Escolar Documentos
Profissional Documentos
Cultura Documentos
columns
2 Providing and laying stone Soling
in building works with clean hard 9 1.5 1.5 0.15
selected stones, all complete. 1 1.5 0.9 0.15
columns
columns
5
Supplying ,bending,and placing in
position tor steel reinforcement in
all RCC works including cost of
binding wires all complete 22.12cum @ 110kg/cum
Main bar 85 %
Stirrups 8mm dia bars 15 %
6
Filling with available excavated earth
in trenches, plinth,and side of
foundation in building works with
layers not exceeding 20cm all
complete
8 X 7 X
D/D plinth beam 1.59 + 1.91
7 Formwork for all RCC members
Column Base 9X4 1.5 0.15
Column 9X4 0.3 4.4
Tie Beam Long 3X3 7.07 0.3
Tie beam Short 3X3 5.88 0.3
Slab Beam Long 3X3 7.07 0.3
Slab beam Short 3X3 5.88 0.3
Slab 1 8.7 7.94
50% to be reused.
DISTEMPERING:
ENAMEL PAINT 2 x 11.79
Steel:
Sand
VI no:3 6.28 x 0.47 =
VI no:4 22.12 x 0.43 =
VI no:8 113.95 x 0.03 =
VI no:9 305.74 x 0.015 =
VI no:10 48.27 x 0.018 =
VI no:18 0.41 x 0.174 =
VI no:19 33.28 x 0.54 =
39.38 x 1.6 =
Stone:
VI no 3 6.28 X 0.89 =
VI no:4 22.12 x 0.94 =
VI no 10 48.27 X 0.036 =
VI no 18 0.41 X 1.17 =
VI no 19 33.28 X 0.106 =
Stone to be provided for item no 4
only
Therefore total qty for loading and
unloading considered 20.79 x 2.2 =
24
Carriage of Stone Chips by
mechanical means for 55km radius 11.33 X
1370.93
SUB TOTAL
P/F/F of all WATER SUPPLY AND
SIANITATION items @
Electrification @
Provision for septic tank
Provision for hill cutting and
protective works
26 Add Cess @
Chief Engineer
RM&DD
G MISSION
Quantity
unit Amt for unit
house Rate Unit house
36.45
0.34
36.79 164.74 /cum 6060
3.04
0.20
3.24 560.28 /cum 1815
2.03
4.12
0.14
6.28
2.03
3.31
3.56
1.59
1.32
1.59
1.32
6.91
0.14
0.12
0.04
0.02
0.02
0.03 0.280437
0.05
0.07
22.12 5495.67 /cum 121568
24.33
20.68 6728.3 /qtls 139160
3.65 6728.3 /qtls 24558
0.20 11.2
3.5
7.7
68.44 /cum 527
4.05 363.77 /sqm 1473
23.76 511.89 /sqm 12163
9.54 371.49 /sqm 3546
7.94 371.49 /sqm 2949
9.54 371.49 /sqm 3546
7.94 371.49 /sqm 2949
34.54 473.89 /sqm 16368 8.5
7.64
18.03
14.99
6.56
18.11
15.62
15.05
4.72
17.35
14.83
125.25
10.80
0.50
11.30
113.95 639.14 /sqm 72831
227.92
14.54
2.10
2.74
3.06
18.51
15.76
7.38
6.30
0.68
1.35
2.70
1.80
0.90
305.74 116.33 /sqm 35567
12.90
12.13
6.27
11.52
5.46
48.27 274.14 /sqm 13233
0.04
0.11
0.01
0.04
0.20 28501.8 /cum 5809
200.00 kg
10.80
0.99
11.79 1799.88 /sqm 21221
6.27
1.95
8.22 2373.5 /sqm 19506
224.27
14.54
2.10
2.74
3.06
18.51
15.76
7.38
6.30
0.68
1.35
296.69 19.11 /sqm 5670
0.20
0.14
0.07
0.41 2971.66 /cum 1204
LS 15000
21.35
176.96
24.27
33.33
16.41
0.52
8.45
281.29
281 bags
141 qtls
14 MT
14 153.58 /MT 2150
24.33 153.58 /MT 3737
2.95
9.51
3.42
4.59
0.87
0.07
17.97
39.38 cum
63.01 87 /MT 5481
5.59
20.79
1.74
0.48
3.53
32.13 cum
45.75 87 /MT 3980
14.06 MT
24.33 MT
0.06 MT
0.20 MT
38.66 MT
1159.72 MT-Km
1159.72 5.57 /MT-Km 6460
63.01 MT
2.20
Mt 5.57 Mt-Km 7636
140.767 MT 3509
643269
LS 32155
LS 32155
Sub TOTAL 707579
27000
70000
68463
Total 873042
1% 7076
GRAND TOTAL 880118
Amount to be restricted at
68463.29 = 0.59
= 59 %
%
X 100 = 98.33
X68463.29= 135783.2
= 1336140
1264000
48291 + 143852.00
Escalation = 192143.00
As per WPI from April 2012-Dec 2015 = 21.831504 %
Therefore, year wise increase in escalation = 7.2771681
Increase in percentage from April 2012-Dec 2017 (5yrs) = 36.39
ie 1200356.33 - 880118
880118
X 100 = 36.39
+ 320238 = 1200356
6
Providing, fixing & removing form work for
casting R.C.C items as indicated with locally
available timber
Roof 1.5
50 % to be reused
7
Providing and laying cement mortar in
specified mix including curing etc. all
complete (1:4 mix)
Base 1X 1.5 X 0.75
Long Wall 2X 1.5 X 1.3
Short wall 2X 0.75 X 1.3
Partition wall 2X 0.75 X 1
Bends (110mm)
LS = 4000
bags
bags
bags
qtls @ 5.41 /qtls = 13.43288
Mt @ 153.58 /mt = 38.13348
MT-Km @ 5.57 /mt-km = 41.49046
cum
cum
cum @ 127.97 /cum = 51.65394
@ 87 /cum = 35.11677
Mt/cum
Mt
Mt-Km @ 5.57 /mt-km = 222.5798
cum
cum
cum @ 127.97 /cum = 77.01679
@ 87 /cum = 52.35962
Mt
Mt-km @ 5.57 /mt-km = 405.6185
Sub total 20684
Add Escalation for 4 years @7.5% PA = 6205.2
Total 26889.2
Add Cess @ 1% = 268.892
27158.09
Say 27000
BREAK UP OF INSTALLMENTS