Usually an Initial Reservoir Filling Plan (IRFP) is developed and approved by the appropriate
regulatory agency. The IRFP includes a detailed plan os instrumentation and monitoring and an
EAP. The IRFP will set the rate of reservoir rise, including temporary holding elevations to permit
evaluation of instrumentation data, the behavior of the dam, and reservoir rim conditions.
Because many of the monitoring instruments are first operated during initial filling, it is important
to evaluate each instrument even if data appear satisfactory. For example, a piezometer in an
upstream shell should be expected to respond rapidly to reservoir levels above the piezometer tip.
A slow response or no response would suggest a defective piezometer possibly requiring
replacement.
First filling of a reservoir is the first indication that the dam is safe and will function as designed.
Therefore, first filling of a reservoir should be carefully planned and implemented to ensure safety
of the dam and future success of the dam. USBR & USACE (2012) studies indicate that
approximately two-thirds of all failures and one-half of all dam incidents occur on first filling or in
the first 5 years of reservoir operation. Thus, it is vital for dam operators and engineers to have as
much control over the first filling as possible allowing as much time as needed for appropriate
surveillance, including observation and analysis of instrumentation data. Depending on the
location, type, size, and intended purpose of a dam, the duration and rate of its first filling can
vary.
SEGUIMIENTO DEL PRIMER LLENADO Y REDACCIÓN DEL PLAN DE PUESTA EN
MARCHA
DESCRIPCIÓN
El Reglamento Técnico sobre Seguridad de Presas y Embalses,
aprobado por Orden del Ministerio de Obras Públicas,
Transportes y Medio Ambiente, de 12 de marzo de 1996, indica
en su artículo 24 que entre las fases que se diferencian en el
desarrollo y utilización de las presas y los embalses se incluye la
fase de Puesta en Carga. En el artículo 28 se recoge la
obligatoriedad de que esta puesta en carga sea llevada a cabo
por un equipo técnico dirigido por un técnico competente, que
además se encargará de redactar una Memoria del desarrollo
de esta fase, que se deberá incorporar al Archivo Técnico de la
presa. De forma inevitable, un primer llenado está conectado
con el Plan de Emergencia, que deberá estar implantado
previamente, pudiendo ser necesario declarar un determinado
escenario de emergencia en caso de sobrepasarse los umbrales
establecidos o cuando el Director del Plan lo considere preciso.
ATI ofrece un servicio de seguimiento del primer llenado del
embalse, también de redacción del Plan de Puesta en Carga,
basado en una amplia experiencia en los últimos años (presas
de varios tipos como El Castro de las Cogotas, El Pontón Alto,
José Torán, La Llosa del Cavall, Monreal, Villaveta, Artajona,
Yalde, Ibiur e Irueña), disponiendo cuantos recursos técnicos y
humanos resultan necesarios.
La puesta en carga de una presa constituye una fase de importancia trascendental, posiblemente sea la obra de ingeniería civil
cuya entrada en explotación, en especial por sus implicaciones geológicas y geotécnicas, presente mayores incertidumbres.
Por otro lado, el comportamiento durante la puesta en carga de otras estructuras puede ser analizado y comprobado, en
general, sin riesgos asociados; éste no es el caso de una presa, donde el mantenimiento de la velocidad de ascenso del nivel
del embalse puede ser problemático. El ingeniero responsable del primer llenado debe contar con un adecuado equipo técnico
para analizar la información recogida de las necesarias inspecciones visuales, así como aquella aportada por el sistema de
auscultación. Tal asistencia debe estar disponible, y con adecuada capacidad de respuesta, en el final de cada fase en
condiciones normales que se hayan podido establecer en el Plan de Puesta en Carga, emitiendo aquellos informes de
comportamiento con recomendaciones para el seguimiento del llenado, en períodos semanales en llenados muy rápidos o en
períodos más largos en condiciones de llenado lento o muy poca carga sobre la presa. En condiciones de avenida puede ser
necesario emitir informes, incluso verbales, en períodos más cortos. El seguimiento de los datos de auscultación principales
resulta conveniente efectuarlo semanalmente o con mayor frecuencia en situación de alerta. De forma esquemática, los
trabajos que conlleva el seguimiento del primer llenado pueden resumirse de la siguiente manera:
La directriz básica de planificación de protección civil frente al riesgo de inundaciones, establece la obligatoriedad por parte de
los titulares de las presas de las categorías A y B a elaborar e implantar ejecutar un plan de emergencia para activarlo en caso
de peligro y así avisar a la población.
