Você está na página 1de 8

Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities

Submission 70
1

Obstacles and opportunities for


effective life-of-mine implementation

aBsTracT
red dome mine was a highly complex gold copper operation developed over a number of phases between mid-1986 and october 1997. it operated with only
three years of production ahead at one time and therefore required a proactive practical approach to mine closure. in 1989 the domains concept approach
to life-of-mine planning and mine closure was created as a proactive response to the proposed changes to Queensland legislation. The domains concept
aimed to integrate mine closure during production at red dome. The concept provides a straightforward approach to mine closure, simplifying the usual
complexities and optimising cost-effective, whole-of-mine, life cycle planning. in the subsequent 20-year period the concept has been misunderstood and
poorly implemented to a large extent. as a consequence, opportunities in using the domains concept have been missed.
The process produces a meaningful and operationally practical document, with clear objectives, and a rationale for achieving measurable rehabilitation
and closure outcomes. With proposed activities clearly defined within a landscape context and within landscape units, there is a much better understanding
of why a particular final landform/use has been nominated. This information provides a construction roadmap for personnel and better transparency of
intentions for the community. By using this approach, there is potential to significantly mitigate legacy issues as well as maintain compliance.
This paper, originally presented at life-of-mine 2014 in Brisbane, re-examines the many advantages and applications of the domains concept as a
management tool. it uses focused landscape investigation techniques to underpin life-of-mine planning decisions and maximise closure outcomes. The
paper also examines the role of current financial modelling and project viability assessment in creating post-closure liabilities and long-term mining
legacies. The use of net present value and deferred costs in financial models are considered an inadequate method of assessing true project viability as the
available analytical tools do not include sufficiently detailed life-of-mine development and closure costs.
The engineering and financial processes used at feasibility have overlooked the scientific appraisal of landscape constraints, and limited the placement of basic
and progressively required infrastructure to maximise closure outcomes. Furthermore, because financial models never include detailed provision for progressive
and well-managed rehabilitation and closure, there is rarely sufficient finance to undertake such works. Therefore, this paper proposes a new approach, including
the concept ‘starting with the end in mind’, which could be used to address the challenge of assessing the true value of a rehabilitated site.

hisTorical conTeXT 1989 the Red Dome mine implemented a detailed life-of-mine
(LOM) decommissioning plan, the Red Dome LOM plan, using
Twenty-five years ago the original Domains mine closure concept this spatially explicit approach.
(the Domains Concept) was developed at Red Dome Gold Mine in
north Queensland (Figure 1). This operationally focused rather than approvals-focused plan
became the primary reference document for all progressive
Red Dome was a complex gold and copper operation developed rehabilitation activities and was accepted by the site management
over a number of phases during its 11-year operation. The deposit team. The plan provided the main vehicle through which to
was characterised as a porphyry gold copper type and contained
understand, agree on, implement and manage objectives and
significant polymetallic base-metal mineralisation, notably lead
costs of mine closure as part of everyday production activities. As
and zinc. Fully operational from 1986 to 1997, it processed gold
time progressed, the clear and systematic focus on post-mining
and copper ores using a combination of heap leach, flotation and
outcomes built transparency, credibility and trust with regulators
carbon-in-leach production techniques, singly and in various
and the community.
combinations. At the time, its open pit was the deepest and steepest
excavated in Australia (320 m deep) and abutted the Piano Caves
National Park. At any point in time the mine had a life expectancy The domains concepT
of only three years or less, which created a degree of urgency with Domains are defined as ‘contiguous spatial units within a
respect to rehabilitation planning and implementation. landscape (subcatchment) with similar challenges to eventual
The technical basis of the early versions of decommissioning closure’. These units segregate the mine site into operational,
plans were usually written from a particular technical physical and related components, enabling a suite of individual
specialist’s perspective – for example, a water engineer using a plans to be developed. Applying the Domains Concept is
water management template. The Domains Concept came about fundamentally different from engineering approaches because
as a common-sense multidisciplinary approach to developing it assesses the inherent opportunities, threats, flaws and
a decommissioning plan based on the specific activities weaknesses of the landscape prior to making decisions on where
located or proposed to be located within the landscape. In to place infrastructure within subcatchments.
its most simple form, the concept divides the mine into a
In its first application at Red Dome, each domain unit had its
suite of interlocking mutually exclusive but spatially related
own individual plan with a clear site description of the landform,
subcatchment components, each with its own rationale,
topography, underlying stratigraphy and structure, material
objectives, detailed execution plan and cost estimates. From
characteristics, drainage, soils, operational and closure objectives,
discussion of likely operational constraints and a rationale, as well
as the basic assumptions for undertaking the work. This enabled a
detailed suite of defined tasks to be developed for which realistic
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
2 From start to finish: a life-of-mine perspective

