VINCI I SUMITOMO MITSUI .JOINT VENTURE VIETNAM TELEVISION CENTRE PROJECT PACKAGE No.

XL-1

No. 1A, Lane 75, Nguyen Cong Hoan Street, Giang Vo Ward,

Sa Dinh Dist., Hanoi, Vietnam

TEL: + 84-4-771.-2567 Fax: +84-4-771-2667

Date: 24th October 2007

Ref: JVCW-PM/PSjNTTGj2007-2740

From = Philippe Schorsch

To: PMU - VTV Center Project 43 Nguyen Chi Thanh Street Ba Dinh District,

Hanoi, Vietnam

Attn: Mr. Luu Huu Bao Executive Director

VTV~PMU

2 5 -lD- 2D07 \~\t~_

Cc: NHK Integrated Technology Inc.

Attn: Mr. Nasato Kawai Project Manager

Subject: EOT Claim

Dear Sir, We attach herewith our claim submission for an extension of the Time for Completion of the Works pursuant to Clause 44 of the Conditions.

Best regards,

Project Director Vinci - Sumitomo Mitsui Joint

Attachment; Interim Application for Extension of Time for Completion

1 c

c_ •••• _' ____

Interim Application for

Extension of Time for Completion

Application for Extension ofTime for Completion and Additional Cost Claim - JVCW-PM/PSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

Contents

Section One

Introduction

Section Two

Notice

Section Three

The Origins/Causes of the Delays

Section Four

The Impact of the Delays on the Planned Programme

Section Five

The Prolongation Loss and Expense

Section Six

Conclusion

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMlPS/NTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

2

I , l

Appendices

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMIPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

3

Appendix A

The Progress of Design

Appendix B

The 4 March 2006 Planned Programme

Appendix C

The As-Planned versus As-Built Delay Analysis

Appendix D

The Impacted As-Planned Programme

.. . ~''''···:·",:1

Section One

Introduction

1. On 7 November 2005, the Contractor was awarded, by the Employer, a construction contract in relation to the VTV Centre Project. The contract was based on the FIDIC Conditions of Contract for Works of Civil Engineering Construction (Fourth Edition 1987).

2. As is customary under the usual arrangements for this type of contract, the Contractor was to construct the Works in accordance with the design provided by the Employer, which design was to be translated into various plans, drawings, calculations and the like (hereinafter referred to as "drawings" or "construction/working drawings" as the case may be).

3, Certain delays, which are not attributable to the Contractor, have arisen to date on the project and these delays have delayed the progress of the Works and caused a critical delay to progress. The Contractor is, as a consequence of these delays, entitled to a fair extension to the Time for Completion.

4. In order to allow a full and proper consideration of the Contractor's rights to a fair grant of an extension of time, the Contractor feels that it is an appropriate time to submit a wrap-up interim application given that no extension of time has been granted to date.

5. This wrap-up application supports an interim extension of time application of at least 147 days.

6. It should be noted that this submission will only address excusable delays up to the completion of the ZOIZI level slabs. Thus this submission only addresses delay up to 8 May 2007. Excusable delay post 8 May 2007 will be the subject of a further interim submission (if and when required).

Application for Extension of Time for Completion and Additional Cost Claim - NCW-PMIPSfNTIG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

4

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PM!PSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

5

7. In previous correspondence, the Contractor confirmed, and the Employer had subsequently agreed, that the Commencement Date was fixed as 17 February 2006.

8. The Contract Period is 28 months and the Time for Completion was set as 16 June 2008.

Section Two

Notice

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PM/PSINTfG/2007-2740 Vinci-Sumitorno Mitsui JV ("the Contractor")

6

9. It is accepted that Clause 6.3 of the Conditions requires that the Contractor provide notice(s) setting out the ramifications oflate Drawings, information and/or any other delaying event.

10. For the following events, the Contractor believes that this submission fulfils the notice requirements.

11. The Contractor has submitted notices in the form of various documents and correspondence, during the material time, dealing with both the general and specific delays as discussed in this submission. The Contractor will not, for the sake of brevity, list those notices here. In the event that parties wish to see these notices, the Contractor will compile them separately.

Section Three

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMIPSfNTTG/2007·2740 Vinci-Sumitomo Mitsui JV ("the Contractor"}

7

12. The origins/causes of the delays incurred by the Contractor are threefold: the untimely provision of incomplete drawings; the rejection of a nominated sub-contractor; and the constraints linked to the November 2006 APEC summit. None of these delays were attributable to the Contractor.

The Origins/Causes of the Delays

The Untimely Provision of Incomplete Drawings

13. The Contract provides that the detailed design of the Works (excluding temporary works) is the obligation ofthe Employer.

14. Thus, "for construction" drawings would need to be issued by the Employer by the Commencement Date.

15. As part of its design duties, the Employer was to provide the Contractor with construction/working drawings (i.e. drawings which are necessary to construct the Works and to enable the Contractor to meet the programme submitted in accordance with the Conditions of Contract).

16. The Contractor does not mean that all construction/working drawings must be issued to the Contractor on the commencement date of the works. Construction/working drawings are required by reference to the Contractor's programmes showing either the actual date drawings are needed, or, on the date procurement, shop drawing preparation or site work activities require the reference to and use of such drawings.

17. As an example, construction/working drawings for the foundation work and ZO/ZI slabs, and M&E services below, or through, these works, as well as drawings for long lead items, would be required at an earlier stage than, for example the drawings for the roof structure.

The 10 February 2006 Drawings

18. The drawings were initially issued on 10 February 2006 under EI-002 (the "10 February 2006 drawings").

19. It is understood that these drawings were considered to be construction/ working drawings as required by the Minutes of Contract Negotiation Meetings -Contractual Adaptations.

20. By a letter dated 16 October 2006 the Engineer stated that "IFC ["issued for construction"] drawings is not a definition which is referred to under the Contract". Notwithstanding this, the Contract requires the Employer to provide construction/working drawings (which are fully detailed in all respects) as required by the Contractor to meet the Contractor's programme submitted under Clause 14.1 of the Conditions. Whether such drawings are called IFC drawings or construction/working drawings is irrelevant.

21. It is the Contractor's position that the 10 February 2006 Drawings were not prepared and developed, or completed, and hence could not be construed as construction/working drawings. Such terminology refers to a set of drawings that were capable of being used by the Contractor to prepare full shop drawings andJor from which the Contractor could order materials and/or commence and progress its work.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PM/PSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

8

22. Notwithstanding the lack of detail inherent in the 10 February 2006 drawings, the Contractor commenced, as far as was possible, the planning and preparatory works to allow the site works to commence as per the Contractor's original intentions.

23. Upon review of the 10 February 2006 drawings, the Contractor became aware that these drawings were the same as the Bid stage drawings. It appeared that the many changes that were discussed and agreed between the Employer and Contractor during the Contract Negotiation Meetings had not been incorporated into the 10 February

2006 drawings. The Contractor notified the Engineer/Employer of this issue.

24. The aforesaid was acknowledged via the Engineer's letter of 1 March 2006 wherein it was stated "the Drawings issued for Construction ... do not reflect any changes made post 30 September 2002 ... ".

25. The 1 March 2006 letter also stated" ... accordingly revisions can be traced by reviewing the documents referred to within section 2 of the Contract Agreement ... ".

26. As a consequence of the inadequate detail contained in the 1 0 February 2006 drawings, the Contractor was compelled to submit a multitude of requests for information or clarification C'CLR's") to resolve uncoordinated matters and missing information.

27. As an example, the ZO slab was shown by the 10 February 2006 Drawings to have a number of different levels, but the locations of the steps and/or transitions between the various levels were not clearly identified.

The 10 June 2006/24 July 2004 Drawings

28. Further supplementary drawings were then issued 4 to 5 months into the Contract.

These supplementary drawings were issued on 10 June 2006 and 24 July 2006 respectively.

29. The 10 June 2006 Drawings did not adequately answer to the various requests for clarification issue by the Contractor to the Engineer.

30. The 10 June 2006 Drawings also included significant changes when compared to 10

. February 2006 Drawings (which changes amounted to a variation of the Contract terms).

Application for Extension of Time for Completion and Additional Cost Claim -JVCW-PMIPSINTTG/2007-2740 Vinci-S umitorno MitsuiJV ("the Contractor")

9

31. As a result, the Contractor had to produce extra-work (exceeding its scope of work which led to the Contractor incurring further delays).

Rejection of Sub-Contractor

32. It is submitted that the Engineer's design checks, and incorporation of the agreed outstanding information - and the introduction of further changes and variations to the detailed drawings required - for the 2:0 slab as an example - some six months before the majority of such drawings were finalized and could be considered suitable to progress to M&E co-ordination (which then led to further changes and amendments which will be the subject of further submissions at a later date).

33. The Contractor sets out, at Appendix A hereto, a comparison of the 10 February 2006 and 10 June 2006 drawings along with a detailed explanation of the changes that were introduced via the 10 June 2006 Drawings and the impact this had on the shop drawing preparation process and the subsequent impact on the progress of the site works.

34. Athough the Contractor had started the piling works on time, excusable delays occurred to the pilecap, ground beam, ZO and Z 1 slab works.

35. The first reason for the delay to the pilecap, ground beam and ZO/Zl slab works is because the sub-contractor selected by the Contractor for this work was rejected by the Employer and it was suggested to the Contractor that a specific alternative subcontractor be proposed notwithstanding the Contractor's objections that the proposed sub-contractor did not possess the necessary skill and/or ability to take on the structural works.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW -PMIPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

10

36. Pursuant to Sub-Clause 59.2 of the General Conditions of Contract "The Contractor shall not be required ... to employ any nominated Subcontractor against whom the Contractor may raise reasonable objection ... ",

37. The fact related to the aforesaid were:-

i) The Contractor had chosen and proposed Messrs Cofico to act as its structural sub-contractor on 15 May 2006 in anticipation of a commencement of work to enable pilecaps to commence on 7 July 2006.

ii) The Contractor considered that a duration of some two months was needed by Cofico for planning, rebar shop drawings and fabrication and mobilisation of Cofico's resources. The application was thus made around 2 months ahead of work starting on site so that final commercial, technical and planning details could be executed to avoid delay.

iii) The Employer denied approval for the appointment of Cofico.

iv) Despite appeals by the Contractor, the Engineer, on behalf of the Employer, continued to reject the appointment of Cofico through further letters and this occurred during the period 29 May 2006 and 20 June 2006.

v) Approval for the appointment of Cofico was finally given on 20 July 2006.

vi) This is a delay of 66 days from the planned appointment date (16 May 2006 to 20 July 2006).

38. By the Schedule of Supplementary Information contained in the invitation to Bid, the Contractor was required to submit a list of proposed sub-contractors in accordance with Form 7.2-Al and 7.2-A2. The Contractor understands that this procedure was drawn up to allow the Employer to consider the track record and experience of such sub-contractors at an early stage before the Contract was awarded and it is suggested that the early submission of the list of proposed sub-contractors was required for the purpose of saving time during the Contract.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PM/PSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

1 I

39. In its Bid, the Contractor submitted a number of subcontractors it planned to use for various parts of the work (Cofico were shown as one of those subcontractors) - as per attachment 10 - List of Sub-Contractors - 5 pages.

Application for Extension ofTime for Completion and Additional Cost Claim - JVCW·PMlPSINTTG/2007-2740 Vinci-Sumitorno Mitsui JV ("the Contractor")

12

40. Item 3.7 (page 7) of the Minutes of Contract Negotiation Meetings recorded "Subcontractors and suppliers listed by Vinci-SMCC in the list attached hereby and/or in its Bid are approved ones by VTV-PMU". In other words, the Contract documents confirmed that Cofico were already approved as a sub-contractor.

41. The delay in the appointment of Co fico caused by the late appointment was 66 days ".

42. The Contractor thus respectfully requests an extension of time of the Time for Completion of 66 days.

43. However, the Contractor notes that this delay was also, in the final analysis overtaken and subsumed by the excusable delays that occurred in the commencement of construction of the Area C ZO/Z 1 level slabs.

44. As at the end of July 2006, when Cofico was finally confirmed, the resolution of the various issues pertaining to the ZO/ZI structural works was still ongoing.

Constraints linked to the APEC Summit

45. Traffic restrictions were placed on the Ha Noi road network as a consequence of the APEC summit held during the month of November 2006.

46. The imposition of traffic restrictions was a Government directive pursuant to SubClause 70.8 of the Conditions of Particular Application and these restrictions impacted the progress of the works.

47'T~Vhilst the restriction covered the period 30 October 2006 to 22 November 2006 (24 days) the Contractor was able to deliver a restricted amount of rebar and concrete in the first days of the aforesaid period, but from 11 November 2006 no materials were delivered.

48. Following the lifting of the travel restrictions by the Government there was a surge in requirements of contractors (as all projects were backed up due to the three week stoppage of all construction related traffic) and as a consequence it took a further period of time to return to 'normal'. The Contractor calculates that the actual delay to the critical concrete progress was 21 days.

49. In conclusion, the late provision of incomplete drawings, the Employer's involvement in the selection of sub-contractors and the imposition of traffic restrictions by Govenunent directive have caused delays, which in turn impacted the progress of the works as envisioned by the planned programme.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMlPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

13

Section Four

Impacts of the Delays on the Planned Programme

i) The first submission was the programme for the site construction activities submitted by the Contractor on 4 March 2006 which set out the start and end dates and the sequencing of the major activities as planned by the Contractor (the "4 March 2006 Programme"). This is set out at Appendix B hereof

50. The dates that construction/working drawings and information were required by the Contractor can be determined by two important submissions made by the Contractor early in the works.-

ii) The second submission was the project monitoring matrix for engineering drawings submitted by the Contractor on 4 April 2006 which set out the dates that specific responses or approvals were required to be issued to enable the Contractor to undertake shop drawing preparation and procurement/planning works to allow the Contractor to meet the dates set out in the 4 March 2006 Programme. This document also set out the time frames that the Contractor required to finalise its own pre-site work. Hence the Contractor considers this document to be an integral part of the 4 March 2006 Programme and future reference to the 4 March 2006 Programme shall also include reference to the project monitoring matrix for engineering drawings. This document is also set out at Appendix B hereto.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMIPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV (lithe Contractor")

14

such costs ... ".

51. The project monitoring matrix is a schedule the Contractor has derived based on the timelines set out in the 4 March 2006 Programme. The intention of the monitoring matrix is to establish when information and approvals are needed by the Contractor. Essentially, the monitoring matrix was intended to, and did, show when the Contractor required information to be supplied. If information was not provided by the dates shown, then delays could occur.

52. Sub-Clause 6.4 of the General Conditions of Contract provides that "If, by reason of any failure or inability of the Engineer to issue, within a time reasonable in all circumstances, any drawing or instruction ... , the Contractor suffers delay and/or incur costs, then the Engineer shall ... determine any extension of time ... and the amount of

53. Sub-Clause 44.l(d) of the General Conditions of Contract entitles the Contractor to claim for an extension of time "in the event of any delay, impediment or prevention by the Employer".

Application for Extension ofTime for Completion and Additional Cost Claim - JVCW-PMIPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

15

54. As a result of the events mentioned in Section 2 above, which include the need to resolve the various issues that arose in respect of the dimensions and levels of the ZO/Z1 pilecaps, primary and secondary girders, pits and slabs, excusable delay arose in the progress of the works.

55. In order to determine the quantum of delay that has occurred as a result of the above, the Contractor has undertaken what is termed an As-Planned versus As-Built Delay Analysis. That is, the Contractor has undertaken a comparison of the actual progress versus the planned progress (i.e. the 4 March 2006 programme).

56. The Contractor has prepared a delay analysis narrative, and this narrative is set out at Appendix C hereof.

57. The Appendix C analysis shows the extent of the delays in the various work activities.

For the sake of convenience however, the Contractor summarizes the individual delay events as follows.

Piling and Pile- Cutting Works

58. The 4 March 2006 Programme showed that bored piling would commence on 25 April 2006 and pile cutting for pilecaps would need to be completed by 7 July 2006.

59. The piling actually started just ahead oftime on 22 April 2006 thus showing that the Contractor was on time and on progress concerning mobilization and work commencement.

60. There were two individual piles which experienced unforeseen obstructions.

However, the dominant delay in the piling works arose as a consequence of the lengthening of the majority of the piles. The 10 February 2006 drawings had set out that all piles would be a fixed length.

61. The lengthening of the piles resulted in more time being needed to complete the piling works. The Contractor has submitted the cost impact of these claims separate to this submission including the associated loss of productivity of piling resources (including reinforcement work which was no longer standard length and had to be individually fabricated for each pile in situ).

62. However, these delays in piling were, in the final analysis, relatively minor and were not critical delays. The piling delays were ultimately overtaken by the pile hacking delays. The pile hacking could not progress on completion of the piling because of the ongoing finalisation of the ZO slab design levels.

63. Pile ha~king began in late July once the pile cut off levels were conclusively finalized.

This was three weeks after pile cutting should have been complete.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PMlPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

16

64. When pile hacking work was able to commence, the pilecap/ground beam and ZO slab progressed immediately thereafter showing that all that work was dependent upon, and related to, the same completed design information.

Application for Extension of Time for Completion and Additional Cost Claim ~ NCW-PMlPSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

17

65. As such, the quantum of the delay to pile hacking will effectively be determined by the delay to the pilecaps, ground beams and ZO slab which is discussed immediately below.

Pilecaps, Ground Beams, ZO and ZI Slab and the Resolution of Structural Details

66. The pile hacking works were supposed to begin on or about 24 June 2006, or two weeks before the pile cap commencement date. The pile hacking did not begin until the end of July 2006. This is a delay of38 days.\

67. The ZI slab works were supposed to be complete by 12 December 2006 but were only finished on 8 May 2007. This is 147 days late.

68. The Contractor sets out the reasons for this delay in more detail in Appendix A and Appendix C hereof, but in summary, the Contractor states:-

i) The structural details for the ZO/Zl level (particularly the Area C works) were resolved through clarifications and the issuance of further detail and this process was undertaken progressively over time which caused delays to the work - this is described in more detail at Appendix A hereof.

ii) To illustrate the delay impact on the progress of the work, the Contractor has prepared an impacted as-planned programme. This programme is set out at Appendix D hereof. This programme sets out the relationship between the resolution of the structural design and the ability of the Contractor to then progress site work. The programme also considers the dates of drawing or information issuances that needed to be correlated, checked and incorporated into the concrete body shop drawings by the Contractor.

iii) As a result of the resolution of design issues, as described in Appendix A hereof, this process resulted in the works not only being delayed but also be more complicated. Thus the physical works on site took longer than planned. The Contractor had, on many occasions as described in Appendix C hereof, to introduce additional steps (e.g, the addition of filler beams) in the sequence of work which added significant periods of time to the whole operation on site.

69. In conclusion, the multiple delays incurred by the Contractor, for reasons not attributable to the Contractor, have had a significant impact on the Project's planned programme. As a consequence of the processes described above and the consequential excusable delay, the Contractor has incurred an excusable delay of 147 days and thus claims an extension of time of 147 days.

Application for Extension of Time for Completion and Additional Cost Claim - JVCW-PM!PSINTIG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

18

Section Five

The Prolongation / Loss and Expense Claim

70, As a consequence of the above excusable delay(s), the Contractor has incurred, andlor will incur, additional cost

71. Such costs arise from the need to expend additional time related costs associated with the Contractor staying on the site longer than planned.

72. The exact cost cannot yet be ascertained, and until it can the Contractor submits that a pro-rate using the preliminaries method of payment as prescribed under the Bill of Quantities is fair and reasonable.

This equates to US$ 1,536,165.00 based on an exchange rate of 1 US$ = VND 17,759

74. That sum, for 147 days20, can be calculated as:-

VND 158,117,023,760 I 852 days (28 months) x 147 days

VND 27,280,754,099

Application for Extension ofTime for Completion and Additional Cost Claim - JVCW-PMIPSINTTGI2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

19

75. The Contractor acknowledges that actual cost is the correct means to evaluate the prolongation cost claim - however, for the purposes of interim payment the Contractor considers that the above sum is a fair and reasonable on-account amount to be paid.

76. In addition to the above the Contractor claims the under-recovery of head office overhead caused by the holding back of its valued and skilled resources for an additional 147 days.

77. The Contractor cannot yet ascertain this amount as it relates to a cost in the future.

The Contractor estimates a cost of US$IOO,OOQ per month which equates to US$3,287.67 per day. Thus, for a delay of 147 days, this claim is or US$483,287,49.

Acceleration Measures

78. The total estimated claim is thus US$2~019,452.49 plus financing costs and the cost of extension of the retention guarantee.

79. The Contractor confirms that it will take all necessary and reasonable mitigation measures to reduce the delay as much as possible and to keep the costs as contained as is reasonably possible.

80. The Contractor is unaware whether the Employer wishes to expend acceleration costs in an effort to reduce the delay and hence reduce these time-related costs (and, of course, the Employer's own time-related costs).

81. If the Employer wishes to explore such possibilities the Contractor is willing to

discuss such matters at the soonest opportunity as it is crucial, from experience, that such actions be implemented as early as possible whilst time for planning and preparation and alternative work sequences or measures still remain. The longer the wait to discuss such opportunities the more difficult will be the ability to effectively reduce the incurred excusable delay.

Application for Extension of Time for Completion and Additional Cost Claim - }VCW-PM/PSINTTG/2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

20

Section Six

Application for Extension ofTime for Completion and Additional Cost Claim - JVCW-PM/PSINTTGI2007-2740 Vinci-Sumitomo Mitsui JV ("the Contractor")

21

Conclusion

82. A number of delays, none of which are attributable to the Contractor, have impacted

the Contractor's planned progress of the Works.

83. Pursuant to Sub-Clauses 6.4 (Delay I Costs of Delay of Drawings), 44.1(e)

(Extension of Time for Completion) and 70.8 (Subsequent Legislation) of the Conditions of Contract, the Contractor is entitled to an extension of time for completion.

84. The Contractor estimates the delay impact on to amount in total to 147 days and

requests that the time for completion be extended in due proportion.

APPENDIX A

A Comparison of the 10 February 2006 IFC Drawings and the 10 June 2006 Drawings

APPENDIX A

THE PROGRESS OF DESIGN

I. The Contractor has compared the 10 February 2006 drawings S-O 18 and S-O 19 to the 10 June 2006 drawings S-018 and S-019 (as issued on 10 June 2006 via ElA- 0145 dated 9 June 2006) for the substructure works up to the ZO/Z 1 level. The Contractor's findings are set out as follows.

Drawing S-O 18 - ZO Floor Plan

2. The following ZO level changes were introduced via the 10 June 2006 drawings:-

i) The slab level was changed from ZO-2330 to ZO-2180 (i.e. the slab level was raised 150 mm) in the Zones bounded by grid lines Yl to Y13/X2 to Xll, Yl2 to Y13/XII to XI8, Yl3 to Y17/X2 to X3 and Y9 to YI2/XI to X2.

ii) The slab level was changed from ZO-3950 to ZO-3700 (i.e. the slab level was raised 250 mm) in the Zones bounded by grid lines YI2 to YI7/XI to X2 and YI5 to Y17/XO to Xl.

iii) Eight girder beams type FW were added at the oil tank Zone.

iv) The slab level was changed from ZO-3950 to ZO-IOOO (i.e. the slab level was raised 2950 mm) in the Zones bounded by grid lines YO to YI2IXII to XI2 (excluding the Zone bounded by YI to Y5/Xll.5 to Xl2), YO to Y121X12to X13 (excluding the Zone bounded by YI to Y5/X12 to X13), YO to Y12/XI5 to XI6, YI I to YI2/X13 to XI5 and YO to YIIX13 to XIS.

v) The slab level was changed from ZO-3950 to ZO-3700 (i.e. the slab was raised 250 mm in the Zones bounded by YI to Y5/Xl1.5 to X12 and YI to Y5/X12 to X13.

vi) The slab level was changed from ZO-3950 to ZO-2600 (i.e. the slab was raised 1350 mm) in the Zone bounded by grid lines YI to YIlIXl3 to XIS, YI/X12 to X13 and Y5/XI2 to X13.

vii) The depths of a significant number of FG primary girders were changed.

2

Drawing S-OI9 - Z1 Floor Plan

3. The 10 February 2006 S-OI9 drawing indicated that the ZI floor level would be cast at 8 individual levels. By the issuance of the 10 June 2006 drawing, a further 4 separate floor levels, over and above the original 8 specified levels, were added.

4. Similar to the ZO slab levels, the ZI slab levels were changed significantly by the issuance of the revised drawing S-OI9 on 10 June 2006.

i) Grid lines YI7 to Y18/X5 to Xl8 changed from ZI-1200 to ZI-1000 (i.e. the slab was raised 200 mm).

5. The changes in the ZI slab levels comprised:-

Ii) Grid lines YI7 to YI9/Z0 to X5 was changed from ZI-1200 to ZI- 1000 (i.e. the slab was raised 200 mm).

iii) The oil tank slab was changed from Z 1-1300 to Z 1-1700 (i.e. the slab was lowered 400 mm).

iv) Grid lines VI5 to YI7/X3 to X5 changed from Z 1-300 to Z 1-900 (i.e. the slab was lowered 600 mm).

v) Grid lines Y9 to Y13/X3 to X5 was changed from ZI-100 to Z1-60 (i.e. the slab was raised 40 mm).

vi) Grid lines Y13 to Y14/XI to Xl was changed from ZI-1200 to ZI-650 (i.e, the slab was raised 550 mm).

vii) Grid lines Yl l to YI2/Xl to X2 was changed from ZI-30 to ZI-650 (i.e. the slab was raised 620 mm).

viii) Grid lines Y9 to Y12/X5 to X7 was changed from ZI-1200 to ZI-60 (i.e. the slab was raised 1140 mm).

3

IX) Grid lines Y3 to Y9/X6 to X7 was changed from Z 1-30 to Z I -60 (i.e, the slab was lowered 30 mm).

x) A portion of the slab at grid lines YI I to Y12/X7 to X9 changed from ZI-30 to ZI-200 (i.e. the slab was lowered 170 mm).

-~-.~~--~-----

xi) A portion of the slab at grid lines Y9 to YIlIX9 to XIO was changed from ZI-200 to ZI-350 (i.e. the slab was lowered 150 mm).

xii) A portion of the slab at grid lines Y II to Y 12/X9 to X 10 was changed from ZI-30 to ZI-350 (Le. the slab was lowered 330 mm).

xiii) The Zone A slab from grid lines Y3 to Y13/XI2 to XI8 and YO to Y4/X16 to XI8 was changed from RI-I00 to RI-60 (i.e, the slab was raised 40 mm).

xiv) The Zone C slab from Y14 to Y17/X5 to X14 and Y13 to Yl4/X9 to X14 was changed from Rl-300 to RI-30 (i.e. the slab was raised 270 mm).

xv) The Zone C slab from YI4 to YI5/XI to X5, Y12 to YI4/X2 to X3 and Y15 to YI7/XO to X3 was changed from ZI-1200 to ZI-111O (i.e. the slab was raised 90 mm).

xvi) The Zone B slab from Y9 to Y12/X2 to X3 and YI to Y9/X2 to X6 was changed from ZI-1200 to ZI-1110 (i.e, the slab was raised 90 mm),

6. From the above, the Contractor calculates that some 62% of the Z I level slab was changed via the issuance of the 10 June 2006 Structural Drawings.

7. A further significant change was the introduction of stairs along grid line XIS/YO to Y12 and YO/YI6 to XDI8.

4

5

The 10 June 2006 Drawings

8. Drawing S-O 19 received on 10 June 2006 included no less than 20 separate floor level changes. The levels of the floor varied ZI-30 to ZI-1700.

9. The configuration of the floor level changes was very complex. Notwithstanding this complexity, drawings S-O 18 and S-O 19 did not clearly define where the floor level changes were to occur. Nor did the S-018 and S-019 drawings show the spatial relationship between the slabs and the associated primary and secondary girders.

10. The Contractor acknowledges that drawings S-018 and S-019 cannot be read in isolation, and the Contractor is aware that the framing elevations at drawings S- 030 to S-044 provided further information in respect of the primary girder levels. The framing elevation drawings, however, did not show the secondary girder and/or slab elevations in any detail whatsoever, and the Contractor submits that these drawings read in conjunction with drawings S-018 and S-019 were inadequate to understand the design intent.

1 I. The 10 June 2006 drawings can only be considered as preliminary design drawings. The Contractor submits that these drawings were not sufficiently detailed to allow the shop drawing process to progress in a timely and productive

manner.

12. For example, a simple comparison of Framing Elevation of the YI6 Frame on drawing S-043 to drawing S-O 19 shows that the finished floor elevations as indicated on drawing S-019 at grid lines X5 to X9 is ZI-30 whilst drawing S-043 shows the top of girder elevation to be ZI-450.

13. This is a difference of 420 mm (this example spans from Y 14 to Y 17/X5 to X9) and the 10 June 2006 drawings do not specify how this anomaly is to be addressed.

14. Furthermore, drawing S-061 shows the FG22 primary girders (i.e, the main girders in the Zone bounded by the aforesaid grid lines) being cast monolithically with the ZI level slab. Drawing S-064 also shows the secondary girders B-13 being cast monolithically with the ZI slab level.

15. Considering that the slab is shown as being 420 mm above the top of the primary girders and secondary girders, it logically follows that the ZI slab cannot be cast monolithically with the girders.

16. As a further example, drawing S-019 shows the slab level at grids Xl to X2NII to YI2 and YI3 to Y14 to be at level ZI-650. Drawing S-030 shows the top of main girder as being at level ZI-I110. There is no detail provided as to how the slab is to be supported given that the top of slab level is 460 mm above the top of girder level (ultimately filler beams were added to resolve this problem).

The 10 June 2006 Pit Drawings

17.

Drawings CP-OOI to CP-006 were issued on 10 June 2006. The CP drawings issued on 10 June 2006 were the first drawings which depicted the Zone C pits in any detail.

18. The CP drawings introduced significant changes to the heights of the primary girders, secondary girders and the ZI floor slab in the Zone C Zone.

19. Notwithstanding the changes to the main substructure elements in Zone C which were instructed via the 10 June 2006 CP drawings, the Structural Drawings issued on 10 June 2006 did not reflect these changes at all.

6

20. The CP drawings were not clear as to where changes in the top level of primary and secondary girders were to occur. For example, Section C-C on drawing CP- 004 showed the top level of the primary girder a~ grid line X6, X7 and X 8 as Zl- 300. Section D-D of drawing CP-004 showed the top level of the same primary girders as Zl-800. Notwithstanding this change ~n level, the plan drawing CP-OOl is silent as to where this elevation change is to occur, or if the beam was to remain at one level, which level that was to be.

21. The 10 June 2006 drawings incorrectly specifieq the top levels of the majority of the secondary girders (this is based on the assu[nption that the top of secondary

I

girder was to be the same as the top of slab) as the 10 June 2006 drawings

indicated).

22. By the issuance of the CP drawings, it was left to the Contractor to work out the complex geometry of the Zone C main girders, secondary girders and slabs.

l I

The Impact of the Drawing Changes on the Shop Drawing Process

23. As a consequence of the issuance of revised structural drawings S-O 18 and S-O 19 on 10 June 2006 and the new CP drawings on 1;0 June 2006, the effort put forth

I

by the Contractor in producing substructure shop drawing in accordance with the

"

10 February 2006 drawings was essentially wasted in that the issuance of the 10

June 2006 drawings rendered the majority of the previous shop drawing preparation obsolete.

7

24. This situation was exacerbated by the piecemeal nature in which supplementary design information was issued. As an example, EA-00035 was issued on 17 April 2006. This EA comprised copies of the Contractor's shop drawings which had been extensively marked up by the Engineer. Essentially, the Contractor's shop drawing was relied on to modify andlor clarify the design. By EA-00035, it was stated that for the level of the pit bottom slab in the Zone of XJJ-XJ6 and YO- Yl2 for Zone A (tower building), the Engineer will inform the Contractor in due

course.

