The equipment comprises one Mini Blast Furnace and Sinter Plant, the delivery period of which is

normally 4-5 months. The order for it should be placed. The delivery period of the crane, electrical
equipment, etc. will be about 3-4 months. Therefore, pending the delivery of the Sinter Plant, all
necessary electrical jobs and water supply arrangement should be executed as far as practicable. The
arrangements for installation of the Mini Blast Furnace, Stock House, Stoves and Sinter Plant should be
initiated along with structural jobs for the project to facilitate easy installation of Mini Blast Furnace.
The entire water circulation system should be ready by the time the test / trial run commence