FIG 1 – Red Dome project location.

costs and resources could be assigned and scheduled for the potential issues concerning geological structure and stratigraphy,
implementation of works as necessary. contaminant exposure pathways and/or geotechnical failure
The process provided a corporate vision of closure for the risks. Furthermore, when landscape investigation is coupled
management team within the business plan. The format of with geochemical assessment and risk reduction controls of
the document was modular and easily adapted to changing overburden, useful specifications can be built into constructed
production scenarios – one domain, one subplan – reducing landform design. In turn, these can guide production activities to
the mine closure ‘elephant’ to a series of manageable pieces. maximise eventual closure success. Thus the very act of mining
In  this way, progressive rehabilitation was incorporated within becomes the key component of the mine closure outcome.
the operational and capital budget expenditure procedures Indeed, the components of mine closure need to be recognised
and reforecast every three months as a unit cost of production. and managed in the operational phase as a unit cost attributed to
The format of the plan was sufficiently flexible to accommodate each tonne of commodity produced, and boards should expect to
ongoing design, research and development studies and could be report such information in annual reports.
updated in response to changing production scenarios without
having to redo the complete document or myriad of costed tasks. THE LAST 20 YEARS
The Domains Concept approach is easily adapted to current Towards the end of the 20th century, mines in Queensland
project management practices and software systems, enabling focused most of their environmental energy on closure outcomes,
scheduled implementation of works and tight cost control, and understanding environmental challenges and putting plans
providing real cost/value-based evaluation of environmental together to attempt to control the longer-term liabilities by
impacts and controls within each spatial unit. The comprehensive effective operational management. This was in part due to a degree
list of costed tasks meant that the overall cost estimates for the of kudos afforded to performance, and also to the knowledge base
site were very robust and over time provided documentary proof that had been accrued by industry and the regulator. A change in
that original closure cost estimates were sound. the administration of mining rehabilitation in Queensland in the
The cumulative track record of final landform objectives and early 2000s, coupled with a rapid expansion in the sector during
rehabilitation was able to demonstrate that most closure success 2000–2010 arguably contributed to a shift in the knowledge and
criteria were achieved within seven wet seasons following mine experience base and subsequent rehabilitation outcomes. On-
closure. Most of all, this way of planning and project management the-ground LOM performance has been replaced by increased
provided a vehicle to build transparency, credibility and mutual monitoring and reporting. Operational staff numbers have been
trust with government agencies, landholders and the community. reduced, regulator documentation has grown exponentially and
All parties could support the vision and see measurable success the main thrust of environmental management is now primarily
towards the outcome. the production of approvals documentation.
The real strength of this mine closure approach is in detailed A form of the Domains Concept was broadly adopted by
landscape investigation during the exploration or development a significant number of mining companies and government
phase to properly understand the underlying features and agencies. The Queensland Government introduced Technical
landscape characteristics that could increase the risk of failure Guideline 18 (Department of Environment and Heritage
of mine closure. Once the structure of the receiving landscape Protection, 2012) and the NSW ESG3: Mining Operations Plan
is understood, proposed mining landforms and infrastructure (MOP) guidelines (Department of Trade and Investment, 2013).
can be placed and designed in such a manner to eliminate Both use the term ‘domain’, but the concept now defines a spatial
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
The domains concept 3