25. Thus, as at 17 April 2006, the Zone A pit details remained outstanding, and this information was only provided on 10 June 2006 via the supplementary drawing issuance.

26. Upon receipt of the 10 June 2006 drawings the Contractor commenced the undertaking of the extensive revisions and re-works that were required as a result of the changes introduced on 10 June 2006.

27. Whilst the Contractor has mainly listed changes in slab levels in the foregoing section of this narrative, it is a fact that the change in slab levels had a consequential impact on the pile caps, the primary girders, the secondary girders etc.

28. The aforesaid changes impacted virtually all of the works in the affected Zones and these changes necessitated extensive revision of the associated substructure shop drawings including all affected plans and sections related to the ZO and Z 1 levels.

29. As noted above, the initial shop drawings prepared by the Contractor were used to finalize the design of the substructure works (although this practice was not limited to the substructure works only).

8

i) In response to queries B6, C20, C22, C25 C26, C20 and B23, the Engineer had responded via EID-002101 - Please refer to comments on the shop drawing (Zone A).

30. As further examples of this practice, the Engineer had responded to queries raised by the Contractor in May 2006 on 8 August 2006 via EID's 00201, 00202 and 00203. By these EID's the Engineer had provided responses such as

ii) In response to queries B15, B27 and B28 issued via EID-00202, the Engineer had responded - Please refer to the comments on the shop drawing Zone B and Zone C.

iii) In response to queries BIO, B12 and B251B26 issued via EID-00203, the Engineer had responded - Please refer to the comments on the shop drawing Zone BIC and Zone B.

31. The Contractor did not plan and was not required to be the initiator of the design of the works. This is the sole responsibility of the Employer andlor the Engineer. The process of "design by shop drawing" caused significant delays in the commencement of the substructure works and the increased complexity of the Zone C ZOIZI secondary girders and slabs contributed to an increase in working duration over and above the planned duration of these works.

32. Further substructure changes were introduced post August 2006 via EA-00234 (23 September 2006), EID-00289 (3 November 2006), EID-00298 (11 November 2006), EID-00270 (27 October 2006), EID-0027I (27 October 2006), EA-00220 (2 October 2006), EID-00249 (5 October 2006 - modification of beam positions), EID-00238 (28 September 2006), and EA-00406 (2 December 2006) amongst others.

9

33. The shop drawings for the pile caps and ZO level structural elements were completed and approved as follows.-

i) Zone C - 3 August 2006 (a delay of 87 days as per 10 37 of Appendix D)

ii) Zone A and B - 30 August 2006 (a delay of 114 days as per ID 38 and 39 of Appendix D)

34. These delays then impacted the completion of the reinforcement shop drawings and fabrication and these critical drawings were only completed one to two months later (see Appendix C for details).

35. This excusable delay In the shop drawing preparation and approval consequentially delayed the commencement of the detailed excavation, pile hacking, and the pile cap and girder.construction works.

10

APPENDIX B

APPENDIX B

THE PROGRAMME REQUIREMENTS

List of document attached:

- Letter Ref. No. JVCW-DED/SCW/VTT/2006-0316 dated March 04, 2006 from JV

- Letter Ref. No. Itec/CWj2006-015 dated 20 March 20, 2006 from NHK

- Letter Ref. No. JVCW-DED/SCW/CTU/2006-0399 dated March 31, 2006 from JV

- letter Ref. No. JVCW-DED/SCW/VlT/2006-0412 dated April 04/ 2006 from JV

- Letter Ref. No. Itec/CWj2006-064 dated April 25, 2006 from NHK

- letter Ref. No. Itec/CW/2006-035 dated April 3, 2006 from NHK

- Letter Ref. No. JVCW-DED/SCW/NTTG/2006-0501 dated April 21/ 2006 from JV

- Letter Ref. No. Itec/CW/2006-084 dated May 4, 2006 from NHK

VINCI I ,SUMITOMO MITSUI .JOINT VENTURE VIETNAM TELEVISION CENTRE PROJECT PACKAGE No. XL-1

No.1A, lane 75, Nguyen Cong Hoan Street, Giang Vo Ward.

Ba Dinh Dist, Hanoi, Vietnam

TEL: + 84-4-771-2567 Fax: +84-4-771-2667

To:

Attn:

NHK Intergrated Technology Inc. Mr. Masato Kawai

Project Manager

Date: Lt.- ~-:=; ~2006
Reg nO: ' 0\/t • .i ~ 'r:Jb-P _j_
Act Inf Ans
PM
DPM 1"-
,DED j1:<
MED 1<
CMD JJ( I
QESD ,
Ix:. 1
COD ;
AFD
CCD
Others Date: 04 March 2006

Ref: JVCW-DED/SCWNITI2006-0316

Cc: PMU - VTV Center Project 43 Nguyen Chi Thanh Street Ba Dinh District,

Hanoi, Vietnam

Attn: Mr. Luu Huu Bao Project Manager

From : Philippe Schorsch

SubJect:

EID-00004 dated 17 Feb 2006

- Notice of commencement of the cMI works.

Dear Sir,

1. Thank you for the Notice and the confirmation of 17 Feb 2006 as the Commencement date of the civil works.

2. As requested, please find enclosed hereto the following;

a. Overall work schedule and detailed work schedule

b. Mobilization and construction execution plan

c. Detailed cash flow estimate for progress claims

3. Your required insurance matters have been dealt with separately in our letter ref.

JVCW-AFDIMT/2006-0238 dated 9 Feb, 2006.

Thank you very much.

Regards,

1'< H I( k(Q.ived <Xv b Mcu - os

Philippe SCH RSCH Project Director

Vind - Sumitomo Mitsui Joint Venture

._._ .... _----_- ... _--_.--- .~

r ''\

,- 1.

i

.~ .~.-_..

. OVERALL WORK SCHEDULE

( .•.. , <::

_+~I~~-~·~·~·~·~·~·-C~-·~·~·~-~-~·~-~··~·~·~-~_.~·~··~'~-+'~'~'~"~-~'r-+-~'~'~--~'~-P-4~"~'r-'~-'~-r'~"~'~



>

..,

Z o i= o :::l It::

I(I)

Z o (,,)

5

(I) I-



o .::i!:

~ :§

:::l (I)

Z o j:: (,,) :::l It::

I(I)

Z o o

(3 z s

.,
o
w ~
~
z ~
~
I- "fi
CI)
Q OVERALL WORK S·CHEDULE. (DETAILED)

. (

'r --'-C-"-"T-"T~-~~.--r-r---.---'-~ -r~~---Y--'- -,----,----,----,---,.---.---.---.--l

HH-++-r+~+~-~-~~-~~+4~~-i~.+~~~f~~~~~~-~+~-~-+~~~~~-~~+-~~4-_1 ~-~_~--~~~~~4-~_+~~~~~lti=F~=F*i=.F~t-i=Fti=t-t~~=F~~+-~r=F--*-i=Fti=t-+~~~ ~~

-~-~~~-+-~~-~-+~~-+~~~4-~1-+~-~i~~++4-+-~~1-~~~+-~4-+-~~~~~-+4-~~-4-~-+4-+-~I++~I~~.~+-I-+~~+~-~-~~-----+~.+~f-+4-4-~~~-+4~+-~--+-l~+-~~ -~

-.

'"
0 l...,~!
~ 11.,1
" ~ 1--
'"
!
1<1: N~
b~ ref
J~-
~I~~
I ..,1
10"'1
1 I
Iz~i
10 N!
!",91
"'i -
~ ~I
,:t - .,

~

Z

!

