Você está na página 1de 10

gonic lines of end winding mmf, Fig.

3 end paper, the field determined in the neighbor- ponent of armature leakage reactance with
view, reference 2 of the discussion. hood of the air gap does not correspond to the same assumptions given in this paper
As mentioned in the assumptions of reality for the following reasons: The air gap and I am planning to present this work in a
this paper and in references 1 and 2 of this is represented by a return current assumed separate paper.
paper the boundary at z=0 is an unbroken to flow in a filament; this makes the cal- A comparison between the results of
plane, assumed to be of iron with infinite culated maximum flux density tend to in- reference 4 and this paper is inappropriate
permeability. Thus gap and slots are finity as we approach the radius p. because entirely different machine construc-
covered. The effect of the air gap then is A better result can be obtained in this tion types were studied. The end core
considered by assuming the fictitious re- area if the return filament is replaced by a plane, which in reference 4 is assumed to be a
turns of the coils on a circular filament lying washer covering all the width of the air perfect conductor, is assumed in this paper
in the middle of the air gap. On the other gap and carrying a distributed peripheral to be a magnetic mirror. Due to this con-
hand, the protruding part of the coils is current. The conductors can also be re- dition the return current and radial current
connected with the return current part, placed by a staircase instead of the cylinder. sheet must be considered.
along the slots on the end-core plane, by The actual conditions in this area considering Furthermore, the surface of the retaining
means of the radial parts which are assumed also the complicated geometry (stepped ring considered to be magnetic, is taken as
to be made of the current bands of the coils laminations and slotted teeth) renders the the internal cylindrical boundary in refer-
by changing direction from axial to radial. analytical treatment of the field difficult. ence 4. In this paper, the retaining ring is
In this way the radial current sheet is I also wish to thank Dr. Smith for his nonmagnetic and the rotor shaft is taken as
also assumed to be a continuous current valuable discussion. The analysis in this the internal cylindrical boundary. As a
sheet. This configuration gives satisfac- paper has as its main purpose the calculation consequence of this last condition the effect
tory results for the greater portion of the and controlling of associated losses and re- of the rotor field must also be considered in
tooth area as it is deduced from Figs. 11 and actances as well as the calculation of forces the rigorous determination of the end zone
12 of this paper. on the end winding conductors. I have magnetic field and the end component of the
As was stated in the conclusions of the used these results to calculate the end com- armature leakage reactance.

Over-all Design Philosophy


500-Kv-Line Design In January 1962, the Pacific Gas and
Electric Company aild the Pacific Power
1- Model Studies and Light Company announced plans
for the construction of a third intertie
between their electric systems. The
W. R. JOHNSON D. D. WILSON J. G. ANDERSON existing interconnections operate at 60
FELLOW IEEE MEMBER IEEE SENIOR MEMBER IEEE kv and 125 kv, respectively. The new
line is being designed and constructed
Summary: The use of model techniques to number of different techniques. High- for conversion to 500 kv (nominal) or
assist in the design of a 500-kv transmission voltage test lines built and operated 550 kv (maximum), but will be operated
line is shown. These techniques supple- initially at 230 kv. The 230/500-kv
mented full-scale tests and theoretical cal- under a wide range of conditions provide
culations. Transient Network Analyzer information of corona loss, radio inter- interconnection will be approximately
(TNA) models were used to establish levels of ference, and some of the physical prob- 100 miles long, extending from Round
switching-surge overvoltages; and nano- lems of extra-high-voltage (EHV) con- Mountain, in northern California, to a
second geometrical models of conductors struction. Full-scale structures sub- contlection with the Pacific Power and
and towers, combined with a Monte Carlo Light system near Klamath Falls, Greg.,
lightning performance computer program, jected to test voltages are used to deter-
gave estimates of the transmission-line mine insulation and air-gap clearances as shown diagrammatically in Fig. 1 (A).
lightning performance. required to withstand impulse, switching- While the Round Mountain-Klamath
surge, and 60-cycle voltages.1 Falls litne will serve as an interconnection
Although these direct empirical meth- between 230-kv systems, it is expected
THIS PAPER describes the methods ods give results which are directly appli- that it will ultimately connect to a 500-ky
and results from the use of model cable to the 500-kv-line design, it is still network required for bulk power trans-
studies with respect to the design of a necessary, for example, to determine mission between major generating sources
500-kv transmission line. Two com- what magnitude of switching-surge volt- and load areas in California. For this
panion papers'2 present the results of ages the line is to be designed co with- reason it was necessary to consider the
flashover tests on full-scale towers and stand. Since there are very few data on effect of additiolnal 500-kv-line sections
the results of corona loss and radio actual switching surges at this 60-cycle uponl switching-surge magnitudes on the
noise1 2 studies. The model studies were voltage level, and since it is not feasible Round Mountain-Klamath Falls line.
for the purpose of investigating the follow- to cover the range of conditions by full- Because of the importance of 500-kv
ing: scale testing methods now available, the
Paper 63-73, recommended by the AIEE Trans-
1. The probable magnitude of switching method of electrical analog testing is mission and Distribution Committee and approved
surges and the effect of various system pa- particularly valuable. Likewise, in by the AIEE Technical Operations Department for
rameters upon these voltages. presentation at the IEEE Winter General Meeting,
studying the effect of ground wires and New York, N. Y., January 27-February 1, 1963.
2. The effect of overhead ground wires and footing resistances upon lightning flash- Manuscript submitted October 24, 1962; made
available for printing November 20, 1962.
varying levels of tower-footing resistance overs, the use of electrical models com-
upon lightning outages. W. R. JOHNSON is with the Pacific Gas and Electric
bined with mathematical analysis offers Company, San Francisco, Calif.;, D. D. WILSON
The design of 500-kv transmission lines a powerful tool to assist in design of the is with the General Electric Company, Schenectady,
N. Y.; and J. G. ANDERSON is with the General
can be approached and assisted by a line. Electric Company, Pittsfield, Mass.

