Se debe realizar una predicción a 71 años.


Probabilidad = 0.99

CÁLCULO DEL CAUDAL MÁXIMO DE LA CUENCA DEL RÍO TARAY 4


UNIVERSIDAD ANDINA DEL CUSCO
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
PRÁCTICAS DE IRRIGACIONES
La distribución que mejor se ajusta mediante el programa EASYFIT:

CÁLCULO DEL CAUDAL MÁXIMO DE LA CUENCA DEL RÍO TARAY 5


UNIVERSIDAD ANDINA DEL CUSCO
ESCUELA PROFESIONAL DE INGENIERÍA CIVIL
PRÁCTICAS DE IRRIGACIONES

Calculamos nuestro caudal en base a nuestra probabilidad:

Y pudimos obtener que:

56.908 > 51.20