polygon of a land disturbance type and allow the grouping of In the author’s opinion, the real benefits of using the Domains
landform and infrastructure types for ease of closure-report Concept has been misunderstood, inadequately applied and in
production. These polygons appear to be an administrative tool to some cases misrepresented. As a direct result of the apparent
calculate financial assurance, rather than a technical and scientific simplicity of the original concept, its true possibilities and
tool to optimise closure outcomes. opportunities have been overlooked.
Today, under various jurisdictions, governments and mining The Domains Concept approach, if applied properly, allows for:
companies seem to agree on a way of issuing approvals for mining •• The effective use of EIA and geoscientific data to manage
projects; however, it appears to be more about following a process infrastructure location and controls. It makes the best
ahead of achieving a satisfactory final outcome. use of the landscape to tailor rehabilitation and closure
Assessing mine approvals for licensing or overall project outcomes, minimising the overall LOM cost of progressive
viability without a detailed life cycle assessment, including mine rehabilitation and closure. It thereby increases shareholder
closure costings, will never hold any mining company accountable value and renders compliance a by-product of the final
for long-term liability and legacy risks. outcome, rather than being the outcome.
•• Robust financial liability assessment to be quantified for
The regulatory processes across Australia are based on
the life of the project, from prefeasibility to closure and
compliance, and with such administrative complexity it is almost
lease relinquishment, because the spatial units capture
impossible to hold a mining company and/or its directors
sufficiently detailed information.
responsible for ineffective mine closure. While taxpayers may
•• Increased confidence in a more transparent and self-
take comfort from governments securing billions of dollars of
evident process by the regulators and community, as well
rehabilitation bonds, these are greatly understated in the main.
as providing the potential to explore options, other than
Furthermore, regulatory personnel often lack the necessary
financial bonds, insuring against the cost of reclamation
experience and skills required when working with these bonds. failure.
When mining companies approach mine closure, the industry •• The full consideration of all spatial environmental factors
standard (International Council on Mining and Metals (ICMM), relating to closure in the planning stage of a project,
2008) is initiated after the project has been constructed and providing for a LOM perspective to be adopted. When this
operations have commenced. As a consequence, the placement is understood, documented and adopted it provides the
of significant infrastructure within the landscape is usually done operational vision, specifications, direction and continuity
without any reference to optimising mine closure. of purpose for earthmoving contract negotiations and the
Applying an arbitrary unit cost per hectare of a domain operation of the mine. It also negates the impact of inevitable
disturbance type may have administrative advantages, but it changes to personnel.
won’t optimise an outcome for the receiving landscape and the •• Progressive implementation of the plan with a holistic
community because there is no technical or scientific assessment monitoring data management system to demonstrate
based on the domain’s underlying characteristics. a measureable track record of rehabilitation success,
such that ultimate lease relinquishment timelines can be
If environmental domains are identified from environmental
easily understood by financial institutions, regulators and
impact assessment (EIA) information prior to or during
community stakeholders.
feasibility studies, the real impact of specific infrastructure on the
•• Effective project management and cost accountability
receiving landscape would be better assessed, understood and
during the complete life cycle of the project from feasibility
controlled. McLeary (2009), ‘Brukunga Mine forward program’
to final reclamation, by capturing costs by domain in a
South Australia, captures the essence of the Domains Concept.
similar manner to an item of equipment. This approach
Here, a technical advisory group of national and international
makes possible the accrual of an appropriate provision
expertise was brought together to develop a potential walkaway
for closure within the financial ledger, in a similar manner
remediation solution by functioning under a self-guided model.
to capital, and documentation for the shareholder and
The model incorporated shared information, shared decision- community in corporate fiscal reports.
making and application of selected expertise across numerous
•• Community–mine transparency and credibility, allowing
mining companies and agencies to generate creative and holistic
stakeholders to become involved in post-closure planning,
solutions to complex problems.
confirmation of the rehabilitation approach and the
Domains actually define themselves from the underlying establishment of an achievable and agreed end land use.
landscape and geology, rather than being a two-dimensional
polygon created around a particular piece of infrastructure. As An inconvenient truth
such, landscape domains should be defined as a critical output
Tinsley (2007) made the observation that due-diligence
of an EIA, and then the considerations and challenges presented
processes are consistently undermined by consultant capture,
within each domain applied directly to LOM planning for poor professional standards, idealistic industry belief/
feasibility and viability assessment. commitments, omissions from scopes of works, inconsistency
Without this basic step, the most fundamental element of and fragmentation. He also showed that the casual relationship
impact assessment is not addressed: the suitability of a proposed between project viability and mine closure means that
placement of infrastructure in the landscape with respect to non-corporate stakeholders are exposed to significant and
closure. As a consequence the whole EIA and feasibility process undervalued risk. Over the years the author has witnessed the
cannot satisfactorily assess, quantify or address the legacy issues Domain Concept being utilised, yet missing the mark through a
that could accrue over the life of each project. lack of understanding.
The author believes that this administrative and management In reporting on mine activities, capable practitioners can
disconnect between the EIA and feasibility is fundamental to the generate a conceptual mine closure plan using a template of
failure of mine closure outcomes. Additionally, the associated previously captured high-level strategies and tasks. Most attempt
lack of transparency on an understood measurable outcome to cover all the bases with a set of generic environmental risks
may also cause uncertainty in the community, contributing to from previous projects.
individuals or groups holding up projects for years on largely Design engineers tend to lack the operational experience
ideological grounds. required to plan the practical development of the mine through
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
4 From start to finish: a life-of-mine perspective