572 Johnson, Wilson, Anderson-500-Kv-Line Design-I AUGUST 1963


lines from a system standpoint, a high KLAMATH FALLS ROUND MOUNTAIN
level of reliability is desirable. There- 230/500 KV 500/230 KV
fore, special attention has been given to
the design with respect to outages re-
sulting from switching surges and light-
ning.
The investigation of switching surges
was planned to include the effects of
variations in major system parameters
such as low- and high-side switching, litle
length, shunt reactors, series capacitors,
and adjacent sections of 500-kv lines.
The results of these tests have provided a
guide in the selection of a switching-surge
level of 2.5 times the maximum 60-cycle
voltage as the criterion for insulator string 300 200 300 400 400 500 500
and air-gap withstand voltage levels as MVA MVA MVA MVA MVA MVA MVA
described in a companion paper.1 (B)
Although the Pacific Gas and Electric
Company has not generally used overhead Fig. 1. Initial and ultimate 500-kv system (numerical quantities are approximate and dotted
ground wires on its 230-kv transmission components are tentative)
lines, it was decided to give careful con-
sideration to their application on the A-Initial Klamath Falls-Round Mountain section
500-kv line This line will traverse an
B-Planned Final system
area estimated to have an isokeraunic
level of about 15, compared with a level of Klamath Falls, 2.OX106 kva (kilovolt-am- device. Positive-, negative-, and zero-
0-10 for most of the system. The in- peres) sequence leakages are matched to the
complete information available indicated Round Mountain, 5.7X 106 kva actual transformer as well as the satura-
that a substantial improvement in line Station X, 15 X 106 kva tion characteristics, both positive- and
performance can be achieved by the use Station Y, 3 X 106 kva zero-sequence. Experience has indicated
of overhead ground wires, provided that that the entire saturation characteristic
tower-footing resistances can be reduced TNA REPRESENTATION of a transformer is extremely important
to reasonable levels. The line is ac- The system being studied was repre- in transient studies, particularly where
cordingly being constructed with over- sented on the TNA as a 3-phase model high dynamic overvoltages may be
head ground wires, and tower-footing system, equivalent to the actual system, encountered; thus, it is very important
resistance will be investigated as the line but operating at a reduced voltage.3 that the transformers are correctly repre-
is built. The base model frequency is 60 cps sented.
(cycles per second), although slight fre- Shunt reactors are represented by
Switching-Surge Studies quency-base changes may be utilized to linear reactance, with the correct phase
correct model parameters to those of the coupling (if such is present in the actual
Investigation of the switching-surge actual system. reactor), as in the case of a 3-phase unit.
transients on the Pacific Gas and Electric The model transmission lines are repre- Source reactalnces (or equivalent system
proposed 500-kv line was essentially sented by L sections with the parameters reactances) were represented by linear
divided into two phases: as noted in Fig. 2. Each of these sec- inductance. In this study the equivalent
Phase 1: The initial Klamath Falls- tions represents a nominal length of 10 X0/Xi ratios were 1.3 and a neutral
Round Mountaini line utilizing 230-kv low- miles, and the correct number is con- reactance was utilized to give this ratio.
side switching. (A line length of 110 miles nected in tandem to represent the desired Circuit breakers (or other switching
was used for this investigation; the route line length. devices) were represented by a synchron-
now proposed for construction is approxi- Transformers are represented by model ously driven switch, each pole (phase)
mately 100 miles.)
transformers which duplicate the actual capable of accurately opening or closing
Phase 2: An assumed extension of the
500-kv line in both directions with line seg-
ments of various lengths as shown in Fig.
1(B). This phase assumed 500-kv switch-
( CI CO
ing on all line sections. Since the study was
TIT A~~~~~~
-

primarily concerned with the performance of


the initial 110-mile section, phase 2 results
are restricted to transient voltages produced RI LI
on this section as a consequence of abnormal
conditions or to switching, either on this
initial section or on adjoining sections of the
500-kv system.
Fig. 2. Typical nominal 10-
Fig. 1 depicts the configuration of each mile model line section used
phase of the system investigated on the in the TNA study (subscripts -L CO
TNA. The appropriate 3-phase short- 0 and I denote zero and
circuit duties of the 230-kv components positive-sequence quantities,
were assumed as follows: respectively) 1/3 (Ro- R1) 1/3 (L-LI)
AUGUST 1 963 Johnson, Wilson, A nderson-500-Kv-Line Design-I 573:
Fig. 3. Oscillograms of ages. In the cases where switching was
mI~' energization transient voltages involved, the results were given for
t g3 30 at Klamath Falls 500-kv bus ETHEV equal to 1.00 per unit.
Scdl e:
Vertical: 1 div.=0.47 per- PHASE 1 [SEE FIG. 1 (A)]
unit crest volt Dynamic Overvoltages
Horizontal: 1 div.=5 msec
(milliseconds) Initially, the dynamic overvoltages
present when the line is energized only
through Round Mountain, with the low-
side breaker at Klamath Falls open, were
considered. The effects of shunt-reactor
compensation, series-capacitor compensa-
tion, and no compensation, were investi-
gated; the results are summarized in
Table I. These results indicate the bene-
fit of shunt reactors in reducing the dy-
namic voltages, although without reactors
the voltages are not detrimental to line or
terminal-apparatus insulation for reason-
able values of voltage at the infinite bus
(1.00 to 1.10 per unit).
Next, the dynamic overvoltages present
when the line is energized through Kla-
math Falls only, with the low-side circuit
breaker open at Round Mountain, were
investigated. In this instance, no shunt
reactors or series capacitors were present
at any point on the driving-voltage sine 1.15. A source voltage of this magnitude on the system. The results (summarized
wave. Energization angles were re- applied at the infinite bus in Fig. 2 (B) in Table II) in this case were, in general,
stricted to 180 degrees (1/2 cycle) between would duplicate the fundamental-fre- more severe than those noted in Table I.
the first and last phase to close, which is quency conditions demonstrated by the This was to be expected, since the line
consistent with modern power circuit a-c board study, but would also include was energized through a much weaker
breakers. Upon opening, the circuit the correct harmonic distortion produced source.
breakers were assumed to open on con- by overexcited transformers. One ap-
secutive current zeros and to be restrike- proach to ascertaining the voltage ETBEV Energization Transient Voltages
free. The driving-source voltage for the to be held behind the equivalent reactance
was to perform an a-c network analyzer
To determine the severity of initial
model system was a sine-wave generator, energization transients, the 500-kv line,
large enough to appear as an infinite bus study and arrive at the exact values for with the terminating Klamath Falls
to the model system. various conditions. It was decided,
autotransformer, was first energized from
however, to vary ETHEV over a wide the Round Mountain 230-kv circuit
Results range, thereby encompassing all possible breaker. With ETHEV equal to 1.00 per
conditions.
The base voltage throughout the study The voltages in the results are expressed unit, this switching condition gave rise
in per unit of the line to neutral crest to an energization transient of 2.6 per
was predicated on a Thevenin's Equiva-
unit at Klamath Falls if no reactors were
lent approach. The system behind a voltage applied at the infinlite bus. A present on the system, and was not in
given point was represented by an im- wide range of per-unit voltages was
excess of the anticipated values.4'6 This
pedance in conjunction with a constant applied; thus not only the normal op- transient voltage, however, was more
fundamental-frequency voltage source erating region of voltages was considered,
(ETHEV). With this equivalent, a given but the limiting conditions were defined,
steady-state case could represent various where the interaction of system ca- Table I
system-operating conditions such as ener- pacitance and the nonlinear magnetizing
gization, de-energization, or load drop- impedance of coninected transformers Crest Line-to-Neutral Voltage
ping. mnay give rise to abnormal conditions Klamath Falls
For example, assume that the voltage such as ferro-nonlinear oscillations or to Round Mountain
500 Kv 500 Kv
at the Round Mountain 230-kv bus severe distortion due to harmonics of Source
Voltage 1* 2t 31 1* 2t 31
rises to 1.2 per unit upon loss of load at frequencies higher than 60 cps.
Klamath Falls, as shown by fundamental- In energization cases, the three poles of 1.00 .... 1.13..1.11 1.16..1.11
..........
frequency network analyzer studies. Un- the circuit breaker were adjusted to pro- 1.05 .... 1.23..1.13 . 1.27..1.13
der these conditions, the line will supply duce the maximum transient within the 1.10 .... 1.32..1.18 . 1.32. 1.18
1.15 ... 1.37 ..1.23 . 1.41 . 1.23
approximately 260 mvar (megavars). limitation of 1/2 cycle between the first 1.20 ... 1.49.. 1.30.1.46 ... 1.60 ..1.30..1.60
For a system having a short-circuit ca- and last poles to close.
pacity of 5,700 mva (megavolt-amperes), Although each phase voltage was * No shunt-reactor or series-capacitor compensa-
tion.
the source voltage, interpreted in terms of recorded throughout the study, only the t 100-mvar shunt-reactor compensation on the
a Thevenin's Equivalent ETHEV cor- highest voltages were reported for eac tertiary of each transformer.
I No shunt compensation-50% series-capacitor
responding to these conditions, would be value of ETHEv for the dynamic overvolt- compensation at Round Mountain.