I

~ I~~ II I~~ •

~~~~~~~-~-~~~:~~~~HH~~+4-++++~-+444~44~H-~4~~~~II~~ •• I.II~I.+1~+~++~44-~~I~~~~.IH~++++~~-~~.~~-+~~iH-

~o'~1 I~ -r~.+~~~I-+-4-~~~~~~~~~-+-~_'++-~~H-~~I~~·I~~4·~-~~~~+~~~I~4-~4-~4-1-.I~f~-~~4-~4~

0;:!1 I ~ .

Z~ I ~ •

<0 i m!
~ ~N'
i , I:; reI
16
<fi 1 ... ! --~
1« "'I
!:
~~:
I.e ~; II I •
,
8! ; I I
"I
",'-, "';
<J :11 J
z~t
NI
<fiN
'"
-c
I .~ +++-4~+-+-+-+-HHH---+--+--l--+--++---l-+-+-+-+-+-IH-...jH--4---+--+--++++-+-~- -- - --f-l--+-+-+--l--t--+-+-t-t---I---+-+--I- -I-I-I~-+ ++-!-+--I----j-l-f-H---+---+4-+





~ .

-J

::l C w :J: (,) (J)

~ tX: o

3:

...J ...J

~

W

> o

c w (J)

o n,

s

e,

>!;

:e

itt j

:A.;c:c~

-g;

:0') !

:5 i

::: t

':E

!~ :

d

-- I

'" ",i
5:
q , -, 'N! 1-·
;g' I. 1
m ~::;:~i
'" .... 1
..:(NI
~~;
u. ~!
8 ~!
N
",I
0"'1
~l i
:z'"
~
06
"'+t
",I
.0; f--
f--
f, I:;:;~
~.
J I;:; ...
f( ec
~~, u.~
{
\J 0-
z~J -·1- -_ . I-~r-+-
-~
.1
:... ~
i •
:::~ ," Ifif! J
.. 1 .1 1 J ,. 1
... Ii . ..- •
•• • ....
~ c- --I--- ... ... E ,
I ... I I
:1
.... ,~
j" ,.

I

-

-. .. . - - -. - - - r-~ '-~+'-" _,_._ _... • •• • - - • _. • •••• -... - - - ri= . .. . .... .... . _. . .. . ., - ... - - -- - . -- . .. . .. . .... . .. - . - - - - - . - - . .... .... . .. . .. . .. - - - . .... . .. . .. - -. - - - - - - - .. . .. . .. - .. . ... - - - . - - - - - .. ~""

UUU If!!lf~~~

nUii

!f!f~l!lfr

i ;

unn~~~iU~ :~~~lf~~~II~S

f~

,,,

~o

I~i

j

II NHK Integrated Technology Inc. ~VVlElNAM 1El.EVISION CENlRE PROJECT

~ N. NO. 1A, L..ane 75, Nguyen Cong Hoan street, Giang Yo Ward, Ba Dinh District. Hanoi, Vietnam III Tel : 84-4-7719181 Fax:; 84-4-7718565

To: Vinci-Sumitomo Mitsui Joint Venture

Attn: Mr. Philippe Schorsch Project Director

Date: 2.2- - s -2006
Reg nv: HHK 2oVt.- OA '9-.
Act Inf Ans
PM )0
DPM X
BOO 2><
MED
CMD Xl
QESO
COD V
AFD
CeD
Others Date: 20 March 2006 :r Ref: ItedCWl2OQ6..015

Cc:. PMU-vrv Centre Project

Attn: Mr. Luu Huu Bao Director

Subject: Submission of Documents

OearSir,

Further to your letter Ref. JVCW-OED/SCWNITI2OO6-0316 dated 04-March-2006 we respond and comment upon your submissions as follOWS:

Comments on Contractor Submission

• Overall Work Schedule:

o Theaitical path and theaiticaJ path activities need to be identified on the Sdledule.

o EanystartlfiniSh and·latestart/finish are not shownbnthe Schedule - therefore float cannot be determined.

• OveraIlWork: Sdledule (Detailed):

o Theaitical path and the aitical path activities need to be identified on the Sdledule.

o Eal1ystarVfinish and late start/finish are notshown on the Sd1edule :-thereforefloat cannot

/~-', . be determined.

, -!'

o The Contractor further needs to explain the following activity issues:

• The addition of 1D-14 which was not previouSly subniittedwithin the Overall Work: .

Schedule as submitted within the Project Exea.rtion Plan. Bidding Dowment Volume 1.

• An explanation as to why the mass excavation quantity of 5O.950m3is much higher than 32,306.6m3 within thePriced Bill of Quantity. .

• Mass excavation, the Number Of tipJ6ny (24) is not the same as within the Project Execution Plan Bidding Document Volume 1.

• The submitted schedule ni:J.N shows fewer activities· than the schedule submitted within the Project Execution Plan Bidding Document Volume 1. The schedule is required to shoW the detailed activities, (Which appear to be hidden) of all main works (such as Pile caps, Ground Beams, Earth backfilling, Superstructure etc.).

.'

Comments on Contractor SubmiSSion Conrd.

• Mobilization and Construction ExeaJtion Plan

o ~ Organization Chart is required to be update for blank departments and the CVs of their respective managers. need to be supplied ..

o . AppendiX 2-Overall manpower sdleduJe is required to show the detall of indirect labour (Manager, Engineers, office staff etc ... ) and Direct labour (Supervisor, Foreman, Workers etc ... ).

o Appendix 3 ...,. Expected Madlinery Equipment Numbers of Equipment (sudl as Polymer plants, rebar cutter, welding madline, tipper forty etc .. )are not rorresponding the ExecutiOn plan .. The durations of using these equipmenfs are not corresponding to the durations ·in the Sdledule such as duration piling \'\fOrks, excavation etc ...

o For earthworks the· details of Disposal Works (such as disposal areas, .equipment. .. ) are required.

o The Contractor is required to submit the fOllowing sectons in his execution plan:

• Quality management system is required

• PrOject safety plan is required

• EnVitohh1entprotection"plan is required·

You are advised to review the above a resubmit as soon as pdSSibJe.

Yours Sincerely,

Masato Kawai Project Manager

NHK Integrated Technology Inc~

Date: - -200
ReI!; nO:
Act ~nf Ans
I~M
DPM
OED
MEl)
eM))
. QESD
COD
AFD
ceo
Others VINCI I SUMITOMe MITSUI .JOINT veNTURE VIETNAM TELEVISION CENTRE PROJECT PACKAGE No. XL-1

No. 1A, lane 75, Nguyen Cong Hoan Street, GiangVo Ward,

Ba Dinh Dist. Hanoi. Vietnam

TELD +·84-4-771~2567 FaxD+84-4-771-2667

Subject: .

IteclCWI2QOO.()1 s dated 20 March 2006 Submission of documents

Date: z ,. Z -200£
Reg II": l7t ;VI ~.
Act lor Am
PM
PPM ."Xj
.. 1):8.1} ~
MEO
CMD 1:>'<'1
_QESD
COD
AFO
CCD
Others Date.: 31st March 2006

Ref: JVCW-DED/SCW/CTU/2006-0399

. To: NHK Intergrated Technology Inc.

Attn: Mr. Masato Kawai Project Manager

Cc: PMU - VTV Center Project

43 Nguyen Chi Thanh Street 8a Dinh District, e

Hanoi, Vietnam

Attn: Mr. Luu Huu Bao Project Manager

From: Philippe Schorsch

Dear Sir,

We would like to respond to the above subject as follows:

1. Overall work schedule

a. The critical path and critical path activities are identified as attached.

b. Earlyllate start and earlyllate finish infonnation are identified as attached .

. 2. Overall work schedule (Detailed)

a, The critical path and the .critical path activities are identified on the schedule as attached.

b. Early/late start and ear1yllate finish irifonnation are identified as attached.

c. . Explanation to your quesnons are:

i. 1014 is related to mass excavation at Zone A and is not new.

ii. The mass excavation .quantity ·of 50,950m3 was based on tender stage estimation andis now obsolete, the quantity of 32,306.6m3 is correct as per Priced Bill of quantity. we have removed 50,950m3 from the attached sChedule.

iiL Mass excavation, please refer to the attached Appendix 3 for the

machinery .breakdown. .

iv. All hidden activities are now exposed as per attached Detailed·

overallwork schedule. .

3. Mobilization and Construction Execution Plan

Thank you. Regards.

a. The updated Organization Chart is attached and the required CV Were sent via letter ref. JVCW~PMlPSNTTI2006-0380 dated 25 Mar 2006.

b. Overall manpower schedule for both direct and indirect workers and staffs will be submitted soon.

c. Appendix 3-- Expected Machinery/equipment schedule is shown.

d. - For earthworks, the details of Disposal Works will be explained in the Method Statement of earthwork which will be submitted soon.

e. The QuaJity management plan, Project safety Plan and Environment protection plan have been submitted via Document Transmittal ref. no. JVCW-QESD/NTH/NTH/NTKD-2006-019 dated 29 Mar 06.

Philippe SCHORSCH Project. Director

Vinci - Sumitomo Mitsui Joint Venture

~_LWORK ___________ ... D ULE

...

. CRITICAL PATH

~~

"--'/ .~'"

~i

Fri 21-04-0E

Ear1yStart

Late Start

Early Finish Late Finish

VTV -OVERALL WORK SCHEDULE (As perltec/CW/2006-015 dated 20 March 06)

Task Name

Duration

I

2007 2008

-31-21-1 1 2 3 4 5 6 I 7 8

Free Slack Critical I--.--~+ !2£0~06~T-:-:--,-:'-'-:-:-"--T-;--r:-

N 10 J F M AM J J fA S

1 CONTRACT SIGNING 0 days Man 07-11-05 Man 07-11-05 Mon 07-11-05 Man 07-11-05 0 days Yes t-07-11 , ! __J-l--l---+--+---1r---+-+-t-~+-+-t-t--+-+--i~rl--t-1--r1

2~~~~OO~~~ ~~ T~u-e-'~5~~~1-~~S~-~T~u-e-'~S-~~1~-O~5~-M~M-·~1~~12~.~~~-~M~O-O~1~e~~~2~-O~5+---~0~d=Q~s+-~Y~e=s+~~.~~.~~~~-H:~~~-~_~!

f-3;-;::S~IT:;E=O-;::F~F;-;:IC;-;Ec;S-;-;::S ... E:;::T~U~P-=~==~==~c:-: ~~ ~~__+_-_S-'_:d-a;-y-sb-~Tu=_e_:_2o_:O-~'2=_~=5t_-T"Cu;:e-2:;:0-:_c'::_:2:_c-0::_:5+--T-;:h:-:U":o'~&'o~2-_;:O::::6+----Th;::U~'6o;-~02;;--O-;:;6;;--!-- __ -;:0,-:d;::a:::ys:+ __ Yv.e;:s+-i·-·","'r--i""~·rT--H-' --\.--1f--t+!I--+-··":"."_-_L...i_J_i-~-+1 ~~b+~~I--+--+~~t-t---t-~-j-i----r-

: 4 COMMENCEMENT OF SITE WORK (OFF. ICIAL) 1 day Fri 17~2-06 Fn 17_02_06 Fri 17~2·06 Fri 17_02-06 0 days Yes ," 1

'-::--:"7:":::::-:=-:-:-:==~7:":";::--:c:-:=-:::-::--:c~=c~-::--:c-o-:::-=-=-=cc::---~~-_:_--------+----+----o-------..1l__--"---4-----:::--o-=-:-:-=-,,,,+--=--:--=~d-------::;-:;-:::-::+--=++--+1~ r-f-M-iir----t- j-...1'

5 LAND SURVEYING AND MOBILIZATION OF MACHINERY 13 days Sat 1S-02-06 Sat 18-02-06 Sat 04-03·06 Sat 04·03·06 0 days Yes rI

ON D J F M AM J J AS 0 N 0 J F M.A M J J

9 10 11 12 13 1.l 15 16 17 18 19 20 21 22 23 2425 26 27 28 29 3(

6 STRUCTURE WORKS 472 days Mon 06-03-06 Mon 06-03-06 Tim 06-oe-07 Tue 09-10-07 0 days

6_1 SUBSTRUCTURE 206 days Mon 06-03-OG Mon 06-03-06 .Tue 31~1D"IJG Fri 24-11_06 0 days

6_1.1 TEST PI LES I NST ALLA TION 6 days Mon 06-03-06 Man 06-03-06 Sat l1-03-·06:-+----:::S~a:-t 1:-:':-_O"'3-Qc--::-:6:.f.-----;::0-:cd;:cay:"::s+--;Y:;:e=s-l-+----i--I+L.:'tt,-t-i--t---jrt--t--t

6.1.2 TEST PILES CURING 21 days Mon 13·03-06 Man 13-03-06 Wed 05-04,Q6 Wed 05-04-06 0 days Yes i hi

___ -;::6-:;.1;--.37-;;L:::;O;:-;A"'D=T-;E::;S;-T;;-;-:;:- -'--- +- _ _:22:"--d:_a-ys+-"""'T=_h-U__:3:-::0-:-0'"'3:-..()6dl-__:T=-h~U_c:3:_=0_:-0:_:3__:-0:_::6+_-_M=lln~24-0+~::.-.:-0s::+~_M"C0=_n"C24-()4-Q6 0 days Yes .. . .... - .. J---l~'!" .. ~: l--~-+---l--+--+I___,I-+-+--t-I--+-+-t~~+-+---l:--t-T---t-I-rll-tl

6.1.4 BORED PILING 58 days Tue25-04-06 Tue25-04-06 Fri30.(J6cOO Fri30.:o£-iiil· Od"3yS, Yes

:,.....~

Yes

Yes

6.1.5.2 Zone 8

6.1,5.MASS EXCAVATION ' 30 days Wed 14-06_06 Wed 14-06_06 Tue 18-07-06 Fn 11-OS-06 0 days Yes i!lI~

30 days Wed 14-0~G Wed 14-06_06 Tue 18-01_06 Tue 1S-07-06 0 days Yes ....

6.1.S.3 Zone C

30 days Wed 14_O~S Wed 14-0~6 Tue 1B~7-OS Tue 18~7_O6 0 days' Yes ... __ .

42 days Fri 07-07-06 Fri.07-07-06 Thu 24-08-06 . Fri 22-09-06 ti days Yes Ilf;l·~

6.1.6 PILE CAPS

42 days Fri ONl7_06 Fri 07_0],(16 Thu 24-08-«> Thu 24-<1S-06 0 days Yes rri!! ~ J.LI-.t--+---I-----;!---+-__+_~-t_+--+--1r-_r+--t-r---T-t--t-t-T

~--~~~==~~~------------~------~---+--~~~~~+--=~~~~~=+~~~d_--~~~~~~~r+~~~~" 1

6.1.6.2.1 Pile headtreatmeot 42 days Fri 07~r..()6 Frl07-07"()6 Thu 24-08..06 Thu 24-{)8_O6 P days Yes ,iii I--

6.1.E'i.2.2Rebar{17.600kg} 42 days Fri07~7..()6 Fri07-07-06 Thu24-'O&-(l6 Thu24-{)8-0S o days . Yes t· •. _

------~~~==~----------------~------~--~~~--~===+--==~~~~==~~==~----~~~~~-+,-~-T~t-r .. l~.~_~+-~~+-~~+-~-rT-rl~~rT

6.1.6.2.3 Fwk {592m2} 42 days Fri 07~7~6 . Fri 07-07~S Thu 24-0S.:o6 ' Thu 24-08-06 0 days Yes I •. _

6.1.6.2.4 Mechnical underground piping

42 days Fri 07~7-06 Fri 07_O7~ JblI 24-08-06 Thu 24-(16-06 0 days Yes I. !Ill

42 days Fri ONJ7..()6 Fri 07-O7~ Ttiu ~8-06 Thu 24-06-06 0 days Yes [ ••

. 6.1.6.2.5 Electrical puR box/manhole/PVC undergrd piping

.

6.1.6.3.1 Pile head treatment

42 days Fri 07-07_06 Fri 07-01-06 Thu 24-08-IJG . Thu 24-08_06 , 0 days . Yes '11Ii! 1iifiI

42 days Fri 07"()7-0G Fri 07 ~7 -06 Too 24-08-06 Thu 24"()8.-Q6 0 days Yes I- .. _

6_1.6.3 Zone C

6.1.6.3.2 Rebar (22.2l10kg)

42 days

42 days Fri 07~7-06 Fri 07_07-06 Thu 24-08-05 Thu 24-<J8-06 0 days Yes I_ . n.

Fri 07_07-06 Fri 07-07"OS Tff:.! 24-08-06· Thu 24-08-06 0 days Yes ,_ ...

6.1.6.3.3 Fwk (744m2)

Fri 07_07-06 Fn 07-07-06 Too 24-<18-06. Thu 24-08-06 0 days :. Yes I. _

6.1.6.3A Mechnica' underground piping

42 days

Fri 07_O7..()6 Fri 07-O7~6 TItu 24-08-06 Thu 244>3-06 0 days Yes 1-· '-

6.1.6.3.5 Electrical puR box/manhole/PVC undergrd piping

42 days

55 days 1 Tue O{l-08o{16 Tue 08_08-06 T-ue·10·10;.oo Wed 08-11_06 0 days' Yes :1!liII~"

6.1.7 GROUND BEAMS

6.1.7.2 Zone B

30 days Tue 08-08-OG Tue 08-OS-06 Moo 11-0$-05 ' Moo 11_09_06 0 days Yes IUI4-

.

i

I

__________ _;:6~.1~.7~.~2.~',R~e~b,a~r(~1~50~._;:0~00~k~9-)~-------- ~ ~ __ ~ -+ 370~d~ays~--__:T=-1I-e_:0~8-0~~~~--~T~ue__:0~8-0~8-O~6+_--~M~on-·~1~1-O~~~~_t-~M~on~l'~-O~~~t-----~0~d'_a=ys=·t_--vy=es~_+--~~-t~~t_-r-i-tt~~ •

6.1.7.2.2 Fwk (4744m2}60worl<ers 30 days Tue 08-08-06 . Tue 08-08-06 Moo 11_09-06 ' Man 11-09-06 0 days' Yes ~ •.

6.1.7.3 Zone C _" 30 days rue U8-08-O.6 rue UIHI8-06 Mon 11-09-(1) Mon 11-1J9-Oli 0 days Yes IEII -.cl--l-___jf--:~-+---+-l--+--+-1f---+-+-t--,--j-i---t1 ~-tl---l I:_!I

~--------~6.~1~.7~.3~.~1-;::R~e~ba7r~(~15~0~,4~0~0-kg-)--------~---- }_ __ ~30~da-y-s+- __ ~T~u-e~o7sc~0~e.~0:_=6~--~T~u~e~07s-O~S~~+_~M~on-1~'~-O~~~·~.~~M~o~n-'~'~..()~~~~·------~O~d~a~ys~·---yve=$~_+--~~_r~~t--r-t-t~~i~-tI-.~~I~--+-~-+~~+-~-4--+-~-t--~t_-·t_t__t_1!--t_i

____ ~~~6~.~'~.7~.3~.2~Fwk~~~~.7~O~07.m~2-)-------------------------------- }- __ ~30~da-~~--~T~U-e~O~8-0~a..()6~J---~T~u-e~0~S-O~~~6+_~M~~~1~.1~-O~9~-06~~--M-;Q~n~'~1;--O~9.~~~-- __ ~0"da~ys~--__:vYes~~+__r_i~r_lr~~r_i__~.

6.1.8 EARTH BACKFILLING 39 days Tue 12..09_06 Tue 12-09-06 ThU26-10-0G Frl24-11-01i o days Yes 1 I IR! !

6.1.82 Zone B - ----6.1.8.3 zOne c

1\

_____ ~ JL __ ~1:4~d:a~Ys~--~T~U:e~1~2~-O~&-06~:t--~T~u:e~1~2~-~~~S~ __ ·~~~ed~2~7~~~~·~ __ ~VV~ed~2~7~-O~9-0~6{_~--~;O;d;.ay~$4_--~y;.es~~~i--t~--+-~~--t-i--+~i~t-1-_t-l~t__r_t--r_~_t_lr_t__r_t--[1~--r-~-r~~

- ... -. 21 days Tue 12-09-06 Tue 12-09_06 .' TI'Ui 05-10-06 Wed'OS-11-06 . 0 da~ Yes : i

6. t.S.3.2 C5

. 21 days Tue 12~6 Tue 12~9-06 ThiJ 05-10--06 Thu 05-10-06 0 days Yes 1 L'6

43 days Tue 12..o9-OG Tue 12-09-06 t-.- Tui·31-10-6"fi·· ... ffl24·11-06 0 day$- YeS I!!I ""

6.1.9 ZO

..... - - . ---!----+---+-+--+--+--+-+-+-+---!

6.1.9.2 Zone B

1 .. days Tue 12-09-01> Tue 12009-06 WeqI 27009-06 Wed 27-09-06 0 d8)'$

28 days Tue 12..09-0& Tue 12-09..06 F.ti43--:10-06 Mon 23·10_06 . 0 days Yes I 8l

14 d~y~ TUt! 12.{)9..Qe Tilt! 12.(19-06 \"'kd~l-O.9~ WItd Z7-o9--Ol5 0 days Yes I ' •

(;.1.9.2.1.1 Re~r/conerete

14 days Tue 12-09..06 .. Tue 12-09_06 Wed.27-t19-OG Wed 27-0.9-06 0 day;. Yes m I'

6.1.9.2.2 B2

!

6.1.9.2.2.1 Rebar/concrete

.14 days Tue. 12-O~ Tue 12-09-06 Wed27"09-06 Wed 27_09-00 0 days Yes ! I. ! .,

Ii. SUPERSiRU·~CT;;:;. ;:;U·;;R=E----~~~-------...,..-...;....---------+--::!:-:44-:-::da-ys-f---=Th~u-2::::8:-"-O:;::9:-"_O~6::+----;;T:;-;h-u-;:2C::8·-O-::c::9·-O-::c::6 --_. MOIl 09:07:Oi·· . 1=1110-08_07 'IH1ars Yes r-M

==~~~~~~----------~------ __ ------ -- __ -- +-~~~--~~~~ __ ~-=~~~=-~~~--~~~~--~~~+_-..~~~~r4~~~rl~-- '

6.2.1 Z1 65 days 1l1u 28..09-06 Thu 28_09..06 ttMl"12-12-OG. Sat 30-12.06· 0 (1';1)'$ Yes

6.2.1.2.1.1 Fwk

14 days Thu28-0~ Thu28'-Q9--06 Fril3-10-0G Fril3-lO-06 o days' Yes

6.2.1.2 Zone B 44 days Thu2S-09.()6 Thu28-09-06 FrltT-11-06 FI111-11-06 o day$- Yes (l!iI~,

-----=-8 ..... 2""'.1'"'.2,-.1,.-:,6.,-1 -------.- .. .... . .... "- - .. .." ..... -.- ---···--·-·----J___-22~d~iI::ys=-!.. ---:Th~U~2~8~_O~9c-,_06~-~1~hll=-:2B~-O~.~9_O.;..6 ~~M:""o-n~23T~ .. 10-;::.o":t.r&k-:'.7M:-:O:--n""l23"'· :-:-1~0:-;"O::;:6+----.0 ... dr.:a;)'$:+_:-;Yii:e::s++-i-t-+--t4-t-+--t-t-j~lDrl-t-r-t-r-r-t-rlf:-j-r-T1-

i

h

S.2.1.2.12 RebarlCQnCfete

14 days Sat 07-10-06 Sat 07-10-06

Man 23-1(l:.06

o days

. Yes

!CCW2006-15(290306)

ViNCI CONSTRUCTION- SUMfT6MO MITSUI CONSTRUCTION JV

1

. -
Critical 2006 2007 .200B
[0 Task Name Duration Early Start late Start Eaily Finish Late Finish Free Slack M A M J J A S 0 N 0 J F M A M
N 0 J F M A M J J A S 0 N 0 J F
-1 1 :) .4 5 6 7 8 9 10 11 12 13 14 15 16 .17 18 19 20 21 22 23 24 2S 26 27 2\
-3 -2 2
B8 6.2.1.2.2 62 Thu28~9'{)G Mon 23-10~6 Mon 23·10-06 o days Yes , ~
22 days TOu 28-ll9-OG ,
._. I~ H ---
89 6.2.1.2.2.1 Fwk 14 days Thu 28-09.Q6 Thu 28-09-06 Fri 13-10-06 Fri 13-10-06 o days Yes t-·T 11
~ ... ,_ ,_"_ ~ ._.
90 G.2.1.2.2.2 Rebarfconcrete 14 days Sat 07-10-06 Sat 07-10-06 Mon 23-1 0-06 Mon 23-10·06 o days Yes ;
. _. ' . .-
91 6.2.1.2.363 22 days Tue 24-10-ll6 . Tue 24-10-06 Fri 17-11.(16 Fri 17-11-06 o days Yes I-i , I fpill
'-- ~- - - I
S2 6.2.1 .. 2.3.1 Fwk 14 days Tue 24-10-06 T ue 24-10-06 WedOlH1-06 Wed 08·11-06 o days Yes : ~1
.~--. -._ ~ ~
93 6.2.1.2.3.2 Rebarfconcrete 14 days Thu 02-11-06 TOu02-1HJ6 Fri 17-11-06 Fo 17-11-06 O·days Yes
94 6.2.1.2.484 22 days Tue 24-10-OG Tue 24·10-06 Fri 17-11-06 Fri 17-11-06 o days Yes 1 ~I!§
95 6.2.1.2.4.1 Fwk 14 days Tue 24-10-06 Tue 24-10-06 Wed 06-11-06 Wed OB-11-06 o days Yes I '~l
, .. ..
96 6.2.1 2.4.2 Rebar/concrete 14 days Thu 02-11-06 Thu 02-11-06 Fri 17-11-06 Fri 17-11-06 o days Yes ~
97 6.2.1.3 Zone C li8days . Fri 06-10-06 Fo 06-10..{l6 Tut.> 1Z-12..{16 Sat 30-12-06' o days Yes lif!!!!! IS
.,'~; .~
100 G.2.1.3.2 C2 18 days Fri OG·10-06 Fri06-10-ll6 Thu 26·10-OG Thu 26-10-OS o days Yes
101 6.2.1.3.2.1 Rebarfconc 18 days Fo 06-1Q..{16 Fri 06-10-06 Thu 26-10-08 Thu 26-1D"06 o days "fes iI

108 6.2_1.3.5 cs 22 days Fri 27-10-06 Fri 27-10-06 -rue 21-11..{1G rue 21-11-06 o days Yes Ii!
-
109 6.2.1.3.5.1 Fwk 16 days Fo 27-10-'06 Fri 27-10-06 Ttlu 16-11-06 Thu 16-1'1..{16 o days Yes ..
• ~-Ollays - ... - I
110 6.2.1.3.5.2 Rebar/cone 10 days Fri 1 D"11-06 . Fri 10-11-06 Tue21-l1..{16 Tue 21·11-06 Yes ... I II
._.
I
114 6.2_2Z2. 58 days Fri 17-11..{16 Sat18-11~ Tue 23-01-07 Sat10:.oZ-07 1 day No I.:.. .. l IIJ!i!!!I ,..
-
124 6.2.2_2 Zone B 41 days Sat 18-f1..{1G Sat 18-11-OS Thu 04-01-07 Thu 04-ll1-O7 . 0 days Yes , . !III!!I! I

125 6.2..2.2.181 20 days Sat 18-11-0$ Sat 1"8-11..()6 Man 11-12-06 Mon.11-1Z-06 o days Yes

126 6.2.2.2.1.1 Columns Sdays Sat 16-11..{1G Sat 16-11-06 Moo 27-11-06 Moo 27-11..{16 o days Yes
127 $.2.2.2.1.2 RCWaHs 14 days Tilu 23-11-06 Thu 23-11-06 . Pri06-12-06 Fri 06-12-06 o days Yes , i h \
128 6.2.2.2.1.3 Slab 12 days Tue 26-11-06 Tue 26-11-06 Moo 1-1-12-06 Man 11-12-06 o days Yes .. ~
;
129 6.2.2;2..262 20 days Sat 18-11-06 Sat 18-11-06 Mon 11-12-06 Mon 11-12-06 o days Yes ; i!B.
130 6.2.2~2.2. 1 Columns 8 days Sat 16-11-06 Sat 16-11-06 MOO.27-11-08 Moo 27-11-OS o days Yes
132 6.2.2.2.2.3 Slab 12 days Tue 28-11-06 Tue 26-11-06 Moo 11-12-06 Mon 11-12-06· o days Yes "-
133 6.2.2:02.3 83 18 days Sat 09-12-OG Tue 12·12.06 prJ 29-12-06 Fri 29-12-06 o days Yes il!!
134 6.2.2.2.3.1 Columns 8 days Tue 12-12-06 Tue 12~12..{16 Wed 20-12-06 Wed 20-12-06 Od8ys Yes I
-
136 6.2.2.2_3.3 Slab 12 days Sat 16-12-06· Sat 16-12-06 Fri 29-12-06 Frj 29-12-06 o days Yes
137 6_2.2.2.4 B4 21 days Tue 12-12-06 Tue 12-12;;(1G Thu 04-01-07 Thu04-01-07 o days Yes I
136 6.2.2_2.4.1 Columns Sdays Tue 12-12-06 Tue 12"12-06 Wed 2D"12-06 Wed 20-12-06 o days Yes •
139 6.2.2.2.4.2 RC Walls 14 days Sat 16-12-06 Sat 16-12-06 MOO 01-01-07 Mon 01-O1..{17 o days Yes jj'l
,
140 6.2-2.2.4.3 Slab 12 days Fri 22-12-06 Fo 22-12-06 Thu 04-01-07 Thu 04-01-01 o days Yes I ~
141 6.2.2.3 Zone C S8days Fri 17-11..{16 • Wed 22-1HI6 -Tue 2·3-O1..{17 Sat 10-02-07 4 days No tJ!IIIi! fIJ ,
14i r-t- "
6.2.2.3.2 CZ 16 days Wed 22-11-06· Wed 22·11-06 Sat09·12..{16 Sat 09·12:06 Oday:o Yes
147 6.2:2.3.2.1 Columns 8 days Wed 22-11-06 Wed 22-11-06 Thu .30-11-06 Thu 30-11.Q6 o days Yes
14.8 6.2,2.3.22 RC Walls 12 days Mon 27-11-06 MOn 21-11-06 Sat 09-12-06 Sat09-12..{1S o days Yes h
149 Sat O'f-12-06 o days Yes , f'I". I
6.2.2.3.2.3 Slab 12 days Moo 27-11-OG Man 27-11--00 . Sat 09-12-06
158 6.2.2.3.S CS 18 days Mon 11-12..{16 Mon 11-12-06 SaUO-1Z..{I6 Sat 3:0·12-06 .. o days . Yes i lpi
159 Tue 19-12-06 o days Yes , I i
6.2.2.3.5.1 Columns 8 days Mon 11-12-06 Mon 11-12.Q6 Tu·e 19-12'006 -j
.. ... _, .. f· .. • -~r ·-d---· .. .-~ _.~
-165- 6.2.2.3.5.~dl:C waifs· 12dByS -_·---F-;r15.::fi-06· •• L. Frt15:iz,oo Tilu 2S-12..{1G Thu 26-12-06 . o days Yes
,
161 6.2.2.3-.5,:7 Slab 14 days Fii 15-:12-06 Fn 15-12-00 . '&rt 30-12-06 Sat 30-12-06 o days Yes ,
162 6.2.3.Z3 .. 60days Mon25-12..oS Sat 30·H:.oG T.ue 20-02-07 Fr1 06-04-07 5 days No 1 i [1111
~ 1111
172 ·6.2.3.2 Zone B 39 days Sat 30-12-06 Sat 30-12-05 Tue13-02-07 Thu 1S-02-07 o days Yes ,
173 G.2.3.2.1 81 ··18 days Sat 30-12-06 . Sat 30~"2-O6 ·Fri 19-O1..{17 Mon 22-01,(17- OdaYli. Yes ,
i I
174 6.2.3.2.1.1 Columns 8daY$ Slit 30-12-06 Sat 30--12"06 Miln084)1·07 MonOtHl1-07 o days Yes [
"
176 6.2.3.2.1.3 Slab 10 days TueO~1-07 Tue09cm..{l7 • Fn 19-01-07 Fn 1~1..{17 o days Yes " 1 t-
177 6.2.3.2.2 B2 Fri OS-01-07 . Fri QS-01..{17 ·tnu 25-1)1-07 Sat 27-01-07 o days Yel> -' ._.
18 days .
178 6.2.3.2.2.1 Columns 8 days Fri 05-01-07 Fri 05-0t..{l7 sat 13-01-01 Sat 13-01-07 o days Yes
180 6.2_3.2.2".3 Slab 10 days Mon 15-01-07 ··Mon 15·0~-O~ "ffIl125-01-07 Thu 25-01-07 o days Yes ! t~ ,
i
181 6.2..3.2.363 1Gdays Sat 20-01-07 Sat 20-01-07 . Wed07..{1Z"()7 Fri 09-02-07 Odays • Yes ~ I
162 6.2.3.2.3.1 Ct;ilumns Sdays Sat 20-01-O~ Sat 20-01-07 Man 29-01-07 Mon~1-07 o days Yes I i
, VTV OVERALL WORK SCHEDULE (As per ItecfCW/2006-015 dated 20 March 06)

Fri ;

Nan(Qverall)ltecCW2006-15(2903OF) VINCICONSTRUCTION-SUMIT~MO MITSUI CONSTRUCTION JV

--------------~--------------~~~~~~~~~~~~~~~~~------~~----------------~------

" .. ~ '".,.;:. '-. ~ ,," ~ ..

""'\'-".'." ..

VTV ~OVERALL WORK SCHEDULE (As per Itec/CWf2006-015 dated 20 March 06)

Fri 21-0

10 Task Name Late Finish Free Slack Critical 2006 2007 2008
Duration Early Start Late Start Early Finish J A S 0 N 0 J F M A M J
N D J F M A M J J A S 0 N 0 J F M A M J
-3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 2~
184 6.2.3.2.3.3 Slab 8 days Tue 30-01-07 Tue 30-01-07 . Wed 07-02-07 Wed 07-02-07 o days Yes :
H_ ..
185 6.2.3.2.4 B4 16 days Fri 26'{]1'{]7 Fr; 26'{]1.{]7 TUc 13'{]2'{]7 Thu 1S'{]2'{]7 o days Yes
-- -- --- r-" .. _- ._- -- . __ . .- -
186 6.2.3.2.4.1 Columns 8 days Fri 26--01-07 Fri 26-01-07 $aI03--02-07 Sat 03·02-07 o days Yes I
-
1BB 6.2.3.2.4.3 Slab 8 days Man 05-02-07 Mon 05-02-07 Tue 13-02-07 Tue 13-02-07 o days Yes
._. !Dill
189 6_2.3.3 Zone C 4l! days Wed 27-12'{]6 Mon 01'{]1'{]7 Tue20.{]2"(}7 Fri 06..(}4-O7 4 days No :
,
194 6.2.3.3.2 C2 14 days Mon 01-O1"(}7 Mon 01..o1"(}7 Tue 16"(}1..o7 Tue 16"(}1-O7 o days Yes Ii
195 6.2.3.3.2.1 Columns 8 days Men 01..01-07 Mon 01-01-07 Tue 09--01-07 Tue 09-01-07 o days Yes
196 6.2.3.32.2 RC Wans 10 days Fri 05..01-07 Fri 05-01-07 Tue 16-01..07 Tue 16--01"(}7 o days Yes Ii
197 6.2.3.3.2.3 Beams 10 days Fri 05..(}1-O7 Fri 05-01-07 Tue 16..01-07 Tue 16-01-07 o days Yes ~ II
206 6.2.3.3.5 C5 16 days Wed 17"(}1-O7 Wed 17-(11..(}7 $at-03-(12"(}7 Sat03-02'{]7 o days Yes j i
L_" •• ~, •• ~ .. u . -
207 6.2.3.3.5.1 Columns 8 days Wed 17-01-07 Wed 17-01-07 Thu 25-01-07 Thu 25-01-07 o days -- yeS ~ I
208 6.2.3.3.5.2 RC WaUs 10 days Mon 22-01-07 Mon 22-01-07 Thu 01-02-07 Thu 01-02-07 o days Yes I
209 6.2.3.3.5.3 Beams/slab 12 days Man 22-01-07 Mon 22-01-07 ' Sat 03--02-07 Sat 03-02-07 o days Yes I
Ie
210 6_2.4 Z4 63 days Wed 17-(11-(17 Mon OS--Q2'{]7 Fri 30-(l3"(}7 Fri04-OS"()7 16 days No III

220 6.2.4.2 Zone B 44 days Thu 08'{]2-O7 Thu08-02'{]7 'Fri30-63"()7 Mon OH)4'{]7 (I days Yes
221 6.2.4.2.1 B1 3Sdays Thu OS.{]i-07 Thu 08-O2"()7 .Tue 20-(13-07 Tue 20..()3..()7 o days , Yes fiI!lI!
-- 'F« 16-02-07 Fri 16-02-07 o days Yes
222 6.2.4.2.1.1 Columns 8 days Thu 08-02-(17 Thu 08-02-07
--- Wed 26--02-07 o days Yes
223 6.2.4.Z.1.2 RC Wans 14 days Tue 13-02-07 Tue 13-02-07 Wed 28-02.,Q7 ."
224 6.2.4.2.1.3 Slab 12 days Mon 19--02-07 . Man 19-02-07 .Sat o:HJ3-07 Sat 03--03-07 o days Yes ~
225 6.2.4.2.1.4 Curing 7 days 7 days Mon05-03-07 Mon 05-03--07 MOIl 12-03--07 Mon12--03-07 o days Yes ;~
226 6.2.4.2.1.5 Post Tensioning 7 days T ue 13--03-07 Tue 13--03-07 Tue 20-03=-07 Tue 20-03-07 o days Yes t.
227 6.2.4.2.282 3Sdays Wed 14-O2'{]7 Wed 14..()2-(17 Moo 26-03--07 Mon26.{]3-07 o days Yes fIIi!I
228 6.2.4.2.2.1 Columns 8 days We(! 14-02-iJ7 We(! 14-02-07 ThO 22-02--07 rnu 22-02-07 o days Yes
229 6.2.4.2.2.2 RC warlS 14 days MOil 19--02-07 Mon 19-02-07 T ue 06-03--07 Tue 06-03-071 o days Yes Ih
,
230 6.Z.4.2.2.3 Slab 1Zdays Sat 24-02-07 Sat 24"()Z"()7 F«09--03-07 Fri09-03-07 o days Yes if
231 6.Z.4.2.2.4 Curing 7 (fays 7 days Sat 10--03-07 . Sal 10--03-07 Sat 17-03--07 Sat 17-03-07 o days Yes t;
232 6.2.4.2.2.S Post Tensioning 7 days Mon 19-03-07 Mon19-03-07 Moo 26-03-07 Mon 26-03--07 o days Yes
233 6.2.4.2.3 63 17 days Mon05-03-(17 Sat 10"()3-(17 fii 23-03-07 Fri 23-(13-07 o days Yes IBI
236 6.2.4.2.3.3 Slab 8 days Thu 15-03-07 Thu15-03-07 Fri 23-03--07 Fri 23--03--07 o days Yes ~
237 6.2.4.2.4 54 18 days Sat 10-03-07 Tue 13-03-(17 Fri 30-(13-07 Mon 02-04-07 2 days No IIiIIIi!
240 6.2.4.2.4.3 Slab 8 days Thu 22;'{)3-07 Thu 22-03-07 Fii 30--03-07 Fri 30--03-07 o days Yes •
241 6.2.4.3 Zone C 42 days Wed3-1~1~7 Mon ()S-02-tll fue~-tlj-ot ~ri 04-05-07 4 days No ~""
- 6.2.4;3.2 ClI Mon 05-(12'{)7 thu22..oZ"()7 Thu22-(12-07 o days Yes ~
24£ 16 days MonOS-(l2-07
-- Tue 13-02-07 o days Yes I
247 6.2.4.3.2.1 Columns 8 days Mon 05-02-07 Man 05-02-07 Tue 13--02-07
248 6.2.4.3.2:2 RC Walls 10 days Fri 09"()2-O7 Fri 09--02-07 Tue 20-02-07 Tue 20-02-07 Qdays Yes Ii
249 6.2.4.3.2.3 Beams 12 days Fri09-02-07 Fri 09-02-07 Thu 22'{)2-O7 Thu 22-0Z-07 o days Yes Ii
258 6.2..4.3.5CS 2a'days Fri 23-02-07 Fri 23-(12-07 .: Sat 1143.:.07 Sat 17.Q3..()7 o days Yes I !lID
259 6.2A.3.5,1 Columns 8 days Fri 23-02-07 Fri 23--02-07 sat 03-03-07 Sat 03-03-07 o days Yes , I
~ ..... .. -- .. -~ 8.2.4.3.6.2' RC Wana Wed 28-02-01 Wed 28-02-01 Tnu 15-Q3-07 Thu 15--03-07 o days Yes
14 days .Q
. '-'_"''''''''- ._-_= ... r • - "-'-
">0 ·"·WdayS .. ,-~----- "--.'~-' ~~- - ._. We42e-02;-Q7 .. -.,.- •. -.-~ - . o daY!> YI15
261 6.2.4.3.5.3 Beams/slab We<), 28--{1Z-Q7 '~117-Q;HJ7 sat 17-Q3--Q7
. ' ..
2112 6.2.6Z6 . - .. . ,.'., .. .. ,," .... _. ,~" .... _. _" .. ,-._-_.-._._ --_ . 'Frl1HIEi-Q7 Sllt2ii-Clli-tl1 QrJay" No ~