to closure, and typically there is no continuity of personnel operations and eventual closure, with a typical approvals and
with the necessary experience or overarching vision for the progressive rehabilitation process embedded. Typically mine
full life cycle of the project. During design and construction, closure planning isn’t even initiated until two or three years
environmental controls are usually seen as secondary to building into operations. The author believes that to gain most return for
the necessary infrastructure on time and under budget. Data investors, detailed mine closure planning needs to occur at the
captured in the EIA process appears to have little influence on feasibility stage, as has been stated.
the development of a feasibility document, nor the optimisation If the most notable input to the viability of the project from
of closure outcomes and, ultimately, almost no impact on the the EIA process is merely whether approval has been given,
mitigation of long-term LOM risk. adequate provision for staged mine development and closure is
The author asserts that operators can only truly effect not accommodated in the feasibility capital funding. Therefore,
management control when they embrace the reality of a situation. there may be no funds to achieve successful rehabilitation and
The industry needs to acknowledge that the subject of the real closure, including the installation of appropriate impoundments
costs of mine closure has been avoided, and this has happened and drainage features.
primarily because mine closure and its associated costs do not The prevailing perspective from clients and engineering
conveniently fit within engineering project management tools or groups appears to be that anything to do with environmental
financial modelling parameters of feasibility studies. As a result, management during future operations equates to unnecessary
the currently available modelling tools are flawed, producing an cost in their net present value (NPV) financial model. Therefore
incomplete financial assessment for project viability. LOM issues generated by the EIA are not adequately considered
As a consequence, real LOM environmental costs are omitted or are avoided. This is unfortunate because the potential LOM
from the financial landscape. It is little wonder then that good cost-saving opportunities in the construction and operation of a
closure outcomes are absent from the actual landscape and are project using the landscape’s best attributes are missed.
not sufficiently reflected in the regulatory landscape. Nethery (2003) recognised this:
A time of more discerning investors is coming and they will The feasibility process includes a tension between the
require mining companies to be more transparent regarding mine Owner’s desire to have a viable project with low capital
closure costs when considering a project’s viability. It will not be and operating costs, and the engineer’s desire to design
sufficient to produce conceptual plans that are mere checklists conservatively to maximise the likelihood of a technically
within a mining control plan that includes quality assurance / successful project.
quality control (QA/QC) for things not publicly available.
However, Nethery did not include the other part of the tension
Industry needs to start to recognise another elephant in the triangle, which is the appropriate placement of infrastructure in
room, one that is a major obstacle to attaining satisfactory mine the landscape from the perspective of sustainable closure.
closure outcomes – the negative impact of a compliance culture.
The principal purpose of a BFS is to demonstrate the technical
Workplace health and safety legislation has driven a much and economic viability of the proposed project to expert third