574 Johnson, Wilson, A nderson-500-Kv-Line Design-I AUGUST 1963


severe than the anticipated line insulation Fig. 4. Oscillograms of
would withstand; thus 50-mvar shunt voltages at Klamath Falls 500-
reactors were added at each terminal kv bus during Fault clearing
transformer. With these reactors con- Sca e:
nected, the transient was reduced to 2.12 Vertical: 1 div.=0.24 per-
per unit at Klamath Falls. unit crest volt
Fig. 3 illustrates the transient voltage Horizontal: 1 div.=5 msec
on the 500-kv bus at Klamath Falls,
where phase C reaches the value of 2.12
per unit. The point of energization was
changed to the 230-kv low-side breaker at
Klamath Falls and, with 50 mvar on the
tertiary of each transformer, the maxi-
mum energization transient was 2.32
per unit, occurring on the 500-kv bus at
Round Mountain. The waveshape was
similar to that of Fig. 3. The foregoing
illustrated that the energization transients
caused by 230-kv low-side switching
could be reduced to acceptable limits.
As the next step, line-to-ground faults
were investigated to ascertain the tran-
sient effect caused by the first circuit
breaker to clear in the process of opening
both terminals of the system. The poles
were opened on consecutive current zeros
so that no current chopping occurred.
It was found that no discernible disturb- concerning the future system was confined thoroughly system performance with
ance occurred when the first circuit to energization and fault-clearing tran- shunt-reactor compensation.
breaker opened. This was not altered sients. Energization of the Klamath Falls-
by the sequence of pole openings, i.e., Station W line from the 500-kv circuit
faulted phase first, second, or last to Energization Transient Voltages breaker at Klamath Falls was investi-
clear. The transition is shown in Fig. 4, gated to ascertain transient voltages aris-
where a fault on the 500-kv bus at Round The first case investigated was ener-
gization of the Klamath Falls-Round ing from switching-line sections ad-
Mountain is present. The oscillogram jacent to the Klamath Falls-Round
illustrates the voltages at Klamath Falls Mountain line from the Klamath Falls
500-kv circuit breaker. The system Mountain section. The system was
prior to and following the opening of the represented by lines and transformers
Klamath Falls 230-kv low-side breaker. included 500/230-kv autotransformers at
Station V, Station W, and Klamath Falls, from Station W to Station X [Fig. 1(B) ],
The steady-state voltages on the un- and from Station X to Station Z by an
faulted phases were calculated by a with the appropriate 230-kv-system im-
pedance behind each transformer. All equivalent reactance maintaining the
linear analysis and substantiated on the proper X0/Xl ratio.
TNA during this portion of the study.6 the 500-kv-line sections were represented
The voltages on the unfaulted phases were here. With 100 mvar of reactors connected
equal to or less than 1.00 per unit. The Klamath Falls-Rotnd Mountain at the Station W end of the 500-kv line,
line was assumed to have no trapped the maximum transient was 1.80 per unit
charge previous to energization. If a at Klamath Falls. This case actually
PHASE 2 trapped charge were present, it would illustrates two conditions, normal ener-
The first phase of the study resulted in represent a reclosing operation, which gization and high-speed reclosing. With
no severe dynamic or transient overvolt- will be discussed later. The maximum 500-kv reactors permanently connected
ages. Since the dynamic overvoltages energization transient is illustrated in at the Station W end of the line, the
would be even less severe (because of the Fig. 5, where a voltage of 2.36 per unit is trapped charge would be greatly reduced
absence of harmonics) if no terminating shown to occur on phase B. To as- in the reclosing time. If no reactors were
transformer were present, as would be the certain the effect of series-capacitor present at Station W, the possibility exists
case with high-side switching, the study compensation, capacitors were added, of reclosing on trapped charges. Trapped
the locations noted in Fig. 1(A), and the charges equal to crest line-to-ground volt-
energization repeated. The series ca- age may remain on the line for a period of
Table 11 pacitors reduced the transients slightly. many seconds, which is well within the
The voltages across the series capacitors reclosing time.4 This case was simulated
Crest Line-to-Neutral Voltage at each bus were recorded, and in no in- and a transient voltage of 2.36 occurred
Source Round Mountain Kllamath Falls stance were the voltages greater than the at the Klamath Falls 500-kv bus. Fig.
Voltage 500 Kv 500 Kv crest voltages likely to occur during nor- 6 illustrates the voltages obtained where
mal line-load conditions. The effect the 2.36 per-unit transient occurs on
1.00 .11.32 ....... 1..1.30 of shunt reactors would be to reduce the phase B.
1.05 . 1.39 .. 1.34
1.10 . 1.41 .. 1.39 transient voltages. Since the value of As a note of interest, a transient voltage
1.15 . 1.44 .. 1.41 2.36 per unit was not excessive, it was of 3.9 per unit was possible at the Sta-
1.20 . 1.46 .. 1.46
not deemed necessary to investigate tion W 500-kv bus for this reclosing case
ATUGUST 1963 Johnson, Wilson, Anderson-500-Kv-Line Design-I
with trapped charge, and could impose ating circuit breaker were investigated. Lightning-Performance Studies
severe duty on terminal equipment at The most severe overvoltage was ob-
Station W if line-insulation flashover tained when a single line-to-ground fault Because of the over-all high-level reli-
occurred. at the Klamath Falls end of the Klamath ability requirements of this line, careful
Falls-Station W line was cleared with the consideration had to be given to its light-
Fault-Clearing Transient Voltages breaker on the Station W side of the ning performance for various alternative
Single line-to-ground faults were placed Klamath Falls 500-kv bus. A voltage designs. No lines of similar construc-
at various locations on the ultimate of 1.56 per unit is shown on phase A of tion passed through the same territory;
system and cleared with the different Fig. 7. This oscillogram depicts the therefore, outage figures, from which esti-
500-kv circuit breakers. All pertinent voltages on the Klamath Falls 500-kv mates of probable performance could be
combinations of fault location and oper- bus. made, were not available. As a result,
all performance estimates had to be based
on fundamental considerations of tower
and line geometries, footing resistances,
Fig. 5. Oscillograms of and estimated distributions of strokes.
energization transient voltages At the beginning of this study, the
at Klamath Falls 500-kv bus usual AIEE method of predicting line
&SE A ~~Scale:
Vertical: 1 div.=0.47 per-
lightning performance was deemed un-
acceptable in its present form because of
unit crest volt its demonstrated inability to predict
Horizontal: 1 div. =5 msec outage rates EHV lines within an
on
order of magnitude. The method
adopted instead consisted of a 3-step
approach described in a previous paper :7
1. The construction of nanosecond geo-
metrical models' of the towers and con-
ductors, from which the per-uuit 'ightning
voltages generated at tower-insulator strings
and in the spans could be established for a
representative range of defined lightning-
stroke characteristics.
2. The preparation of statistical distribu-
tions of footing resistances and meteoro-
logical conditions that could be expected in
the vicinity of the line.
3. The incorporation of the results of the
above two steps into a Monte Carlo cal-
culating routine7 to simulate 20 years of
lightning experience by means of a digital
computer. The computer generates statis-
tical distributions of lightning strokes with
magnitudes, rise times, and frequencies
equivalent to those found in nature, and ap-
plies the proper number of strokes that would
occur in 20 years to a conceptual line stored
in the computer memory. For each stroke,
since it can refer to the line-response charac-
teristics determined by the nanosecond-
model tests, the computer determines
whether or not a flashover will occur and
tabulates the results. These results are
finally printed out as a sort of experience
table for different insulation levels and line
geometries, so that the probable effects of
various design choices can be weighed.
This method has been used to calculate
the lightning-outage performance of many
transmission lines, with generally agree-
able results between calculated and meas-
ured values.
Fig. 6. Oscillograms of A photograph of the 50:1 scale-model
transient voltages on the tower undergoing a test is shown in Fig.
Klamath Falls 500-kv bus 8. This model was tested with all 3-phase
caused by high-speed re- conductors and two shield wires installed
closing and properly terminated. Simulated
Scale: strokes were applied to the tower, and to
Vertical: 1 div.=0.47 per- the shield wires at mid- and quarter-
unit crest volt span, and voltages were measured at the
Horizontal: 1 div.=5 msec line insulators and between shield wire
576 Johnson, II'ilson, A nderson-500-Kv-Line Design-I AUGUST 1963
and nearby phase conductors. Footing distribution of footing resistances, rather strokes contacting the line would cause
resistance was duplicated by small car- than a single value, and applies a statis- a tripout, and that the resulting outage
bon resistors at the bottom of the tower tical distribution of stroke amplitudes to rate is also high. This high outage rate
legs and the longitudinal guys, with about these resistances. Fig. 11 shows three is caused by the high footing resistances
twice the resistance in the guys as in the footing-resistance distributions that were of distribution A, Fig. 11, although bal-
legs. A few tests were made with the used in this analysis, in order to assess the anced somewhat by the low isokeraunic
guys isolated to simulate anchoring into probable effects of various grounding level of 15. By reducing all resistances
rock. In all, tests were carried out with practices. to distribution B, case II shows about a
six values of footing resistance ranging four-to-one reduction in outage rate over
from zero to 300 ohms. CALCULATED LIGHTNING PERFORMANCE case I. It should be noted that even for
Table III shows calculated outage rates case II, the median resistance is 30 ohms,
MODEL TEST RESULTS for up to 30 insulator units for 110 miles so that the footing resistance can still
Some of the model test results are of this line. Case I of the table points be considered high by usual EHV line
shown in Figs. 9 and 10. Fig. 9 shows out that between 12% and 15% of the standards. If, however, a further im-
the maximum voltages created across
the insulator strings at the tower by a
stroke to the tower. The data are pre- Fig. 7. Oscillo-
sented in terms of maximum voltage per grams of voltages on
ampere of stroke current for current the Klamath Falls
waves having a "quasi-ramp-function" 500-kv bus caused
waveshape, i.e., a reasonably well-simu- by fault clearing
lated straight-rising front and a flat Scale:
top. The computer program applies a Vertical: 1 div.=
"severity factor" correction to account 0.47 per-unit
for the nonstandard voltages developed crest volt
across the insulators. For zero values Horizontdl: 1
of footing resistance, tower behavior is div.=10 msec
quite similar to an inductance that
changes somewhat with time. The effects
of shield-wire coupling are automatically
included. As footing resistance is in-
creased, more current is driven out the
shield wires and less passes down the tower
through the footing resistance. Fig.
10 shows similar voltages generated by
a stroke to midspan. These data do not
include the effect of the corona envelope
on the shield wires. The corona en-
velope will tend to improve performance
by lowering the equivalent surge impe-
dance and improving the coupling, but
by inspection of this initial data, and
knowing the spacings involved, it was
apparent that midspan flashovers would
not be a frequent problem. One also can
note the negligible effect that tower-
footing resistances have on the midspan
voltages up until the time required for a
reflection to arrive from the nearest tower.
DISTRIBUTIONS OF FOOTING RESISTANCE
In the design of any transmission line
it is of great interest to estimate the prob-
able effects on lightning performance of
various attempts to limit tower-footing
resistances to certain maximum values.
It is obvious also that one can be con-
siderably in error by assuming all towers
to have the same footing resistance, when
in reality it may be the frequency with
which unusually strong strokes contact
towers with unusually high footing
resistances that causes outages. The
Monte Carlo method is extremely useful Fig. 8. Nanosecond geo-
in this respect in that it utilizes a whole metrical model undergoing test
AUGUST I1963 Johnson, Wilson, A nderson-500-Kv-Line Design-I 577
TOWER FOOTING RESISTANCE-OHMS

