Escolar Documentos
Profissional Documentos
Cultura Documentos
quiva ent o.
E .| .
wircuits t
£or
n
Power-Flow studies, is reproduced in the stub loads
and generators at the interconnection
Studies
tuies terminals. In system planning studies
established at each terminal of the equiva- erence, by means of the analyzer vector- source currents can be converted back
lent circuit, corresponding to a given metering equipment. into power and reactive loadings, using
schedule of generation and loads at the 3. In order to establish a convenient known or estimated tie-line terminal
actual stations. This can be accom- notation for the distribution factors, let voltages.
plished through the medium of a set of the internal busses be indicated by letters, 5. The system generation and load
distribution factors, determined as de- and let the points of interconnection can be reflected separately to the tie-line
scribed in the following paragraphs. which are retained in measuring the terminals in this manner, to appear as an
This description is given in terms of equivalent line network be indicated by equivalent generator and an equivalent
generation. The loads can be considered numbers. Use the first letters of the load at each terminal, or the two can be
as negative generation and can be treated alphabet to indentify generator busses, combinedinto.anethloadornet generation
in exactly the same way. and assign the remaining letters to load at each terminal. If the currents
Iae ub,
1. In a detailed set-up of the network
being reduced, with load and generator
busses. If a load or generator appears at
tion. on the right hand side of equa-
one of the retained busses, assign both a tions 1 include all busses, with the proper
circuits disconnected, connect each in- suitable letter and a number to this bus algebraic signs to distinguish between
terconnection bus to the analyzer neutral When station a is energized by impressing generation and load, these equations give
bus through a metering circuit. In the unit current, denote the currents in the equivalent net current sources. The
system of Figure 1, for example, connect metering circuits connected to terminals distribution factors, once determined, per-
points 1, 2, and 3 to the neutral bus. 1, 2, 3, . ., by the symbols Dai, Da2,Da", mit representation of any desired schedule
2. Connect an analyzer source be- . , respectively. Similarly, when unit of generation and load.
tween one generator bus, such as ter- current is impressed at station b, label 6. In reducing a large system contain-
minal a in Figure 1, and the analyzer the corresponding distribution factors ing many loads, this method may become
neutral bus. Adjust this source so that as: Dbl, Db2, Dbs, . . .
quite lengthy and cumbersome. An
its output current is equal to one ampere 4. The distribution factors are used approximate apportionment of the total
or unit current. Measure the currents in to obtain an equivalent generation at system load at the terminals of the
the several metering circuits connecting each terminal of the equivalent line net- equivalent circuit can be carried out more
the terminals to neutral. work, from known or specified power and rapidly as follows,
These metering-circuit current readings reactive generation and bus voltages at In the detailed set-up of the network
are the distribution factors associated generators in the reduced system. Ac- being reduced, disconnect all generators,
cording to the usual practice in analyzer but represent all loads in the usual fashion
ANALYZER studies, voltages are expressed in per cent as constant impedances to neutral, ad-
LSOURCE
SOUE
orsperunit of a nominal base voltage, and justed to consume the correct scheduled
power
___0 quantities are
powr quntiies recorded either
re rcored etlie inin real and reactive power at normnal bus
b 22. terms of actual svstem value or in per voltage. Connect all the terminals re-
*NETWORK unit. tained in the equivalent line network
c 3 .
Express the powcr and reactive loading
. through metering circuits to one terminal
. a single analyzer source, which
of each station as a complex number in of in turn
_~~ ~ ~~~~e per uni of th
unit of chsnpwr1ae
tTe base.d
NEUTRAL power s-
s S connected
c
minal. Adjust
to neutral
this
at the other ter-
source to deliver unit
' |
| ~~~~suming that normal angular displace-
suming tha noZ,/,z,,,,z,rmal,,,7,/,,/ o
angular current to the system. Read the currents
.-,,METERING CIRCUITS--_ ments between bus voltages are known, in the metering circuits and label these
either from previous studies or from a
i _JUNCTION (X) J_
__
- special analyzer test made for this pur- circuits to terminals 1, 2,
express each bus voltage in per unit tivelv. These are treated as total-load
, respec-
to be also one of the generator or load the per unit vector power by the conjugate EQOUvACLENT
busses, it is not necessary to carry out the of the corresponding per unit bus voltage. OR LOADS
test for this bus. Unit-current input to If the bus angles are not known, the use, { ~T2
this bus all would return to neutral either of estimated angles or of only\ :
through the metering circuit connected to voltage magnitude may give sufficiently\\
the same bus. In this case, the one dis- accurate results. I3
tribution factor is unity; the others are Represent the resulting per unit current
zero. Writh this exception, distribution loadings of stations a, b, c,...,by
factors are measured with unit current Ia Ib, h, ,respectively. Denote by
impressed successively at each bus. Il, '2, Ih,...,the equivalent generator
Usually, the metering circuit currents per-unit-current loadings at terminals 1, Figure 4. New simplified equivalent circuit
will be nearly in phase with each other 2, 3,...,respectively. The determina- for the system of Figure 1
shouldemfresiuade wthr ratas setwt norml the equivalent loads are held at constant acteristics under certain conditions, no-
tamned terminals are small or zero. If a values of real and reactive power. tably short circuits and power swings.