En presas de nueva construcción, todo ello debe estar instalado y funcionando antes de poder realizar el primer llenado.
SEGUIMIENTO DURANTE LA CONSTRUCCIÓN
DESCRIPCIÓN
Una presa a lo largo de su vida útil pasa por varias fases
interrelacionadas entre sí: proyecto, construcción, primera
puesta en carga, explotación y puesta fuera de servicio. Durante
los trabajos de construcción (excavación, levantamiento de la
estructura de cierre, tratamientos del cimiento, etc.), es
precisamente donde mayores repercusiones pueden tener
determinadas circunstancias sobre la calidad de la obra, que
bajo las particulares características de la ubicación geográfica,
geología y geotecnia del terreno subyacente, se verán reflejadas
en mayor o menor medida posteriormente durante la primera
puesta en carga y, sobre todo, durante la explotación de la
infraestructura.
Por las anteriores circunstancias cabe indicar que resulta de
vital importancia para las condiciones en que prestará servicio
la presa que, con independencia de su tipología, se efectúe un
adecuado seguimiento del comportamiento de estructura de
cierre y su cimiento durante la construcción, por tratarse ésta
de la fase crítica para el futuro de la obra. ATI ofrece un servicio
de seguimiento del comportamiento basado principalmente en
los registros obtenidos a partir del sistema de auscultación, que
podrán apoyarse también en las inspecciones visuales y
determinados ensayos sobre materiales en caso necesario. No
en vano, en los últimos años el equipo técnico de ATI viene
efectuando el seguimiento durante la construcción de presas de
distinta tipología: gravedad, arco, materiales sueltos, etc.
En un seguimiento típico de la construcción de una presa se analizan los registros de auscultación que se van obteniendo, de
forma manual o con unidades provisionales automatizadas, redactando los informes de comportamiento correspondientes,
con una periodicidad que dependerá de los requerimientos de la Dirección de los trabajos y de las particulares características
de la obra. Con este seguimiento se pretende controlar, por ejemplo, en presas de fábrica la retracción y la efectividad del
curado del hormigón, así como su estado térmico; por su parte, en presas de materiales sueltos, la evolución de los asientos
producidos por niveles, la disipación de presiones intersticiales en el núcleo (caso de disponer) y porcentaje de carga que van
adquiriendo determinadas zonas del cuerpo de presa con el tiempo. El control de éstos y otros parámetros podrá optimizar los
trabajos de construcción, corrigiendo determinadas condiciones de puesta en obra que pudieran haberse considerado como
óptimas, pero que en la práctica no lo son tanto. El objetivo final es obtener una infraestructura de calidad, detectando en una
temprana edad circunstancias anómalas que puedan tener repercusiones negativas durante la explotación, corrigiéndolas
durante el proceso constructivo.
USACE-EM 1110-2-2300
9-9. Initial Reservoir Filling a. General. The initial reservoir filling is defined as a deliberate
impoundment to meet project purposes and is a continuing process as successively higher pools
are attained for flood control projects. The initial reservoir filling is the first test of the dam to
perform the function for which it was designed. In order to monitor this performance, the rate of
filling should be controlled to the extent feasible, to allow as much time as needed for a
predetermined surveillance program including the observation and analysis of instrumentation
data (Duscha and Jansen 1988). A design memorandum (DM) on initial reservoir filling is required
for all new reservoir projects.1 b. Design memorandum. As a minimum, the DM on initial reservoir
filling will include the following (EM 1110-2-3600): (1) Reservoir regulations during project
construction stage(s). (2) Water control plan. 1 Additional information is given in ETL 1110-2-231.
