Você está na página 1de 2

EMERITA DE GUZMAN v. ANTONIO TUMOLVA project within which to file claim.

Prayed for dismissal of action and


October 19, 2011 | Mendoza, J. | Temperate Damages interposed a counterclaim for actual and compensatory damages for
Digester: Roa, Annamhel Monique C. the additional work/change orders made, attorney’s fees and
litigation expenses.
SUMMARY: De Guzman entered into a Construction Agreement with respondent ● Construction Industry Arbitration Commission Arbitration – Awarded to de
company, with a certain plan and specifications for the perimeter fence. The Contractor, Guzman – 1) actual damages for reconstructing the fence (P187 509), interest on
however, made deviations from this plan. The fence collapsed during a typhoon. De the said amount at 6%/ annum and 12% thereon from finality of the judgment
Guzman sought to recover actual and compensatory damages, among others, for the herein, 3) moral damages (P100k), exemplary damages (P100k), and attorney’s fees
reconstruction of the fence. The Court found that she failed to adduce evidence to and expenses of litigation (P50k)
satisfactorily prove the amount of actual damage incurred and ruled that she was not ● CA - Modified, deleting award for actual, moral and exemplary damages, but
entitled to actual damages. The Court, however, awarded her temperate damages. awarding temperate damages in the amount of P100 K for reconstructing the fence.
DOCTRINE: When pecuniary loss has been suffered but the amount cannot, from the o Although the Contractor deviated from the plan, the award of actual
nature of the case, be proven with certainty, temperate damages may be recovered. damages was not proper inasmuch as De Guzman failed to establish
Temperate damages may be allowed in cases where from the nature of the case, definite its extent with reasonable certainty.
proof of pecuniary loss cannot be adduced, although the court is convinced that the o Temperate damages, however, are appropriate considering that De
aggrieved party suffered some pecuniary loss. Guzman suffered pecuniary loss as a result of the collapse of the
fence due to the Contractor’s negligence and violation of his
FACTS: undertakings in the Agreement.
● De Guzman, represented by attorneys-in-fact, entered into a Construction o Award for exemplary damages cannot be sustained absent showing
Agreement with A. M. Tumolva Engineering Works for the construction of an that Contractor acted in wanton, reckless, fraudulent, oppressive or
orphanage. Incorporated in the Agreement was the plan and specifications for the malevolent manner.
perimeter fence. The Contractor, however, made deviations from the agreed plan MFR by De Guzman denied.
with respect to the perimeter fence.
● Sept 2005 – After the project’s completion, De Guzman issued a Certificate of RULING: WHEREFORE, the petition is denied. The Decision of the Court of
Acceptance. Contractor issued a quitclaim acknowledging the termination of the Appeals dated February 24, 2009 and its Resolution dated May 26, 2009 are
contract and the full compliance therewith by De Guzman. AFFIRMED with the MODIFICATION that the award of P100, 000.00 as temperate
● Nov 2006 – A portion of the perimeter fence collapsed during typhoon Milenyo, damages is increased to P150, 000.00. The award shall earn interest at the rate of 12%
with other portions tilting. De Guzman, sent a letter to the Contractor demanding per annum reckoned from the finality of this judgment until fully paid. SO ORDERED.
the repair of the fence in accordance with the plan. Contractor claimed the
destruction was an act of God and expressed willingness to discuss the matter to Whether De Guzman is entitled to actual damages – NO.
avoid litigation. De Guzman, however, reiterated her demands for the restoration ● There is no doubt that De Guzman incurred damages as a result of the collapse of
of the wall w/o additional cost on her part OR in the alternative, for the the perimeter fence. The Contractor is guilty of negligence and is therefore liable
Contractor to make an offer of a certain amount by way of compensation for the for the damages caused. These are factual findings of the TC affirmed by the CA
damages sustained. This was also unheeded. and are generally accorded not only respect, but also finality.
● Construction Industry Arbitration Commission (CIAC) Arbitration – ● Award of actual damages by CIAC, however, is not proper under the circumstances
o De Guzman: Alleged the Contractor deliberately defrauded her by as there is no concrete evidence to support the plea. In determining actual damages,
undersizing the required column rebars of the fence. Contractor also one cannot rely on mere assertions, speculations, conjectures or guesswork, but
failed to anchor the beams, and place drains and weepholes along the must depend on competent proof and on the best evidence obtainable regarding
lower walls. Prayed for actual, moral and exemplary damages, as well specific facts that could afford some basis for measuring compensatory or actual
as attorney’s fees and expenses of litigation, among others. damages. SEE Art. 2199 of the NCC.
o Contractor: Denied liability for the damaged fence, claiming it was an ● De Guzman failed to adduce evidence to satisfactorily prove the amount of actual
act of God. Though he admits making deviations from the plan, he damage incurred. The handwritten calculation of reconstruction costs made by
says that they were made with the knowledge and consent of De Engr. Santos and attached to his affidavit cannot be given any probative value
Guzman through her representative, Architect Baterna and Project because he never took the witness stand to affirm the veracity of his allegations in
Engr. Santos. Also, the claim for damages was barred by the 12-mo his affidavit and be cross-examined on them. Neither is there any evidence
period from the issuance of the Certificate of Acceptance of the presented to substantiate Engr. Santos’s computation of the reconstruction costs.
● De Guzman is, nevertheless, entitled to temperate damages as provided compensation, were not heeded by the Contractor. The latter’s unjust refusal to
under Art. 2224 of the NCC for the loss she suffered. When pecuniary loss satisfy De Guzman’s valid, just and demandable claim constrained her to litigate
has been suffered but the amount cannot, from the nature of the case, be and incur expenses to protect her interest. SEE Art. 2208 (2) of the NCC.
proven with certainty, temperate damages may be recovered. Temperate
damages may be allowed in cases where from the nature of the case, definite
proof of pecuniary loss cannot be adduced, although the court is convinced
that the aggrieved party suffered some pecuniary loss.
● As De Guzman failed to prove the exact amount of damage with certainty as
required by law, the CA was correct in awarding temperate damages, in lieu of
actual damages. But, after weighing carefully the attendant circumstances and taking
into account the cost of rebuilding the damaged portions of the perimeter fence,
the amount of P 100K should be increased to P 150K.