7adaYii Frl1G·02-07 TUI! n-tl~-OT
272 6.2.6.2 Zone S 42 days $at24-03..o7 $at24-03-{)7 ·Fn 114S-{)1 Wed 16-0$-07 o days Ycs ~i!ii
- •• M __ -
6.~.5>2.1 B1 -~-~- .. UdaYs S~t 24..03..07 . Sat24.o~:07 '" ~ ,----.-~.,---- Mon 16.04-07 Odllyn Vila , . ~
273 firiU-04-Q7
.. ~, .. ~ . ... _" ., - __ ,,_r ... ..-, .. - _ ....
Man o2':-6i.bY _._.- Vea' ... ..
214 ~ 6 ".5." 1.1 cOiumns .... _ 8 days Sat 24-03-07 Sat 24-03-07 MQIl 02-1)4-07 oda.Yil . ~ h
2:76 6.2.5.2.1 .a Slab ... _. Tue 03-04-07 Fri 13--04:-07 Fri 13-04--07 o days Yes Jt
10 days Tue 03-04-07
2a1 .. ~--~ .•.
6.2.5.2.3 03 18 daye Sat 14-04..07 Sal 14-04..Q7 ··I~04-{)5..o1 Fri 04-(1[1..01 OdllYIS Y.IS ., E
.. i -_ --
.~--. Sat 14=ii4=Of f--._ ......... .c._~. _
282 6.2.5.2.3.1 Columns 8day5 Sa! 14-04-07 Man 23-0+07 Mon23--04..(t7 o daYli Yes
-_ .. _- ... ... _-
284 6.2.5.2.3.3 srib __ T_· 10 days Tue 24-04-07 Tue 24-04-07 1"1104-05-07 Frl 04--05-(17 o days Yes •
~ .. -;-- -_ ... -;-;- -_._ ,-._- .. __ . "'1 .orT 1--- __ ,.-n. ."._- - .... _., - II IfIII!II!
289 6.2.5.3 ZOne C 4GdaYl; Woo 14-03-07 Mon 19-03-07 iSat 05-05..07 Sat2G-OS-07 4 days No
302 6.2.5.3.3.C3 30 days Mon 19..03-07 Mon 19-03-(17 :,Sat 21-04-'07 Sat 21'{)4-O7 o days Yes I !lID
..... -- : ian(OveraU}ltecCW2006-15(290306)

VINcr CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

-
2007 2008
ro Task Name Duration Early Start Late Start Early Finish Late Finish Free Slack Critical 2006
J J A S 0 N 0 J F M A M
N D J F M A M J J A S 0 N 0 J F M A M
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
-3 -2 -1 1 2 3
303 6.2.53.3.1 Columns 8 days Man 19-03-07 Man 19-03-07 Tue 27-03-07 Tue 27-03..07 o days Yes -~.
,~ _._,.- _._.
304 6.2.S.3.3.2 RC Walls 10 days Fri 23-03-07 Fri 23-03-07 T';e 03-04-07 Tue 03-04..07 o days Yes In
---'- .~-. ~--- I tt
--, Odays Yes
305 6.2.5.3.3.3 Beams/slab 12 days Fri 23-03-07 Fo 23-03-07 Thu OS-04-07 Thu OS-04-07
._ I-- It
306 6.2.5.3.3.4 Curing 7 days 7 days Fri 06-04-07 Fri 06-04-07 Fri 13-04-07 Fri 13-04-07 o days' Yes
l
307 6_2.5_3_3_5 Post Tensioning 7 days Sat 14-04-07 Sat 14-04-07 Sat 21-04-07 Sat 21-04-07 o days Yes
-. i-. _c_._ m
312 6.2.5.3.5 C5 28 days Wed 04.04-07 Wed11l-04-07 Sat 05.05-07 Tue08-05.o1 2 days No ,
315 6.2.5.3.5.3 Beams/slab 12 days Man 23-04-07 Man 23-04-01 Sat 05-05-07 Sat 05-05-07 o days Yes , i
,
316 6.2.6 Z6 83 days Man 19.03-07 Thu 12-04-01 Fri22.o6.o7 Sat 23..o6-ll1 1 day No
,
326 6.2_6.2 Zone B 42 days Sat 05.05-07 Sat 05-05-01 Pri 22-06-07 Fri 22.06.(17 o days Yes fi!!jiI!1l
327 6.2.6.2.1 B 1 16 days Sat 05.(15-07 SatOS-OS-01 We<:(23.oS-07 Wed 23-{l5-ll7 o days Yes iii
328 6.2.6.2.1.1 Columns _ .. 8 days Sat 05-05-07 Sat 05-05-07 r;1on 14-05-07 Man 14-05-07 o days Yes I-]
... - - l
330 6.2.6.2.1.3 Slab 6 days Tue 15-05-07 T ue 15-05-07 WeP. 23-05-07 Wed 23-05-07 o days Yes
33S 6.2.6.2.3 83 16 days Thu 24-05-07 Thu24-OS-01 Mon 11-06-07 Man 11-06.07 o days Yes Ifl

336 6.2.6.2.3.1 Columns 8 days Thu 24-05-07 Thu 24-05-07 Fri 01--06-07 Fri 01-06-07 o days Yes it
~
338 6.2.6.2.3.3 Slab 8 days Sat 02-06-07 Sat 02-06-07 Mon'11-06-07 Man 11-06-07 o days Yes ! ,
339 6.2.6.2.4 B4 20 days Thu 31.05-07 Tue05-06-07 Fri· 22-06-07 Fri 22-06-07 o days Yes ~
342 6.2,6.2.4.3 Slab 10 days Tue 12-06-07 Tue 12'{)6-07 Fri 22-06-07 Fri 22-06-07 o days Yes i,
380' 10 ARCHITECTURAL WORKS 3G3days Sat 20.01-07 Wed 14-{l2-O7 Wed 19-03-OS Wed 19.03.:08 o days Yes
381 10.1 BRICKlBLOCKWALUPlASTERING 193 days Sat 20-01-07 Wed 14-02-07 Mon03.o9-07 Wed 05-09-07 1 day No
10_1AZ4-Z5 Tue24-{l1-07 Wed 25-01-07 o days Yes I ,
394 86 days Sat 14-O4-{l7 Wed 16-05-07 ,
398 10.1.5 Z5-Z6 9Sdays Tue 15-05-07 Sat 09-06-07 . Moil 03-09-07 WedOS-09.{)7 o days No j
I
400 10.1'.5.2 Zone B 45 edays Fri20-07-Q7 Fri 20-07"{)7 Moo 03-09-07 Man 03-09-07 o edays Yes I ~
414 10.4 INTERIOR FINISHES (TlLES,CEllING,WALI ... FLOORI 21"1 days Wed 1S-07-07 Thu 19-07.:07 Wed 19-03-OS Wed 19-03-OS o days Yes
417 10.4.3 Z3-Z4 205 days Wed 25-07'{)7 . Wed 25-07'{)7 Wed 19-03.{)8 Wed 19-03-0S o days Yes
594 . 12 ELECTRICAL WORKS 462 days Thu 26-09-06 Wed 04-10-06 Wed 19-03..Q8 Wed 19-03-08 o days Yes
622 12.2 POWERSUPPL Y SYSTEM 34Sdays Mon 12-02-07 Mon 12-02-07 Wed 19-03'-OS 'Wed 19-03.08 o days Yes
625 12.2.3 Installation of HV Panel and LV Panel 60 days Mon 12-02-07 . Mon 12"{)2..{)7 .5at21-04--07 Sat 21..Q4..()7 o days Yes
626 12.2.4 Installation of AVR.UPS.TR;Bus duct 60 days Mon23-04-07 Mon 23-04-07 Sat30--Q6...07 Sat 30-06-07 o days Yes
Yes I+-
627 12.2.5 Cable connection adjustment 150 days Mon02-07-07 Mon 02-07-07 Sat 22-12-07 Sat 22-12-07 o days
629 12.2.7 6MS wiring,connection and Adjustment Test 75 days Man 24-12-07 Mon 24-12-07 Wed 19-03-06 Wed 19-03-06 o days Yes
636 13 STUDIO CONSTRUCTION 246 days Fri 04-05-07 TueOS-06-07 Sat 16-02-08 Mon 18-02-OS' 2 days No
671 13.4 STUDIO 3,4,5 Mon04.()2-08 Mon04-02-{lS o days Yes -:
132 days Mon03-09.o7 Mon03-09-07
67; 13.4. 1 FlOor flOating 2ewks Mon 03-09..07 Mon 03·09-07 Mon17-09-07 Mon 17-09-07 Oawks Yes ..,
. - ._. '-- ~- ._ ....
673 13.4.2 Scaffold to eeiling 1-" ·MOO01-1Q..O'T .. Moii 01:10:07 ,_ o ewKs Yes ;
2t!wk~ Mbn 17-09--01 Mon 17-09-07 .~ ,.- f---
; --- - .- 1- ... _.- f- .. , ' .... - ...
. -. ........
674 13.4.:! Ceiling sound insulation layer 5ewks Moo 08-10-07 Moo 08--10-07 Moll 12-1,1-07 Mon 12-11-07 Oawks Yes PIl
! ifl
675 13.4.4 Ceiling acoustic finishes 3ewks Mon 12-11-07 Moo 12-11-07 ,Moo 03-12"{)7.. Moo 03-12-07 Oawks . Yes
, .. - 1-.- .... T __ _. - , .. - I'h
676 13.4.5 Grid pipes instanq_tiQn 3ewks Moo 10-12-07 Mon 10-12-07 Mon 31c't2..o7- Moo 31-12-07 ' Oawks Yes
, I.-
S80 13.4.9 HolizonlwaR 5ewks Mon 24-12-07 Mon 24-12"{)7 Mon 2a:.o1"{)S Man 2a:.o1-08 Oawks Yes
682 13.4.11 Floorffnishing 3ewks Mon 14-01-08 Man 14-01-08 Mon 0-Wl2-OS Moo 04-02-08 Oewks Yes ..
... _ .... . . _ .. , _ . ~ .. - .~ ." ..
694 14 STUDIO liGHTING .. _ .. L ~ _L ___ .~. __ -- Thu 10-01-08 . Wed'16-<!4-O$ Fri 1S-04-{l8 3 days NO'
109 days Tue 11-12-07 :
14.4 STUDIO 3,4,5 •• ~_' ___ ~u Fri 04--04-0B Fri 04-04-08 O,edays Yes
698 60 edays Mon 04-{l2-O6 Mon 04-02-06
720 19 TEST 76 days Wed 19·03-08 Wed 19-03-08 M6n 18"-06-08 Man 16..06..(18 Odaya Yes f
r~ ~.- -- - .... .... - .... " pL.
_.-. Toe " •• _. _. _.L." __ . __ - - ... r-'
721 19.1 PRECOMMISSIONIN.G TEST . --~- .. ~-_~ ._ .... _ .•. __ 61 edays Wed 19-03-08 Wed 19-03-00 Moo 1 s-Os:.iis- . Mon19..Q5-0B O~ys Yes
! .1---
.. -~ .-_ .... ... - .. ~_r . y~ ... - :
722 19_2 COMMISSIONING TEST 2B,edavs Mon19..Qs-Da MQn 19-05-08 ~Otl 16-06-0fl Moo 16-06-{)s OM~y$; , ;
, .... L_ _ .... _,.,_ ..•. ,. . - .. -~ ,. ~ .,.'--' +.- 1'-- , .. _-- .- _r._,. ,+-_. iLfl
20 TRAINING & TECHNICAL ASSIST BE~ORE HANDING OVER I
724 1mon Sat 24-05-0S Sat 24-05-0B Man 16-Q6-..QB Men 16-06-08 o mons Yes
, '-1-- . _- . ...
21HANDOVER .... Tue 17·06·08 Tu(;! 17.06.08 rUG 17·QG..08 Odaya Yea
726 1 day Tue 17-06-08
; VTV OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Fri 21·

fan{Overan)ltecCW2006-15{290306)

VINCI CONSTRUCTION- SUM1TOMO MITSUI CONSTRUCTION JV

.. ~. '._, ,~ .... :., .•. '.,. c·,'', ,.

.'-' .. -----:.".-':.;':"""'

· VTV -OVERALL WORK SCHEDULE (As per ItecfCW/2006-015 dated 20 March 06)

Wed 29-03-06

10 I Task Name i

i

;

o days .

Mon 07-11-05:

Mon 07-11-05

Mon 07-11-05 ,

Mon 07-11-05

Fre€ Slack ,~I Critical I i 2006 i 2007 2008

iN '0 l.r iF 1M A M iJ J A JS 0 N Q_j_,j_jF JM !A M J J A SON iO J iF M A lM!J iJ

j ;-3'-2'-11112 3 4 5 6 iie 9 1011112113;14'15 16 17 18 192021 22i23 2412526 27i28129i30

i 1 CONTRACT SIGNING

Duration !

I

EartyStart

Late Start

Earty Finish

Late Finish

n(Overall)ltecCW2006-15(290306)

VINCI CONSTRUCTION-SUMITOMO MITSUI CONSTRUCTION JV

1/2

VTV-OVERALL WORK SCHEDULE (As per Itec/CWf2006-015 dated 20 March 06)

Wed 29-03-{)

10

I Task Name

!

345 days

Early Start I Late Start Early_-Finish Late Finish I Free Slack ! Critical : ~

Odays; Yes! '

2daYS~L -! ----+--+___:__---'----+--+-+_;-i,~:--!__f--,- -i--:+-+-+--+-+ f. --+-

Mon 12-02-07 ;

Mon12-02-07

Wed 19-03-08 :

Wed 19-03-08

o ;J IF M A M IJ lJ ,A S 0 iN ro ,J iF MiA 1M iJ lJ iA Ts '0 iN IDJ.,LiF 1M A ,M i.LJl -21-1123 4!5i6f7 8 9:10,11112i I , i' 27128i2913

12006 .2007 i 2008

12.2 POWER SUPPLY SYSTEM

Duration i

I

Sal 19-01-08 ,

Wed 23-O1-{18

23.S·StUDiO LiGHTING EQillPMENT (sfOotO 3;.t.5)

359.days?: Wed 18·10.(15 i Thli 19·10~6: Mon 10·12-07 j Wed (l9.(11~8' 1 day?! No I Ii' I !

----- .. -- .. ----.--.------~ 416days j Wed 18-10.(l5! -~Sa-t-2-1--1-0·~-j.._: --Th-U--1-4-.(I·-2--O·-8_;.i----M-o-n·-18.(12~8 t-------3-di~-NNoot-t!; -I-I-t!, -i-ir-t-t--t-t! ;-, n iiii -,_ rti~r-t-T

~~i ~~~i ~~~i ~~~I ~~~! 1~i ~~tt~-~~~~~~~-ti~·h ••• ~~.~~ •••••••••• ~4~-~r

918 23.4 STUDIO UGHTING EQUIPMENJ" (STUDIO 8,9,10)

~-.----- . .

927 23.5 STUDIO UGHTING EQUIPMENT (STUDIO 11,12,13)

-

Hall

Wan(OvaraU)ltecCW2006-15{290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

2f

.-~~--. -_._----- -_ __ .. _ _ __ ._ _ _. __ .

OVERALL WORK SCHEDULE (DETAILED BREAKDOWN)

VTV -OVERALL WORK SCHEDULE (As per ItecfCW/2006-015 dated 20 March 06)

Wed 2~

[D

i Task Name

!

Duration I

Earty Start

late Start

Eart/Finish

Late Finish

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

11

Nan(OveraU)ltecCW2006-15(290306}

I

i _l

VTV -OVERALL WORK SCHEDULE (As per Itec/CWf2006-015 dated 20 March 06)

Wed2~

ID

70 I

!

1

71 I

721

-6~ 1:i:3:-2-"C2-" '_L_~~._. ~~ ~ __ .. _

6.1.9.3.2.1 RclJariconcrele

I

WaI1{OVerall)IIecCW2006-15(290306)

VINCI CONSTRUCTIONMSUMJTOMO MITSUI CONSTRUCTION JV

VTV -OVERALL WORK SCHEQULE·(As per Itec/CW/2006-015 dated 20 March 06)

Wed:

10

I Task Name

I

Duration I

!

f

Ear1ySlart

Fri 06-10..(16

Tue 12·12..(16 :

Sat 30·12..(16

o days j 16 days:

Critical , ! 2006 2007 2008

i.N ! 0 l J : F M I A M I J i J i BA,-+S~I ",!O'....j_!l N'4! !,!.O,+!J-:+i Fy!!,M'c+'A?:ci-,!M'4,!:J:;fi J I A is ON! 0 J ! F Yes 1-3: -21·1 11 2 i 3 4 5T6T 7 8119 ~o i 11 12113 14 15 16 17 "18! 19 j20 21 22 !23 24 !25

M A)M 26 2712t

late Start

Earty Finish

late Finish

Fnee Slack

97

6.2.1.3 Zone C

58 days

Fri 06-10..(16

6.2.1.3.1 C1

Thu 26·10..(16 : - .... -.-- ...... ---.- ..... - - -18dayS~' .. - .... - i=i;06~10:OO"--"Wed25:1'O;oo-o-' 'Tti(a:6~1[)~6': ... -··-Tue·14~1~1:OO~--··--··-··O-da-ys ; ..

18 days

Fri 06-10..(16 :

Wed 25-10..(16

Tue 14-11..(16

116 6.2.2.1.1 Ai 22 days j Wed 29-11..(16 ~ Sat 23-12..(16 ; Sat 23-12..(16: Wed 17_01_07 21 days!

~ --- .. -----.-.--- 6.2£i"T.1-Cotumns -~---------'-~"""-'-'--~---- ;---lidaYlt--w8d 29-1.1-06 r Sat23-12.oo i Thu 07-12-06 !-----,;{OiI01.Q1-07: 0 days ,'-'--N-O 1--+~-;"'--4--+-~i-+--+--+---,l-l-1---HillJ.ljl-W--1--+-'+-+-'_+--+---i~-t-+-+--l-t-+--+--+-

118 I ... --_ 6,2,2.1:1.2RCWaifs--------------·---------·--·-·--------'--14daysi-·-Mon-Q4:.12_06:·" Thu28-12_06: Tue19-12-061 FIi12.{J1-07! Odays! No 1 I 1

---m-l-- .. ·--···- .. -·---····--·6~22i1_:3St96------···---·-··---· .. --- --·----· .. --·····-·---·- .... ----------·---~--;-·-· .. 14(jaysT·----i=ii-OB"--12-06 i -'-'-;=ue02:OHl7' -·--sat23-12.ooT ~·~weCr17':01:{ijt--------O-daysr--- No I ~ -I !

~ U~,~. ~:; :::: :::: ::~ :::: '=! :~~~~~!~~~!!-~~~~w-~w~~4~1-~~~~-~~+~~-~~~+-

- r

122 6.2.i1.2.2 RCWaltS 14 dayS r MOn04-12-&d Thu 28-12.Q6 ,'rue 19-12.Q6! Fri 12_O1-O7! ociays i

-1~2-3-!--~--------'-~ 6.2.2~1.2.3 Slab ------~------·----·----- .. ·--~--~-------- .. ----;...---14 dayst-~--·~F-ri-08--1-2--06-;.:· .. ---T~'ue-·-02c--O-~1.wt- Sat 23-12-06 t'-wecfi7-01-07 i ----·--0 daysf----N-O·.j._-+-~-.i--U--+-l-+--+--+~4-+-+mt=-!IHl-++-ii --+-+--+--+___,~+--+---f-+---r--+----f--if--+-+-

_1_2_4~_.~----~:2~2:2Zone-B---------·-- .. ·-------·-······--- ..... ---- ... ·----- .. ------.--------.--.------c----r--··-4fdaysr---····saT18-11:06!·---sai18-11~ij6T--TiiI.-ii~1 .. -il7l---jiiu-04-01:07r·----Odaysl··-._Y_es---+_j__+~_l./_~+_+_j..._+__+H-f_Ilill.hm_._+t-.--;-+rl---:~-+-+___f-+_+-+--j-+-+-+-.-+;_j--

125 6.2.2.2.1 B1 20 days! Sat 18-11..(16) Sat 18-11-llS! Mon 11-12..(1S! Mon 11-12:O6! 0 days! Yes! i

No

Fri 08-12.{J6 ,

o days j Yes i~!

0&:'01 Yes I, .

~

~

1?7 I

128 J

6.2.2.2.1.1 Columns 6.2.2.2.1.2 RCWaUS .

8 days! 14 days i

Sat 18-11-06 i Thu 23-11.:06 j

Sat 18-11_06 ! Thu23-11-06 !

Mon27-11-Q61

MOil 27-11-06 j

Fii Q8-12-06 !

.

-~~2.~~S~------- 12~1 ~2~1-06! ~~11_06! MOO1M~! ~n11~~! o daYS! ~~~_L~~_.~~!I-~~~_l_l_j__~I~~~+lj__~+-+-j__+-4-~~+~___iI___,+ii~-+--+~

__::_-===~~~~~ B2 ---- ~ - ... ----- ---- --~ .----- .. ~.-.--.---- - .... --- --------.-~----.---- .. -_ .... - '---'2(ldiiYS:'f---S"at 18-11:oGr·--sat1a.11~-t"-· .. Mon11~12--il6r·-·-~~n-,j'i-12:oot-·---"-Odaysr~'-Yes ,.j .j. -.t[-+--+-+-+H-HJI!+II+I-4-j-i! -+--i-- L --i--..j-+--l--i--+-f---i~.i.-...j_-!

130 6.2.2.2.2.1 Columns ~'----------'-~~ Sdaysj - Sat1S.11_06! 8at18-11_06: Mon27-11_06! Mon27-1H)S, o days 1 Yes I ~ iii I

131-~"--·---··-·--6:2.22,2,2 RC Walls ---~- .. ----.- ... ~~--.- ... ---------~.~---~---~. S days t"---- Thu 2S:-1'1:Qs; --"-jiiu 3O-1-1:OOY----Fri 01-12_06 r-"-Fli 08-12-06,----- 0 days! ---~-N-o!.--l-_L---!.__]iJ--+--+--+-~___:I--+l-+-+-W1f1..H1-1-+-I--+___;!--+--+--+---l-+--+-+-+--j--l--+---i:-:--+---+

~ 6.2.2.2.2.3 Slab 12 days! Tue28-11-061 Tue28-11.oo 1 Mon 11-12-00 r Mon 11-12.06 i ociaYs!

133 S.2.2.2.3 83 ."-~---.---------------.--.--- ·--~·---+---:1""8--;dc-ays-i~-s":;:"a-:t:-:0:-9"c-:.1-2..(1-6+1--·-T-u-e--1-2--""12-.{J-6---' --F-'ri""29~=-·12-ll6 i Fri 29-12-ll6; 0 days l

i

134' 6,2.2.2.3.1 Columns 8 days: Tue 12-12_061 Tue 12-12;.06\ W9d20-12·&i"\ Wed 20-12-06 : Odiiys! I

135 -----·--;6~.2~.2~_72.~3-:.2-:R~C~W~~~---------------------------~-----------r--~S~d7a-~~!---S~a-:t-:09~-1~2-:.{J6~!-~F~rl~22~-1~2~.{J6~1--:T~h~U~1~~~1~2~~~1-~W~ed~2~7~-1~2~_06~'----~0~dLa~~:~:~· ---NOj !

--~--- --- :-=-:-------- -----__ ------'----------.;_---_. __ -_.- : " -~

136 -.--. '''-·-''-6.-2.-2,-2,-3.3 Slab --.--------- .. -~ ---.-- 12days i -- Bat 16-12-06; Sat 16-12-00 ! Fri 29·12-00 r---- Fli 29-12-08 : 0 t1<1}'l; I Yes I! I

137 6222.464 ------~----------·------·----·-~--·---·--~-·--~--·-2-1-d-ays-J:~ .. --T--u-e-1-2-.-1-2-.{J~6-·i-----T~~u-e-1-2·.~1~2~~a+:---'T=h'-U-Q~~o~1~..(I~7=-fL·--·~T"'I-I-U·~D~~:c=c1:~_O=T~:~-·-----·~o~daysi----y~e-s·~-+I--~4--U-~~.--~!!---;L_·+-~-+~i--+4~~~1--~4--+~L_+-+_'--~-r

... ;,;_--.-----:~~= ----. - ,:::: :: ::::; :: :::;~: :~::~:!-::::; ::;: I :: I i ti lij·.;.....-i--IIIl-+HI+++-+--i+;-i:--+--l---i-t-_;_-+---;c--t--+-+-+-t--+

j J

!

Yes

Yes

I

! I

! r

--tJ_J

! i \ i i

142

140 6.2.2.2.4.3 Slab 12 days i Fli 22.12_06 : Fli 22-12_06! Thu 04-01-071 Thu 04-01-07 f 0 ~ 1 Yes I

141 6.2.2.3 Zone C 511 dayS i Fri 17-11-D61 Wed 22-1H6 ! Tue 23-01-llr ! Sat 10-ll2-ll7 ; 4 daYs I No

143 144

6.2.2.3.1 C1 .------------ 16 days Fri 17-11-D6! Fri 15-12..(16: Tue05-12-ll61 Tu;"02..(11:Q7'"-- 24daYS i --. No I \

-·---·~···-·--····--6-:-2:2~3:1-:1COiumns .. ----------··--·------------ .. -.----- .. ---.-.----- ... ----.-." -·--~~----·--8(j8YS!----Fii-1i-"11:oot·- .. ·-~Fif1s:12-O"6i~-sat25-11-oot--··saT2j.:i2:OO+-·--··-- .. 0daYst-·-·--·-N-O-.j..:_-!:........-L_.;...~j..-i---J.---+--;...-+-,,-, ;H-+-+OO-.J-Ul+l++-+-T+; ---ji--+-+--t-+-+-+---ir--+-+-t---+-t-ii -+

Wed 20-12_06 \ Too 05-12~ I Tue 02-01_07 i 0 days! No i.! i

6,2,2.3.1.2 RC Walls

12 days

Wan{OveraH)ltecCW2006-15{290306)

VINCI CONSTRUCTION .. SUMITQMO MITSUI CONSTRUCTION JV

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed29-O~

10 i Task Name !":" Duration ! Early Start 1 late Start Early Finish ! late Finish Free Slack Critical I

i I l1iJD

! ! i -3 ~ -2

145 I 6.2.2.3.1.3 Slab 12 days Wed 22-1HJ6 Wed 20-12_06 . Tue 05-12_06 ! Tue 02-01_07 0 days' NO!

1",~. U~Q 16~ ~~1~' ~~~. _~~, ~~~" o~! ~~,~-~~~~-~~~~-+~~~~~~+4-~~+~-~~~~-~++~-~~-

i

2006 2007 2008

J iF!M A 1M J J !A Is 0 iN ,0 J iF M A lM!J J A SON iD J iF M A 1M iJ -1 j 1 ! 2 3' 4 56! 718 9 10111 12113 14 ls!16117 18 19 20 21 22123 24,25 26 27:28129

147-r . '-. S.2.2.3.2.iCOlumns - .. -.... ---.-------- .. --.-.--- ----- . --ildays- Wed22-11::wr-Wed22:11-.:oS-· ·····Thu-30-11--06:---Thu·30::i'-i=O-Sj"----o-dayiT··· Yes I

148 j' 6.2.2.i2:2RGWaUs- 12 days' ·Moii·27:11:06T·--Mon27~11:06-safii9:12-06r··saTog--1·2:06r- ..... -. 0 days j Yes i-1--+-+--+--4~-+-+-+--!~+++-+-:_; ~::lH1+H-l+-+----t-+-+-+~-+-+---+---:,--t-+-+-f-+-+-

149 j.--·-------·· .. ····6~22~~~lib-- --- -.- --~~---------.-- .. -- - -.-.-.. ·T· .. ·--12days·i········-M0ii27-11-06t--···-MOii27-=11-O~--&ii!i9.12.oo!--_·-_· _s~a_.!_0_9-_1_2-O_=6~(._-_-_--_ .. ., .. cc'O_'"d",a_ys-+-i _--,Y,,_es_. ~i-! -+-~+--4-+-f--+--l--t ·-+++---+--.:;:~::wWI+-+-+~f-+-+-}~t-+--+-f-1--+-+_l-+-+~

~ 6.2.2.3.3 C3 36 days: Wed 13-12-06 ! . Mon 01-OHI7 . 'fue 23-01-07: Sat 10-02-07: 16 days! Nol ."

1~ ! ~~a~~~~ W~%i Wed~~6' Moo~~~! ~~1~6i ~1~~! o~ys! ~~;~-~~~~-~~~~-4~4~~+H-l++~-~+~~-~+~~~+-+~-f-~+-

::: 1-- --- -- ~:~~;~------ ------ --------~::::;~::::===r~'::F::::=~~--~,i-j ---l-.;__j_-1l_....;-j..........L-.+--t-4-+--+---l-Jl...l44ll-l+-i----\-+--_+_-+---l-+-_+_-+-i--+--+-+-f__+--+-

:: 1--·---n .. --~~~~~~~2:4~ ~Iumns---C" .. - ... - ... --.--n·-· .. -----=~=~=~~·===== .. r-~~~1_~~~.~ __ ;:;~~ __ :: ::::; i .~:: ~;::;j. .. -- :; :::~t·----- 2:::: i :;·~1-j-~_.;..---4l-i-...;-_L-1-1--H-+-~-+-:1:J1.#l+l-J.-.-lH--. t..i -}-~+-+-j'_~+-+-I'---i-+_'_~f---i--!

~~ ~~~~~~____ . U~ ~114~; ~OO~~ ~~~i ~~~~! o~l N~a~~e~i-~~~~-~~~~-~H-+~~OO~~~i-~-+--+~-~+-+~-~+-+_I-+-+~

157 I 6.2.2.3.4.3 Slab 14 days i Moo 11-12-06! Man 08_O1.()7 i Tue26-12-061 Too23-01-07: Oda%~,; No)

-----I 1~+_~_1--~+_~~-j_+-~~ __ j_~~~-+~+_+~-~~-+~-+_+-+-I~+_+-+f--~

158 6.2.i.3.sCS 18 days 1 Mon11-12-06! Mon11-12-06' Sat30-12-06'j Sat3O-12-OS, odaYSi Yes

~ -----.---------------.-"------ .. --------- --j.._+--L-_j_---+t--.:;_.J..--+--+-+-H-.;_~_l_+IlIfl_H4+--+_+_+--i-+_+__+_4__j,_+___i_+_+_i-+__i

159 6.2.2.3.5.1 Cofumns 8 days i-- Moo 11-12-06! Mon 11-12.Q6: Too 19-12-06! Tue 19-12-06; 0 days! Yes i. !

""160 ----·--·-· .. -·-·-···-S~2.2.-3.-5.2-R-C WailS-"'--- __ · .. _n. ._ .. .... _ -~-----------+- .. - .. ·-1C""c""2 days""r"-- --Fri"15-12-00+-'--'-Frlt-5-12-OO t--fuU28-12-OO i Tlju 28-12-061 0 days i Yes ! ! t

Sat 30-12-06 i Sat30-12-06 i ---0 days.:! --Yes i,1 1 /

~'---·~--~----~~--~~~+-~~~~~++~~~·~!'i~+-~-+-r~+-~-+~+-~~

162 r 6.2.3 Z3 50 days! Mon 25-12-061 Sat 30·12-06 : Tue 20-02-07 ! Fri OS-04-07 , 5 days 1 No r"

::: j 6_.2_.3~:~.2ZO~.3~~~~71A~A~1------------------------------------------------------L---:~·:~:~:-::~!--~:~:-:-~~5-~ .. ·~::~::~-~···Ll--~::~·-:-:~:~:~:~:~:~:--~;~::-:~:~::~-7::~··~:+i--~:~:-:~::~:~:~:~:~:----~:~:~~~a::~··~j~--~:~·:~-+~--+-~~~--+-+c+~"lH-+-~-+~wtt-H--+-l~+--r-fl.--~+--T-i--r-i--T-i--~i--i

=:1-" ----- ::~:::::~ ::: .. ---- .. ----- .. :~-==-===~~~~-------·--+----1; ::~-~~-~;~~:~ 1- :::::~+- .. -T·s-ue-at-·:-~-·-.{1·-:-:·-:-j:l-- .. -----M·-:-~-~-~._o--:.--O_o.-:.J.~------:-:.-:s-ys-j-; .. _ .. __ :_:--l-l _j-';_-4--!l--i-.J--_J_-+-I'---'.4+--+---l'--l!Jlll.j~.g..-..j'__.J--+-+___,~+-+~-i-+ !i--i--i-+-+--h

~··-------- .. · .. -··---- .. 6~2:i11~3S-l8""b--~· .. -:--· .. --- .. ·--· --.- --.------------------.- .. -- - -- ---l .. ----12daysr·······we;fo3-Q1·::iI7+---sat27_oi:07·!·- .. - .. Tue1641:07i----Fri-09~2-0ji--· 0 days i No Iii

~16~91 ~~~ . ~~i ~~~! ~~«: ~~~i ~~~i ~~1 ~~~~~'--~1~-~~-+~-#~~~~~~*~f--~+4-~~+~-~~+-+-~~+~

~ ~121~~ 8_ ~~~I ~1~~, ~~~I ~~$! O_j ~~~~_..j'--~~-~!I_..j'--~~~W~+-+~~4+_+4~~~+~_~+-+~--+--~-+~-~

170 I 6.2.3.1.2.2 RCWaits 14 days Fri 29-12-06f Thu25-01'()T: Sat 13-01_O7! Fii09-02-o1< o days I NO!

1n I ---~~~~--------------~----~--- U~: ~OO~$i ~~1mi ~1~~1 ~~~! O~i ~~I--~+-4~~~~i-~++~+~++-lm~+--~+~~-+-+~-~~+~~~~+4~

~ - --- --.- • .- .. --- --____ _ ~~ • _ .. __ no .. • __ .. .. _. _ ..... _ • • ~ :._ .. • _:_ ..:_._ .. _. .. ~ ~; ... __ .;........;....1 ~~

172 S.2.3.2 ~ne B __ ._._ . 39 days .. Sat 30-12~ : Sat 3O-12.oS . Tue 13-02-07 : Thu 15-02.07 • 0 days: Yes I j., i

6.2.3.2.1 B1 . 18 days Sat 30-12-06 : Sat 3O-12-OS Fri 19-O1-O7! Mon 22-01-07 0 days: Yes! ,I

6.2.3.2.1.1 Columns 8 days Sat 30-12-06 : Sat 30-12-00 . Man 08-01_07: Mon 08_01_07. 0 days! Yes I :;

~ ~~~~W~ 12~' ~~1~1 ~~~~: ~1~~1 ~~~i 0~~1 ~~~-l-~-~~+~-~~~i~iH--~+~~*~+4-1-~+~~~~+~--~~~~--~i

176 6.2.3.2.1.3 Slab 10 days Too09-01'()7! Tue09-01-07j Fri19'()1-07i Fri 19_01_07 , Odaysj Yes

-1-7-7' ·--- .. -- .. -·--·----G:2~i2:iB2----·--·-··----·------._-------. ----·--·----·------·-···--·-···-··--·-----~-----'----18days1-----Fri-05:01-Oit---FriO~1~t .. -·ThU25:O'"'1,~-O,~7~1-·- .. _·-_- -a Sa;:-·-.,-t27.7~.{I;;c1:-:'O:o:7,..;!----:0:-d.;-a-ys-~;..: _-;y~es~~~:~~~~~~~~~~~+li;~:~~~-~;~4H~:r_---!:~;~-t!ll::::::--i;::~_+:::~~,---!;~:~--+;~;~;r_-~;~:~-+;~:~~r_-~

~ ~-~-}-!-.-2.-1~~~~-~------ 8~! ~~~! ~~~I Sat~1ml Sat1M~~ __ ~_d_ays~I __ Y_es~~-~~~~~I-~~~4!1~-~~~.W-~~++~!-~-i-+4~-~~++~~

=::J---- 6.2.3.22.2 RC Walls 12 days i Wed 10_01_07 : Mon15-0f:O~Tue 23'()1.{17! Sat 27-01_07: 0 days! No

~ U~~~ W.' ~1~~! ~~~ ~~4 ~~~, _O~d-ays~!--~_~_·~~I-~~~~~I-~~+~h-~~~~*~~~++~-~~-+-~~-~~++~~

~. 6.2.3.2.383 16 days: Sat 20.01-07 j Sat 20.01.07 : Wed 07-02.07 j Fri D9-02.(]7 i 0 days! Yes ! !

~ . 6:2.3.2.3. 1 COlurTlns 8 days ita! 20-01:.071 Sat 2O-O1..(l7; Mon29-01-071MOn 29-01_07 j 0 d3% i Yes i

~-------66.·2~.~3-.·2.~3~.·3~S~fa~b~~------- 10.: ~~~! ~~~I~~~i~09_-O_2_-O_7~i O_d_ays~I N_O~~~~~~~~!-~~~~h-~~.Am~~+-++~-~~+4~-~I~-j-~+_!.,

1M I 8 days! Tue 3O.{I1-07 i Tue ~1_O7 : Wed 07_O2_O7! Wed 07-02_07: 0 days! Yes I'

185 6.2.3.2A B4 .. ---------i...--fS-days i ---'-'frj-26-01:07 ~ Fri 26-o1:07+---1"ue13:02-.o'1 ! Thu 15-02-07 ; 0 days T-~'~Y'~es--'I-+--+--+-li+i ---t-I-j! ~-~J--+I--t--t-+---m-lUJf-~++---t-+-+4---:~~+-+ 11-11-+-+-+ 11 -~+'

"'"186 --------·---·- .. ---· .. · .. 6.2.32.4~iCOlumns-- .. - .. ---------·---------- .. --------------·-·-- .. ·--·-·-----·----t-----8days-t~--"-Frii6-01::Qit-----frj 26-01:07t"-""-S~i'o3-02-07! Sat OM2.o7 :-------O-daY6T·-~-yes !! I

~- U~~~~ , fu~! ~~~r·~~7iSat1~i ~15-0~i ~~I ~L·~-~~~!~~1~:-~~~~w-~~3*ffi~~~+4~-f--~+4-~r:-~~++~~

~------------6~2.2.3.5.3 SIab-------------------~---~-----·-·---·----·---------;----14days ;

Fri 15-12-06 !

Fri 15-12-00 !

1

I

168 6.2.3.2.4.3 Slab 8 days: Man 05..Q2-07 i Man 05..Q2-07 j 'rUe 13-02_07 i Tue 1M2-{17, 0 days I Yes I I !

~ ~U~C ~~l ~~~i ~~~1 ~~~I ~~~! ~~!·~~~1--~-+-~~~+1-~+-+4~1--i-+~~~~+4--~~+~--+-+~~-~+~~--+-~

190 S.2.3.3.1 C1 ------------.-.------ ... -~---~-----------------+~ 14 daysf-~Wed 27-12-06 ; Wed24-01:07; -Thu 11-01-07: Thu 08-02-oiT-·----2-4·-d·~a-ys~! '-~N=Q-+--+ !:-+--!--+l:__:f-+-_+_~--l~+ !, +-!--i-+-\;lIj,jf:H-I~-!i--i--+-+-~++--j-t-+-+---t--+-+-+-+

- .. --- .. ------ - ----------.----.- ----.- •• -- .. ------- c .. _._.c_._ _.~ -L.. .-----.J- .. -.------ ---J_~------------.;...-.--~ .. --.----.---l·---------.J_---------i---·~-~+-_j'l._+_-+-_+r__.;~_1_-+--i-!__+!_1_+_++__HIHfl-fj1+_-+--f-+-+-l-_I'--~+~-i_+_+_+_Ii~+__+

1~ Ull1~Cofu~ . ; 8~: ~~~I ~~mi ~~~I ~~~! ~0~d~ays~I--~~+4-~~_+i~~++-+~-~IH~~+-~*ffi~~+_++~~~+_+~~_~I~~_~!I~~

192 6.2.3.3.1.2 RCWalJs 10da%: Man 01'()1_O7 ! Moo 29.{11.{17[ ThU11-01-07! Thu 08-02_07 ! OdaYSj No i I I r.

Wan(Overan)ltecCW2006-15(290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

41 ;

---------~---~--- ...

10 'I Task Name Duration Early Start] ! Late Startl2arty Finish I Late Rnish Free Slack Critical J 2006 2007

'N ro J IF I"'JJAJ1'!LLL_J_J iA is 0 N!O J iF M A M iJ J A S 0 'N

! 1-3'-2 -1111213\4 \5161718 91011112\1314151611718 19!20 21122

12008

VTV -OVERALL WORK SCHEDULE (Asper ItecfCWf2006-015 dated 20 March 06)

Wed 29-{

o IJ IF 23,24125

MiA iM J 2612712812~

217 6.2A.1.2_1Columns 8daysi Wed 17-01-<l7i Sat 10-02-07: Thu25-01-07j Mon 19-02-07 ! odaysi No j !

21"8 6.2A_1_2.2 RC Walls 18daysj Mon22-01-07Thu15-<l2.{i7: Sai10_{)2_{)7: Wed07_{)3-07: o days 1 No j I

~'_=-~-=-~~~~~=:-:-=_==-=====-_-=~=--=~-=;;"~~=::1~~_-::;.~_-;:-t+-_··- __ ~:.y_::;:~.~=:~=~==:=~~::=~I==~=~~:~=:~~~~~=~~~:~:ii~1HIf-+!',--_-1+-:_+!--_-1~c----+l_---:---tl_---~:--t+_---:---i+_---~_-_-t+--_-~L----t:---1...;

221 6.2.4.2.1 B·1 -~·--~~---·------·-·-------------------+---:3'"'5=-d-;-a-ys--i- Thu 08-G2-G7 i Thu 08-G2-07 :. tue 20-03-G7 I Tue 20-GJ.07 , 0 days 1 Yes i~ !III I

~ -------------~6~_2.~4~.2. .. 1.71~Co~ru~m==ns~--------------------------------------------t----~8~~~ys~:-~T~hU-M~-O~2~-O~7~!--~lO~U~~~~2~-{)~7~;~--~Fn7·~1:6-{)~2~_O~7~j~--~F~ri~16-0~2~-O~7~; ---~O~da~ys=+i--vye=s~r_-+t-~:-~-+t--~~~-~~--l:!~~:~~~;~~~;~~~:~t~:~:.~::~::.~~~~:~~:~:~::~;~:~~;~:~~;~i---T~--~t~-_J~~--+T--~+

---m-- 6.2.4.2.1.2 RC WaIlS . 14 daYs i fue 13-02_071 Tue 13_02_07 j WfJd 28:O2~7 i Wed 26-02'()7, 0 days : . yeS '!I I , f- ! t I

62~j~~ 12~j ~~~I ~1M~~~~:~=~3_0~7+1-~&~to~3-0~~, O~: ~~7e-s~(-1~'~-~*4~!-~++~~+~+4~.~H*~*~-~+~-~~+~-~il-~++~~

~ ~-~-.- .... ----- .... ----~ 62A.~2::i_:_4Culiog7daYS------······· ·-----··-·~---·-·------·------~-·-··-·---------r--·····~jdaY5t--MO;;-O~3=OiT~· ~-MOOo~3:{j7T~-~Moo12::OO--07! ---MOO-12:Q3=Oiy···------··O·d:iiYs-··+i -~~~~·y·:es~+-+--f--+-*+--+--1---+--+--+H---f--+---H11I-+flHH±H--+--!--i--+-+-+--!--t-+-_T_+____+--!_+_...;..

-I - ~tl -------. i 7_1 ~~~:~13_0~1 ~~~I~~i o~i ~_es+__+-+__+~~-+--+~~-*+~~___+II+~~~~~~~~-~+_+~-~+_+~-t_+~~

-. ---····----··6.2.4.2.2B2·------··-----··-·--~ ---.---.--. ---··------·---·----·---'--35 days: -··Wed 14'()2..o7; Wed1i.02-G7 i ~Mon 26'()3.o7 ('--Man 26:0"3-:071 -.-_. 0 days i ~"--Yes 1 I .j! !

m ~Ui~~8~1 ~~~1 ~~~1 ~~71 ~~~t ~~i... ~~~~~~~+-+i!-1---+-+4~1---~+~+OO~~iH,--+-+--+~--!-+--~~--!~+-+~--!I~+-+

