Installation Instructions
SIAE – E band- Single polarization

LEAX Arkivator Telecom disclaims any liability for the results of improper or unsafe installation, inspection,
maintenance, or removal practices.

Torsgatan 5B Telephone: +46 31 386 11 00


SE-411 04 GÖTEBORG customer.lat@leax.com
SWEDEN www.leax.com
Unpacking
Place antenna on an appropriate surface, such as on top of the specially designed inlays in the packing
material. 0,6m antenna can be left in the box.

Handle Antenn and Feed


carefully at all times.

Included parts
Item Qty Description
A 1 Antenna
1 Antenna
1 Antenna support
1 SIAE interface (mounted to antenna)

Antenna Antenna support

Tools required
 Combination wrench (ring/open jaw) Hex 13 for M8.
 Allen key: 3mm for M4.
 Tool for torque levels; M4: 2,6Nm and M8: 24Nm.

2(4)
Assembly
Step 1 – Adapter plate
a) Place Antenna facing down.
b) Unscrew 4pcs of M8x20 (Hex) screws with washers and spring washers.

4pcs M8x20

c) Turn the adapter plate 180o to get the 4pcs M6 Hex distances pointing out from the
antenna.

4pcs M6 Hex
Distances,
pointing out from
the antenna
4pcs
M8x20

d) Mount 4pcs M8 Screws (Hex) with washer and spring washer again. Tighten the screws
with 17Nm±5%.

3(4)
Step 2 – Polarization
a) The Feed is delivered in Vertical possition. If Horizontal possition is requietred unscrew
4pcs of M4x10 (Allen) screws.
b) Rotate Feeder 90 degrees and align H markings. Do NOT take out the feeder!
c) Mount the 4pcs of M4x10 (Allen) screws and tighten them witn 2,6Nm±5%

Marking aligned for


Vertical polarization

Vertical polarization (delivered this way)

Do NOT remove
Feed, only rotate
90 degrees

Marking aligned for


Horizontal
polarization

Horizontal polarization

Step 3 – Antenna and Radio equipment


a) Continue mounting the antenna according to antenna manual.
b) Remove protection tape from Feed and mount Radio equipment.

4(4)