EM 1110-2-2300 30 Jul 04 9-6 (3) Project surveillance. (4) Cultural site surveillance. (5) Flood
emergency plan. (6) Public affairs. (7) Safety plan. (8) Transportation and communications.
First Filling The first filling of a dam is a critical period during which special procedures are adopted
to ensure dam safety. A survey by ICOLD3 reported that of 167 dam failures investigated, 35
occurred during first filling. One example of such a special procedure is that, it is desirable to fill
the dam slowly. These procedures cannot be compromised by the need to bring the dam into
effective operation as rapidly as possible for financial reasons. It is good practice (and required by
SA dam safety regulations) for the operating procedures manual to have been completed before
first filling commences. These are supplemented by special arrangements during first filling. During
the initial phases of filling the emergency plans are usually invoked to the status of an alert.
MANUAL DE MONITOREO
Antes del incio del llenado del embalse, será preparado por el Proyectista un “Manual d3e
supervisión y monitoreo de las estructuras civiles” a fin de establecer los procedimientos básicos
wue deben seguirse en la supervisión de condiciones de seguridad de la obra principal y conexas,
su fundación, en las fases de llenado del embalse y operación.
Presentación de Resultados
Las lecturas de los distintos instrumentos de observación de una presa, luego de ser procesados y
representados en tablas y gráficos deben consolidarse en un informe completo de los datos, cuya
frecuencia de emisión puede ser de la siguiente manera:
1. Red Sismologica
2. Estaciones meteorológicas compactas
3. Piezometros: tipo Casagrande y eléctricos
4. Celdas de presión y área de registro
5. Instrumentación de edición de temperatura del concreto
6. Medidor de filtraciones, Parshall
7. Medidor de deformación tridimensional
Magnitudes a medir
1. Hidráulicas
Filtraciones en galerías
Filtraciones aguas debajo de la presa
Subpresiones y niveles piezométricos
2. Deformacionales (estructura y cimiento)
Desplazamientos absolutos horizontales y verticales
Desplazamientos relativos
o Entre bloques
o Entre cuerpo de presa y cimientos
o Entre elementos singulare (zonas de fallas)
Movimientos en juntas y fisuras
Giros
Movimientos y deformaciones en fallas y accidentes geológicos
Deformaciones en el hormigón
3. Térmicas
Temperaturas internas del hormigón
Temperaturas en los parámetros de la presa (aguas arriba y aguas abajo)
4. Tensionales
Tensiones en la estructura y esfuerzos transmitidos a los cimientos
5. Volumétricas
Cambios volumétricos del hormigón (expansión y retracción)
6. Dinámicos
Aceleraciones
Desplazamientos
Frecuencia de medidas y observaciones
1er llenado
Explotación
Puesta fuera de servicio
El Vigilante de presas
Es la persona encargada de realizar los recorridos, medidas y observaciones de forma periódica y
regular siguiendo el plan de Auscultación y Vigilancia incluido en las normas de Explotación de la
presa.
Es la persona encargada del mantenimiento básico que requiere los dispositivos auscultación así
como conservar en buen estado los equipos de lectura.
Nadie conoce mejor la presa que el Vigilante que lleva años realizando las labores de auscultación.
El conocimiento de la presa
Consistencia en la metodología de lectura y por tanto en los datos obtenidos.
Archivo Técnico:
Plan de Emergencia
Plan de Auscultación
Control de Sedimentos:
Seguridad Estructural
Para iniciar la operación comercial de la central se prevé tomar algunas acciones previas,
que permitirán una generación continua y libre de tropiezos posteriores. Las principales
acciones se indican a continuación.