.---~ 6.2.4.2.2.2 RCW~----~ 14 days; Mon 19-02_{)7i Mon 19_02-07, Tue 06-03_07 r Tue 06_03-071 0 days! Yes / r.· I·

23() S.2.4.2.ia Slab 12 days: Sat 24-02_07 Sat 24-02_07' Fri 09_{)3-07T- F~ 09-03-07 i ·0 days j Yesli

231 -------------cC:-"C.20-.4-=-.7"2.-:""2.---:4""""'CUO--,ring---,7=-d-a-ys---- 7 days j Sat 10_O~7 i Sat 10-03-07: Sat 17_03-07 j Sal 17-o"3=Oj: 0 days i Yes j, !

232 -~-- .. ----- ... - 6.2.4-:2.2.5 Post Tens-foning --.- .. -~---.- .. -------~--~-.--- .. -~~-------- : --~--7 days (---Mon 19_03_071 .- Mon 19.:oa:.o7 i Mon 26'{)3_07 1 M-;::o.n,~26=--Oc:.3-0,~"",7~'. ·=o~d,..,..a.ys- . ..;If-~.~~ -; y:c;-es:-::-~l._-l-I---,~+--tf-_+-f__+-+-f-t++_+_+_+H_HI_IHi1i+H-t-+-+--f-+--t---+--"\:---+ ii -rl- -+---,r-+!! --ir-t-

233 6.2.4.2.3 B3 -.------------~~---~-------~------: ----17 days: -MOnOS.oJ.07 ! Sat 10-G3.o7Frl23.o3-07 ! Fa 23-G3-a7 : 0 days i Yes! ~ , ! ji

. ., 1.J i!

234 --···-·-------···~-~~-·-6:2.4.2.3TCOluiiins-·~--~·-~~~-·-- __ n __ ··-~~--·------·--~-~-~-~·---------·--~-+-----8 d8ys·t----Mon-os:oa:ojt---sat1~~t----Tue 13=03=071~~MoIi--i9-oa:oii------~~o~daysT----No . t : 1 . j I I

-zas- ~ 6.2.4.2.3.2 RC Walls . ! i days! Fri 09-03:'CrT: Thu 15-03_07: Frl16-Qa:i:I'r [ Thu22-03-07 : 0 days! No~+--+--+---;ft--+---ii--+--+--t---;-t-~· ~ --HHl-l-Hlf.lll-!.-:!HIt-:--+-+-+--j-+ I I

8 daYS i Thu 15-03.a7 j Thu 15-03-07: Fri 23-03-071 Fri 23-03-07: 0 days 1 Yes 11 1 i

2.3'l 6.2.4.2:484 -18 days 1 Sat 10--03-07 r Tile 13,;o~T: Frl3Ij;,ij3-07 f· Mon02..G4-0i'· 2 days JNo· II i 1

238 ---~"""'--~-~S:2A.2.4.1 COlUmns ------------.~~~~--~------------~--.- 8 ~ys i ~ 10_03-07: Tue 13_03_07 i Mun 19-03-07! Wed 21_03-07 i 0 days: No I ! Ii; i !

239 .. ----~-~--.- ·-~-··6~2.4~i4.2RCWaifS~~~----·----- ·-··-·-~-~~----···---~~~-····-----------~-~·--·~r_---10days-t-·-·-TiiU-15:03:07T·-~~ Thu 2"2:oa:07 i ---Man 26=03:07i---MljilOi.:04:0it--------Odayst-·· --·-;'N·'o-+-+-+ 1i ---i-H-j1 ---f-I-+-+--+-+-H,--+--+i__+H-tIt-IH--i:II:I+-t-t---c+_--,l~- T- j I

240"" _.. 6.2.4.2.4.3 Slab 8 days ! lOu 22'{)3_07 i lOu 22-Q3-07 : Fri3O-{)3_07 i Fri 30_03_07 i 0 days \ Yes! I ~l! I

224 225:

229

~ !

I

236

6.2.4.2.3.3 Slab

I

lVan(Overall)ltecCW2006-15(290306)

VINCI CONSTRUCTION- SUMfTOMO MITSUI CONSTRUCTION JV

5/2

. '. c:- ~ '. ':. ~.'.:'. , ~

~ ... :- .

....... ~ .. :.

10 I Task Name

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed

Duration. i... Early Start I Late Start Early Finish Late Rnish Free Slack Critical 2006 2007 2008

: N i D J iF i MiA M J J j A . S 1O.J_N:!...).!!.D~J,--+i<:.F-!j.!lM4' A~·.!lM~f'T, J~~J~! A:':-Ip-S,::-+::,O,:-t'!, N~.:;D';cfJ~'r::F:;::t'M:7i-::A~i M

111 -31-2 -lil 2 t s 4 5 6 !718'9 i10 11 12:13~4"5 16r17 181'9202112223241252627121

270 6.2.5.1.2.2 RC Walls , 18 days Wed 2H12"()7i Sat 17..03-07: Tue13-0:M71 Fri06..Q4..07i o days! No j! ~! 1 J

""""""27-1 6.2.5: 1.2.3siah 12 daYs ; MonOs:oa:.oi! Thu 29..()3.07!"· . "&rt17.:oMJi',I,' wed 11"-o.t:<ii; 0 days ',,: NO I !r,l[ 1_!: ;

~2=n~~-----6~~~.=U=~~n-e~B~----------------------- ~~' ~~~I ~~~! ~1H1~1 ~~~! o~1 ~_~~1~~1~_~~'~_~1,~_~~~~_~~~~~~1~".1~_~~~1~~+~~~~++~~I_~+

~ -'---"-"~ -'- -6.2~i:1BT -- -- .. ------ .. - --------- ---.--.~-- - .. ------ -----, - ------------. ------1·Sday;r-Sat 2~iG7 t- .- --Sat24:03'"oiT---'-Fri1i~7 ! -MOii-16:Q4=Oi:-------o day;t-- -Yes I j ~ I

~~-----~~~~-------------~-~~-----~-~~-~~~-~~~~~d_~~~~-~~~~~~~~~~~~~~~~TT~_rrTYT~

274 I 6.2.5.2.1.1 Columns , 8 days, Sat 24-03-071 Sat 24-03-<17, Mon 02-Q4.07 j Mon 02..Q4..07 i .0 days i Yes

--:.-=- -'-'.--'-.,-~~--'----~---.~--,--~------.-.-----~-,--- .. --.--~---.--j_--"- -_j_ .. ----.--~,j----.---.J_,--. ,

275 6.2.5.2.12 RC Walls ! 12 days \ Thu29..()3-07j Tue03-Q4-{)7j Wetl11-04-0lj Mon16-C4-07i Odaysi No i

""""276 6:2.5.2.1.3Sia"b10days iTue oj.04:6i r TOe 03-04-07 ;i=ii 1i04-.(rit Fri 13.()4"()7 i o daYs I Yes J 1

277 6.2.5.2.2 B2 18 days ; Saf31..oo.o7-1:--·-=T~U-e""O""'3--04-0-:-:-:7""" ~~-F::'-rl~20--64-0-::-:-.--=-7+-1--=:W:-;-ed--;-':2"'5:-:-O::-C4;-:-O"'7";i-----2:=-;;d-aYS·--;tr------;:;No j.._~-+_j:__.!l--.J.--+_ji-+-+~+-+-+-+-fjH-t-Hl+--ffil::IlH!--i----+---+--i--i-+-t-t-+-+-t---:f-i--T-

278 6.2.5.2.2. -(Columns i 8 days i sai j{6~ir TUe 034t-Oi l Mon 09-04-071 WEid 11..04-071 0 days! No I 'Ii [ i !

279 62.5.2.2.2 RC Walls 12 days ) Thu 05-04--07 : Thu 12-04-0~7""i;"', --cW=ed-~18'-.{)4-0~""1'+l ~7.W'""ed--;-=25-04-{):::-:;:C-:-:=:7=-'i[_---:O;-d7:a-ys--C:~' -~N;-C-Ot--+ If .--j-i-~+-+-+-+-l:-+]H---;r-rtt-1Hitt-ilit.jfW,---t_'r-t-li-T- -1'1'1

280 ~----·--'-'----·-6.2.52.2.3 Slab -----.-,~--~-------.--" ---~- .. ·----i 10 daysr~Tue 10~ri Thu 12-04-07 i Fd2O.()4..()7j Mon 23-Q.4.07 i 0 daYs 1""-- No I I i I

_:_ ~~_~~~=~~===~~~-~-:_-~- .. _-_~-_-_-_=====~~~=~~~=.~==_-_- __ -~==_- __ -_~~====~~_--_-_~~=1==- __ 1-~:~~1~=~~~--,~-~1_- .. -_-_-~~-~~~~?i-_-F-~-~-_-s.O~t=_-F_rl .. ~~1_-.-_--_-- __ -_--_ O- __ -d~-~·- __ -+i---·-_ .. =-:Yc~--~~~--..j..i;l---_++-----l~----ll~~~~..f+II~~:~:~:~~~:~~~:~!f_!-_l+~il-_I+_tt++!H+-:~+HIltIllf_r-~+--_1-+c....----1t-!; --fi-_-_1+~--:r----tt---'-tj:~:~:~:~=:~;~~-

2B2 6.2.52.3.1 Columns , 8 days, Sat 14-04-07 ! Sat 14-04"()7 i Moo 23--04-07 i Mon 23.()4.07 , 0 days i Yes I Ii!,

~ ~u~~ ~~I ~i~ji ~~il ~~il ~~7 0~1 ,~~~~J~k~~~4~~~+4~4HH~KHh~-~+!-~~+~-~~~+~~-~

j

I

I

an(Overall)ltecCW2006-15{290306}

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

6/20

v

10 ] Task Name !

late Finish

VTV ..oVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Critical ! 12006

!N 10 IJ 'F

Free Slack I

2008

A iMJJ J A S 0 iN 10 J ,F M A :.-;::T16 i17 18 19 20 21122 '23 24125 26 2

Early Start I Late Start

Ear'ly Finish i

j

Duration

1-3:-2'-1'1

2007 M 1 AiM'J J ! A SO' N 0 J j F

Sat 05-05-07 :

4 days i

289 I

!

~ 28 days

~.

: I. 6.2.5.3.1.1 Columns 8 days . . .

i 292 I 6.2.5.3.1.;'>··RcWa:iiS· 10 daysMorii9~a.:o7t---Wed2s.:04·:Oi:· ·· .. fhu29:03:.QiT - -Sat ()S-()s:.viT Od:3%1- No

293 J-" .----- .... - -. ---. 6.2.5"3.'1.3 Slab~---'---- .--.-- .. - .. -.~-.----------.- --'-"';i"O-daysr"'-"Mon19~3:::Q7T- Man 16-04-{)7 r----Thu 29'{)3-07 i--'-ThU 26-04=O;iT "--------·Odays r-'-'--' No

294 i 6.2.5.3.1.4 CUring 7 daYS-' . ---------·------+----:7::--;da-ys~.-- .. Fri 3O..o3'{)7 Fri 27.{)4-07 : Fri 0641-07 : Fr; 04-05-07 , ·----=O-d""a-ys--+-! -~N:-:-O+-+~-+--+t~-+--+--+--1f---++---j---1i---r--tt-t1~t-

295 I 6.2;5.3.1.5 Post Tensioning 7 days i Sa! 07..<J4-.07 : sato~5.{)i ; Sat 14-04-07 i Sat 12'{)5-07 : 4 daYs 1

:: 1- ------ .,:<:;,~~,,;=--==~--==-===---::=~-~1=-~=~-;-;;,:;-;~;;;:+-;-=t------;;j__~,-:+--+--4-~4--+---+l-+-+-+--,-+-i--+-+-HI-tiHl+-H±tlHf*++-+----if--t-+---j---1-t--t---t-

298 j ---.-------- 6.2.5.3:2.2 RC Wans---··----- .. -·---·--·-·---~-·-··---·-· --·-~~odaYs+--· .. ·- Fri 23--03-07 i---Fri 06.{)4-01r--- Tue 03-04-071 Toe 17-04-07 -------oa'ays r No !

o r-' -- .. --.--.- - --"-'-:::::~~::~~-7"~:-"------"-"--"--"'--- .. --.-.--.---- .-.-.- .--- - --- ~----~:-.- 1: :~-'-. -:=::: j M:: :~~ ~;~~~: :- T;: :::: , .. ---- : ::: l -'-'7:,-:+-+--+-+---++___+-+-+_+--++-t--+--+--tH+I-H+-

I -----~'---.~~~~+------~~-~~~~~--~~4_+_~~~~_+r+~~~t+rH+-

301 I 6.2.5.3.2.5 Post TenSioning 7 days: Thu 12-04-07! Sal 14-04'{)7 : Thu 19-04-07 j Sat 21.{)4-Q7 i 0 days i No

-302--1' 62 5 3 3 ca 30 days j Man 19-03-07 t Mon 19-03-<J7! Sat 21-04-<J7 [ Sat 21-04-01 j 0 days i Yes I--+--+~+--*-+~{--+-+-lc-++-+--i~+-*+f-it+-

~----- .... - .. --- .. -- .. ~.~.5.3.3.1 columiis------------···~--······-··- .. ·---··-------.. 8 days: Moo 19-'03-07 ; Mon 19-03-07: Tue 27-O3-07! Too 27.(13.()7: 0 days! Yes

304 1····---·········· _ - 6.2.5.ii2 RC Walrs--" - --- --.- --.-.-- - - --- -----.-.--t--·-10-dByS·j-··---Fri2~~2j:Q3:0ii-TiJe~-··Tueoa=o4::07t··------O·da~--···~~e-s-l--+----1-+---H--+--,!--+---+--+---l+-+-+-+-HI-+H-I+--Illi

3O~.. -·----·---·---·-----6~2.5-:-3.3.3Beam5/siah--- .. -------------------- .. -.--.-.------- 12 days i Fri 23--03-07 i Fri 23-03-07; Thu 05-04-07 ! Thu 05-04-07 i ° days ! ---,Yes-jl-+--+--+___jfl--+---+___l-,-t--+---HH-c-+--t1t-+t-tHHHl

3()(_ 6.2.5_3.3.4 Curing 7 days 7 days i Fri 06-04-07 [ Fri 06-04-{)7 i Fri 13-04-07 i Fri 13-04.{)7 i 0 days f Yes I! . !

~ 6.2_5.3.3_5 Post Tensioning i days I Sat1"4-04-07: Sat 14-04-07: Sat 21-ei4-a7j Sat 21-04-07; 0 days! Yes i

~t~--~~- __ ~_-:~~~=====-=~===_ , -3~1~ ~;;;:I :::: -:"..:..,.:-:-..j..; -- . ...,:c;:+-+:-+--+-4~-+-+-+--t-++-+-+---f--\1H+lItf_--fHilIItHlH-l'---;-r__-j---t-___t---;r--_r__--r---j--r~ ··· .. ··-----··-·-······--· .. ~~;~~~;.;~~::b------------·---------.--- ..... -----.--.---- .. - ... -.----.---- ... ---~---~~~~--·-~:-=;I·- .. M:;~~::+_- .. - .. -:~;~;t--·--~~:-~~;~·-----;:-:·-:--+: ----:-:·-+--+li-l--_)._-!+---4-+-+--+---+-++-+--+--fll-1-H1+HHti!!lf:-t-H++__+_---r-r--+--+-+--:__t--t--

::: '1 6.2_5_3.5 CS' 28 days: Wed 04.04_07 1 Wed 18-o4..t17] Sat 05-05-07 f Tue 08-{)5-0ii 2 daYs i

6_2.5.3 Zone C

Wed 14-03-07 • Wed 14-034)7 :

Sat 26-05-07 :

46 days'

Man 19-<J3-07 Wed 11-04..oi

6_2_5_3_1 C1

24 days j

Sat.14-04-07 :

Sat 12-<15-07 Thu 19-04-07 .

o days j

Nol I

No

No NO'

!

No

yeS

No

318 I

.-m1

320 I

32t.

Tue 17-04-07j

Fri 11_05-07 i

6.2.5_3.5_1 Columns 8 days i Wed 04-04.{)7 : Wed 18-0407 , Thu 12.{)4-07 ! Thu 26-04-07 : ° days I

314l 6.2.5_3_5.2 RC wiiilS : 14 days I· Man os'{)4-07iMon 23-0<HJ7: Too 24-04-07 i Tue 08-05_07 i 0 daYSi

~·-~-------------·~~6-:-2.5.3.5-:-3 BeamslSrab~----~----------~------·-·--·--·-·----------+--'12 daYS~----Mon-~7 ! MOn-~·:(i7T-~Sat 05-05.{)71-----8-a-t·-0--5_0-·-5_0-7-J..; --·--·---o'-d-a-ys.....;..i ---Y-es-l-----+-.;.-~--+J.~-+-+-+--I-+++--+--i--lil---1f-t1H+'I-llti!tlmll±i!::Hll-iHIH:-t---r--T--r-r--_t_--t---t-!--

-:I--·----··--··6~~~.~~_~~:::~ .. =~---- .. --~------- .. --.------.-.---.----~~_-._- .. _···-·_-·_·-·_:=----J_-::i-::-:-:=;-::=--:.:-=;-~=;--~-::+=.-··-· -:-:-l---i----l'--+---H---+-I--+-+-+---'c:++-+-+-tiHHH!j- j H:-+--+--+--+-+--+--+__+-f--

21 days t

6.2.6.1.1_1 Columns 8 days: Mon 19-03-071fhu h:.o.t-67 i Tue 27.{)3-07 ! Fri 20-04-07 ' o days [ i

·--~---'---6-:-2.6.1.1.2 RC Walls 18 days i Fri 23-03-0li Tue 17-{)4-O7 i Thu 12.{)4'{)7 i Mon 07-05-07 T ° days i No . ,I'--+-'-'+! --f-H-+-+-+-HI-HHtiHW~tHt--j--t--t---t-i-r-t-"_t_,--t------.-----L----------~--+!-----~~-+_-+--~~~~~~ .. _4~·~!_4--+++_4--~~+t;tt1*h~ittt_r-i--+__r_t--j__i__t~;-i__

- ----""- ·-·-----6-:-2.6-:-1T3SI8b·---~-------···----------·""·---~------- .. -----·-----·---------------f---·12 dayst---Wed~7i---sat26~7t---fu;;1'7.:Q4:ij7r--- Fri 11-05_07 i 0 days i No !

-----1__ -- . .- .. -------.;__--=:--;--_+-=--;:=-:::7"":;=+--;:;:--:--:=-;~=+--=---cco--,.~+--~--,-".,...",o.__,,~----=-_:_;_-+---~.I---l--+---I----!lJ..-~-i-_+__+_lI-_!+_)._+_+_4iH-H_IHhlW.lHttMH_+--+-+__+-j~t_T--+_+___1-

322 I 6.2.6.1.2 A2 : 26 days j Man 19-03-07] Thu 124)4-07 i Tue 17-04-07 i Fri 11-05-07: 21 days 1 No I

-323-r .. ·---·--·~-··-·6-.-2.-6-.1-_2-.1--cO~lu~m-n-s ~.--- .. --.-----.-----.-.---.--.-.----.-- .. "".--.----. -r-----:8;;-d""a,-ys-,+;--;M;-;-::-oo::-:;:19;;--O;;:3-0;;:-;;::;7 r Thu 12-'04-07 : '''T'iie27-03=07 i- Fri 20-04-07 r---'---Odays ! ---- No i

~ ~1~~~ , re_i ~~~! ~~~7f ~i~1 ~6~1i ~aysf ~~~~-~44-.~!~-~~~k-~~*+t~Hill~~~~+~~~~-t-~~-~~

~ 6.2.6.1.2.3 Slab ,. 12days/ Wad04-04.{)7r Sat28-Q4007j Tue17.{)4-O7' Fri11-'05-071 o days i

~ 6.2.6.2 Zone B 42 days :.'. S.'at O~5-0i ! . sat 05-05.;0] ! Frl22-06.of! fOri 22-.06-01 0 days i:., 1 iii 111.,

327 6.2.6.2.1I,l1 16 days : 53t05-05-07! Sat 05-05411 : Wed 23'-O!Hl7! Wed 23-<J5-07 i 0 days! Yes I 'li! '~!i- -+--l--lH+++++H-II-f,'iolJ;-,+++--+-j! -r-!-+--+_+--i- !,-+-t--

~ ~ __ . ._.c_. 6.2.6.2.1.1 cOlUmns -.----------- ... - .. -.... -- 8 days: Sat 05_0s:Q7r-Sat 05-0S::W+-- Mon 14-<i"ij:orr-' Man 14-'05_07 ! 0 days! Yes I i Iii

--:::=-- -----------------------------------------------~----------------~~-:- ... ----~-----------l.-------_L ~ __ .i_ .L_------l---~+---l---,--.;.--:+--+---1!~·_+___l-t___++_+__;-l__H_++tHlH_**+_IIl!:::I_H:___t___r__t-r_+__+___t___j~t-

329 6.2.6.2.1.2 RC Walls : 8daysj Thu1O-Q5-07! Sal 12-'05-07: Fri18'{)5-071 Mon 21-05_07 ! OdaYSj No :1

330)--.- .. --- -- ·--~·-·----6.2.6.2.1.3Srab·--·------------··-····----------------·---""···~------------·----·-i.---·-idayst_---Tue-15=OS:Oif~--'""Tue15:0s=ii7t---wed23_05_0it---We(r2J:OS:Ojl-~--·-·-cO'-dC'a·-ys-·~fk-· ~--y;·c:es·--l--li'-+-+-+l---{~-i-!---+-:'l!-l--+++-+--+~H++t+t-H-JHi-till:l++---t---t--,:-t--t--t--t--+-t--

~331"l6.2.6.2.2,.B2f6 daYs i sat 12-05-0i1' i"hu ,i4is::oi' [ Wed30-os_oij Mon 04-06_07: 4 days 1 No Ii III

No

No

, . ,

,

, . ,

Fri 01.{)6-O7:

o days 1

Wan(Overall)lleccw2006-15(290306)

VINCI CONSTRUCTION~SUMITOMO MITSUI CONSTRUCTION JV

6_2.6.2.2.1 Columns S !iays 1 flat 1?-O5-07 : Thu 17-05-07: Mon 21.05-071 Fri 25-05--07 : 0 dQ~ ! No I I.

6.2.6.2.2.2 RC Walls ' . 8 days ! 'Thu 1-i.{)5.{)7_'·:~: Th~.U--24-0-·.-S'O- .. -7--;~: __ :_F_ii._2s-0_··· _. 5-0.'_' ~·-7=" .. ff.-: .~F-ri-O:-1_·.{)6.-···-·· . .{)_._ ·_7_ +-i . __ ."O.-:d,--ays._4l------:N..,o-··l--+ j'-i-+--l+--+-i'-+--+-+";'+! H-+-+--Hl-++tH+Hit-H±t--t-jI-t_-r---r---t--t--~t_-r-

----------, 6.2.6.2.2.3S~--------~-~-----·---' 8 days! Tue 22-'05-07 j Sat 26-05_07 : Wed 30-05-07] Moo 04-06-07 : 0 days! No : 1-

---- .. ·-""·---·-···-·-6.2.6.2.3B3--------·--~--------·~-------·--··-·--------·-·-·-----·--·------·-·--~--:---16daysi----TIiii-24-GS:Oit--ThU24=Os'(i7i·-'··-;;..-on~11:06-07 r---Mor.-1f':06:Oft-----ocfaysi----·-:Y·-:es·--t-!I-+-+--H---<-+ il-j ,!-i__f---++-+__+-i'--lil-l+l-H--t-t1i-11i+., liIMI-+-+----i-t--t--t--t-jl --t-1-t--

Yes I Ii!

6.2.6.1.1 Ai

26 days i

Thu 12.04-07 f

Mon 19-03-D7 :

6.2.6.2.3.1 Columns

Thu 24-05-07 i

Thu 24_05-(j7 !

Fri 01-OEKl71

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29-{

Early Start I late Start Early Finish I Late Finish Free Slack !I

i

Thu 31-05-07 'Wed 06-06-07 !

Critical- rl-~--t2~0l.C0~6~~~"--'------r-'---',-:-.-::--.c:c-.-c~=-~; 2~0~0,f:7 :-;-:--;--,-:-,-;-;---r;:-r-;---,--;-,-;::---,-;::;---,-..,--,r;:;-t! 2O~0~8",~r-;:-,.-;~ IN '0 J iF M A iM !J lJ iA Is 10 IN 0 jJ iF M A 1M IJ jJ A!S 10 iN iD !J iF M A 1M iJ

i-31-2 -1;1 2 31415 6 17!819110 11112113 14 15Ti6T17118 19i20'21i22i2:il24125 26 27j28~

NO! !' !

~1-+~~~~~~+--+-~-H~-+-+-ij~~~~1~4i~-r-T-T~-i~~r-~+-t-j-

M ,-d,';~'-'_ S.b_____ ----,;::;:,--Th=~--i ... , • ..,c____.",,~i-- -'rl"-:-"~'-diYit---~: I

i 340 i 6~2.6:2:4·.·1'cOiumns·---·'----- 8days··Thti31:'OS::Oj·i---·TueOs::O"s':07T-j::,roa::Q-ii"Oii Wed-1j..Q6:-OjJ---O-dayS;---NO·t!~l-.L-i-~f-:\-----+--l--f~'-'-+++-+__';~~-jf-HftH.++lf-IH--1.JjIt+-l-+--t-r-t-+--t-t-t-i--j--

~--. -.--- - -- '--6.2:£;24:2 RC wafiS-----------·---·-------·· ----_···----·----------------;..--··-·-12days--;----Tue 05-06-o7f--Sal09-:OS-07 i-Mon 18-06-Q7 j~--Fii22-06-Q71 0 days! --'-'Ne> i ! • 111

"342l"'---'--"- 6.2.6.2A.3Slab . -·--·-10 days -T' Too 12_06-07 i Too 12-06-07 Fri ;22-Q6-Q7! -·-=Fn~·-22--O-6-_O-7.;-! ---....,O-d~a--ys I Yes ~ I

3 ----~';~;;~- __ -_-~=~~==~=~- __ -. __ -_==~_-_- .. - .... -.~=-~~~-·~~- ... -- .. ----===---.------=:l~;~i_~_;i_;~;_=_~~;~~t-_. ~:-:-:-:-:--:--:-:-:.-l:-----:-:--:~:.-:-~:--~:~:.-+j ~i---+--+--Jj~'--+--+----+~f.;-+++-+_;HHH+1fH__HtlHl1o:::£:.J1t-+-ttf--+-~· t-' -1-T-+---t--t~t-+--;--

34S [ 6.2.6_3_1.1 Columns ' 10 days i Fri 04-Q5-Q7 i Man 28-Q5-07: Tue 15-05-07 J Thu·07~S:07T-------~O-daysT·----- No

~-------·----·----·-6:2:s.3.1.2 RC Walls .-----~-~.~-------- ... ---~----------j---~ 14 da-Y;;-- Fri 11-05-07 i Mon 04-06-07 (-Sat 26-05-071---Tue--j-g-Q6-Q7 : -.-- 0 days I ·~--,N,--o+-+-+-l-4--+--+-l-+-+-,+l+-,f--+-+--It+lH+*"1HhIl-f=t±HI-+-I1+-~-t--+--;--t-t-t--t--t-t--

~.-.-...- - ----6:2:"6:3.1.3 Slab - ----.---.- .. -.--.---------.--.-.--.----- "-~-"'--""-----'- '-----'18daysi----FIi·TM5-:Q7 t---MOn-~7 ---'ThU31415-07j--''''-sat 23:.06-:Qir---2days! ---No i

-~ ~~ci H~; ~~~i ~~~i ~~~i ~~~i ri~1 ~L_~!~L~~W~~il-~~~4~l-~+~~~~~~~~~~H-ttf--+~~-T-+-t~-~~~-

----------6-:2.6.3.2_1 COlumrjs---~-------------·----- .. --------~-·-:.___-10 days ,-- Mon 07..05-07 i ---Mon 2a:.o5:Q7:--rhiJ17-05-Qri---· Thu 07-06-07 t 0 days I No Iii

10

Task Name

Duration j

! !

8 days

o days;

337

6.2.6.2.3.2 RC Walls

Fri 08-06-Q7 :

Tue 29-05-07;

Sat 02-06-07

o days \

Man 11-06-07;

Mon 11-06-07

Man 04-06-07 '

Too 19-06-07 ;

Odaysj N_0t-~~~~~-;T~+-~~_H~~~~~~~~~fHlliH~t_+_~_r_+~~~~+-1-~~

Sat Q2-oS::07r--S;;-t 2-3-06-0---7_,ic-------c-O-,dc-ays~! . No t i

:: 1---~-::O=:.~--;====-_::==~=---===__~~=~~1=:-:.~:"O.-G--O-:-J.1------_1-:-:_:_:._j_! -.--:~:--!--l!-.i_+-U~-+-! ----!l-+--+--+H-+-+-l:*~i +I-+I-+-l8iHhI1i±iII:+lH-+-#l!l-i -+-i--~-+-t-i--i--+-t-r-

354 r 6_2.6_3.3.2 RC Walls 14 days j Moo 14-Q5-07! Moo 04-06-071. Too 29-05-07; Tue 19-06-07: 0 days! No ! I~

355 I 6~2:.6.3.3.3Si31:l 18 daySl Man 14.()S·lii: Mon O4-06-Q7 : Sat 02-06-071 Sat 23-06-07 ! o-dayS! No iii!

349

Mon 14-Q5-07 :

Mon 04-Q6-07 :

350

351"""" ----.----

S.2.6~3.2.2 RC Wahs 14 days !

~6-.-2-.6-.3-_2.-3-S-Ia-b-·--------~----~---- .... -------------""' ..... -""18- days ,

Mon14-05-07i

Ll._

i

356 I 6.2.7 PENTHOUSE & PARAPET WAlLS & PUNTHS 71 days i Wed 18-04-07: Tue 19-0G-Q7 :~on 09-O7_O7! Fri 10-O8-O7! 28 days t No I -,-

357 I .. --6~2]_ 'i"Zone A -Pentoouse-------· .... ---·-·-- .. - .. --- .. -----------·-· 25 days! Wed 18-04-07 i Tue 19-06-Q7 ) Wed 16-os:.o7 '-_-_T __ OO __ 1_7 .. ::Q. __ 7.-O_7_l..! __ .. ., __ 1_S._d __ ays_ll N,_o~_+! __j~+-_ll_+-l+j -l-+---I--H~~-!-H-I-I-lf.H-++HRF; HbHH-+-+-+-r-f--t-+-+---!-t-

~=~==1~-=:----==--==--==--:1=,:;:~~:=T:-:~l-~=H:t~l-..j. i:_i---+---i!il-~-!-li_+-+-+-+-l-+_t--+---HI~H-I-H+-~Wl.! 1_db!~b,k!----1-i-+-+-+--+----';-+-+-

373

374

8_3.12 Zone C roof

.8.4 Garage roof

:~~~ ::I:=:::~;:~I ==: ~f :~..j.j-t--+--*+4~-~~*++-ti,~~wllll~.~~~i~~~~~~~~~~~~i

382'" ----- 10. t:1-Z1::z2---------,--·--------~-.. 65 days Sat 20_01-07 i Wed 14-0Z-Q7 !f'rl0s.04-Q7 ! Wed 25-04_07 ) 0 days! No ! I !

$83 ------·-:--1IiTi1"-ZoneA-- .. ·---------·----------------·------ .. ---·------------------------i---59edaysl·---slit-204i:tlif-·--sat17~2{)7t--- Tue 20:03=07 i-----Tue-17...Q4:01------0 edays j --.. No iT! 1lII ... '.· t,f,

I I III

I

384

No

47 edays i

10.1.1.2 Zone B

II

Thu 01_02-07 j Wed 14-Q2-07 ,

Tue 20-03-07 i

Mon 02-04-Q7 !

Oedaysr

-Nan(OveraR)ltecGW2006-15{290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

814

VTV -OVERALL WORK SCHEDULE (As per ItecfCW/2006-015 dated 20 March 06)

Wed 29-

!TaskName

I

Early Finish

Late Finish

. 4W'· ------------10":1.5.3 ZOne C---·-·--~~~~--- -~----~--~---~-------'---45 edays i Fri 20-07-m! Sun 22-07_01: Moo 03-09-07 i Wed Os.o9-07: 0.63 edays! No ~ J!

40< I ,O~,~~~~RTAJN·~VV~A~LLS~--~------------------~~--------·~-1~::~:~~~~~I~~:u~.~~.~~1~~~.~:~f~~W~sed-m7-.~~.~~~~.9-0~.~:~i--~F=F:7.:0~0:~::~:=.:~1~-FzF:~:~=26~.~7.1:O~.-G=;~.:------1~:~:~:~::~~~;··-----.:~:~.~!t-1--r-ff-i--1~t-l--t-it-r-t--r-ttH--r-~ .... WiW..~ .. ,ti-n-i--i-1-lrtt-i--r

1----~1~02~~~Z2~~~---------------------------------------------L--30~d7a-ys-L! ~~Sa~t~07~~~=7~:-~W~ed~~~~7~~: -~F~ri~1~1_O~5_0~7~i--~T~ue~29~_O~5_0~7~:---O~da~ys~l--N .. O~-+~~+-~~-+!i~-~+-~-+~-+-it~-i-i~tr~HtHf~ir!r;~~r-t--r-tii--~t-

---:ws--·---10-:2.3-Z3-Z-4--------··-~·---·--------·-------------·------: --L_ -3-0-d-c-ays----ji----.."s-at.,..,05-05-0~ 7: Sat 09-06_07 : Fri 08-06:07 j-' Fri 13-07-07: 0 days! No! ~ 1

-4-06-l-------1-0-.2.-.-4-Z-4-Z5---·-----~----------·----·-----------------------------·-------·-"----::::-30=-d-;-a-ys-i:--·..,.w:7ed-"7::3Q-O::-=s.o"-=-"7+f -·-W-ed--~1~8-_O-7=_O-7-J--:· -·~T~ue----0·3--_O-~7~_O~7'11--·~Tc~ue--2'c1°_O·""..8-O-:7~·'(._.l -------:o:-da~ys--!if.---- No i i II ! ii' !I i !

~----1~~-------·-----------------~--~~1--s-m--oo-~--O-7~1--S-a-t-1-~-~-7~:--~~~~-~---~~--N~0~+4~~~~+4~~~4+4~-~~+~~*~i~'~~' I

---:.wa- 10.3 EXTERNAL WALL· TILES 193 days! t=rl 11..05.071 Wed 30~~7 ! Sat22.-12-{l71 Thu 10~1~ 1 15 daysl No l-+--+---+-l-j_..:\--+j! ~-.;__.f--'-Hf-+~~+---+++l___4---1-I_l1 • .i.I.l.! i i 1 -iii. itj ~=Rt-t--t

10

Duration t ;

i

Early Start

Late Start

385

10.1.1.3 Zone C

Tue 20_02-07 ,

Sun 11-03-07:

Fri 06_04_07 !

45 edays

Wed 25-04_07

17_63 edays 1 ~

-Fii11..Q5-07j Wed 30_05_07 MOn2s:.oo~ii &it 14-07_07 i oe<iayS[ No .. ~.

::: -:-=~~~~:~=~~-------======----====--==---__=8!~+=-:=I--:-=~ =+~~;;;':t~: ~=--:-"O~-l--i--+----i-~~-i----+---+--I'----++-+---+~-l+l-l--++-++-4I-+-+H:I:~I:+': !H+-rtl--i--+l--+--++i-+-+

~::;-;:;---;1-----..1-,;-0.-.4 .. ~O .. ~3:;:;E;::-5;:;;:;;;IO;-;;:;-F;::;,~N;;;,S:;;H-;;E:;;S~(T1=L-;E:;;S~,C;;:;E;::;,;-;-L;;,N-;-;G;O-,-;-;W-;cA;-;L~L.,-,F=L,..,OO==R-;-) --------------+--. 2::-:::-:::,"'" edd;-:ys_YS...;: .• -...,,;::-:....,n,..,;==-::-o-=. =-7~-=:;::c!i---~T:;-:-' ;-;-;:,..,:::;;~;-;~::::;c+:-...,,:::-:---;-::::::~-;-1::::::-=:;-:+-: _::-:;-:~:;;--~-:::;;:;1-:;~~·-O:S=-7~L;:~-------O:0-eda-:;d-,-a=-:~-+-;i--:--~:~y~N=es~°:-iT+l!f----+t----i~--~--,-HIJ---~f----i:--:--~1-]----l!--_-~y:-,+f----j+-~:---+:fffl-----i;--:--;:r_-i+-t:;..,H:IIi-~:it1W.±l:~i-.tt;;;~;;~;~-H++-r-

"I ~~~~~~!~,!~.""

- .. -.. 1 +--+-- ~~

Thu1g::(ji.:oi! 1'0016-03-681 Wed 19-03-0a! odaYSi NoT i !

::~ --_.-._- .. _-_-~~;-~.~.~--~~~---~c=--------- .... -- ... -"-_--c_-._.-.CC-"_- __ -·_-"_-_·_-_-_-_-_- __ -_·-_--_-·_-_-~-~-----------~.-~---------------------.---------------------.----------.------~--.--~-T~-----:a7-~·~:-"~:~~-ys~"1:~~~:!ed-ed~~~~8~-O~;~-o~~~;J;~~~W=T~~·~~~~:9-0-·:··:;~:-o-Oi;1:==:'w~T~~e~:~:~:~:::~~:=:~:~::~:~:~;~·::~·-~:~~=-·=====i:~:~:~:~l=-~y~~~°i:=l:i1==t=!=I~'l_l:l:Jt:ll:l:t:=;l_ll~=I:l~i:~~~~Il~i1~'~~J:·· ~~~:l==t

418 10.4.4 Z4-Z5 -.----------~-------------~-----.--; -204~ays i Wed 25-07-01 f Thu 26-07_07 : Too 1~3-08 ! Wed 19-03-08 ! 0 days ; No I

419 1 OA.5 ZS,zS -----.---- .. ----.--- ~--.-.- ---------.---.------,---16~9--d~ays--'i--'~T-ue-04-09-O.,.-,-~"'7,.;j---W=-ed~O::-:5-09-0:-::-:=-=-7 r------=ru--e-1c-=a--o-ccc3-O_O=8+j-.,."Wed 19-03-08 j 0 days 1 No Llj_JJLLLj_lJ-LLJ_j_jjWL11J_W.Jl!ll~~~~~~t~~~LLJ_

42iJ 10.5 ExtERNAL PAiNtiNG 60 days lWiK(~1:OO : Thu 10-01-08 j Tue 18-03-08 j Wed 19..03-08 i o daYs j No I I

i i N'o~I--r~~j~-t!~liiJ--ri--rTItt--rJ--TIff"""IE.' I ... '~~, '. "J'~~i--T

339 days i Fri 07-03..Q81· Wed 19-O3~8 i . 1o(laysl I ! i-'

423 11.1Z0toZ1 306daysi Fri23~2'()7i Thu29~3~7: Thu14-02~8! Wed19-{l3_GS!ii-daysl No

424 11.1.1 MECHANICAL WORKS 306 da~ ; Fri 23~2~7 : Thu 2g.o3~7 1 Thu 14-02-{l8 j ~--W-ed-19-~-U--S-+' -----2-9-d-ays---'fl----NN'(;ot-+-+---l-l1r-r-r!-r_-J-+-fH-t-t--nHtHl ..... .w~1 j .... i. : •••• .- iTHt-t---t

m -~p~~~~-------------------------:-~~I ~~«I ~~~I ~~~I ~~~: ~d~-~N~o~~~-~~jl~-l~!~~~~~~~-I~ffffl~~~~~~~ •• ~ •• l •••• ~m~-t

"426-------·----··-·-·-·ii.i:i"1:-1-COldwaterSupply W~-rk----------------------------------+---7idays:-----Fii 23~2:Oit---·Ti1U-29-~-3~7 : ---Fri1i:OS:07i~--T-hU-21_G6-nit-----29- d-ayst-----NOo t_+-+~___lt__r__t 11 ---,f---r-r---nH-r---t--Hifj-ij .... iiffittt-tHir-ll,'t"-ii-titt-it

427 ~11.1_1.i·1~fEquipmer.-flristallatiOn ' 27 days : Fri23-0i_oi!' , th~29..Q3.()7 i MOr126-03-0il Sat'26-04-07: odaysi No !j_!

73 days : Fri 23-02_G7 i Thu 29-03-07 ! Fri 18_05_07 i Thu 21-06-07 : 0 days I No I i

10.3_1 Z1-l2

Mon~11-071

Thu 10_01-08 ,

45 edays ]

Wed 07-11_01 I

Sat 22-12_07 i

No

45edays :

-

415'

10.4.1 Z1..z2

210 days i

wea 18_07_07 :

421

-_ _ .

422 11 MECHANICAL WORKS

428

11_1_1.1.1.2 Piping works

_______________ . . '-_. __ 45,,·, ~d--:_a-~--'--j _~M.,_on-~16.o_.()4~"-::O~-7,__i-!-·- _--:5..,_ .. -r ii9.o~7 i wed 06..o6~7t -Tile 10.0'7.:0'71" 29 days i_·. _~_N_o-+---l-i ----i-+--4-+--i-----i-l----+ j; --J.++-+-+--t4-+jH-l-+-+:Jl=t-I-~_+i-wff_HH+llH_~~f----+-+++H___if__+_

15 days! Moo 16-04-07: Sat 19_O5-07! Wed 02-05-07 j Tue 05-06_07: 0 days I No I I I

431 ----··-----------·--··-·-11~i1~1.2~2sOifpiping·woriS~as-teWaterPfpTr1g~1b-----------------" .. ---··------·-·----··--~··-"·-_--_;4_=5~(f_aYs_·-_j.-t-_-_--c-M=-Onc--:1:::6-04-0C7-=-===i+t_-_---~Sat~1;_9,--::'O:::5-0:-=7~c+;-·"----w~-:-ed7-06-06==-::--::-:-o_c-O==7:_l1'-.----~T;;;_OO_;_-:::;1-0-0,...--"'7,..,:O:;:-_;7:-i;_-------::-:;:-.;0c--d7a-ys-+-f _-··_--_-~-N:;--o+-+__I+_+__jjHf___+__++-+ !,~r-t--t_+_+__t!_t_t1Itt+-+'-t--t_W.i'.tttiHiir-t---tt--r--t---r_tiflr-r--t_

432 11_1_1.1.3 Rainwater Dt:ainagework 15 days: Thu 07~6-07 i Wed 11~7~7: Sat23..()6~7! Fri 27~7~1: 29 days I No i I !

11.1.1.12 Drainage Pipingwo~

11.1,1.1.2.1 Equipmentlnstallation

lVan(Overan)ltecCW2Q06..15{290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

9

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29·

10

jTaskName

Duration 1

1

i

Early Start

Late Start

I Early Finish

I

Late Finish

Free Slack 1

1

433

11.1.1.1.3.1 Equipment Installation 11.1.1.1.3.2 Piping work

15 days

Thu 07_06_07 :

Wed 11_07-07 Wed 11-07-07

Sat 23-O6.(l7 :

Sat 23.(l6-07 :

Fri 27_07_07 .

o days:

Critical I 12006 2007 :2008

!-!iN4'!D!L....! . .4J_jJiF=---l1'Mt!L.j~A4JiMY!._f-"=J+iJ4~A-II:s:S40':'--i.!'N'::-PD4J~·:--f;.!:F:;:-:f!)M41A?::---lI1!'M!::+IJ~,..! ,A is 10 IN iD !J IF MIA 1M j,

NO!-! -_3+:_-2_;..!-_1_;_i_1-i:+2-+_3",",fi--4~_5_;.I. 6--4-_7-'.-, 1-8+-9-j...1_0+-11-----;.J1H2-1';.H13_:l-1_4+i-15-i!-i~f+6IT+I+17Hift1tt8E.·' 19 121 :22 :23 24 :25 26 ;~

N°I : 1'1'

No!

___ I ! ' l

434 i

_____ i. ..

435 !

• -.-.--- .•.• _,_, __ "._~.~"~ ~ _· __ L_.~_. ._ .. _

11.1.1.1.4 Sewage Water treatment" --------------- .. -------

15 days - - -----·79d"ays :·····--Fri·20:.w~7T-· .. Thu23-:08:OT·-- .... Fii·19~{o:071----Th·u22~11-o7t .... ·····-··--29days:-

Thu 07-06_07 .

Fri 27_07-07 .

o days:

445 ! '446l

I