valued increase in safety awareness in recent years; however, parties for the purpose of obtaining financing for the project.
compliance systems, including environmental ones, focus on Unfortunately, civil engineering groups focused on project
process and are big on historical documentation, but poor on construction commonly do not have the technical expertise to
environmental objectives and explicit outcomes. They are often deal with closure planning and costing. As a result the engineering
focused in the present, are reactive and require significant group tends to focus on making the numbers work for the client
personnel and resources to maintain the status quo. and overlooks the engineering of potentially significant LOM
This situation leads to ad hoc reactive and costly retrofit environmental risks, instead deferring them to operations.
of management controls rather than sound proactive The author believes that the mining industry needs to properly
environmental planning. Most compliance cultures tend to incorporate mine closure considerations from the EIA within the
create an operational arena that is shy of innovation and is overall feasibility and mine development plan to maximise the
heavily controlled and inflexible, without the necessary latitude overall LOM economic return for shareholders.
to implement appropriate environmental infrastructure and
In the concluding remarks of their paper ‘Use and abuse of
planning to optimise closure outcomes. The author believes
feasibility studies’, Mackenzie and Cusworth (2007) note that
that operational environmental and safety compliance should
feasibility studies:
be a product of a job well done, founded on appropriate
and considered long-term LOM planning that is inclusive of •• are regularly portrayed as being much more comprehensive
rehabilitation, closure and relinquishment, rather than focusing and accurate than they are
on being compliant now as the only outcome. •• are often not fit for their intended purpose
•• tend to focus on technical issues at the expense of critical
STARTING WITH THE END IN MIND business and project delivery issues.
They conclude that:
The crux of the problem causing the avoidance of adequate LOM
planning is the focus on permitting/approvals as the key driver of The poor track record of the industry – which indicates only
project commencement. The commitment to a project EIA process half of projects meet their feasibility study expectations –
(provision of scientific data) is largely formatted to fulfil regulatory demands a better approach to the feasibility study process.
requirements. This means that it is somewhat disconnected from Good environmental management of mine sites should
the parallel prefeasibility and feasibility processes (provision of include the best available engineered solution to mitigate
best, least-cost option financials), which are conducted pursuant and control identified environmental risks within the actual
to Project Management Institute (2013). Unfortunately for landscape. It should not be about attempting to finesse approvals
LOM operational and closure planning purposes, the granting documentation to fit a chosen engineering solution, nor meeting
of approvals is the signal for the engineering group to focus on the required administrative format just to gain an approval.
detailed design and the bankable feasibility study (BFS), with the Nethery (2003) observes that:
requirements of the EIA barely applied. The level of risk assumed by the parties to a project is related
The mining life cycle (Figure 2) describes the different phases to quality of the feasibility study, the quality of the concepts,
of a project from scoping through feasibility, construction, the depth of analysis and the team of people doing the work.
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
The domains concepT 5