Para la limpieza del embalse se utilizara maquinaria apropiada que pueda retirar y acopiar
la vegetación arbustiva. La madera utilizable para construcción o muebles será separada
para su comercialización. El resto del material deberá enterrarse en zanjas excavadas en el
sitio, luego cubiertas con una capa de suelo de 0.50m, compactando con una pasada de
tractor.
Este material al descomponerse no afectara a la calidad del agua debido a que los
sedimentos finos que caen en el embalse impermeabilizaran las zonas de entierro, no
permitiendo la salida de los contaminantes orgánicos.
Primer Llenado
El primer llenado del embalse es una de las tareas importantes del proyecto, ya que para
eel mismo ocurren una serie de acciones que deben ser cuidadosamente coordinadas para
poder dar seguimiento a los diferentes elementos que intervienen en la operación. Entre
estos se pueden señalar los caudales de aporte, la apertura de las compuertas, la
velocidad de llenado y la calibración de los equipos de control, entre otros.
En principio, la mejor época del primer llenado seria durante la estación seca, ya que los
caudales son bajos y la velocidad de llenado es fácilmente controlable por medio del
desagüe de fondo. Previo al primer llenado, debe haberse realizado la limpieza del
material vegetal del vaso del embalse y se asume que las condiciones sociales derivadas
del proceso de expropiación y reasentamiento, al igual que las compensaciones e
indemnizaciones asociadas hayan sido totalmente superadas.
Los instrumentos de control de la presa deben estar calibrados para tomar las mediciones
de partida. Esos valores servirán como línea de base para comparar con los valores que se
vayan midiendo durante el llenado. Durante el primer llenado, los registros de plomadas,
piezómetros y caudales escurridos se tomaran cada dos horas para luego establecer una
rutina de control apropiada.
Previo al primer llenado las compuertas del desagüe de fondo deberán ser revisadas en
sus aspectos mecánicos, sus sellos y sus sistemas de izamiento, de manera que una vez
que se deslicen para iniciar el llenado del vaso no se tengan dificultades de última hora.
B) Operación y Mantenimiento
La Operación y Mantenimiento (O&M) del proyecto será realizada por personal permanente
SISTEMA DE MONITOREO
MONITOREO DE LA PRESA
Se debera de medirse:
Temperaturas
Subpresiones
Caudales
Desplazamientos
Puntas Vinchon
Acelerógrafos
The initial reservoir filling is defined as a delibérate impoundment to meet project purposes and is
a continuing process as successively higher pools are attained for flood control projects. The initial
reservoir filling is the first test of the dam to perform the function for which it was designed. In
order to monitor this performance, the rate of filling should be controlles to the extent feasible to
allow as much time as needed for a predetermined surveillance program including the observation
and analysis of instrumentation data. Information furnished in the filling plan should generally be
concerned with actions that can be taken without a significant impact on project purposes,
provided no unsafe conditions are observed. The filling plan should be prepared by the
Engineering Division in cooperation with the Construction and Operations Division.
ACTION
a. A design memorandum which outlines an initial reservoir filling plan will be prepared for
all new Corps reservoir projects prior to the initiation of reservoir filling for operational
purposes. The revised ER includes the requirements for preparing the Design
Memorandum. The design memorandum should be prepared after all pertinent
hydrologic, hydraulic, structural and geotechnical information has been developed during
design and construction.
b. Existing projects that the operational, where the maximum pool has not been
experienced, should be reviewed and the O&M manual modified, if necessary, to include
the information delineated in paragraph 6.
