Você está na página 1de 6

CCDC DOCUMENTS DESCRIPTIONS

CCDC 2 - 2008 Stipulated Price Contract


Standard prime contract between Owner and prime Contractor to perform the required work for
a single, pre-determined fixed price or lump sum, regardless of the Contractor's actual
costs. (Table of Contents Preview)

CCDC 2MA – 2016 Master Agreement and Work Authorization


CCDC 2MA is developed to meet the needs of Owners with an on-going construction or
maintenance program: to enter into specific work arrangements quickly and easily, without
having to review and re-negotiate general terms and conditions for each work order.

The Master Agreement is a contract form between Owner and Contractor that is applicable for a
defined period of time and is intended to establish contractual terms and conditions (excluding
scope, time and cost) for multiple projects during that time period. Each project will be ordered
by means of Work Authorizations, that define the project specific requirements like scope, price,
time. (Table of Contents Preview)

CCDC 3 - 2016 Cost Plus Contract


Standard prime contract between Owner and prime Contractor to perform the required work on
an actual-cost basis, plus a percentage or fixed fee which is applied to actual costs.
(Table of Contents Preview)

CCDC 4 - 2011 Unit Price Contract


Standard prime contract between Owner and prime Contractor to perform the required work for
a pre-determined, fixed amount for each specified unit of work performed. The total price is
determined by multiplying the unit price by the actual, measured quantity of work performed for
each specified unit. (Table of Contents Preview)

CCDC 5A - 2010 Construction Management Contract – For Services


Standard contract between Owner and Construction Manager for which the Work is to be
performed by Trade Contractors. The Construction Manager acts as a limited agent of the
Owner providing advisory services and administering and overseeing the contracts between the
Owner and Trade Contractors. (Table of Contents Preview)

CCDC 5B - 2010 Construction Management Contract – For Services and Construction


Standard contract between Owner and Construction Manager to provide advisory services
during the pre-construction phase and perform the required Work during the construction
phase. At the outset, the Work is performed on an actual-cost basis, plus a percentage or fixed
fee which is applied to actual costs. The parties may agree to exercise the following options:
Guaranteed Maximum Price (GMP), GMP Plus Percentage Cost Savings, and conversion into a
Stipulated Price Contract. (Table of Contents Preview)

CCDC 9A - 2001 Statutory Declaration of Progress Payment Distribution by Contractor


A sworn statement for use by the Contractor as a condition of receiving payment for either the
second and subsequent applications for progress payment or the release of holdback funds. *
This document is a free download
CCDC 9B - 2001 Statutory Declaration of Progress Payment Distribution by
Subcontractor
A sworn statement for use by the Subcontractor as a condition of receiving payment for either
the second and subsequent applications for progress payment or the release of holdback funds.
This document is a free download.

CCDC 11 - 2016 Contractor's Qualification Statement


A standard form for obtaining information on capacity, skill and experience of Contractors
bidding on building construction projects. (Table of Contents Preview)

CCDC 12 - 1994 Project Financial Information


A model form to assist the Owner in showing that financial arrangements have been made to
fulfill the Owner's obligations under the contract (e.g. CCDC 2).

CCDC 14 - 2013 Design-Build Stipulated Price Contract


Standard prime contract between Owner and Design-Builder where the Design-Builder performs
Design Services and Construction under one agreement, for a single, pre-determined stipulated
or fixed price. In addition to the common contract terms and conditions for construction
projects, CCDC 14 clearly defines the roles and responsibilities of the contracting parties:
Owner

 Provides project information;


 Makes decisions;
 Interprets the Owner’s Statement of Requirements;
 Reviews and approves Construction Documents;
 Requires inspection or testing of the Work.

Design-Builder

 Controls the Design Services and the Work;


 Reviews Owner’s Statement of Requirements or other project information;
 Develops Construction Documents;
 Engages Consultants, Other Consultants and Subcontractors.

CCDC 14 also identifies and describes the roles of other parties such as the Consultant and
Payment Certifier as well as Owner’s Advisor, if any.
(Table of Contents Preview)

CCDC 15 - 2013 Design-Builder/Consultant Contract


Standard contract between Design-Builder and Consultant to perform the design services
required under a design-build contract between Owner and Design-Builder.