FIGURE 1 - The mining life cycle


Scoping Study Prefeasibility Study Feasibility Study & Implementation & Operations Closure & Lease Relinquishment
Funding Start up Decommissioning

Determine Determine Determine Extract the Closure & Post Closure


Deliver Project
what it could what it what it will construction Value Decommis- Management
sioning Plan and Lease
be should be be Capital works Relinquishment

Final Rehab Report


EIS Process - Permitting and Approvals Plan of Operations
and Financial Closure
Assurance implementation plan

Develop
Investor
Concepts
Review
Assess Progressive
& Rank Development Agreed
Does Instigate
it Alterna Capital Works
Progressive Acceptable
make tives Demonstrated
Rehabilitation Final land use Rehabilitation
sense
and Closure
Effectiveness
Plan
Is it
viable

Construct Operate Complete final


Project Project landform
Is it construction
Detailed
the
Costings and
best
financial anaylsis Progressive Progressive rehabilitation and
Rehabilitation and monitoring to demonstrate
monitoring to success
demonstrate success

Identify
management From projected
domains and final land form
instigate detailed
assess
closure planning
infrastructure

After : Why Feasibilities fail McCarthy, 2013 (Presentation to AusIMM Melbourne Branch June 2013)

FiG 2 – The mining life cycle (mccarthy, 2013).

Current engineering practice neglects to properly engage the There are currently detailed guidelines for incorporating
science of the underlying landscape and optimise the placement of significant material costs with the resource and reserve
progressive infrastructure development within it. Consequently, statements to develop a project viability statement.
detailed LOM cost estimates are not addressed in feasibility The author argues that feasibility studies need to include the
studies so the outcomes are ill-conceived and the viability of the expected real life cycle cost of a project, including closure, to
project can be questionable. properly assess its true viability. This will lead to:
The general approvals-based excuse offered by most mining • corporate decisions about the viability of a sustainable
companies when challenged by regulator or community project being made on assumptions
interests is that these are operational matters that will be • significant impairment of the investors’ ability to make
worked through when the operation starts generating revenue informed business decisions about the project’s actual
– essentially, ‘Don’t worry about that, we’ll get around to it later’. shareholder value, the real rate of return and their potential
Of course, mining companies almost never do, because over time exposure to long-term liabilities
most knowledge is lost when representatives of the proponent • the project possibly becoming unviable at a reasonably
and the regulator involved at approval are no longer involved early stage during operations because the actual cost of
approaching closure. doing business, including rehabilitation, will outstrip the
Unfortunately, significant financial resources are not economic value estimates suggested in the BFS
allocated to these LOM matters, once the project gets its • potential missed opportunities for smarter, more innovative
approval and initial capital reserves become depleted and and less environmentally damaging ways of developing the
there are no resources to expedite necessary controls. The resource to be considered
operational phase of the mine has to then exist on a nominal • the considered development of appropriate rehabilitation
annualised compliance/staffing budget just for necessary or closure success criteria not being possible, or confused,
compliance monitoring, because, the author would argue, the because planning is not sufficiently thought through or
bigger picture was not accommodated in the overall project detailed, increasing the uncertainty of outcome
viability during feasibility. • an almost inevitability that most sites are at risk of becoming
The latest version of the JORC Code 2012 attempts to deal with a long-term liability for governments and communities
all the inherent project risks at project viability assessment: because no resources have been allocated.
The feasibility study is supposed to define all the likely risks It is surprising that the current system of project viability
and propose a coherent and effective plan for mitigation. assessment could retain these oversights, because planning
system and feasibility guidelines for major projects are clear
VALMIN 2015 9.3(c) now states: about what the financial model should consider, such as all
Depending upon the scope of the Public Report, the aspects of the project’s cash flow, including financing costs,
Practitioner should report upon liabilities, commitments interest during construction, royalties, taxes, sustaining
and financial exposures … (c) the cost of environmental capital, reclamation and closure and risk assessment and
regulatory requirements, rehabilitation and mine closure. mitigation. It is instructive to reflect on why there are rarely
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
6 From start to finish: a life-of-mine perspective