Fig. I1. Assumed frequency distributions


MICROSECONDS TO CREST OF MICROSECONDS TO CREST OF of tower-footing resistances
APPLIED CURRENT WAVE APPLIED CURRENT WAVE
A-Highest value distribution for rocky terrain
Fig. 9. Maximum insulator voltages for a B--All resistances improved by better ground-
stroke to tower Fig. 10. Maximum voltages produced by a ing practices
stroke to one shield wire at midspan, neglect- C-Same as distribution B, but maximum
ing corona effects values held to 50 ohms by counterpoise
provement in footing resistance is at-
tempted by reducing all footing resist-
ances of case II that are above 50 ohms Table Ill. Calculated Lightning Outage Rates*
to a value of 50 ohms, case III shows only No. of Shield Footing Per Cent of Outage Rate
a small improvement over case II, Insulator Wires Resistance Line Strokes Tripouts
demonstrating that it would be better Case Units Installed Distribution Causing Tripout Per Year
to decrease all resistances instead of re-
ducing only those over 50 ohms. Cases [25 14.8..
4. 1I
4. 12
IV and V show outage rates with no A 13.8- 3.89
shield wires installed, and demonstrate 29YA 12.6.
3.76
3.54
the very beneficial effects of shielding. t30) I2.3 ......
3.48
After these lightning studies were com- 251 5.4. I .52
pleted, it was deemed necessary to use 35 261 B1 4.8. 1.36
27 .... Y es ... B 4 .3 1.23
insulator units for the line insulation in 281 3.9........... 1.11
l291 3.8 ........ 1.10
order to withstand possible high switching ( 30 J 3.8 -. 1.09P
surges. This can be expected to cause (251 4.6 ............... 1.31
261 4.2
a further and probably significant reduc- III ............... ....... Yes . C .......... 4.1....-.-
1.20
1.15
tion in outage rates over those reported 128'
1291
3.6
3.5
1.02
for 30 units in Table III. 0.99
(30l
..
3.5. 0. 99
IV . 30. No. A. 75.3 . 13.3
Conclusions V. 30. No. B. 56.7 . 10.0