Based on an approach similar to standard client-consultant contracts (i.e. RAIC Document Six
and ACEC 31), CCDC 15 lists all the basic design services that are considered necessary in a
design-build contract. These design services are listed in a Schedule, which allows flexibility for
the Design-Builder and Consultant to establish the scope of services and compensation
method. CCDC 15 also includes a schedule that lists typical additional design services that the
Consultant may be required to provide. (Table of Contents Preview)

CCDC 17 - 2010 Stipulated Price Contract for Trade Contractors on Construction


Management Projects
Standard contract form between Owner and Trade Contractor to perform the Work for a single,
pre-determined fixed price, regardless of the Trade Contractor's actual costs. It is specifically
for use where the project is performed under the CCDC 5A Construction Management method
of contracting. (Table of Contents Preview)

CCDC 18 - 2001 Civil Works Contract


Standard prime contract between Owner and Contractor for civil works construction, e.g. roads,
bridges, dams, underground utilities, etc. (Table of Contents Preview)

CCDC 220 - 2002 Bid Bond


Standard surety bid bond form guaranteeing the bidder's intention to enter into a formal contract
and to provide the specified contract security if the bid is accepted.

CCDC 221 - 2002 Performance Bond


Standard surety performance bond form guaranteeing performance of the contract by the
Contractor.

CCDC 222 - 2002 Labour and Material Payment Bond


Standard surety labour and material payment bond form guaranteeing that the Contractor will
satisfy all labour and material payment obligations incurred in performing the contract.
CCDC GUIDES
CCDC 20 - 2008 A Guide to the Use of CCDC 2 - 2008 Stipulated Price Contract
A guide document designed to assist users of CCDC 2 - 2008. (Table of Contents Preview)

CCDC 21 - 2016 A Guide to Construction Insurance (Table of Contents Preview)


CCDC 21 covers all important issues relating to construction insurance:

General Liability Insurance – Coverage offered by standard policy IBC 2100 and CCDC
Endorsement IBC 2320, who is insured and the coverage for Additional Insured, exclusions,
Umbrella Liability insurance, six-year coverage for completed operations etc.

Builder’s Risk Broad Form Property Insurance – Insured and excluded property, major excluded
perils, suggested additional coverages (e.g. soft costs, delayed start-up, expediting expense,
early occupancy, testing and commissioning, valuable papers, electronic data and cyber
threats), renovation projects, negotiating coverage etc.

Other Insurance – Important considerations for Boiler and Machinery (Equipment Breakdown)
Insurance, Automobile Liability Policy Insurance, Aircraft and Watercraft Liability Insurance,
Contractors’ Equipment Insurance, Professional Liability Insurance, Wrap up Liability (with Wrap
Up Difference in Condition Endorsement and coverage for completed operations), Installation
Insurance.

Practical Tips on Critical Insurance Issues – Selection of insurance representatives, claims


process (reporting, handling, proof of loss), subrogation etc.

CCDC 22 - 2002 A Guide to Construction Surety Bonds (Table of Contents Preview)


The purpose of this guide is to help the construction and business communities in Canada
better understand surety bonds and the suretyship process. This guide was prepared by the
Surety Sub-Committee of the Canadian Construction Documents Committee (CCDC) and is
endorsed by the constituent organizations of the CCDC and the Surety Association of Canada.
CCDC 22 describes the suretyship process and clears up some commonly held
misconceptions. The guide is divided into three parts. Part 1 reviews suretyship, what a bond is
and how it differs from other risk management tools. Part 2 discusses how suretyship works in
practice, how bonds are obtained, the requirements of a surety company, and how the company
proceeds through the prequalification process. Part 3 examines the various forms of bonds with
a view to understanding the purpose of each bond and the claims process.

CCDC 23 - 2005 A Guide to Calling Bids and Awarding Construction Contracts (Table of
Contents Preview)
CCDC 23 provides recommended best practices for procuring construction services by means
of a competitive bidding process for any public or private sector project, large or small, where
the lowest bid selection method is used.

CCDC 23 addresses all aspects of the bid calling and contract award process:

 Principles of the Law of Competitive Bidding A summary of fundamental principles


under the law of competitive bidding, e.g. the legal obligation of owners and bidders
under Contract A and Contract B.
 Preparing the Bidding and Contract Requirements Instruction to bidders, information
available to bidders (typically created by parties other than the consultant), bid form
(sample forms), and bid form supplements (list of subcontractors, alternative prices,
itemized prices, and unit prices).
 Calling for Bids Open vs. invitational bid calls, distribution of bid documents, bidding
period and scheduling, pre-bid meetings and site visits, and bidder inquiries and
issuance of addenda.
 Receiving Bids Bid closing dates and times, receipt of bids, late bids, bid modifications,
bid closing (including two-stage closing), and single bids.
 Contract Award Bid analysis and evaluation for compliance, bid irrevocability period,
letter of intent vs. letter of acceptance, post-bid negotiation and re-bidding, and privilege
clause.