DESIGN MEMORANDUM CONTENT. The design memorandum should include but not be limited to
the following:
a. Preferred filling rate and the available options to control the rate of filling as well as the
consequences of operation with prime objective of controlling the rate of reservoir rise.
b. The most likely type of problem that might develop during initial filling and the
survilleillance necessary to detect those problems.
c. A plan for reading the instruments and evaluating the data with regard to the filling plan.
d. A plan for inspecting the dam and downstream areas prior to and during filling, including
the relationship between frequency of inspection and rate of pool rise.
e. Instructions for observers on conditions that require inmediate attention of personnel
authorized to make emergency decisions. Clearly identify who is responsible for decisions
and how they can be contacted. Alternate decision makers should also be identified.
f. An emergency plan listing responsabilities, name and/or positions, telephone numbers
and radio frequencies to be used. (See ER 1130-2-419)
The Manual needs to be prepared primarily for the dam operations staff and their supervisors
who are assigned the responsibility for the physical operations and maintenance of the dam. It
should contain, as a minimum, all information and instructions necessary for them to perform
their allotted tasks. In addition to instructions for dam operations staff, the Manual should also
include all necessary instructions for other staff directly or indirectly involved in operating and
maintaining the dam.
In general, it is a global practice that the O&M Manual is available prior to the initial filling of
the reservoir.
The following basic data in addition to the salient features & basic drawings mentioned in
chapter 1 will need to be enclosed under this chapter of O& M Manual:
Area – Capacity curves.
Data of the historic floods.
Latest design flood and flood routing study.
Sequence of operation of spillway gates during monsoon.
Discharge through spillway for different reservoir levels with different gate openings.
Where more than one spillway exist, the sequence of operation of spillways need to be
included
Operating procedures are to be developed for both normal operations and emergency
operations.
In addition to dam failure, it is common for design, construction, and/or material deficiencies
of a new dam to become apparent during the first filling. For example, evidence of seepage,
cracking, and erosion are often noted when the reservoir is raised to new levels for the first
time. Inspection and assessment of these potentially hazardous conditions prior to the
completion of filling is important and it may be necessary to halt filling or in some cases lower
the reservoir before the desired operating water level is achieved to investigate signs of
seepage, cracking and erosion. Repairs to any project features that did not function as designed
can be re-evaluated and modified to ensure the dam operates according to its original design.
All the water release facilities including gated spillways, outlet works, sluices etc. are to be used
for control of reservoir levels during initial filling. The O&M Manual should be available
before initial filling of the reservoir.
The initial filling criteria for the reservoir shall be available in a separate supporting document
which shall be referenced in the O&M Manual. Before initial filling of the reservoir is taken up,
the State Dam Safety Organization shall arrange for safety inspection of the dam either
through its own engineers or by an independent panel of experts, who shall also examine the
initial filling program and prepare a detailed report in respect thereof.
Reservoir filling schedule is governed by the Indian Standard, IS: 15472 - Guidelines for
planning and design of low level outlets for evacuating storage reservoirs in which the
Guidelines regarding initial filling of reservoirs have been described. It stipulates that the filling
rates for concrete/masonry dams are much less restrictive than for embankment dams and
specify a general initial filling program in respect of embankment dams, which can be suitably
modified as necessary, as under:
a) The first stage consists of filling the reservoir up to MDDL. This filling can be done without
restraint as the hazard potential to the public and economic development downstream of the
dam is low.
b) The second stage consists of filling the reservoir from MDDL to the crest of spillway. For
earth and rock fill dams this stage filling should be done in two parts.
The reservoir above MDDL should be gradually built at a rate not exceeding 3 m per fortnight
and filling should be temporarily stopped at half the height between MDDL and crest of
spillway, for a reasonable time in order to assess the behavior of the structure on the basis of
observed values and to take a decision about further storage and remedial measures in case of
distress.
After a decision is taken to continue the filling, further building up of the storage should be
done in gradual sub-stages of 2 to 3 m per fortnight depending upon the height of the dam
and increase in storage capacity. The reservoir should then be temporarily held at the crest
level of the spillway for a reasonable time for monitoring and evaluating the performance of
the dam and to take a decision about further storage.
c) The third stage consists of filling above the crest of the spillway up to the full reservoir level
(FRL). The rate of reservoir filling above crest of spillway should be restricted to substages of
0.3 m in 48 h. The reservoir should be temporarily held at half the height between FRL and
crest of spillway for sufficient time for monitoring and evaluating performance of dam and to
take a decision about further storage/remedial measures, if
any.