1. For all cases studied, only line energiza- * Based on an isokeraunic level of 15, a line length of 110 miles, and a shielding failure rate of 1% wherever
shield wires are employed.
tion and reclosing caused overvoltages in
excess of twice normal line-to-ground voltage.
Energization produced transients of 2.36 L. Thompson, L. 0. Barthold, J. J. LaForest, C. B.
per unit and reclosing an adjacent line section MODELS, F. A. Fisher, J. G. Anderson, J. H.
Lindh. Ibid., see pp. 587-97 of this issue. Hagenguth. Ibid., pt. III-B, vol. 78, 1959 (Feb.
produced a similar value. The maximum 3. MODEL TECHNIQUES IN THE TRANSIENT NET- 1960 section), pp. 1725-34.
overvoltage on fault clearing was 1.56 per WORK ANALYZER SOLUTIONS OF POWER SYSTEMS 9. THE ROLE OF LIGHTNING STRIKES TO THE
,unit. PROBLEMS, L. 0. Barthold, R. F. Silva. Proceedings CONDUCTORS BYPASSING THE GROUND WIRES IN
of the Amer-ican Power Conference, Chicago, Ill., THE PROTECTION OF HIGH-VOLTAGE-CLASS LINES,
2. Because of the high median value of vol. 22, 1960, pp. 722-31. M. V. Kostenko, I. F. Polovoy, A. N. Rosenfeld.
footing resistance involved, lightning trip- 4. SWITCHING SURGES: I-PHASE-TO-GROUND
Elektrichestvo, Moscow, USSR, no. 4, 1961, pp.
outs of about one per year can be expected if VOLTAGES, AIEE Committee Report. 20-6.
AIEE
two shield wires and 30-unit insulator strings Transactions, pt. III (Power Apparatus and
are employed. Without shield wires, outage Systems), vol. 80, June 1961, pp. 240-61.
rates of 10 to 13 are likely. The use of 35- 5. SWITCHING SURGES DUE TO ENERGIZATION OR
unit strings will cause a further decrease in
these values.
RECLOSING, I. B. Johnson, R. F. Silva, D. D.
Wilson. Proceedings of the American Power
Conference, vol. 23, 1961, pp. 729-36.
Discussion
6. TRANSIENTS IN POWER SYSTEMS (book), H. A. C. L. Rudasill (Virginia Electric and Power
Peterson. John Wiley and Sons, Inc., New York, Company, Richmond, Va.), and H. M.
References N. Y., 1951. Smith and C. L. Wagner (Westinghouse
7. MONTE CARLO COMPUTER CALCULATION OF Electric Corporation, Pittsburgh, Pa.):
1. 500-Kv-LINE Design: II-ELECTRICAL TRANSMISSION-LINE LIGHTNING PERFORMANCE, The authors have presented an interesting
STRENGTH OF TOWERS, W. R. Johnson, E. G. J. G. Anderson. AIEE Transactions, pt. III
Lambert J. B. Tice, P. J. Turner. IEEE Trans- (Power Apparatus and Systems), vol. 80, Aug. 1961, and timely discussion of the use of the TNA
actions on Power Apparatus and Systems, see pp. pp. 414-19. and geometrical models to predict the per-
581-87 of this issue. formance of 500-kv lines. The subject has
8. DETERMINATION OF LIGHTNING RESPONSE OF
2. 500-Kv-LINE DESIGN: III-CONDUCTORS, R. TRANSMISSION LINES BY MEANS OF GEOMETRICAL been of special interest to the discussers since
57s Johnson, Wilson, A nderson-500-Kv-Line Design-I AUGUST 1 963
they made similar studies as part of their S. Price, A. J. McElroy, H. M. Smith, D. F. Shankle. Table IV
over-all system study for the Virginia Elec- Ibid., see pp. 487-500 of this issue.
tric and Power Company (VEPCO) 500-kv 3. FIELD MEASUREMENT OF SWITCHING SURGES
AS MODIFIED BY UNLOADED 345-KV TRANS- Authors' Outages
transmission system. In this regard cer- FORMERS, A. J. McElroy, W. S. Price, H. M. Number of Minus Shielding Clayton-Young
tain questions on procedure and interpreta- Smith, D. F. Shankle. Ibid., see pp. 500-20 of this Insulators Failures Calculation
tion of results have been raised by the paper. issue.
It has been stated that the purpose of the 25 .1.124 .............. 1.20
model studies was to determine the probable J. M. Clayton and F. S. Young (Westing- 26 ....... 1.08 .............. 1.13
magnitude of switching surges on the system. house Electric Corporation, Pittsburgh, Pa.): 27 ......... 0.95 ............. 1.08
How can probabilities be assigned from The authors have presented a very interest- 28.. 0.83 ............. 1.05
29 ..... 0.82 .1.02
these studies? Are not the maximum mag- ing discussion of the lightning and switching- 30 ............. 0.81. 1.00
nitudes, within the limits of the initial as- surge studies made on this 500-kv transmis-
sumptions, the values that are determined? sion line. Our particular interest is in the
The only means of obtaining probability data lightning protection problem, and we have
is by making actual system measurements 5. There is a conspicuous absence of insu-
several questions to ask. lator data and, consequently, it is difficult to
and determining the probability of various
pole-closing sequences and the overvoltages 1. Distributions of footing resistances assess the apparent leveling-off effect in
that they generate. In the ANACOM shown in Fig. 11 of the paper provide a very outages as the number of insulators in-
study for the VEPCO project, for example, realistic way of calculating the performance creases. Even when shielding failures are
all the variable parameters, such as breaker of the entire line. We wonder, however, if subtracted, there is no significant improve-
pole-closing sequence, were adjusted to give the authors have not placed too stringent a ment in performance shown when insulators
the maximum system overvoltages. The limitation on the line by assuming a distri- are added above 27. Could the authors dis-
results, however, were modified, based on bution such as A having an average footing cuss this problem? Is the leveling off due to
experience factors obtained from field tests, resistance of approximately 75 ohms. Rea- "window effect" of the tower or can it be
such as are described in references 1-3. lizing that this line traverses mountainous accounted for by other phenomena?
The authors state that the leakage and terrain where one would expect high footing 6. What span lengths were assumed in this
magnetizing reactances of the system trans- resistance, we wonder if the authors have any study? Also, it is not obvious what A and
formers are duplicated by the model trans- correlation between measured ground re- B refer to in Fig. 10. Could this be ex-
formers. How do the leakage resistances sistances and the resistance that the light- plained?
and the hysteresis losses compare? In the ning surge current would see. This would
VEPCO study and other studies run on the provide a clue as to which distribution most We have nmade a comparative calculatiosn
transient analyzer (ANACOM) used by the accurately reflects the performance of the using footing-resistance distribution B and
discussers, the model transformer losses were line. the authors' value of 28.5 strokes. No
too high to be representative of the system. 2. The authors mention the use of counter- shielding failures were assunied. The insu-
A special equivalent, using a saturable reac- poise as a method of reducing tower-footing lator data available to us are assumed to be
tor and feedback amplifier, was used to resistance. Were actual counterpoise con- representative but are not duplicates of the
match more closely the actual transformer figurations studied during the model tests values used by the authors. Table IV shows
characteristic. or was an upper limit of footing resistance our results.
In using the Thevenin's Equivalent ap- assumed for the digital computer portion
proach to the system behind the switching of the study?
point, the authors seem to neglect any re- H. R. Stewart (New England Electric Sys-
flections from that part of the system during 3. The authors have used a 1 % shielding tem, Boston, Mass.): The authors do not
the transient conditions caused by the failure rate for this line. Although this mention whether they investigated the
switching disturbance. Depending upon agrees with Burgsdorf's data for a 33-degree effect of counterpoise in their lightning per-