sufficient resources or funds available to undertake adequate all stages of the mining cycle, but entrenches the detailed closure
closure work. design at a late stage in proceedings. This defers costs to a point
Nethery (2003) notes that: when revenue is almost non-existent and nothing can be done.
Financial analysis is usually the penultimate stage of the Rather than detailed closure planning occurring late in the
project evaluation and feasibility, where the project cash development of the productive use of a mine, much more detailed
flows are modelled and the NPV and Internal Rate of Return planning needs to occur at the feasibility stage to determine
(IRR) of the project are determined. The models used are whether the project is truly viable and all the major issues can be
often complex and always sensitive, in order of importance, satisfactorily addressed during the life of the operation.
to commodity prices, capital and operating costs. The mining industry is necessarily concerned about red tape,
When financiers are asked to provide debt finance for the project delays and land access difficulties; however, by not
project on the basis of a feasibility review they are basically incorporating detailed costings for the projected life of the project
interested in loan coverage and the project’s ability to support the at the viability stage, it falls short of addressing important whole-
of-project responsibilities for the environment by which the
required level of debt; NPV and IRR is inconsequential from their
perspective. If closure costs don’t fit into current models because
there is no way of handling them in terms of NPV, and NPV is not
Section 3.
mining industry is judged. For many issues, not least landform
drainage and geochemical challenges, leaving the development of
necessarily important to the financiers, the question has to be
asked ‘why should there not be some other financial model and
Framework of a detailed
a LOM plan to such a late stage in proceedings cannot undo the
consequences of ill-advised or simplistic landform construction.
instrument used to determine the true value of the project?’
Nethery (2003) suggests that:
closure
will planthe application and description
The JORC 2012 Code considers that the Feasibility Study
be expected to contain
32 of all Modifying Factors (as outlined in JORC 2012 Table  1
A bankable document is one that satisfactorily provides all Social, environmental and governmental approvals) in a
of the information and auditing necessary for the bank and detailed form and may address implementation issues such as
its engineer to determine that the risks are acceptable and detailed mining information
Contextual schedules, construction ramp-up and project 33
the project is viable, on a standalone project finance basis. execution plans. Table 1 should be further developed to include
Target closure
consideration of theoutcome andcost
detailed goalsof closure and reclamation 34
Financiers tend to use independent reviewers to review the
project, the feasibility study, and to critically examine all aspects with respect to the material impact on the Ore Reserve
Action plans 35
of the project and uncover serious or fatal flaws. These external viability. Without such consideration, Ore Reserve statements
reviewers have a primary function to protect the financial are seriously
Closure inadequate.
costs 36
institution from lending to poor projects, but, without detailed Mine design, construction and mine development must consider
Updating the detailed closure plan 37
closure planning costs, it is difficult to see how they can adequately the inherent costs of a full life cycle scenario contained within a final
fulfil these obligations. closureFacilities
plan intimately
with long linked to lives
and short findings and recommendations 37
In the light of current industry discussions with respect to in the EIA, otherwise there is a material hole in the financial data
sustainability principles, two relevant questions to be asked: and theSudden closure
feasibility is flawed. The straightforward answer is always 38
to start with the end in mind and use the technical capabilities we
•• Why do banks and other financial lending institutions find Application to existing operations 38
currently have to plan the project properly with closure in mind
the omission of significant cost exposures that are likely
(Figure 3).
to accrue over the project’s life acceptable when making
assessments?
Exploration –
•• Does the current approach to resourcing LOM development
and closure at feasibility represent good stewardship?
The NPV mindset used in feasibility business planning CONCEPTUAL
encourages short-term least-cost option judgements to be CLOSURE
made at the expense of considered LOM planning and fit-for-use
PLANNING
Pre-feasibility –
environmental controls and ensures there is no money available
for closure expenditure at the end of the project. Feasibility –

The industry prides itself on representative sampling and


analyses, repeatability, adequate QA/QC and having experienced
and appropriate personnel to sign off reserve statements; Construction –
however, applying the same rigour to mine closure and Operations –
Stakeholder input