~~~----~ .. ~---' 11 r2.1_1.4 Piping wofkS~u~ris.secondary electrical \'t'Ofb. auto wntrol works

~·-'·"·'''··--·11.2.1:2PWMBfNGWORKS---'

~ --- --- --11~1.1:1.4.1 Equipment instaUation - --- .. - - .. - -- - "'.. .. 53dayS--'''Mo;'I20-OB.:Q7! -. Sai-2i.:(j9~i;· FM 19--f6..o7 : ···Thu22-11::Q7t .. ··· ·········O·daYs· r

I i

~4_3_7_~1~' .. -- .. --· .. · .. ----~~-~11~~1~1.4.ipipin9workS ------. ~-~--·--------·------··---·~·-·- .... ; .. ---·-79 days r: Fri 20-07_07: .~_T_h_U_2_3-0_8_-{)_7_'_,_·_--_F_n_·-~19-10-07 r-- Thu_22__,-1 . .,.1_-O,.,.7-+i __ .... _--_""_--".."..0_d.-SY5L1-· .. -····~N~olJ-L1JJ_j-L.L-'Llj_U-Lj_1U!W~L_-DUW~~~~~ft±=±:U~U~_+-L

_4_~ __ ! 1U~AOO~~~~~~ ~~i ~1~~1 ~1~~ ~~~I ~1M~i ~~! ~~l~-~+4~-~+4~~4+4~-~~K~-~#~*+H+~~~~~*I~~~~+

439 J 11.1.1.1.5.1 Oil tank Installation 26daysi W~16-01-08j Tue19-02-O!if Thu14_02-08! Wed 19·03-OS! 29 days] No l ~

~ j----------~~~----------------------~ 26.ys! Wed1~~i ~1H~! ~-h-U-1-4_0-2--{)-8~!--W-ed-19-_O-3-0-8~1---2-9-~-~!--N-O-.~I'~i-Ll~~-~+~~-4~~~-~~_~~~+Hi*~HI+t!~I~+-I~.~i±.~I~I~~~~

~. . . 'iii-Z1:z2' .. ---.--- .--.. .. .. . - - .. · .. ·- - .. --· .. -- .. ·---· .. ---· ----~- .. -----· .. ---------·-ii9-days'1---wei(Ci7-02:iJif-----MQn 19~2.o7t Ffl07:O-3-:Qsi---'W'ed-w.:oo:ort------- .. --9daysr-- .. NO-+----fl--i'---.+--H- -+--+--+----;....:+++-----L-i-+-HI-t- :: : ; i :! ,..-HI--\.-..L

:: ~- '_1 __ .2_~-1M-.2-~1C-.1-H~-C--~--CAL-v .. W~~.~-~-·~·~~-- .- .... __ .... __ ._:~~-_-_-_- ... -_--.-::::::1-. :::::::;r-;;:::::::;.~;:;;;i - W::::~;;+ __ ~"" ::-=~I.. ::1 i" j!" f : t !

444 i 11.2.1.1.1 NCequipment installation 105 days: Wed 07_02-07: Man 26-02-oiiFri 08-06-071 Wed 27-06-07 , 0 days i Nat i

53 days! Man 09.Q4-071 Fri 27-O4.(l7 i Fri 08-06-O7l Wed 27_06-07 i 0 days: No !

105 days: Wed 07_02_07; Mon 26_02_07 i Fri 08-OO-O7l Wed 27-06-07 i o days! No I

~_i ~O~I ~~~: ~~1~1 ~~~i O~i ~N:o~+I~-~l+~-~~~~+~+~~~~======I====~~~~~~~~+

.~~~",..-- 333 days;-- Wed 07.02.011 Mon 26-02-07 i Frf 29.02-08 i Wed 19_{)3.oa! .---~-~-.-- No'1 !

1-8·-6·~d-a·ys-'-';~-W~-ed~-0--7 .o·--2-.o~7+! --M--o-n-..,2·G-O~..,.·2~'O-7· ... , ·~·--T=u·-e-1-1~'O~9--O'"'7o-';·--Sat·-"""2""09...,-<lco9--O:"'7:+: -- 16 days! No T ! !

I I

No

. ,

~

-----------11.2.1.1.2 ventiiatio/i-e-qi"iijJiTient installation

11.2.1.1.3 Chiller plant equipment installat101i

11.2.1.2.1 Cold water supply work

No

r 1

. ~

1

452 I 11.2.1.2.2Hotwatersupplywo~ 81 days: Wed07.o2-G7 Mon2G-02-07! Fri11-05-07! Wed30-05-07i 16daysi No I I.

453 I ·-------· ...... · .... -----1-1.-2-1-.2-.2·-1-P-i-pi-ng-wo·-rks·- .. ·----· .. ·-·--·----~---~- .. ---------J._--s1days i--Wed07_Oi-07; Mon 26_02_07 i Fri 11_O5-07! Wed 3Q.05-07 f -0-d-a-ys-ii!-_·-_~-~-No~11~~~!'-_1.j.._-_~-_~~fl-_-1f._-_l-_1;"_-~-L~-+!---4.!r~f~r~~C:f~li=;:f:i;~~~r~I;'r~1~~~~~~:f~+~~~~f~r~+

454 I 11.2.1.2.3 Drainage & Vent Piping works , 186 days t Wed 07-O2-<17! Mon26-<12-07 i Tue 11.(J9-07t~--sat2M9-01t---~aysj No

~--··---"-------------11~2.··~1T3~1·SOi!Piiiin9-~-rkS~Wiste PiPing-YoQrkS:Yentjilpes .. -- .. -------- .. -- .... · ...... · .. -··---· .. ·!·- .... 186dayS-t---Wed07-02-07 r--' .MOil26-02-07T--- Tuei1:oo-mt---saCi9.m:(i"j~. --------- 0 dSY$t"---·--·~N,..ot~1:~l~lt~~~1:~t~l~~1~l~l11~~~1~~~~11~~:1:~::ii=~;;i;ii=' '~~~~lt+t~~~~t~~~~l~l~~

~ 11.2.1.2.4·RainwaterDrainageworkS·· ". i 186days: wea07~2-oi! Mon2S:02.(J7! Tiie'11'~9:071 Sati9:.:o9-oi] 16 days I Not! ,

457 I 11.2.1.24.1 Piping works ' 186 days f Wed 07-02_07 : Moo 26_O2-{)7' Tue 11_09-07 i Sat 29-09_07 ; 0 days i No i ,! '

473 I . .. 11.2.1.3,2.1 Equipment installation

." --------------- .. 11~2.1.3.£2Plping works ____J. 475

""467-.' """468

11:.2.1.3_1 Sprinkler lHydrantIDry stand Pipe System 11.2.1.3.1.1 E(luTpmenOnst8ii8tfon .. ~ .. ----~-----·------------·--·- ..

11.21.3.1.2 Sprinkler Heads/Control Valve Installation

11.2.1.3.1.3 Hydrant Cabinet installation 1·iii3":1.4 pjiiIilg YoQrks

11.2.1.3.1.5 Secondary EleWical Works

469 [ 470

471 '"""472"' ·--~--------1:-c1:-c.2=-.1-:-.-=-3.2-::-:CO:-=:2:-cF""'I-re-ext-.- 'iiiA'~i~h~r$ntem----

476 47'l

11.21.3.2.3 Secondary Electrical woikS

232 days! Wed 07-02-01: Mon 19-<12.07 r Sat 03-11.01 i Thu 15-11.07 i 10 days j No I i I

227 da~ I we({(i:;;oi.:()j r Moo 1s:.o:i:.o7' jMoo 29.10;071,' ·f:i109~H.:o7T OdsYs I ~N~·O~ .. LllJ-!LllJ-J-l-:l! i-~L-!-_JfJ~tt~~~~t~t~~u~-~' ~~l-+-4

' --_.--'-----+ ; ; ; ,

478 11.2.1.3.3.2 Devicesi"iiSta1lation 53 days: Too 04-09-07 : Sat 15-09-07 i Sat 03-'11-071 Thu 15-11-07 r 0 days I No ' I ! I I: -,-., iii

'"479"" -- .. -----~ - .. ----~---j1:2:1~3:3~3MainCOnlrol Panel Installation "" .. ------- .... --------···----------~ .. +· .. --26daysr- .. ·- Fri osTa:oil--- Wed 17-10:07+--- Sa! 03="11-07 r-Thu .. 15-11:{)7r .. -----·---0-d-a·-ys-+I-·---N~O-l--+-f--+--#--4-+-+-+--i!......;.. +; +-!-+-+-+ !i -HH+--+-+-+-HH++H1+-+-!-1Jj-+-j.....l-i;ft-j-+-+~ ---1'-t1I4----jI~

480 11.2.1.3.4 Rre ExtInguisher Installation --'- .. -----------------j_---:7°--d--;-a~ys-+-: -""""F::-crl;C29-0:-;O-:"'2'"'-08c~i--W'"'""ed-.---:1.--::2.--:-D3-0=-::.-:;;8,.[i~-"'Fri~07""-O:;:3-0=:;:-Bf.! -~W~ed--.--1:;-;M";::3-0;:-=:8:-":~----:1;:;0--:d;:a,-:ys,-'ii-· ---;N--;CO+-+-if--l---tl--+-Tf-+-+-i---'-. t-, H-+--+-+H-H-1f-++H-tttltt+-H--n-:r:--tf-+-t-ti "'";ti,;-fit--tl--t

11.2.1.3.3 Fire A1armlSmoke Extraction System

Nan(OveraU)HecCW2Q06..15(290306)

. VINCI CONSTRUCTION-SUMITOMO MITSUI CONSTRUCTION JV

1

VTV -OVERALL WORK SCHEDULE {As per Itec/CW/2006-015 dated 20 March 06)

Wed

10 I Task Name

I .

1

I Duration !. Early Start I Late start t Early Finish Late Finish I Free Slack

481 11.3Z2-Z3

316 days ;

Wed 14"()2-C7

Sat 17"()3"()7.

Sat 16"()2-C8 !

Wed 19-C3"()8 .

26 days:

482 i 11.3.1 MECHANICAL WORKS 316 days' Wed 14"()2"()7 Sat 17-C3..()7 Sat 16"()2"()S : Wed 19"()3"()6

~483 !.. 11:i:i1ACMV-' ---.--- -.- .. ------ ..... --. ---- ... -.--- .... ·-243-daYS---We(j-14..oi..oif·· .. ··Mon19:Q'i..o7---"·":ii-23:1·1:Oi ;-·····-w;;d·26:.12~7C'--

i 484 ,.. 11.iii::r·NC Equipment installation m105dayS···· Wed 16..{)!H)7' ···· .. Tueo3=Oi..iJY"·---·-·i:'ri-14..:0S:07'T .. -·Thu-01::1'1:Qf'···

~I" · .. -·-- .. · .... ·----11·.3:1:'1Tvenifl8tiOri-EquiPme·iitinstaiiaiiOn--·~---·---· .... ·- .. - .. ·--- .. ·---·-- .. --------·-····--53daY~.. Moo-'1-S::07"{)7: -- Fri 26-10-07: Fri 14"{)9-O7! Wed 26-12-07;

l'!""r'"'!'

27 days!

28 days:

o days j

Wed 18-04-07 ! Tue 2So12-07 i Tue 22-01-08 : 24 days i No i ill

tue 07-08-07 ' Fri 19-1~7 j Thu 00:.12-07: 0 days j No' i , , I

Sat 06-10-07! Fri 19-10-07 j Thu 06-12-07 j 0 daYS]..1 - __ ._~N::oLJTLLl..Jl_1-ILj_J_..l_JJ__!__L_j_~UU_l[_I_++_UW-+U+~!! ~1..l..~i~L....;....~'~; ~ •. '~ii W-l--1---LUi-"+! _

_ ::_ .. ~--I----------~~·:~::::~:~~~:~~~seoo~a~~~WikS,a~o(OO~~-----·--- .. ···· .. ······'·--?:::;--::-::-~::r··--::~-~~:~~::---~-::;-------::~~:; -~:o;o~+;;-~+-*+-ii-i-+-+-+H-t-+--H~~~.;1iii:;1=':I==i=1T=:;==~Lt-~i--I~·

"'515 .-_ ... _-- ... - .. -- 11.4. iiXCold water supply worn ----. . .. --.----.---~; -189 days r·-We<EZ1'.:o3::07'[···---·weci' 18~7 j--' Fri 26'10..o-rt-··-·-Fri 23-11-07 (--~ 24 dayst-.. No ! ! I'. ~~*,~.-n--t-r-t-tlIttL~-

~ ~~1~~ ~~! ~~~I ~w~1 ~~~I ~~~ .. ~~I-~N:o~~~~I,~lt~1~ll~1~~·~t~1~~1~1~~1l1~~1~1~~ttl~~l~1~iii~illili111il~]l~~~1~~~+*~i~

517 1'.4.1..2.2_Hot water supply works 1B9daysj Wed2t'{)3-07j Wed 18<M-07i Fri26.10..()7: Fri23-11-07! 24daysj'" No I

~ ~~~~~~~ 100~! ~~~1 ~1~ii~~~1~~1~i O~'-~N~o~~~-~~!jh~~i'-~~'-·-~:~rrr~:~~f~~rl~rr~i~~~~iiiiiiiiiif~~r=r:r=~r~rr[=l=

_5_'9_~ 11_A_~~~~&~~_~rks ~~I ~~M~7~!_~W~ed~17~~~-07~j_~F~n7·2~~~710~-O~7~!_~F~ri~2~~~1~1~-O=7~1~ __ 24~r ~~~il_~~~~-~~~-;f~~~~+~~~~+4~~*~+~~~4~~~+*~_

~ ~1A1jTI~~~~~~~~~~*~~ 100~i ~~~! ~1~71 ~~~i ~~1~i __ ~~0~d:a~~~IL_~N:O~~I_~~44~i_~~~r~~~~+~~~~=========~~~~~J+

-52-1-1-------~~-·----·1~1·.4-:-.-.1-..2;-.4 -r- Ra~j'n-w·--at.,.e--r~D~ra~i-nag---e-'W"~o-rks~'--'-----------"" , 233 days ;VVetfi1.:o3-oit-- W~ 18-0+07 : Mon 17-12-07 i Mon 14-01-08 T- 24 day$- i NO! !

-5'22- -11.4:1~2A-:-1P1pfng-woik5--"--·--- -----~-.--~--.----- .. -------------------.- .. -- - --189daysr- W;'-i1~:UJjr--wed18.04-0~ ~ Fri 26-10:07t--~F~~11~7r--·----O-dayst-----N~O+--!i-+-+-#-4-+-11 _;'-+-+r~4-+--+--i-I, -+HH-i+-+-+

523" 11.4.1.2.4.2 Sanitary FIXtures Installation 7i' days! Wed 19-09-07 ' Wad 17-10-07 ! M'on 17-12-oi i Mon 14-01-08 ! 0 days i No -r i'

524 11.4.1.3 FIRE PROTECTION 290 days: Wed 21-O3..()71 Tue 17-G4-G7 [ Thu 21.o2-08! W~ 19-OM8 ! 23 days j No i ! I I: I I

~ ~~~~~~~~~~~ ili~' ~~~i ~~~! ~~«I ~~«1 ~~I ~~il-~+~I~~tl!-b~~I~~~~~~~~~~.~~~ ••• ~ •• ~-~~~ffi~1-

~ -----·------~-11.4.1.3.1.1 sprlrikier HeadS/Control Valve Installation 50 days j Wed 19-09-07 [ Wed 17-10-07 j Thu 15-11-O7! Thu 13-12-O7! 0 days ! No

~ -=-_-_·-_-=~_-_--_-_-_-_-_1 -r- 1:_~4.,...·71~_=3_c:1:_;2:-H=-yd,..,-;_ra-iit-Ca.~· ... _bi_n_-_et_l_nsta-_~_.I_lati-_-=o_n_·-_-_-._ .. -_ .. -- .. -- .. --_-_--_-_-_-_--_-_-_- __ -_--_-_-_-_-_--_-_-._-_ ... -_-_-._;.:..~-_~50:;:;::_d.,_a-ys-+i·----.,.,w7ed .. ·-o::":_:9_:':OO=::-:_;:':O~-i::_i!--.- .. -_-""-W..,..ed...,.--:1c;:;7:-.;.1,.,O-:;-O"'7c+j_-_-_Th;:;"'U-~15-~171 .. -O:;o7;--;...j-----...,·Th .. ·L:-U_:_-1:;_;-j:";_:;-;12;_:O:::-7.";'--l_: -_·-_-_--_-_--;:·O:-:-d7:a...,.ys:+t .. · .. -N-'O-.j._~-+-.f-.j.J...+-...f !,-+---+--+l!~H-+-+-+--i+m++-+++-fjH++l+++*+--tjH-. +-,-l-HH---l-

528 11.4.1.3.1.3 Piping Works 207da~i Wed 21-03-07; Tue17-04-07! Fri16-11-07! Thu 13-12-07 i oda~i No 1 I! . i i

510

~

511 I

512.

11.4.1.1 ACMV

1'1.4.1.1.1 Nt Equipment Instauauon 11.4.1.1.2 Venlillalion Equipment Installation

240 days i Wed 21-03-07

. 105 da~ 1 w~ 20.:00.07 '

53 days: Mon 20-08-07 [

Nan(Overan)l!ecCW2006-15{290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed:

529 . 11.4.1.3.2 Fire Alarm{ Smoke extraction system 233 days' Wed 21.{)3'()7: Tue 17.()4.()7 Mon 17-12.{)7: Sat 12'()1'()8 ' 23 days: No i , ;

__ ~_l ~~-+~~rr-~-+~~+-4-~r+--~.-~ritr~~-ri"'HTtrtr-TT11'--TI-~-Y~--~mr-i--

~ I 11A1~Z1Roo~~~~~~~ .~~~ W~21'{)~7 The1~M~: W~1MM71 T~W'{)1~ Od~l ~11-LL1~W~L~J~~~t~~-4~U~~~'~m~~~~~~~~~~~~-

531j~'-- ··---11·~4:1-:-3.2-2Devices -jnstaliation---"---~' .. -------- - -- - .. - .. ------ .. -.--- ··--~---51(fays;_---Fri-19-1o:Oi: ·-filU15-11~t---iiiori17:-"2..{i71· ---siiCi2=O"1:.oi' ----.--- . -o-daysT---No . ..1

~---~~~~~~------~~~-~~~ ~~-~~~~--~~r--~~~+I~~~+~~~~~~~-*+-+~-+~H~~H~~mH~~~H~~-~~~I~~+-

533 ,--'--11.5 Z4-z5--.---.---.----.-.--.- .. -----~.--~- -- ---.- .. - .. -.- - .. -- ----- 265 days ; Mon 1S-:04.()yr--·-Wed 16'{)5_07 : Mon 18'()2'{)8 r'- wed 19'{)3'{)S: --2iidaYs! No I _j

-SJri~-~.1 MECHANICAL WORKS 265 days Mon 16'{)4'{)7' Wed 16.{)5_07 ~ Mon 18'{)2'{)8; Wed 19.{)3.{)S·~~---:::26-=-d:-ays-,-ji--"7N:-o-lI'--+i ---if---+--4--+-;f---i---+--+--!+j-+-+~+-tttT--b;

~~ ~~.5.1~_AC~ ~43 da~~~_~:_~~~~:__ __ Mon ~~5-07 : _ \Ved :~~~~ f _w_~ 05.{)3-08_' __ ._.~_3_.6:::-d~a,ys---;f_1 ~_-;N::-o,..;II__+I-j--+-H-_t-i-+-+_+-++_+-+___jH-tH_t__1-rt__H_tH+tt_+

~~--~--- ~-----~~~~~~~-~-~-~i-:+I~~~~~~-~+~~~*+~~~*~H-~~+~ffi~~i~~~~-i'~~-:~~-'~1~4~~~-

:: ·---··----·~--··-11.5;~5~~~~:;::;;=;~~~~-a-ry-~~~I W~~~~·.~.~~I~_rks_~ . __ ~- ::::: i ---::; ::~;.:- :::::;:;-; ~:-:::: i ----. ~::::; '--3;-d;d:~:~- tl---····- ~:;:t,-~+-+~h~f-+-+-~+t+-+-l'~tt~H__j~=:==~T II r

-s:w- 11.5.12.1 Cold water supply work 191 days i Mon 16-()4.{)7 : Mon 2S'{)5_07\ Fri 23-1-1-oi i FrlO4.{)1".oid 36 days 1;"6 1 ! =;;,: I;;;;o;\~+--;-----t-;t'l-+--

541

~

11.5.1_2.1.1 Piping works 11.5.1.2.2. Hot water supply work

191 days! Mon 16-O4-{)7, 191- dayS lMon 16.{)4.()7 I

Mon 28.{)5.{)7 :

543

11.5.1_2.2.1 Piping works

191 days \ Mon 16.{)4-07:

Mon 28'{)5-07 :

Moo 28'{)5_07 1

~ r------------~11~.~~~1.2.A~~Ra~i~-~er~D~ra-i~n-ag~e-w-O~~----------------.------.-------

54'7 11.5_1.2.4.1 piping ~

191 days i 191 days! i

548

o days l __ --;N,-;--O-+-+-+-+--lHH-+--+--+-! '-' tt--iH--t-+!! Hlt-t-t-l "iiiilliliil : 111111 i &' II' ~ , :iiiiiiiil...-+-! -Ht---+--+

.----r- 265 days: Mon 16.{)4.{)7r---Wed -16'{)5-07 : Mon 18-02.QS r' Wed 19-03.(1S \ -~daY;r No I . I Ii! n : ~!