their time of arrival, such reflections may shielding angle, we wonder if it is not too formance studies. Experience on the New
reduce or increase the maximum voltages. high. Several things must be considered England Electric System, where counter-
The authors do not mention representing when calculating the number of shielding- poises were installed 10 to 15 years ago on
any system loads in their studies. Omis- failure outages a line will experience. The practically all its lines which were built 15
sion of these loads and the system damping sag of the ground wire and phase conductor or more years previously without counter-
that results can give unrealistic dynamic tend to improve the shielding angle while poises, indicates that a counterpoise will
overvoltages. The paper shows that the lowering the height along the span. As the provide at least the tripout-outage-rate
maximum overvoltages occur on line ener- number of insulators is increased, the number improvement between case II and case I or
gization and reclosing. Shunt reactors were of shielding failures is also reduced. Calcu- between case III and case I in Table III of
used to limit these overvoltages to 2.36 per lations we have made for this line indicate the paper. Thus if the tested tower-footing
unit. Did the authors consider the use of that, when considering the tower alone, a resistances of the line turn out to be distribu.-
circuit-closing resistors in the circuit breakers shielding failure outage rate of 0.1 to 0.15 tion A of Fig. 11, and if it is desired to secure
as a means of reducing these overvoltages? flashover per 100 miles each year can be ex- a lightning performance corresponding to dis-
In the VEPCO study, use of these resistors pected. When considering the line as a tribution B or distribution C, it might be sug-
limited the switching-surge overvoltages for whole, the rate drops to a negligible amount. gested that this could be secured by installing
500-kv switching to less than 2.0 per unit. Could the authors elaborate on this prob- a continuous counterpoise, rather than by
Table III of the paper indicates very little lem? attempting to reduce individual tower-foot-
improvement in lightning performance from 4. A fourth problemn arises when we con- ing resistances. It is appreciated that in
using more than 28 insulators, especially for sider the number of strokes to the line. the mountainous terrain cited, the installa-
the lower footing resistances of cases II and Since data on strokes per square mile are tion of a continuous counterpoise may not
III. Would the authors comment on the quite limited, we have based our calcula- be inexpensive, but neither is the reduction
reason for this behavior? Also, in view of tions on data reflecting the number of of tower-footing resistances in such terrain.
this, how can the authors reconcile their strokes to transmission lines. Using these
statement that with the 35 insulators re- data, we would expect about 50 strokes per
quired by switching surges, a "probably 100 miles each year in an area where the W. Piper and R. E. Moran (Stone and
significant reduction in outage rates over isokeraunic level is 15. The authors have Webster Engineering Corporation, Boston,
those reported for 30 units in Table III" evidently used a value of 28.5 strokes to this Mass.): The paper represents a summary of
would result. 110-mile line. We wonder if the authors, a great number of investigations, calcula-
based on their experience with this calculat- tions, estimates, and studies involved in
REFERENCES ing method, believe that the strokes per preparation of some of the design parameters
1. FIELD MEASUREMENT OF SWITcHING SURGES square mile provides an accurate measure of for a 500-kv transmission line. The authors
ON UNTERMINATED 345-KV TRANSMISSION LINES, line performance. If this line had been built
A. J. McElroy, W. S. Price, H. M. Smith, D. F. are to be commended for a concise presenta-
Shankle. IEEE Transactions on Power Apparatus in an area having an isokeraunic level of 30, tion of their effort.
and Systems, see pp. 465-87 of this issue. would a value of 57 strokes have been as- It is interesting to note that, with a single
2. FIELD MEASUREMENT OF 345-KV LIGHTNING sumed instead of the commonly used value possible exception, the calculations and
ARRESTER SWITCHING SURGE PERFORMANCE, W. of 100 strokes per 100 miles each year? tests have resulted in indications that the
AUGUST 1 963 Johnson, Wilson, Anderson-500-Kv-Line Design-I 579
switching surge for this proposed 500-kv The leakage resistances of the model trans- tribution A was chosen by Pacific Gas and
system should not exceed a value of 2.6 per formers were matched very closely to the Electric Company engineers based on their
unit, without the addition of any special de- power transformers. Past studies have prior experience with lines in similar moun-
vices for limiting this maximum. In the shown the hysteresis loss in a model study is tainous terrain. The validity of any
consideration of devices and arrangements much less important than rigorous magnetic lightning outage calculation is strongly af-
for limiting the crest of the switching surge, modeling of the transformer saturation fected by this selection, and it is often per-
it is apparent from the data included in characteristics. tinent to study several distributions to de-
Table I of the paper that the installation of The difference between a Thevenin's termine the sensitivity of the outage rate
series capacitors on this system would not be Equivalent representation and distributed upon this choice.
effective. The installation of shunt reac- representation, when low-side switching was In the model tests, counterpoise was not
tors, on the other hand, would obviously re- studied on this system, was negligible be- actually used. At the time the tests were
sult in a reduction of the maximum value of cause of the isolating influence of the trans- made it was not (and still is not) intended
this surge. Is it intended that some shunt former. Where 500-kv switching was stud- that counterpoise would be extensively re-
reactors will be included in the initial or ied, the appropriate distributed system was quired; hence its effects on the resistance dis-
subsequent construction of this 500-kv sys- utilized, as noted in the paper. tributions were onlv approximate.
tem and, if so, to what extent will the instal- Since representation of full load on the
lation of these reactors be carried out? The Regarding shielding failures, sag in con-
system will tend to reduce switching surges, ductors obviously improves the shielding
shunt reactors, as indicated, would represent no-load and light-load conditions were
a considerable investment. Have the au- angle and reduces line height, but this
studied on the TNA as limiting conditions. parameter was automatically taken into
thors investigated the possibility of other Shunt-reactor compensation on the 500-kv
means for limiting the transient voltage to account by previous investigators when they
system was not intended primarily as a published shielding-failure data on actual
acceptable vaiues, i.e., surge-suppressing re- method of reducing the switching transient,
sistors installed in the circuit breakers? lines. Their tabulated shielding-failure rates
but was applied to minimize sustained used the height of the towers and shielding
These lightning performance calculations overvoltage conditions. It is interesting,
provide an example of the statistical ap- angle at the towers as their basic parameters