A guide document outlining the process of soliciting and evaluating construction bids, and
awarding the construction contract. Includes a sample bid form. * Available in both hard copy
and electronic formats.

CCDC 24 - 2016 A Guide to Model Forms and Support Documents


A guide document to assist users of CCDC 2 - 2008 in meeting the administrative requirements
outlined in that standard contract form. For each model form the guide contains a brief
explanation of each of the administrative processes involved, a short narrative description to
guide users of the form, a list of items which should be included in the form, and an example of
a model form. (Table of Contents Preview)

CCDC 29 - a Guide to Pre-Qualification

CCDC 29 is developed for Procurement Authority (e.g. Owners, Consultants, Construction


Managers, Design-Builders) to explain and recommend best practices through the entire pre-
qualification process.There will be discussions on how to determine whether pre-qualification is
necessary and appropriate during the procurement planning, comparison of various types of
pre-qualifications (unlimited, short-listing, source-list), best practices for Request for
Qualifications (checklist, submissions, evaluation and interviews, notification and debriefing).
There will also be an explanation of the revised CCDC 11 ‘Contractor’s Qualification Statement’
and its correct use. (Table of Contents Preview)

CCDC 40 - 2005 Rules for Mediation and Arbitration of Construction Disputes (Table of
Contents Preview)

Standard rules for mediation and arbitration of CCDC 2 construction disputes to be used in
conjunction with the dispute resolution procedures of CCDC 2.
Construction disputes are commonplace. The multiplicity of parties and technical complexity of
major construction projects makes these projects very susceptible to disagreements. The costs
associated with resolving disagreements can be burdensome even for the largest organizations.
To avoid major expenses, lengthy and drawn out courts cases, and damaging future business
partnerships, many Canadian firms are looking to other processes, often known as alternative
dispute resolution (ADR) processes to manage conflict more efficiently.

Canadian Construction Documnets Committee (CCDC) has adopted this approach to dispute
resolution in its contract forms. The CCDC contract forms set out very speci.c methods for
settling disputes incorporating the ADR concepts of negotiation, mediation and arbitration in a
manner that encourages speedy, inexpensive and voluntary resolutions of construction
disputes.

CCDC 40 – Rules for Mediation and Arbitration of Construction Disputes has been specifically
designed to be used with the dispute resolutions of CCDC contract forms and are incorporated
by reference, most notably CCDC 2.

Some of the features included in this document are:

1. Graphic sequence of the process delineated in PART 8 – DISPUTE RESOLUTION of CCDC


2 – 2005, including timeframes for the expeditious resolution of construction disputes.

2. Rules for mediation of construction disputes broken into three parts which include general
information, the process itself, and subsequent proceedings.

3. Rules for arbitration of CCDC 2 construction disputes broken into five parts including general
information, pre-arbitration considerations, proceedings, the award and project disputes.

CCDC 41 - 2008 CCDC Insurance Requirements


Standard insurance requirements to be used in conjunction with the insurance provision of
CCDC contract forms.
* A free guide that is included as the last page of the CCDC 2 - 2008 electronic document.

CCDC 43 - 1998 A Guide to the Use of CCDC 3 - 1998 Cost Plus Contract
A guide document designed to assist users of CCDC 3 - 1998. (Table of Contents Preview)

CCDC 44 - 2016 A Guide for Use of CCDC 14 and CCDC 15


A guide document designed to assist users of CCDC 14 – 2013 and CCDC 15 – 2013. (Table of
Contents Preview)

CCDC 45 – 2011 A Guide to the Use of CCDC 5A – 2010 Construction Management


Contract – For Service
A guide document designed to assist users of CCDC 5A – 2010. (Table of Contents Preview)

CCDC 46 – 2011 A Guide to the Use of CCDC 5B – 2010 Construction Management


Contract – For Service and Construction
A guide document designed to assist users of CCDC 5B – 2010. (Table of Contents Preview)

CCDC 47 – 2011 A Guide to the Use of CCDC 17 – 2010 Stipulated Price Contract
Between Owner and Trade Contractor for Construction Management Projects
A guide document designed to assist users of CCDC 17 – 2010. (Table of Contents Preview)

CCDC 48 - 2002 A Guide to the Use of CCDC 18-2002


A guide document designed to assist users of CCDC 18 - 2001 Civil Works Contract. (Table of
Contents Preview)

Você também pode gostar