s.no. Name of inspectable item Average no.

of Average lot size Remarks


days for one offered in one call
inspection
1 EHV transformers 7 days 1
2 LT Power transformers 2 days 5
3 LT Distribution transformers 2 days 200
4 9KV Distribution surge arrestors 2 days 1000 72 hrs wattloss
test needs second
visit
5 Station class surge arrestors 2 days 10-15 72 hrs wattloss
test needs second
visit
6 Disconnectors upto 765KV 2 days 20 1000 operation
test needs second
visit
7 Long rod insulators 1 day/4 days(long 100(substation Min. lot size may
duration tests)/8 insulators)/1000 be fixed.L-2
days(for tests on for line insulators Network is the
interfaces and criteria for offered
fittings) lot.
8 HT/MS STEEL BLACK ANGLES 2 days 500 MT Sample
preparation
requires 1 day gap
9 HDG Tower parts 2 days 300 MT Sample
preparation
requires 1 day gap
10 Conductor 2 days 100km Rewinding takes 1
day
11 OPGW 2/3 Days 100/150km
12 Battery chargers 2 days 4 Heat run takes 10
hrs
13 GS Earthwire 2 days 50km Rewinding takes
one day
14 Energy meters 1 day 3000 nos
15 LT Power Transformer tank 1 day 2-4 Pressure and
vacuum test
16 Control cables 2 days 20km
17 AL//CU conductor for LT 1 day Stage inspection
transformers
18 CRGO rolls/laminations 1 day Stage inspection
inspection
19 PEB Structures(Raw/painted) 1 day CIP after review of
TPL reports
20 GFRP Rod 1 day Tests at TPL
21 Dehumidifiers 1 day 4-6
22 Batteries(VRLA/NiCd) 1 day 4 Level-2
23 Al busbar 1 day 300m Level-2
24 Galvanised structures for SS 1 day 10 nos. TPL reports for
Chemical/Mech.
tests