however, that a substantial reduction in to define the line geometry, but midspan
proach to estimating the lightning perform- switching-surge transient voltages results
ance of a transmission line, including com- effects are inescapably included in the data.
from shunt-reactor compensation.
parative results for suspension-insulator The initial section of 500-kv line was The validity of shielding failure assump-
strings for several different numbers of scheduled for completion in 1963, with the tions or calculations is, in the authors' opin-
units. The model tower shown in Fig. 8 2.5 switching-surge level considered desir- ion, the most indeterminate part of any
appears to be designed for free-swinging in- able, based on the characteristics of avail- present lightning outage calculation. This
sulator strings for all three phases. It will able equipment. The design of subsequent is a subject on which more field investiga-
be interesting to note any deviation from line additions for the projected 500-kv sys- tion is required, and we strongly urge that
these data for a V-string arrangement for tem will incorporate any improvements in such investigation be made. At the present
the center phase and V-strings for all three equipment then available. time, one has the choice of using either theo-
phases. Is the statistical sampling of tower- The small improvement in calculated retical calculations or actual field experience.
footing resistance accomplished in an evenly lightning performance for variations in the The calculations in this paper have utilized
graded manner, or at random; i.e., is the number of insulator units from 25 to 30 the latter, since they must finally serve as the
footing resistance of adjacent towers approx- units is also shown in the calculations of basis of acceptance of any theoretical ap-
imately the sanie, or would the computer be Messrs. Clayton and Young who, in fact, proach.
likely to select a tower with very high footing show even less variation than the authors. The number of strokes per square mile was
resistance to be located such that adjacent This small performance variation is all one tak-en as 0.23 times the isokeraunic level.
towers on both sides would have very low could reasonably expect, considering that This is lower than the values sometimes sug-
footing resistance? Would this situation, insulator lengths only changed 20%, that gested by others. It was arrived at from
which may be encountered in the field, alter shielding failures included in the calculations our own field observations and those ob-
the results of the calculations on any way? are practically independent of small length tained from several other investigators. In
Would the authors care to comment on the changes; and that in this range, the only the program, this is an inserted parameter to
relative performance of a line with evenly strokes causing flashover are very-high- be changed as required by geographic condi-
graded footing resistance as compared with a amplitude strokes that have a relatively flat tions and storm paths. This stroke inci-
line where most of the footing resistances statistical distribution. dence is used in association with the Hagen-
have been reduced to some predetermined The authors agree with Mr. Stewart that a guth formula for strokes intercepted by
level, but where a limited number of struc- distributed counterpoise can sometimes lines. If the line had been in an isokeraunic
tures mnay have footing resistance greatly in offer a dramatic improvemnent in perform- level of 30, a value of 57 strokes would have
excess of this predetermined level? ance, provided midspan spacings are ade- been used, all other things being equal. It
quate. The New England Electric System should be emphasized that the number of
experience with counterpoise gives strong strokes to the line has little effect when con-
W. R. Johnson, D. D. Wilson, and J. G. evidence of this effectiveness. In fact, one sidered alone. It is how this value is used in
Anderson: The authors greatly appreciate of the purposes in showing the effects of dis- conjutnctionl with all the other parameters of
the contributions of the various discussers, tributions B and C was to emnphasize that the program, such as current-amplitude and
and are gratified to see the general interest one may gain very little in some cases by re- waveshape distributions, that establishes the
in the EHV transmission problems discussed ducing only the resistance of the highest filnal result One could very easily use dif-
in this and the two companion papers. footing-resistance towers. This should also ferent values for many of the parameters and
Messrs. Rudasill, Smith, and Wagner answer the last question of Messrs. Piper and arrive at a very similar answer-as indeed
have raised the question of assigning switch- Moran. was done by Messrs Clayton and Young.
ing-surge probabilities in these studies. The outage rates were calculated for foot- The "absent" insulator data mentioned
The switching-surge magnitudes reported ing-resistance distributions A, B, and C of by the above discussers are shown for V-
here were the maximum values for the par- Fig. 11 without regard to the means by strings in a companion paper (reference 1 of
ticular switching conditions in each in- which these resistance distributions might be the paper). It did not seem reasonable to
stance. Although switching-surge proba- obtained physically. Actual counterpoise present the same data in both papers.
ability studies, in which the characteristics of does not produce a time-invariant ground re- These data are critical-impulse flashover
air-blast circuit breakers were accurately sistance. The effects of extensive use of values and were used as the starting point
represented, have been done on the TNA, counterpoise can be evaluated by a modifica- for a postulated volt-time curve having the
maximum surges were of principal concern tion of transfer impedance curves in the same type of turn-up as those published
in this case. Since surge levels vary widely Monte Carlo routine. One does not nor- for 18-unit insulator strings. For these
between systems, it was not felt sufficiently mally make this modification unless exten- long strings, this was the best approach
accurate to apply the results of field tests on sive counterpoise usage is contemplated; available, since no laboratory data on volt-
one system to the design of another. In the otherwise it is approximated by a resistance, time curves of very long strings have been
past, excellent agreement has been shown as was done in distribution C of Fig. 11. published.
between field tests on actual systems and The discussion of Messrs. Clayton and The span lengths used were 1,000 feet.
TNA tests representing the same conditions. Young raises many points of interest. Dis- The letter A in Fig. 10 shows the voltages
580 Johnson, Wilson, Ander-sn-500-Kv-Line Design-I AUGUST 1 963
between shield wire and the nearest phase footing resistances for the stricken tower or Towers on each side of the stroke are as
conductor at the stricken point. Letter B span are chosen at random (just as a stroke sumed to have identical footing resistances,
designates the curves for the voltages pro- would do) from an arranged population of in order to simplify calculation. This would
duced across the outside insulator strings at footing resistances. This population is seem to be a valid assumption, and will not
the tower for this same midspan stroke. "biased" toward certain resistance values as greatly influence the results in practially
For the lightning-outage calculations, the demonstrated by the curves of Fig. 11. any case.