---------------11.5.1.3.1 SprinklerIHydrantiDry Stand Pipe System 218 days 1 Mon 16-114'{)7 i ----Wed1G::05-0~7ITi ---;Ti'iUJEe;:2~!5i=-11:2Z:.(Iii:77,j~ --""Thniijui:2~4.{)i=Oi1~.{)iiii8~j:--~ :2zi6j";dioaiiys;sT, ----NNOo!T-t-iTTj-r·l"t';""lj -n11IrtintTi! ••• : •• ~1.; ; j iiiltr-i-j----tl--litr--j---;-

c • • -fi-:s.1.3":1-:1"lfp-iiriidiirHeads IControl VaiVE;lnsi~ijiStiOn~-·---m~.-.----~-----~------- j - -51days i -"Tile 1s.:1o=ilir---i'uev:11.m j -ThTh .. UU113-3-1122-O-o~77' . ~.:,;. --Thu 24:.o1:oat----·-o-daYs ! No

11.5.1.3.1_2 Hydrant CabinetlnstauatioiJ . 51 days! 1'0016-10-07: iue27·11-oi: Thu.24-01=ooj 10days[No

19fdaysj"

Fri 04-01-08 ! Fri 04-01-08 i

36 days j No

odaYSiNO I

I

11,5.1.2.5 Sanitary Fixtures Installation

77daysj

Sat 15-09-07: Sat 27·10-07 : Thu 13-12-07 i

Thu 24-01-08 :

~ ---·--·------1:;-:1;-:.5;;-.1~.3::':::;FIO=RE~P=RO:::-::::cTECTImi··~~--~--c-~--.--.-

----s5O ~ ~

. ....l

T~1i

~555~9 11~~ ~~I ~~~ SatSatO~9~6_0-7; .. ,:: Sat~~~ W~119~3~88: 2_0id~~~I--~~~~-i~~~~-~~~~h~~~~~M-~tl •••• 'lil!iii~i~i.'~~~~'

11:6.1 MECi-fANlCALwORKS 244 dayS)" Wed 16-05-07 ! -v Sat 23.(12.(1S1 "" -v -V2:'days I No iTilir-r-!i--r! __ ,t, ti--lr-iit1tt1!:i~.... f ! .

~ 11.6.1.1 ACMV 244 days j Wed 16.(15-07! ~'S;;:-at·7709.{)6:::-::-~.(I""'7~·----=SaC-:t23-02.(181 Wed 19.(13.(18; 21 days; NO! . . . . , I ;

si" 1_.~ __ ,,_--·c---ti:6.i:1:TAC Equipmeiit-inStaliafion-----------~·---·--------- ·-·---------------------'"----104 daysr--Mon 1i-10:Oif"-- -M,;n1g:ii.:07--'----·--Tue12-oi':08r--~-Tue-18_nj{)8;-~---·---O-daysJ-I_--_-_-_-·~N~Ollj_LJl_-tjl~L_LJJ: i_j_!-t_j_j+'!U-4-_J__jw--uwm-t~~~~~~~4--Ut,--~t-

562 11.6.1.1.2 Ventilation Equipment Instaftat!on 53 days : Thu 13-12-07 : Fri 18-01'{)S i Too 12-02-OS\ Wed 19-03-0S : 0 days 1 No Ii

Wed 16-05-07T Sa! 09-06'{)7: Sat 23-02-081 Wed 19-03-08!

Wed 16-05-07 Sat 16-06-ofi iue -is:.Gi".oil. f .. Fifis:Dz-os'j

565 -·~~--------171;-.·6::-.-:1.2.~.1:-:Co~ld-;--w-at:-e-r-su~p-p-:Iy--W-ork-·-------------~---·--~------·--------+-·-:1;;;9:;;2-:;d;-:-ays~~: --;;Wc;:ed:-:;-:1;;;6:-;-O~;5_0~7;-ii"- Sat 16.(16.(11: Tue 25-12-071 Fri 25-01'{)8 :

~ 11.6.1.2. 1,1 Piping WOrllll 19211ays (Wad 16-(1~7 i Sat 16--013.:on foo ~12.tJ71 Fri25-01~e :

~

563"" .-----.-----~- 11.6.1.1.3 Piping wori<s, duci woOOi, secondary elEiCt. Works, autooontrol works

~ 11:ii:1.2PLUMBINGWORKS

----+~244 days! 210 days !

567

lVan(Overa6)ltecCW2006-15{290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

121

VTV ..()VERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29·03·06

1 -3 ' -2_l-1 i 1 I 2

12008

N D'J IF IM!A1MiJ iJ

i Task Name

I

Duration

Early Start I late Start

Early Finish. I

j_

Late Finish

Free Slack

Critical i i 2006

IN1D IJ IF iM

2007

AiM 'J :J !A IS!O IN D J !F MiA!M IJ lJ lA!S 10

22123124125 26!27128 29130

11.6.1.3.1.2 Hydrant Cabinet Installation

52 days '

Fri 16-11-07:

Tue 18-12-07 :

Tue 15-01-08 :

Fli 15-02-08

o days!

No! i

I~_,_"!,,"~rl· .

61.. f 12 ELECTR'C~LWOR~. __ i95 I 12.1 GENERAL WORKS

462 days ! . .i3idaysl

lbu 28-09-06 ; Thu28-49-06 !

Wed 04-10-06 !

Wed 19-03-08 ! w~20-oi-08 t

Wed 19-03-08 :

Wed 19-03-08 )

O·days I ··SdayS I

,

Wed 04-10-06!

i96

12..1.1 ZOtoZ1

187 days:

Wed 04-10-06 i

No

I

1

VINCI CONSTRUCTION- SUMITpMO MITSUI CONSTRUCTION JV

13/;

"/an(OveraU)ltecCW2Q06.15{290306)

Wed 29-()3-C

Duration

EarlySlart

=~_~_~_::_:~_~_;;_:_._.:_SU_C_fi_ni_S:_ . L __ .;:_~_··~_·-_: _~_:_::;~;:fl'- . __ ~:~~:::.~~1-~~O~.: :~-7:7L!-~·~~-:~·-~::··· ~·~:~::~··:;li _~:::J.~~~::O ·~:~::~··:;Ll-o------6:0~::~o~i----o~:~:t=1 !:==[=t=ltJt=i==[=t=J:=tJJ==~!i=i J'=j1ttJi' t1==I[1 =itJittt:[::]~~~~~;f~f~~~=f: i t~=~t=t=j==tj

13.3_9 Floor finishing : 4 ewks; Tue 18-12-07 \ Sun 23--12-07! Tue 15-01-08 l Sun20-01-Oa: 0 ewks i No I I I· j ! J ! ! I. 1

- ---Ti4STUDio"3A5-------------·-----oo-----------------------------·----------·-----------~--13idiySt----MOn-03-09'Oi"t----ri0nD3:09~li7t_MOri~0«I2_::oato----MOn-~st--------(O'.dliiat;;ys;Sij--'YFees;St--jr-t---t-UI; .nrrt -j-t"T'I! IIJt, ti-r-tt1"m11il1, •••• i!fi.~!if1Mtrl-r-r-1

- !---~--;1;-;;3--;.4~_1~F;:,Ioor=:-.fIoa=ti~-ng7""~------------------------- 2 ewks ; Mon 03-09-07 ! Mon 03-09-07 ! Moo 17-09-071 Mon 17-09-07: 0 ewks ! Yes 1 1 h! []

JveraQ)ftecCW2006-15(290306)

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

14/20

VTV-OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed29~03·

10

I Task Name

DuratiOn!1 Early Start ! late Start E8rly Finish Late Finish Ij.,' Free Slack 1'1 Critical 'I' N ,0 !J20~6F 2008

,. A Ts :0 .N;D JIF M A 1M TJ 1

I . t-s -21-1 1 19 201'21 '22123 24125 26 27128129 i

2007

720 19 TEST

Wan(Overall)ltecCW2006-15{290306}

VINCI CONSTRUCTION- SUMtTOMO MITSUI CONSTRUCTION JV

15

V I V -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29-0;

721 19.1 PRECOMMISSIONINGTEST 61edays Mon19-05-08; Mon19-OS-08: OedaY5,o" Yes!' !J. ; : ttl;';:;', I

J • , H

Wed 19-03-08 : Wed 19"()3-O8 :

10

jTaskName

I

Duration i

1

Early Start 001 late Start 0 I Early Finish

Late Rnish ',I Free Slack Critical 2006 i 2007 2008

! IN 10 J 'F 1M iA M!J °JlA 'S fo ,N iD !J iF iM A MjJ IJ AiS a iliJp J i"F M!A \M IJ

f !-3!-2 -111 2i3 4 '516 \7 8 '9 10111i12:13 14 15 16[1711819120 21122i2;:;3X2-:-4"1-:i2::::S;T;:;26::ct:12"'7:-ti2='8::--t-:i29C=-

1 .-

I'l{OveraB)JtecCW2006-15(290306)

VINCI CONSTRUCTlON- SUMITOMO MITSUI CONSTRUCTION JV

16/20

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

;9 j ~ I

Mt--_'_· -----"··-·-~·-23.1-:5A-Shipping--·' _- .. _ . _" _. ---~ .. - --, .. ,_,-. ---.---.----.,_"--,----" __ · __ ·~' c __ ··, __ , ,~_,,~ , _

!

72 { 23.1:is6ur:iiHNSUi.ATIONDcioRS{sDsi'uDICfi cONn"NuilYRooii) -"--1-SS'daysT .. -Frrio~10-OO'- --'Mon 23=-i-ci-=ii6' ··'-Fri. ii4:05~7t ······Tue-05-OG:'Oi·

__j- ... -- -.- .. -- .... -~ ..... -.-.- .... ---- .. -.---.- .. --.-.-. . ~ ... . __ .... _ .. .... _ ..... ._ .... _'-- .. __ ~_ .. ...i... ._. __ •. _.:. ... __ ._.~ L_~ J ---'- __

73 ! 23.1.6.1 Shop drawings '. 6 ewks ' Fri Z(}-10--06 . Mon 23-10-06: Fri 01-12--06 i Mon 04-12-06 , ···----·o·;;;t;ksT -.. No!

~ ~~~~~ -----. ' 6~ ~~~~: ~~~. ~~~\ ~1H~. 0~1-~N~O+4-~++4-~++~-~~+-_i~~~:~'~+~~~H-~+~~-~-~~tl~~~-~~~

~: ~.~~~~~=~::=~==-=--~-=-~-=~~-==::::~=-Li<~:l-l~:-~~~=j_~i:;'[-~··,~i~--~-;-:-t--t-'_+--;--+-~iiii·",; .iiiii ..... - .... ~rH-tli.t-t-t-r-i--;ir-Tlt!ntr---r-l-r-:l

~---·D~~MD~~~~~~ooro~ ----- ~~i ~~~i ~~~i ~~~I ~~~i -~o~d~a~p*I-~N~o~+~~~~~~~~~~i~~~~~~~~-~r~~~~~~~~~-~~~~~~H

;79 , .. ---.- - ·--23~:~~~:~::·&-~rl:~i;:~·~--"--·---··------··--~-·--~.----.------.-.--.- +--:-:~--::~:::; -.-:-::-=.~-"-::~~~~~;---=:::!- .. - .. - '" :: ::-;'-' : I--+-+--i-~+--.+-~I---!:-i-; +!~ •. +-; -'-l-+-+-++l:+t---+-+-;-+-+~-i_t--t--t'tl---jH-it-+-+_~+--j

~~--~-----23.2.1.1.2AH"U--·---------~---------------------. 60daysi Wed03-05-06! Mon15-05-00\ Tue11-07-06,.:.. Sat22-07-06i 10days:.::· No 1 . , .

. -. ! 1--~-~~:~--~~-+:-4:-~:~~~~-+~--~~~-;--~~-+~r-+-~-+~~+-~~-r-i-+-4--

782 ! 23.2.1.1.3 PAU60daYs j Wed 03-05-06 i Mon15-05-00! Tue11-07-06! sat 22-07-06 i 10 daysi No ~ !

763 f~ ... --.--.-- .. -.-~-.--. ,-'2323 .. 2.2.11_ ... 11 . .45 vF_CUe~~io_n_F_a~~. __ ~ . ._~ ._ .... _~·~-_ ... -_ .. - __ ·.-_-_~:~-:-:6:0~d:a~ys~+ii--:--;:W:.,..ed~:;.0:3-0:-;;-:5-06~;;-:;- Mon 15-05-06 i Tue 11-07-061 Sat 22-07-06 i 10 days 1 -cNc:0-+-+-+-+-+----4-~~+_~+!-+-+-+__+_j-Hrl-ii-+~-t-+-+-i!~+-+_+___1~t___H_i+-r__+_+~--

60 days I Wed 03-05-061-.Jon 15-05-00 i -- Tue11'()7-061 S3t22-07-06 , 'Wdays ,-- No I ,. ~. ! _

rr' .---------. 2321.1.6 PA:C-------· -------------------"-.. 60 days i -we(rO~s:Q6r_--Moi11s:os:oot---Too·11=07-=oot-Sit22':07.oot-- .. --1o-days i·-----N~O-+--+ il--1,:--i-j-1-j --;f--+; =;:=:;:~ :.g-.-'j!-J:'-l----i-i-+-Jh-Jf+-l----;i-+--+-i----+-t-+-+H--r+t-r-+-+-+-+-

60 days : Wed 03-05-06 ! Moo 15-05-06, Tue 11-O7.()6! Sat 22.(17-06 : 10 days t No I ~ i' I

6Od.iiyS' Wed03_05-06] Moo-1~T 'rue 11-07-061 s3ii2-07.()6i 10 days 1 NO ! I ~

23.1.5.2 Approval

6 ewks'

Tue 13_02-07 :

T ue 03-04-07 ,

Tue 27-03-07 !

Tue 15-05-07 .

o ewks '

7 pl9 11011 12:13,14i15!16117'18,19,20

12008

OIN 10 ,J \F iM A 1M 'J J

I Task Name

!

Duration !

1

Early Start

I

late Start

Early Finish I ,

. late Finish

Free Slack !

I

Critical ! IZ006

IN ~O IJ IF 1M 'A iM 'J jJ

i2007

A IS .10 IN 0 U IF!M!A IMTJ IJ 'A!S

, _" __ "C_~' __ '" ' ':""'r

4 ewl<.s ; - .. ··-Tue·1-g:'OS.:Qf-··--Tue-(i7':QS':07T·--Yue17:Di::Q7 : Tue 04·09-07

. ,

6.86 eWksT'

21 T22l23 i24 125126 27128 :29 30

L . ~ !

23.1.5.3 Shop fabrication

12 ewks

Tue 27-03-07'

T ue 15-05-07

TUe 19-06-07 :

Tue 07-08-07

o ewks ]

,

23.2.1.1.7 MAC 23.2.1:1.8 AC

60 days ! Wed 12-O7-06! Mon 24-07-06 \ Tue 19-09-061 Sat 30-09-00 i 10 days 1 No I 1 1..... .! I I

;. 60daySi Wed12..o7-<i6i MCln24-0i-:06f TOO_19-09-061 _~_·3iJ-09-00_··~· .. _·_·~~ __ ~ __ 10_d_aysl ~~~ l!- I ~ ! I , I I

23.Z.2.1.4VentilationFans 60 days 1 Wed 12-07-06j Mon24-07.()6! Tue19-09-061 Sat30-09-06: 10 days 1 No Ii !f~ .: r I ! j I

--··--···-----··---23.2~i.1~5fCU----··-- .... '~-·-----·-------~---' .. - .. -'---·-----~-·-----------~----- .. ·-- .. r--ood3Yi1---WBd'-1i-07-00f-'-Moo24=o7.061··-·-Tue1~r"--satso:oo:oor----'-~10-daYST---"-""N"O-+-+j ---i-+--i l,-}-+-'+' _";if-:_~H-+:-i:!-ll-+-+---'IH-+-I+--+ l,--;f-+-+--+ 'l-7-+--t !

_I j I I..... I

23.2.2.1.2AHU

812 813' 814 815

816

1

23.2.2.1.6 PAC

60 days

Wed 12-07-06:

Mon 24-07-06 !

Tue 19-09.()61

Sat 3O-mJ-OO :

10days!

No

i

Nan(Overall)lteccW2006-15{290306}

VINCI CONSTRUCTION· SUMITOMO MITSUI CONSTRUCTION JV

17

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29-{)3-06

10 I[ Task Name Duration Early Start 1 Late Start '1 EartyFinish Late Finish I· Free Slack Critical! ! 2006 2007 2008

I I· 1 fJJ 10 IJ IF M iA M iJ J !A~ !N:O J iF M!A 'M !J IJ A Is 10 iN!O J iF MAiM IJ iJ

i ; i-3i-2i-111 2 !3 4'5 GIT;8i9 ;1011112'131415 16!1ihe 19120i21!22]23 24]2526 27;28!2913O

817 ! 23.2.2.1.7 MAC GO days Wed 12-{17-{)6' Mon 24-O7-{)6, Tue 19-{)9-OS: $a(30-09-06 ~ 10 days, NO!' ~,' ,

_____j

818 : 23.2.2.1.8 AC GO days, Wed 12_O7-{)6 Mon 24-07_OS' Tue 19-09_OS i Sat 3O-{)9_OS 10 days No i .....

819l ~U~~~~~~---'--~===~~}=~~~~'-~~I=~~~~~~._~~~1~l~-~~4-~~4-~~:~.4,~~+~-H+~~-~+~-~+~-~~~-**~-~~~-

_820~~. ._ ... ... __ ~~_~2~~~~~~~~~.~~~ .. ~. ..... ._ .. .. .. ~. ._ .... _._,~. __ 6_0_da_.~_W_·~.1_2-O_7~.L .. ~o_n_2_4~7-OS! _. Tue 19-09-06_j_. Sa_t_3_0-09 __ -{l_6_:_. .-c10"""_d~a-ys.-;.!-_-.,.,NcO-+ !I-j,____.__+_+_--i-+-+--+----iic-·..c-+: --II__+--+--++H-+--+_T-jf---~-+-~--;'---+--i--++-tt_H__T~-T_+--i

~I nU1.11~~~~~ ! ~~, ~12~S: ~~~! b1H~1 ~~-06 w~~-ys~i--~N~0~·~~~~_+_~4~~+_+:~.+!~I__~_+_----i4~+-+-~+~-~+~-T-~H-+b~-+--+~~

822 j ---- 23.2.2.1.12 VAV----- GO days: Wed 1-2-O7-{)6 T Mon 24-07-{)6 : Tue19-09-061 Sat 30-09-06 i 10 days j No .....

823 i 23.2.2.1.13 Total Heat Exchanger 60daYsi Wed 12-OHS! Mon24-0i--OsiTue19-09-06! Sat30-09-Osi 10 days 1 No ~

~----------2:i2_2.1."1~4-Oi;iiu;;;j(jffier---~---------------~-----. eo days i Wed 12-{)7_OS: Mon 24-{)7-{lS: Tue 19-O9-06! Sat~30~~-{l'""9-_O''"''G-"-:'----'--"'71~0'-d"'a-YS---+l----7N:-O+--+---+-(-+--+--+---'f---+j-'---f-. -.-t:___'I1--+--+--\++++-+~-:--r--+---+-r--+--r-H--H-t+--+~f--+--+--1

:=r~==·~·==~32~::~~~~~:~;n~=·_~-=~-·------·-----'·-"'_=.~==~=~~=~=_~-"'-'--'~-'--::~:'7---::~~:~::"'-"'-::~:::-'--':~:~:~:r--~'-'~:-:=:~~=':~'~-:-:-:--i-I. --------;.::-::+-+____:f-+-+-+----1'-+--...;:---'+!_,_'r'~' -*-\---+--+--H[,-'!.+-+---i---'+-+-\--t--+-__._--+++---+t*---i~+-+-+-l

! .... ,. I ......

S27 r···--·-···------ 23.2:2~22sijbmersj6ie Pump--------· -- ..... -- ..... ----.-- .. ---- .. -- ...... - --------.'-~- 60 daYS: _ .. Wed-12-{l7.:o6'r-·--Mon2W7-{ls1--TOO ;i9":Qs-{l6 (--Sat 30-09--00 i--·· -Wdays j' No ,..... I

328l 23.2.2.2.3 Booster Pump 66 days: Wed 12-07-{)G ! Mon 24--07-{lS : Tue 19-{j9--061 S<ll30.oo-06 • 10 days ) No 1 i.~

rnf-------23.2.2.2.4Sand Fiile;:---------· ~ days; Wed 12-07-06 i Mon 24-07-06 , Too t9-09~·-:c·Sc:+-[ .. ·----:;:Sa-,t:-3:~0_0~-=9-c:-06~=-+!---·---:1 0~-doa-ys'-'-+!--7N:-O+-+-+-i--+--+-+- ,+--+; ~,!--=t;':::::"Il-+--+--+++++-+~-t--+-+--+-i:--+-+-H:---H-rr--+--:r-+--+--I

• '; I i-..m

130 I_~. 23.2.2.2.5 Chorine Sterilization Equipment ~ d3YS • Wed 12-07-{)Gj Man 24-07--O6! Tue19-09c06 i, sat 30-09-00 • 10 days i,: No i ! ! ,!

~~'~~~4-+-~-+-+~~i-+I-+"~~·+-++·H' +-+-!~-+-+~~+-T+~+IT-+~~~

131 J 23.2.i2.S Sev':;;ige Water Treatment Equipme~~-- 60 days !. Wed 12_O7~-' Mon 24--07_OG ; Tue-19-09-06 ! Sat 30-09-06 i 10 days! No i I! ....

~"~~~~=-~=_~_~3.2.2~~~~~~~~---~~-_~_~-_~_-=--_-_- __ -~-~==~~- __ -~-=~~~~~~-==~~=- ~ _ _L __ ~60 __ da_YS_l _~~_12_~~~J __ ~~~7-OG! __ ~~~.~~_i_·'- __ Sat __ ~ l_-_-=~~~~~L~-~-~'"'~N~o~~~f-i----f+----~:-+:-....:,~--~t_l~~~~~i~:t=i_=_~n!. .. ~~:~~~~:~~~::::~~~~:~~~~:~~~~:~~~~~~~:~~~~:::~~:~~~~:~~~~

23.2.2.3 FIRE PROTECTION i 60 days : We<l12-07-C16 ~ Mon 24-07-06 i Tue 19-09-06 j . Sat 30-09-00 ! _1-;-:0,...d:-3_YS+[ _--:N . .,-°-l---i'i-+--+--+--i--j!_+---+l_f-' -i-r-lH: -i-l---f_H+I-H_i-+-+-+~-r--+-+-+-H~+tiI+---+---+----i~H

34 J 23.2.2.3.1 Fire Pump -~--'--~--------------'c---60=-:-d7ays-+:"-7Wcced'-:-12-07-06! Mon 24-07-06 ! Tue19-09-06~ Sat30-09-061 10 days ! No II l~ '! 1

35 i 2i2.2.3:2 JockeyPump60 dayS! Wed 12-07-06 j 'Mon 24-07.;00) -rue 19-09-00 I sat 30-00-061 1() days r -"'0 I ! ! 4-r- f !

:=r= 23.2.2.3.3 Air Compressor 60 days I Wed 12-07-06 , Mon 24-07-06: Tue 19-{1g-06! Sat 30-09-06! 10 days i No L~

37 i ----------~:ii2.2.3_:_4FireEievated Tank FRP .~----.~.---.------.-- .. --.----'--.. 60 days, Wed 12-07-00: ----Mon 24-07-06:"1"00 19-09-=06 :.1 Sat 3O-Il9-06 j 10 days 1, No j .... I'

~ --~~·-~-~-~~-----·~---~-~~----~~------7--+-,~-:~·~-4-+~~~~~i-4'~'-*~~~HH4-+-+-+-~~~~-+~~~-r~~~

38 1--~-'------2:iZ2.3:"5"Fire-Atann-System -~------------------ 60 days : Wed 12-07-{ls-1 Mon 24-07-06 ; Tue 19_09-06 i Sat 30-09-06 : 10 days: No ! ~ i I·

'~--·'----"·'~-----'--2iTi.3:-6C62Gas'RniEXtin9ujSher-----------·-----·---···-----------··--------·--t·---60d~T~·-we(f1·2:07-OsT--·-Monz4:(5f;06l·---yue-19:09-{ls]--saT30-09:OO"···- ~---10-d~i-- No . j..... .1 I

WI ~~p~~ru~G~~~~ I ~~! ~~.: ~~~i ~~~I ~~$j ~~I.·· ~~~~~~~~.:~~~~~-H~ •••• ~~~~~~-~r~~~rt~~tr1~~~~1

~1 I 23.2.3.1 ACMV 120 days i Wed 20-09-06: Mon 02-10. i Tue OG.()2-07 i Sat 17-02-07: 10 days r No I :1

~ ; ,

,



!

Jverall)ltecCW2006-15{290306}

VINCI CONSTRUCTION- SUMITOMO MITSUI CONSTRUCTION JV

18/20

VTV -OVERALL WORK SCHEDULE (As per Itec/CW/2006-015 dated 20 March 06)

Wed 29-03-06

D

i Task Name !

!

Duration

Early Start

I

Late Start

I

Earty Finish

Late Finish

Free Slack

I· Critical i ' 2006 ! 2007 ! 2008 !

~J lF 1M fA M_lJ J lA TSTOTN :D iJ iF IM:A M iJ J A IS10 illJ~D7-r:J:'-c-i!7F=+:M::::-+'.:'A::-+,:[M::-:-+I;~J:-f-'lJ~1

.! 1-3 !-21-1 j 1 2 f 3 415 6 i 7 8 i 9 f10!11l12!13114i15 16 17 18 19,20121 !22i23i24!25 26 27\28 29i301

23.3.1.9 BMS system

Ib<: i 23.3.1.10 FireAlann System 60edays f Wed 03-05-06 i Wed 31-05-06: Sun 02-07-06 i Sun 3O-n7-06: 0 edays I NO I ~ ! W I ,I

l~83 23.3.1.11CCTV-Broadcasting-CailfReader 60edays! Wed 03-05-06 1 Wed31-Os.:&i Son02-07:06,.1 SUO'30-07-OO1 Oedayiil' No i I l i ... r •

_ . ~ ~ rio

396 i99-

300 ~ ~

lan(OveraQ)ItecC'W2006-15(290306)

VINCI CONSTRUCTION· SUMITOMO MITSUI CONSTRUCTION JV

19/20 i

VTV -OVERALL WORK SCHEDULE (As per IteclCW/2006-015 dated 20 March 06)

Wed 29-03-06

Task Name

Duration I Earty Start 1 LateStart Early Finish T Late Finish Free Slack . Critical I 2006 2007 2008'!

I iN io J FiM lA iM J J iA is jOiN 0 J iF MiA M 'J 'J ]A S 10 iN!D J !F M A lMJ..,Lj_,J J

i I l''-'_3=-+'_~2:-l-''-''-1+'':-1-+'-'2:-+''::3--'!!-''4':'-t''::5,-P'6;;-T'::7-;18 j 9110 11 12113 14'15 16117i18119 20!21122i23 24]25 26 27:28129:30]

I ::::~~~~~m ._~ ;~_ ::::, :~:, :::::: :::: :::: ::L~-LL~~-~~J~~:~:~~~~~~-LL1J-~L~~'-~~U~~~~~-i!:

l' ----- .. 23.:fi13-·LigiiininjPrOiection----·-.- --- ..... -,.----------. . 30 edays :-Tt,u-3"f'OB:06T-----Thu--28:(j·g:QS"---sat3o::09-06T----Sai-28--iO::OSr"----'-'--ci"edaysr--'-NO! L».-l !

l ~~~~==:::~::'10) ~~~=~~E-- .. - .. :--:=:-::;,F~:E~l=::::;-~:::::-J!~·- .. ·==;:~:~,!!-=~~~~~~:~=:t~_i~~~~t~~1:~=~t=~t=~~ti-,I_i~!i:l~';:~~:~::~:_!~~~~f:~l:~:-i-tl;~~jJt-:~~:t~~j:~:~!:~~:~~L~~!IlIIll-~r-W-~~--+__J-+-+~

I 23.4.1 Mobilization . 2 mons i Wed 18-1o-{jslThu 19-10-06'1 Sat 02-12-06: Mon ()4.12:.oo i 0 monil NO! .lI.

""1---- 23AZ-Preparaiion ofShOp dwgs---------------·- 3.4 mons i Man 04-12-061 Wed 03-01-{)7: Tue 20-'O2-{)7 j Th-u"-=227-{)-073-0-=7·l: -----=-o-m-on-s+-j ----:NC-;O+! ~-+--++~--l-+-+---j-+-+'..=rr::l_-+:'--t[r-±--i--j ---l-+--+-+---l:--+--+-+---i~+-+++---i+t+---+--+-+--+--j

J·····-··-23-:-4.3-S\ibmisSi(;rlOidwgS-····~'--·--·· .. ·--· - ·---'·-·'···-~··-·--·--·---·------·-·-·-->·'"-·--·2-roon~---Wed-21-_:02:Q7r-----Fii2~3::07t----sai07#Oji-··TueOM~7·~·-------Omons 1 -- No I : \ ~ 1

-j---- 23.4.4APprovaTof dwgs--------·- '"- .. ~=__=_=_=~~~ ..... : .~ da~L Mon 09-04-{)7 i Wed ~5-07 : Man O9-04-Oi1 Wed 09-05-07 , --O=-d-;a-ys--=?+r -~--:N;:;O+--+-t--+-+-!i ---l-+-+--+---l'---+-+-+---l-i-+-+--iE±11-1 ---l'---+-+-+--i:---+-+t+------iH-l+-+-+-+-+--j

i---23.4,i;-procureme-rilofEQuir:imeili--·--·------- .. ----- , 1 man: Tue 10-04-071 "---Thu 10-05-07) Wed o2-{)5-Uif'--'---Fri-01-06-{)7! 0 moiiS1-'--NO! i ~

= 23.4.6 Equipment Manufacturing 7morisi Thu 03-{)5-07! Sat02-06-{)7: Fri 12-10-{)71 Mon 12~-:1_1:~~~7~:. ~o~m:on:s~l~· __ __:N:~OJ II=ttlj=ttjJtttjjt=ttjj=ti ~~~~~~~~~1!tntj=ttlj

-'- 23.4.7 DeUvery·ofRigging Equipment 2.5 mons i Sa! 13-10-{)71 Tue 13-11-{)7: Mon 1O-12-{)7! Wed09-{)1-{)S: 0 mo~s! No i i~

_..... 23.4.8 Delivery O~ .. ~~~htin9 Equipment _~_~ __ ._. ~ 2.5 mons i SaH3·1o.:<i7l Tue 13-11_071 Mon 1O-12'.o7! Wect 09~H18 : 0 mons I No . ! i j .......

23.5 STUDIO LIGHTING EQUIPMENT(STUOIO 11,12,13) 416 days! Wed 18-10-116 [ Sat 21-10-116 : Thu 14-112-1181 Mon 18-112.08; 3 days j No . f

-r---'-'-- 23.5.1 MobiiiU..Uon .---------- -'---.~~---------- .. -~----.- 2 mons! Wed 18-10.()6 i Sat 21-10-06 i Sat 02-12_06 li---cW;:-:-ed""'"Q6-cc:;:-""'"12=C_06cc:;:-f-i' 0 mons I No ~ I

~r_.-· ... -------._-=-23=-.5-=--=2-_=p"re-:-pa__:_rati._,-:__'Q.n __ Ot-=--s _ _.ho~-_P_dwg._-_-s~--_-_-._-_.-_-_-===_-~-_- .. _-_-_-.-_- __ - __ -_~-_~~.-_~_-_~~~~~~--_-_-_--_-_-._-_-_---~----T_; _3_.7-=5~-m~o~ns~i~___..M;;::0-:cn-;:;04-7-:1:2~-06-- .. +i~-Thu~·-O~7~~1-2·'_06 .. .,.......;i'----W--ed·~2-8-·-O-=2=-O=7~!====Sa:=t=0:3-0=:3-0=:7 .i. f===·~~~-0_:~~-m~o~ns=+-ft----~~-.--;.~N~OJt~t~Jt~1~Jt~1~~t~1~~t~1~=t=1~=t:liY·~~~~~~~~:1!=~t=1==t=J~=t=j==1~1==t=l11t=~~=t=~t=1=j

23_5,3 Submission ofdwgs z mons ] Thu01-03-07: Mon 05-03-07 i Mon16-04-071 Thu19-04-07: o mons! No I ~i

- 23.5..4Apjlf'Ovalofdwgs 1day! i'ue1i:04-011 Fri~ii"Tue1i:.Q4-071· Fri20-04-07 (}cfays[NO! i j ! ~

1 .... - ..... _--,2cc3cc·5=-:5cc=procu---,~re __ m_-:e--:n--:i ~f EqUi~~~~~_ _ ~~ _~ __ ',_----:c--;:-1_m_~an-+-i __ W--;ed=-:-1:-;8-04-0:-:.::--:-;7;-ii!-------.s;;:-a:::-t-02-;:;1-04-0-;;;;-=7+, _ Thu 10-{)5-07 i Man 14-05-07 : 0 mons! No !! l i"'!