Central Water Commission (CWC) vide letter no.L25/86-DSS/509 dated 13th May
1986 has stipulated reservoir filling schedule in respect of Concrete Dams as under:
The first stage consists of filling the reservoir up to Minimum Draw down Level (MDDL).
This filling can be done without restraint.
The second stage consists of filling the reservoir from MDDL to the crest of spillway. The
reservoir above MDDL should be gradually built up at a rate not exceeding 3 meters per
fortnight depending upon the height of the dam and held at the level of crest of spillway in
order to assess the behavior of the structure on the, basis of observed data and to take a
decision about further storage.
The third stage consists of filling above the crest of the spillway and up to full reservoir level
(FRL). Above the crest level of spillway the building up of water level till FRL should be
restricted to 0.3 meter (1 ft.) in 48 hours and the same should be temporarily held at half the
height between the crest of spillway and FRL to monitor and assess the behavior of structure
before further filling resumed. The period for which the reservoir is held at this level will
depend on the instrument response time.
The frequency of each type of inspection will depend on the hazard classification of the dam,
the condition of the dam, the CDSO regulations etc.
ii) Establishment Cost of Work charged Staff - Salaries and allowances, Bonus,
Medical Reimbursement, LTC, Leave Encashment, Pension benefits, TA and DA, etc. (as
applicable).
iii) Establishment Cost of Daily wage Staff - Salaries and allowances, TA and
DA etc. (as applicable).
v) Motor Vehicles - Running and Maintenance cost of inspection vehicles, Cost of hiring
of vehicles as required
vii) T&P - T&P requirements for offices, colony, works etc. as applicable.
4.8 O&M cost for dams where owner and operator is different
It has been seen that there are many Hydro- Electric Projects in our country which are under
the control of State Electricity Boards and the O&M of their dams and appurtenant works is
with the State Water Resources Departments. Very often the O&M of such dams gets
neglected due to non-availability of sufficient funds. As such, it is recommended that in such
cases the State Electricity Boards should provide for the O&M cost of their dams and
appurtenant works in their annual budget (based on the cost estimates obtained from relevant
Water Resources Departments) and transfer the said amount to the Water Resources
Departments for the O&M of the dams and appurtenant works.
In cases where the State Electricity Boards are paying levy or water charges to the Water
Resources Departments, the same should be utilized for the O&M of the dam.
Note: the setup up shown is only indicative and can be modified as per actual requirements in
a project.
Figure 4-1: Typical Organisation Setup Chart
Table 4-1: Maintenance Guidelines Summary
(Insertar Tabla)
Limpieza del terreno. Debe considerarse que la vegetación existente en el valle que ha de ser inundado morirá, se descompondrá y por lo tanto
generará una demanda bioquímica de oxigeno muy elevada, lo que podría perjudicar la calidad del agua del embase por varios años. Ante esto, la mejor
solución es limpiar lo mejor posible de vegetación el valle que ha de ser inundado.
Una forma de hacerlo es organizando a la población local para que retire el todo el material vegetal posible, eventualmente mediante la concesión de un
pequeño incentivo, y la autorización de utilizar libremente el material retirado.
Si la población local es escasa, este servicio deberá ser contratado, y debe formar parte de los costos de implementación del embalse.
Retiro de material de interés. Esta actividad puede requerir una preparación de varios meses y hasta años, por lo tanto debe iniciarse oportunamente
para que el llenado del embalse no se vea retrasado por esta actividad. Especial cuidado deberá ser dado a la existencia de sitios de interés afectivo
para la población desplazada, como pueden ser cementerios, capillas, lugares de reunión, etc. los que deberían ser recreados en forma semejante en
los locales de nuevos asentamientos.