Whether De Guzman is entitled to the other damages initially awarded by the


TC – NO.
● As to moral damages –
o Record is bereft of any proof that she actually suffered moral
damages as contemplated in Art. 2217 of the Code. Her testimony
did not provide specific details of the suffering she allegedly went
through after the fence collapsed while she was miles away in the US.
As the CA aptly, observed, “the testimony… as to her worry for the
safety of the children in the orphanage is insufficient to establish
entitlement thereto.”
o It was not clearly established that the destruction was the proximate
result of the Contractor’s act of making deviations from the plan, as it
collapsed in the midst of typhoon Milenyo.
o De Guzman was not able to show that her situation fell within any of
the cases enumerated in Art. 2219 of the NCC.
o Neither does the breach of contract committed by the Contractor,
not being fraudulent or made in bad faith, warrant the grant of moral
damages. SEE Art. 2220.
● As to exemplary damages –
o De Guzman cannot be awarded exemplary damages in the absence of
any evidence showing that the Contractor acted in a wanton,
fraudulent, reckless, oppressive, or malevolent manner as provided in
Art. 2232.
o The award cannot be made merely on the allegation of De Guzman
that the Contractor’s deviations from the plans and specifications
without her written consent was deplorable and condemnable. The
Court regards the deviations as excusable due to the unavailability of
the approved construction materials.

Whether De Guzman is entitled to attorney’s fees – YES.


● De Guzman is entitled, although the Court recognizes that it is a sound policy not
to set a premium on the right to litigate. It must be recalled that De Guzman’s
repeated demands for the repair of the fence or the payment of damages by way of

Você também pode gostar