23.5.6 Equipment Manufacturlng ~-- ~--.- .. - .. -.-... -----------. 9_5mons! Fri11-{)5-07! Tue15-05-07: Tue1S-12-{)7! Fri21-12-{)7: o mons! No j ! ... i ,I

il 23.5..7 Oefivery of Rigging Equipment . 2.5 mons \ Wed 19-12-{)71 Sat 22-12_07' Thu1-4_02-061 Mon18_OZ-08: 0_05 mons 1 Not i!! I'"

·· .. -·--23~-.~2s3-T·5u,BD-DI·oefivl-eIIyG-:-HOfnL-NlgGhiiiigE"'Q--EuqIUpiPMnleE-NTnt-(S~-T' ".-u' ~D-. -IO~-3··-'-4-'·5~)~- ·--···--·------------------- .. ---·--·--·>--25dmon~1- .. -wW--ed~ 1~12:O1! ----Th~at22-12~7: - TS .. ~t~o14-02-~22.~8. t---·-·MMon-::-:-2z:SS-:---0.051-· mo-d· .. -.:--fl------ .. No:-;No~j- 1--- i+ _- _- t-f-- _- i+ _--1-i_- _- t~ _- i-i_- _- ti-- _- t+ _- i~- _~t- -:-- i\- i-.f-- i- ,+-.- ~-+i-.- ~f--t ~;~:;::~~;~;~;~:;~;~;::~!j-:~ IW:,~.~:~~;=~==~=;=:~~

... 406 ays?: 1S-10-06 ! u 19·10-06 : a ... -v 1 on......,,"V: a~, I . 1 I

~

;r~f

1

-

veraII)ItecCW200S·15(290306)

VINCI CONSTRUCTION· SUMITOMOI\llITSUI CONSTRUCTION JV

20/20

VINCI I SUMITOMO MITSUI .JOINT VENTURE VIETNAM TELEVISION CENTRE PROJECT PACKAGE No. XL~1

No. 104, Lane 75, Nguyen Cong Hoan Street, Giang Vo Ward,

Ba Oinh Dist., Hanoi, Vietnam

TEL: +844~771-2567 Fax: +844-771-2667

»> ,,, .. ~~ .... " :.: .... ~")'

Date: 04 April 2006

Ref: JVCW~DED/SCWNTTI2006-0412

To:

Attn:

NHK Integrated Technology Inc. Mr. Masato Kawai

Project Manager

Cc: PMU - VTV Center,,project. 43 Nguyen Chi Thanh Street Sa Dinh District;

Hanoi, Vietnam

Attn; . Mr. Luu Huu Bao .

Project Manager

From : Philippe Schorsch

Subjec.t:

Project MonitQring Matrix for Engineering drawings

Dear Sir,

Please find enclosed hereto the above subject for your perusal.

We would be most pleased to receive your agreement to it and shall use it as the base to monitor the production I approval of shop drawings, technical submittals and samples. (Note that CLR shall lnelude techilical questions, teChnical brochures and catalogues, samples etc.)

Kindly take note 'that the Project Monitoring Matrix for. Material I Equipment will be submitted in due course.

Thank you. Regards;

Ph.ilippe. S ORSCH Project Director

Vinci - Sumitomo Mitsui JOint Venture

\Ji'V,. tP M-lJ fj'S;J Cf f ~'b.

~

.f!.

i

"_

"tJ

c5

.x ..

{!

'~ o o ,..;

.... t-.

OTe;>

> c o ::.

~7

t-. ... .......

.. ..

£-5 EE

... t-.

.. .. .c:;.c:;

SE

... t-.

.. .. .c:;.c:;

EE

.... t-.

> ...

II:

CI .2; ILl

... '" DD

1!2 >-

:> 0

'i~

t-.t-. ........

55 E E

10 ... 00

.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:; ~~~--~~~~---~~--~-

~EEEEEEcEEEEEEEEEE

~~~~~~~~~~~~~~~~~~ 000000000000000000

.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:;.c:; I~~-----~--~~--~~--

IcEEEEEEEEEEEEEEEEE

~~~~~~~~~~~~~~~~~~ 000000000000000000

<> c o u

~ !! ~

..

.. ..

£-5 E E ... t-.

.c:;.c:;

EE

......

5= E E

..,'"

00

.. ..

55 EE ... t-.

-5-5 E E

......

55 E E "l~ 00

.. ..

££ E E ... t-.

> ...

.c:; s:

EE

... ...

-5-5 EE

......

.c:; .c

EE

e-re-

> ...,

.,,'"

~'~

='"

7V!

t-. ... .......

.~

Z ILl

.c:;.c:;

EE

.....

-55 E E

5=5-S5£=~~S5=£i£ E E E E E E E ~ ~ E E E E E

Y'"'T"'T"' ........ ~~"'""''''''~ ....... ''II''''' ....

.. :1j

z .1&1

.... ...

> ...

t-.t-. 00

cu·

.. '"

79

... C> ......

....... DC>

CD

7a+

...... .....

qq

c c .. ..

77

... It> .......

55 E E

... ...

== E E

... ...

",,,, eO

§I~ 7=?

... .,.

NO

... t-. qq

cc ::. ..

77

"' ... .....

~N~~~~~~~O~NMV~~~~~O_~M~ ~ ~ ~ ~ ~ 0_

~~~~_~~~~_««NNN ~ N « N ~ n~

jV

~" NHKlntfIgr{JtfJ.rI t~hitolQgy Il1c~ .

!~·ViErNAM·i'ELEVis1ON CENTRE PRoJECT

;~:No. 1A, Lane 75, Ngl¥!ll'l Cong Hoan Street. Giang Yo Wart!, Sa Dinh District, Hanoi, Vietnam

:1II!:TeI : 84407719181 Fax: 844-7718565 .

Date : 2f!' April 2006 Ref : ItedCWI2OO6-064

To: Vind~umitom6 Mitsui Joint Venture

"Attn: Mr. Philippe Schorsch Project Director

Cc: PMU-VN Centre Project

Attn: Mr. Luu Huu Bao Director

Subject: Overall Schedule

Dear Sir,

We acknowledge receipt the following document in your letter Ref JVCW-DEDISCWINlTGI2OO6-0501:

Extended Overall Schedules .. - CV of QES Manager

We approve the documents with following oomment

- Test piling is carried out concurrently with bored piling as in your Confract's schedule and actual exerution at Site, therefore this activiI¥ and iIs duration shall be adjusted accordingly with Contract. As our past concem, the Contractor can take the risk to increase 1he numbers boring rig to hasten the bored pRing, but the approved schedule 'lvill base on the original estimates during tendering and contract agreement. Therefore the duratbn of bqred piling is required to romply with Contrnd project execution plan.

The rnabix for shop draYJing. is for information and it shOuld be revised after the Sdledule is approved.

We are looking for your submission of completed schedule as approved and commented.

. . .

Yours Sincerely,

.Jor

Masato Kawai Project Manager NHK Integrated Technology Inc.

nate: .:t.b _ 4 - 2<lO_,.G_
Rc~ nl); t'U~~l.t~'- e
Act lnf Am;
')M 'I<
.DPM loX
. ·'·DED )0.
MED' ~ ~
-eMU. 16kd ._-
gRSU·
COD 1* Xl
AI:'"
._q:n II. ~.~ ••• __ ---
Others 11M/( 111t{iJqrated Teehlfll!J1(llJY Inc,

lElNAMlElEVISlON CENTRE PROJECT

U. 10. 1A, Lane 75, Nguyen Gong Hoan Street. Giang Vo Ward, Sa Dinh Disfrict. Hanoi, Vretnam II Tel : 844-7719181 Fax: 84-4-7718565

To: VJnci-Stnnitomo Mitsui Joint Venture

AUn: Mr.PhilippeSchorsch

Project Director

Date : 3m -April-2006 Ref : IteclCWa006-035

Cc: PMU-V[VCentreProject

Attn: Mr. Luu Hun Bao Director

Subj~: Comments on the Revised Overall Work Schedule

Dear Sir,

In responding to your Lettec NCW-DED/SCW/CIUJ2006-0399 dated 31 st March 2006, we would like to comment as

follows for your revision:

1. Overall Work Schedule:

Schedule of Long lead Times for Procurement shall be indicated in Overall Work Schedule as itmight

h /'

J

I' t . r

Critical activities are shown but the critical path showing 1he linking between 1hese critical activities is not properly shown and there is discontinuation of the path. Beside 1hat, the critical activities should use

For critical activities, the late finish date must be the same as Early finish date, therefore please explain the reason of ID7, 8, 13, 17, 36, 46, 53 are critical activities and please check 1he calculation of'fiee slack

"--_'roC

- Please check whe1her the ID 75 & 76 are critical activities since their Early finish dates are different with

Late finish dates. 'e,

- Please check whether IDs 415, 416, 418, 419, 420 are critical activities?

f_··>

Please detail the Pre-commissioning Test (ID 721) to show 1hc reason of criticality of ID 689 Studio

3,4,5.

Please chcckthc frce slackofID 696 Studio 11, 12, 13. 2. Overall Work Schedule- Detail Breakdown:

Bored Piling: Please check the practicability of finishing over 300 bored piles in 58 days by 4 boring

ngs,

Mass Excavation: Activities of Slope Protection and Sheet Piling Works including Strutting should be indicated.

Studio construction: Please be advised that Studio Construction is one of the most important, complex and difficult activities in this VJV Center Project, therefore we consider that typical 180 m2 TV Studio 8, 9, 10 at 2nd floor should not be constructed at the same time because it is necessary to obtain certain quality assurnnce of one before starting finishing work in other studio at same floor. The contractor is requested to reconsider the said point and adjust the schedule accordingly.

The critical activities are shown but the critical pa1h showing the link between these critical activities is

not shown.

ID 8 Substructure is critical activity, but its Earlyfinish andLate finish are not the same. Please confirm, Same as ID 13, 17,36,46,49,53,59 etc ... Please check and revise all the critical activities of which Early finish date is different with Late finish date.

3. Organization Chart:

- We have not received appointment leiter wi1h CV fur the position of Manager of Qaality & HDE )

Department .

)~-

4. Other:

In addition to the above Comments on Overall Worlc Schedule, we would like the Contractor to submit the following managing schedules for smooth execution and mutual understanding;

Shop Drawing Schedule: Schedule of Various Shop Drawing Preparation Activities shall be prepared with consideration totbe duration for Engineer's checking and working schedules. A profonna is for

your reference.

Equipment and Material Submission Schedule for Approval and Equipment Ordering Schedule for Approval shall be prepared with consideration to the duration for Engineer's checking, equipment manufacturing, equipment delivering and installation. Attached profomas of both schedules are

enclosed for your reference.

Your prompt revision of schedule to above connnents would be appreciated Yours Sincerely,

J I )

Masato Kawai

Project Manager

NHK Integrated Technology Inc.

Incl. Attachments

VINCI I SUMITONIO NUTSUI .la.'NT VENTUR.E VIETNAM TELEVISION CENTRE PROJECT PACKAGE No. Xl-1

No. 1A, Lane 75. Nguyen Cong Hoan Street, Ging Vo Ward,

Ba Dinh Disl., Hanoi, Vietnam

TEL: + 84-4-771-2567 Fax:.: +844 .. 171-2667

To : NHK Integrated Technology Inc.

Attn: Mr. Masafo Kawai

Project Manager

Cc: PMU - VTV Center Project 43 Nguyen Chi Thanh Street Sa Dinh District,

Hanoi, Vietnam .

Attn: Mr. Luu Huu BliO Project Manager

From : Philippe Schorsch

Subject;

Date: 21 Apr., 2006

Ref: JVCW-DED/SCWINTIG/2006-0501

~: 2A -04 -200G
nO: PEDlsc,'W 'fJTTG"V'
f Act Inf Ans
1PM lr'
f DPM IX
,-
!~1ff~~ ~ i
i MED
rCMD ')0 .
!
QESD ;
COD
AFD
CCD
Others ZCJ06-050{

A response to /tec/CWI2006-035

- Comments on the Revised Overall work schedule.

Dear Sir,

Thank you for the comments in your letter dated 3 April 06 which we received only on 10 April 06.

Our response is as follows:

1.

Overall WO.rk schedule:

a. The schedule of long lead times for procurement shall be separately presented in the Project Control Matrix for such intention. It has been presented in the Overall Work schedule.

b. Overall work schedule is a summary of task summary. Once anyone of its subtask is critical, the task summary will identify itself as critical.

c. News Studio 3, 4. 5 are critical as the ceiling of these rooms are at soffit of 26 which is higher than the rest of the studios. Thus, the commencement date for its floating floor will be later than other studios but still they have to be completed before Precomissioning test.

d. 10696 studio 11. 12, 13 have been checked and are in order.

e. The overall work. schedulei$ unchanged from our submission dated 31 Mar 06 of ref. JVCW-DED/SCW/CTUI2006-0399.

2. Overall ~ork schedule (detail):

a. Bored piling rigs have been corrected from 4 rigs to 6 rigs.

b. Mass excavation: Activities of slope Protection and sheet piling works including strutting will be indicated in the detail method statement. These are not included here as there are late responses to the relocation of the underground water pipes and the shifting of the existing south boundary fence.

c. We agreed that the studio construction is complex. The schedule for these 3 studios to start at the same time does not mean that there will be individual team for each studio. The intention is to show that these studios are available for construction for various trades by the dates shown.

d. Due to limitation of the Microsoft project program, the critical path on its own is shown in attachment 1.

e. All your comments are related to summary task. Summary task is a summary of subtasks. Once anyone of its subtask is critical, the summary task will identify itself as critical.

f. The detail work"s_ch.~ule is unchanged from our submission dated 31 Mar 06 of ref JVCW4)EDlSCW/CTUf200e .. 0399.

3. Organization chart

a. The CV of the Quality, Environment and Safety Manager is attached.

4. Others

a. Due to complications in the Construction drawings issued to us, shop/engineering drawings schedule is separately submitted in the Project Monitoring Matrix for shop drawings which requires special attention by aU

parties. .

b. Thank you for your sample pro-fomas of Equipment and material submission schedule for approval and Equipment Ordering schedule for approval. We will submit equivalent soon" for all to agree upon.

Thanks.

Regards,

Philippe SCHORSCH Project Director

Vinci ~ Sumitomb Mitsui Joint Venture

B.·WHK Integrated TerJ!1f1ology Inc;

" VIETNAM TELEVISION ceNtRE PROJECT

1A, Lane 75, Nguyen Gong Hoan Street, Giang Vo Ward, Sa ~inh Oisbict, Hanoi, Vietnam : 84-4-7719181 Fax: 844-7718565

To: Vinci-Sumitomo Mit'3ui Joint Venture

Attn: Mr. Philippe Schorsch Project Director

Cc:

Attn:

PMU-VlV Centre Project Mr. Luu Huu Bao Director

":::~- ."

Subject: OVerall Schedule

Dear Sir,

NHK Integrated Technology Inc.

Date: 4th -May- 2006 Ref : ItedCW/2006-084

APPENDIX C

The Impact of the Delay Events on the Works Progress

APPENDIXC

1. The various changes in the substructure works as introduced via the 10 June 2006 structural drawings had a significant impact on the quantum and progress of the physical site works.

2. The Contractor was required to resolve all of the details of the spatial relationships and this included adding many further structural elements via the shop drawing preparation process.

3. Furthermore, the CP drawings issued on 10 June 2006 added complex secondary girder and slab arrangements, which were unknown to the Contractor prior to June 2006. The consequence of these changes was that the Contractor required more time to complete the Zone C substructure and Zl slab level works than had been planned by the 4 March 2006 Programme (which programme was based on the 10 February 2006 drawings).

4. The impact of these changes and the impact of the inadequate design on the shop drawing process are set out at Appendix A hereto.

5. This narrative discusses the impact on the progress of the works on site.

6. This narrative is also linked to the impacted as-planned programme as set out hereto at Appendix D.

The Excusable Delay in the Shop Drawing Completion and the Impact on the Pipe Cap and Girder Construction Works

7. The structural shop drawings for level ZO/Z 1 for Zone C were sufficiently completed to allow pile cap and girder works to commence on 3 August 2006 (as per EA 108 and ID 33 of Appendix D).

8. The shop drawings for Zone A and B were sufficiently completed to allow the pile cap and girder works to proceed on 30 August 2006 (EA 148 and 149 refer).

9. This is a delay in commencement of 27 days (Zone C) and 54 days (Zone A and B) respectively considering that the pile cap works were planned to commence on 7 July 2006 in accordance with the 4 March 2006 programme.

The Consequential Delay to the Reinforcement Fabrication

10. The aforesaid does not consider the sub-contactor preparation and/or internal planning (2 months was planned for these activities in the 4 March 2006 programme) that was required after the shop drawings had been approved. Nor does it consider the impact of the changes on the detailed excavation and pile hacking works which arose as a consequence of the late confirmation of the beam depths and beam/pile cap founding levels.

2

11. As a further consequence of the excusable delay in the completion of the substructure shop drawings, the preparation of reinforcement fabrication and placement drawings was also delayed. The reinforcement shop drawings were delayed as the structural works sub-contractors required fully completed substructure shop drawings to allow the reinforcement shop drawings to be completed.

.-----~--.~ ... --~~---------~~-~---

ii) Zone A - 5 October 2006

12. Reinforcement shop drawing were submitted by the structural sub-contractors as follows:-

i) Zone C2 - 30 September 2006

iii) Zone B - 9 October 2006

iv) Zone CI - 11 October 2006

13. From the above, it can be seen that the structural sub-contractors required one to two months to complete the reinforcement shop drawings and this is in keeping with the time frames set out in the 4 March 2006 programme. Further time was then required for the procurement of the reinforcement.

14. This excusable delay in the completion of the reinforcement shop drawings had an knock on effect to the reinforcement procurement and fabrication which further impacted the progress of the ZO/ZI level structural works. This delay was, in the final analysis, concurrent to the excusable delay in the pile cap hacking and detailed excavation.

3

15. Whilst the Zone C shop drawings were fully resolved on 3 August 2006, the follow on reinforcement shop drawing preparation and reinforcement procurement/fabrication then took a further month (rather than two months as per 10 21 of Appendix C, and hence the Contractor had mitigated the delay impact by one month).

16. The reinforcement shop drawings and procurement/fabrication were sufficiently advanced to allow pipe cap construction to commence on 9 September 2006 (lD 45 and 46 of Appendix D).

The Excusable Delay in Detailed Excavation and Pipe Hacking

17. The bulk excavation works commenced at the Zone C oil tank Zone on 26 June 2006. The planned commencement date of bulk excavation was 14 June 2006 and hence the excavation commenced 12 days late. This late commencement was ultimately non-critical due to the substructure changes introduced via the 10 June 2006 drawings.

18. Whilst bulk excavation at Zone C was able to commence as at early July 2006, detailed excavation to pile cap and girder founding level was unable to proceed due to the lack of approved shop drawings (such approval being outstanding in July 2006 as a consequence of the ongoing design clarifications and changes).

19. As a consequence of the lack of various details relating to the founding levels for pile caps and girders, the commencement of the pile hacking was also delayed. Pile hacking commenced in late July 2006; after the final cut off level of piles had been conclusively determined.

20. The pile hacking, final detailed excavation, hardcore placement and lean concreting was progressed sufficiently to allow pile cap and girder works to commence on 8 September 2006 (10 42 of Appendix D) and thus the consequential excusable delay in the commencement of the pile cap works was 63 days (ID 50 of Appendix D).

4

21. Similarly, the pile hacking, final detailed excavation, hardcore placement and lean concreting were completed at Zones B4 on 11 September 2006 whilst Zones Al and A4 were completed on 19 September 2006 and hence the excusable delay in the commencement of the pile cap and girder works was 67 days and 75 days respectively.

The Zone C Critical Delay - ZO/21 Levels

22. Thus) the excusable delay in the completion of the shop drawings caused a consequential delay in the commencement of the pile caps of 63 days.

23. As the critical delay ultimately occurred III Zone C, The Contractor will henceforth discuss the Zone C delays only.

24. The overall excusable delay in Zone C was 147 days (13 December 2006 to 8

May 2007 as per ID 56 of Appendix D).

25. Of the 147 days of excusable delay, 63 days can be attributed to the late start of pile cap construction (lD 50 of Appendix D) whilst a further 21 days can be attributed to the enforced work stoppage during the APEC summit (ID 43 of Appendix D).

26. The planned duration of the pile cap, girder and slab work in Zone C was 159 days (7 July 2006 to 12 December 2006 as per ID 22 of Appendix D) whilst the actual duration was 243 days (6 September 2006 to 8 May 2007 as per ID 44 of Appendix D).

27. Considering that the enforced work stoppage of21 days during November 2006 is included in the overall duration of 243 days, the actual overall duration was 222 days (243 days - 21 days).

28. Thus the overall duration was 63 days longer than the planned duration (222 days -159 days).

5

29. The additional 63 days that were required to complete the Zone C works, over and above the planned duration, are attributable to the added complexity that arose as a consequence of the issuance of the 10 June 2006 drawings S-018 and S-091 and the 10 June 2006 CP drawings.

30. From a comparison of the Contractor's 3 August 2006 approved Zone C substructure shop drawings to Drawing S-019, it is apparent that the final as-built condition does not reflect the original design intent as set out at drawing S-O 19.

31. From a review of drawing S-019 in the Zones bounded by grid lines YB to YI71 X5 to X 14, and the associated framing elevations, it can be determined that the top level of 57 of 68 primary girders was changed.

32. Drawing S-019 also established that the top of all secondary girders would be the level with the top of the Zl level slab and that the entire slab from grid Y13 to Y17/X5 to X14 would be at one consistent level of Zl-30.

33. Similarly, the entire slab and secondary beams bounded by grid lines Y13 to Y17/X14 to X18 were indicated to be at one consistent level of ZI-1030.

34. In fact, a review of the Contractor's shop drawings will show that the secondary girders are situated at a multitude of levels, and this increased the complexity of the construction process significantly.

35. Furthermore, additional topping slabs were added in the vicinity of X3 to X4 and this added another step to the process that had not been planned by the Contractor.

36. The Contractor sets out as follows, further examples of additional works which arose at Zone A as a result of the issues described above:-

6

iii) Ramp slab at Y9/X5 not detailed. Additional W20 walls added above B14 beams from grid line Y9 to Yl l.

i) W15 wall added at lift pit at grid lines YIO/Y14 to YI5 and Y2/X13 to XI4.

Ii) Filler beam added at grid line YI2IXII to XI2.

iii) Filler beam added at grid line Y8IXI4 to XI5.

IV) Filler beam added at grid line Y5/X13 to XI4.

v) Stair Structure introduced at grid XI8/YO to Y12 and YO/X16 to XI8.

37. Changes in the Zone B substructure works included:-

i) W20 walls added from top of beams FCG liB 13A (level ZO-30) to underside of slab (level ZO+840) between grid lines YO and Y2 at grid lines, X6, X7, X8, X9, X 10 and XII (15 individual lengths of wall added).

ii) Filler beam added at perimeter of slab at grids X2 to X2/YII and Y12 and YI3 to Y14. Filler beam 350 mm wide x 310 mm deep.

7

iv) W20 wall added above beam B36 at grid Y91X3 to X5.

v) W20 walls added at WIO/Y2 to Y3 and YII to Y12.

vi) W20 walls (2 No's) at Xl to X2/YII to Y12.

i) Filler beam required at secondary girder B 13 from Y 15 to Y 17.

38. Example of further changes, and hence additional works III the Zone C substructure included:-

ii) Filler beams required at top of primary and secondary girders, grids XI0 to X17/Y13 to YI7.

iii) Filler beam required at top of primary girder, grid Y17/X6 to XlO.

iv) The majority of primary and secondary girder top elevations changed to suit revised trench arrangement.

v) The level of 57 of 68 primary girders in the Zones bound by X5 to X141Y13 to YI7 was changed. This observation does not consider the remainder of the Zone C Zones.

39. The extensive changes to the Zone A, Band C substructure works caused a knock on effect as the resources were required for a longer period of time in all three Zones. Resources that had been planned to be transferred from Zone A and Zone B to Zone C were held back due to the increase in work complexity and the consequential increase in time that was required to undertake the more complex work.

8

I I I

L

40. Ultimately, the critical delay at the ZOIZI level works occurred at the Zone C, ZI level slab as this was the last slab to be completed (on 8 May 2007, a delay of 147 days when measured against the 4 March 2007 programme).

.. ... -~.--- ...... -. ~~----------"--. .._----

APPENDIX D

2007

10 Task Name

I Duration I

SIabZ1

Shop· Drawing Preparation Pliecaps

Ground BeamSIZO Slabs

281 days 21 days

o days

o days

o days S3days 15 days 31 days

9 SIaiiZ1

I-----w- ·······siicip Drawlngc::ommentSiuidUpiiailng

~. '~ ----r:r-

----:;-;r-

~ 16 ~ ~ ~ I~·

~ f----ao~ f-----Jz f--a3 ~ ~ '----s6 I--s7 ~ '3g-

~ ~ ~ ~ -.r,r-

-.rs-

~ '47 f-------;je

r----w'60 ~ ~ f---s3 I----gr

~ 156

~ ~ ~ f----eo f---e1 ~ f---er f----s4 '------65

Pile Caps

Ground BeamsiiOSlabS Slabi1

EirigirieersShop [)rawlllgFt"vlew and Approval Pile Caps

GrouitdEleamslzO·Slabs

81abZT

Planning bylriiemal Departments and Suboolltractors ··PileCaps

... Ground BeamsiZO Slabs

Start

Tue al7l06 rue 317106 Tue 317106 Wed 31B10e rue 3/28/06 Tue 317106

··Tl.le3i7/06 ·thu3ieios

sa days ·Sal4J22tDS :

........ ·fidaYs Sat 4122106 I

....... ·3fiiays Tue 519106 !

30 days

I

I'"

Finish

Feb

Jul

Mav

Mar

Apr

Jun

Tue 12112106 Tue 3128108

Tue 317106 ··Wed 3/8106 tue3l28!0s sliiiSiiiBioB

Tue 3121/06 Sat 418100



~I2B

Aug

May

Jun

1 4 March 2006 Planned Programme

I~ Last Date to Reply to CLR by Engineer

I~ Pile Caps

!-----.r- Ground BeamsJZO Siabs

62 days : Tue 312B1OS: 8un5l28106

99i1ays'· Wed 3122106 Wed 6128/06

·31 days; Wed 3/22106 ·1",(4121106

30 days J Sun419i06Mon518106

31 days '"Mon·5i29/0s • Wed 6!2BJ06

Issue ReViseii"ibiZiStructural Plans ...... ·issueCP pJi Plans

Shop DralVing FInalization and Approvef AreaC·EA108

Area A ;·EA 148

Areae ·EA:149

E~ousableDeiayil1Shop Dral'ilngApproval· ......... Area c· EAl08

Area A· EA 148

Are" B· EA-149

PlannIng by Internal Oepartments and Subcontractors . Pile Caps

. Ground BeamslZO Slabs SIabZ1

·Excusably Delayed Commencement Date Pile Caps

Ground BearnsiZO Slabs SIabZ1

As·Buiit Bored Piling Pile Caps

Girders and ZO Slabs Z1 Level Slabs

Delay Mltlgailon

Pile CiapCommencement

···Griders AIldZO Slab cemrnencement ·21 Level Slab Commencement Excusable Delay Summary Commencemerii Delay

Pile Cap

··Gliders and 20 Slab ZI Slab Completion Delay

Pile Cap Giidersand· to Slab ···Z1 Slab

Extenslon·of "rIme

Area C Crlti""1 EXcusable Delay

o days

114 days' 87 days 114days 114 days

Thu6i29i06·' .. . Fr! 7128106

Fri 7128106 Mon5i8i06 Thu6Jiiiilli

I""

Sap

Mar

Apr

Oct

Nov

Dec

Jan

Feb

Excusable DelaylDelay Mitigation 1lll!ll1!iII!I1!iII!I1lI!Ii! __ iiIII

Extension oHime Entitlement

142 days Tue 619106·

59 daYS: ·Tue 519106

60 days; . ·Fri 619/06.

I~ Slab ZI 61 days i

~ StruCt~ral Worbi6S days!

~ Piles Caps 49 days.

~Gii:iuiiii·BeiirnsiZo Slabs 85 days

1-25+ LeVel z1 7Eidays

~ Ati:Biilll Programme .. 3iiiiiays

27 As BulitConStruQtlori DralViilgissuancD and CLR Ftesponse • .... ·"days .

~EM035.MiijorChangestOPHriiaryGlrder·Leveis Odayii.

Sat 7/29106 Wed!il2tioi>

Frl 717106 . 'rue 12112101i

. Fd1i7iOi> . Thu 8124106 fue·iliaios: Tue 10/31106 Thu !li2B106 i TlJe12112JOEi Mon 4117106 TuoSi8ioi

.. " ..... _-----_ ... _ .

Mon 4117106 : Sat eifoioif

Mon 4i17ibs .... M"n4t17106

Well 9/27/06 Thu 7/6/06 Mon 817106

....

.. 4117

+611 +6110

o daysThu ail101i ..... ·tiiti 611106

r .

o days: ... Si:if6il 0106 . sat 6110106

27 days· ·····Thu Bi3106 Wed 8130106

. . a days Thu 813106 Thu8i3i6ii

.. ·········bdays . Wed 8130/06 WedS/SOIOe

wedaJ3di06·· Wed 8130/06

Tueliiliiiiif Wed 8130106

Tue5!9106· Tue 5/9106 rue 5!9!06

146 days Tilu 813/06

69 daysttiu8i3!b6

60 days Mon914/06

61 daYs Frl 10127/06

87days Sst 9130106

o days Sat 9130106

o days Thu 1112106

o days Tue1m6i06

243 days FI1 91BI06

176 days Fr! 9/8106

178 days 200 days 110 days

23 days 43 days 67 dais

aOOdays 106 days 63 days 44 days 2:idays .

26idays 190 days 137 days

Thu 9121/06 Sal 10121106

Frl8I2s/06 Fr18l25/06 Wed 11/1i06

147 days· Wa,H2I13ioil

~:: :::. :::~~~::

I""

Thu 8/3/06 Wad 8130106 Wed 8J:iOi06 Tue12i26(06

sat 9130106 rnu 1112/06 Tue 12126/06 Tue 12126106 . sat 9130106

Thu11121D6 Tue 12126106

Tue 618107 Fri 3!2ib1 8at3117107 TueSIBIOi

"" ~13Q +-,"30 ....

Page 1

I

"":

FrlSi8iils Tue 12126106

Fri e1S/()6 Sat 9130106

Tilu 9/21/06 Thu 1112100

Sat 10/21106 : Tue 12126/06

Frl 717106 Tue6lBi07

Frl 717106 Frl10120!01i

Frl7i7l0s Thu 9f7106

tuesiliios Wed 9120106

Thu 9126106 Fri 10r.lOIOS

""

+130

.112

~2126

""

Tue 61B107 . ···Fr(3I2t07

... 5at3117/07 Tue 5IBl07 TueS/BI07 Tue0l8l07

Extension of Time Entitlement of 147 Days