Caudal ecológico. Se define como caudal ecológico: El agua necesaria para preservar valores ecológicos como;
La determinación del caudal ecológico de un río o arroyo se hace con base en un cuidadoso análisis de las necesidades mínimas de los ecosistemas
existentes en el área de influencia de la estructura hidráulica que en alguna forma modifica el caudal natural del río o arroyo.
En el momento del cierre del desvío provisional del río, el flujo aguas debajo de la presa debe mantenerse, garantizando el caudal ecológico durante
todo el periodo de llenado del embalse que puede durar varios meses. La forma de garantizar este caudal mínimo varía de caso a caso, y debe ser
previsto en el diseño de la presa.
Salvamento de animales. Durante la fase del llenado se irán formando islas, las que se achicarán en la medida que el nivel se eleva. Deben preverse
brigadas de rescates de animales domésticos y salvajes, como víboras, culebras, arañas, etc.
Llenado del embalse
1. Perdida de vegetación
Promoción de la extracción de los productos forestales existentes en la zona del embalse.
Se tratará de que esta extracción sea intensiva y que incluya quellos recursos que originen
beneficios a los poseedores y propietarios de la tierra: madera, postes, punales, riostras,
horcones, entre otros.
Promover la coordinación con entidades federales o estatales encargadas del manejo de
los recursos forestales para que se implementen programas de aprovechamiento.
Promover el uso del suelo en el área del embalse entre las cotas del NAMO y del NAME,
en actividades agropecuarios hasta un año antes de que se inicie el llenado del mismo, ello
en coordinación con las entidades federales o estatales responsables del sector.
Establecer una vigilancia a lo largo del embalse a fin de identificar, en su caso, la presencia
de malezas acuáticas. De ser detectadas, se realizarán las inspecciones necesarias para
determinar el origen o fuente de las malezas y a partir de estas definir los puntos de
control y acciones complementarias para evitar la infestación del embalse. Durante este
periodo el control de lo que se identifique será mecánico, mediante retenidas, y su retiro
de la superficie. Asimismo, el material retirado será dispuesto en sitios donde no
represente problemas a la actividad ganadera y que no vuelvan a ser reincorporados al
embalse por las fluctuaciones del mismo.
Filtraciones de agua por debajo de la presa, con arrastre de suelo, o a través de grietas en los
apoyos.Sifonamiento.- consiste en lo siguiente: en una presa apoyada sobre terreno permeable, al
aumentar lacarga de agua, ésta, en su paso por debajo de la presa puede adquirir velocidad de
erosión del terreno.Empieza por arrastrar el material tenue, aumentando el tamaño de los huecos.
Con la disminución de laresistencia que determina menor pérdida de carga y aumento de la
sección de paso, crece la velocidad y elpoder erosivo, y van siendo arrastrados elementos mas
gruesos. Se forman cavernas bajo la presa, aumentael arrastre y llega a determinarse un paso de
agua que lleva consigo el material suelto subyacente de lapresa, causando la rotura de ésta o la
formación de un boquete en su parte inferior, quedando la superior amodo de puente.
Por insuficiencia de perfil.- Cuando la línea de saturación corta al paramento aguas abajo, el flujo
sobre elparamento puede erosionar el suelo e iniciar el proceso de rotura de la presa. También
por la falta de pesoque actúa sobre la base de apoyo puede ocasionar que sea escaso el
rozamiento entre estructura y suelo yse origine el desplazamiento.
Por desintegración del hormigón. - Puede ser por efecto de intensas variaciones de temperatura
que seproduzcan grietas. Por ellas penetra el agua, que al solidificarse aumenta de volumen y
desintegra elhormigón. Por más impermeable que sea, siempre absorbe agua por capilaridad. Por
efectos decompuestos químicos disueltos en el agua.