Assuming that generators in the re- A general statement on accuracy is not
relatively large turn ratio exists between
one terminal and the rest, it mav be duced system are operated at a scheduled attempted, because the importance of
to rede tpower output and fixed terminal voltage, various assumptions and the degree of
mossibleasurement bydaltis ringpossible
t apsetings the real power loading of the equivalent approximation involved depend on the
ofmransoremersbyalteorine taserminal
the i generators is held constant. The reactive nature of the system being reduced. Trial
quetranston.Then,at thea teratio in-
if tun loading of the actual generators, par- on several types of power networks, and
tuedtion. her,ies wthe thrnratitermi
troduced in series with that terminal of of ticularly those near the tie-line terminals in actual system studies, has yielded good
the equivalent circuit, the transfer-im- might vary during studies of different results. The equivalent circuits derived
pedance representation will be aroxi- conditions in the adjoining system. This by these methods are capable, in the
mately correct. introduces a serious deviation from the cases tried, of reproducing with accept-
The sum of the distribution factors basic assumption of constant-current able accuracy the terminal performance
sources, and gives rise to the problem of of the reduced network with various
'described under method I may not be
adjusting the reactive generation in the emergency operating conditions repre-
ecual to unity in the presence of off-
equivalent circuit. For the purpose of sented in the adjoining system.
simplifying this
factors as read wi.th normal tap settings choose, as pointsproblem,
it is desirable to Wlhen an equivalent circuit is used to
retained in the equia-
choeaspitrtindnteeqv- reproduce power flows over inter-com-
should be applied to the source and load lent network, busses where, in normal
shouldent. applyiedt mthesourceIandold pany ties, accuracy requirements are not
currinents. vapplying mhoads Idtden- system operation, the voltage is held at a extremely rigid. One company, in the
termines, thes quialernatiloas
erators, residual aetwend ter-'
turn ratios between
gen- definite, known value. Then, only the
power component of equivalent loads and
process of making a planning study of
proposed future developments, usually
minals should be represented during the
deternination of normal-voltage circti- generation need be determnined. Equiva- has incomplete information on future
plans of its neighbors, yet an approximate
lating flow tlent
reactive generation is adjusted to hold
network voltage. It may be helpful to calculate equivalent representation of neighboring
the equivalent generation at each ter- systems may be necessary in the study.
minal corresponding to the scheduled Joint studies of interconnection problems
Using the Equivalent Circuit real power loading of all suppressed gen- offer opportunities to obtain equivalent
erators and the maximum reactive power circuits of the systems involved as viewed
After the desired equivalent circuit has capability of all generators and other from the inter-company boundaries. The
been derived, it is set up, connected at sources of reactive power. This informa- methods described herein are well suited
the proper points to the detailed repre- tion can be used as a guide to avoid ob- to this type of equivalent-circuit applica-
sentation of the adjoining system, and the taining an unreasonable amount of reac- tion.
desired tests are carried out on this de- tive support from the equivalent circuit Additional approximations can be em-
tailed portion. Some additional sugges- when some particularly severe emergency ployed to simplify determination of the
tions are given here on using the equiva- condition is being studied on the ad- equivalent circuit if the study at hand
lent circuit during these tests. joining detailed network. allows liberal accuracy limits. For ex-
If the information on equivalent loads Since total tie-line power interchange ample, the distribution factors in method
and generation has been derived in terms between the equivalent circuit and the I might be applied directly to kva load-
of per unit current, the corresponding adjoining network depends on the dif- ings, neglecting voltage magnitudes and
loadings in terms of real and reactive ference between total equivalent genera- angles. A d-c board could be used to
power can be calculated, using known or tion and equivalent load, small errors in determine the distribution factors, if
estimated voltages at the tie line ter- these quantities may assume major pro- transformer taps are neglected and uni-
minals. portions in reproducing a relatively small form impedance angles assumed.
If it is necessary to estimate these power transfer. If inter-company ties In general, the new equivalent circuit
voltages initially, the actual conditions are involved, the total transfer usually is representation occupies an intermediate
are established by trial on the first specified. In other cases, it is well to position relative to methods A and B
analyzer study. During subsequent tests, check the initial measured transfer to or mentioned earlier in the paper. It is a