500-Kv-Line Design investigation are significantly different


from previously published results, and
this difference is attributed largely to the
effect of tower geometry. It would seem
II-Electrical Strength of Towers desirable, therefore, for engineers planning
extra-high voltage (EHV) systems to in-
vestigate the insulation strength of the
W. R. JOHNSON E. G. LAMBERT J. B. TICE particular tower geometries which they
FELLOW IEEE SENIOR MEMBER IEEE SENIOR MEMBER IEEE plan to use.
F. J. TURNER
SENIOR MEMBER IEEE The Test Tower
The miock-up of the tower on which the
Summary; The results of full-scale trans- companion papers.2 3 Accordingly, ex- first series of tests was performed, shown
mission-tower switching-surge, impulse, and tensive laboratory investigations were
60-cycle tests, wet and dry, indicate pro- in Fig. l, consisted of a truss made of steel
nounced departure from previously pub- begun in September 1961 on a full-scale channels supported 60 feet above the
lished data where the effect of the proximity mock-up of a transmission tower to estab- ground by two wood poles. Light metal
of the tower was not included. The data lish the number of insulators and clear- angles were used to frame the truss and to
include single-insulator strings, V-strings, ances necessary to meet the design re-
and lhorizontal and vertical tower gaps construct legs simulating the actual pro-
including guy-wire gaps. These data are quirements in the most economical posed guyed-tower design. The two
an extension of previous stu(lies on Project manner. Investigations were made to simulated line conductors were made of
EHV insulation structures' and were under- determine the effect of the geometry of
taken to provide design criteria for a 100- the tower on the electrical strength of
mile linik of 500-kv line running at an Paper 63-74, recommended by the AIEE Trans-
various gap and insulator configurations. mission and Distribution Committee and approved
average elevation of 5,000 feet between The effect of switching-surge waveshape by the AIEE Technical Operations Department for
Klamath Falls, Oreg., anid Round Moun- presentation at the IEEE Winter General Meeting,
tain, Calif. and the relationships of switching-surge New York, N. Y., January 27-February 1, 1963.
Manuscript submitted October 26, 1962; made
to impulse and 60-cycle strengths were available for printing December 5, 1962.
evaluated along with the atmospheric W. R. JOHNSON and E. G. LAMBERT are with the
A SIGNIFICANT extrapolation of correction factor for humidity. The Pacific Gas and Electric Company, San Francisco,
Aprevious experience and data would dry to wet strength ratio was determined
Calif.; J. B. TIcB is with the General Electric
Company, San Francisco, Calif.; and F. J. TURNER
be required to reach the 1,120-kv switch- for various waveshapes, both with and is with the General Electric Company, Pittsfield,
Mass.
ing-surge withstand level chosen on the without contamination of the insulators. The authors gratefully acknowledge the help of
basis of the model tests reported in The data obtained during this extensive the High Voltage Laboratory personnel in obtaining
the data presented here, and the many helpful
suggestions and criticisms by A. F. Rohlfs, J. G.
Anderson, and Project EHV personnel.

Fig. 2. General view of tower indoors being


Fig. 1. General view of tower showing supported by the crane in the High Voltage
measurement of rain on V-string Laboratory Fig. 3. General view of final tower outdoors
AUGUST 1963 Johnson, Lambert, Tice, Turner-500-Kv-Line Design-II 581

Você também pode gostar