progressive rehabilitation planning and costings at feasibility


Mine life cycle

is somewhat lacking. This suggests it is time to align closure


work with The six tenets of sustainability for mining planning
INCREASING
statement (Robertson, 2013): DETAIL
… planning for the sustainable mining of resources is a
global necessity; determination of the potential impacts DETAILED
and the optimisation of mine development, operation and CLOSURE
reclamation, to minimise these impacts, is a requirement PLANNING
of responsible stewardship; and planning and provision Decommissioning –
for post-mining sustainable land use management and Transition to closure
custodial succession are necessary. Closure –
The current approach – pursuant to the JORC Code,
incorporating environmental matters in JORC’s Table  1 – Post closure –
omits or understates detailed LOM closure costs from reserve
statements and project viability, and needs to be completely and
Relinquishment–
appropriately revised.
Likewise, the Planning for Integrated Mine Closure: Toolkit FIG 3 – International Council on Mining and Metals mine closure
(ICMM, 2008; see also Figure 3) clearly identifies closure issues at planning toolkit (image courtesy ICMM, 2008, pPlanning
32). for Integrated Mine Closure: Toolkit
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
The domains concept 7

The process the industry needs to adopt should include: years post-closure, in support of eventual lease relinquishment.
•• The appointment of a senior environmental technical A site contamination assessment was also conducted by domain.
manager with 15+ years’ closure planning experience as the The operational phase is where mining companies should
competent person to oversee the process. extract the value of resources, but the current deferred-cost
•• Extracting a closure context from the EIA study process, approach to closure either costs the company more than it should,
identifying underlying 3D landscape domains with respect increasing the risk of non-compliance, or eventually costs the
to potential exposure pathway considerations. State and the local community in legacy issues. This highlights
•• Each domain nominally being a subunit of an existing that the current practice of analysing financial viability using NPV
catchment and appropriately sized to accommodate is fundamentally flawed.
expected LOM infrastructure. The NPV mindset used in feasibility business planning
•• Optimising the proposed project landforms and infra­ encourages short-term least-cost option judgements to be
structure by spatial unit within the identified landscape made at the expense of considered LOM planning and fit-for-
domains for a beneficial closure implementation. use environmental controls, thus ensuring there are limited
•• The inclusion and implementation of key findings from to no funds available for closure expenditure at the end of the
the EIA to directly mitigate legacy risk. From these control project. It also means that commercial decisions to proceed with
measures produce a LOM business plan, developing it projects are taken without directors, investors or the community
with closure in mind as an integral component of the JORC understanding the real life cycle cost of the project. Consequently,
Reserve statement, assuming a 5–10 year rolling average environmental matters that need to be addressed within the
commodity price and mine life, with costs and scheduled eventual operational control budget framework do not exist or
±15–20 per cent with all uncertainties identified and are at best underestimated and under-resourced.
projected timelines to close them out. The mining industry has the expertise, so why not estimate
•• Making robust LOM cost estimates and financial provision project closure planning at feasibility? Complying with
to achieve a practical closure outcome. environmental licensing in order to get projects up and running so
•• Incorporating LOM cost estimates as a significant material as to generate revenue streams early in the mining life cycle, with
factor to be addressed by JORC Reserve statements, to more little regard for how to achieve a safe, sustainable and beneficial
realistically represent the likely extent of the project for end use, is a poor reflection of current practice. The industry has
one-off placement of infrastructure required for the mine been able to avoid the subject of the real costs of mine closure; it
life cycle within the landscape. is now time to adapt and get smart about how it goes about its
•• Determining a project’s real viability by involving an business in the future.
independent reviewer from financial institutions in the More robust LOM planning and cost estimates over the actual
sign-off process for LOM closure provisions. life of the operation would provide all stakeholders with a
•• Permitting and final approvals only being given after a holistic better understanding and transparency of what the post-mining
cradle-to-grave project business plan has been completed landform could look like. The plan would be built on effective
parallel to, and demonstrating intimate connectedness with, smart design within the parameters of the most likely long-
the EIA and identified landscape domains. term scenario with realistic costs, milestones and measurable
•• Developing an explicit operational closure document. outcomes. This would significantly reduce project uncertainty
•• Adopting an internal provision for closure approach and would provide a good starting point for communities to
based on an assessment of the predicted cost of closure to be involved in a decision-making vehicle towards a common
demonstrate a measurable track record of success as work closure vision.
progresses. This would require the operator of the mine Given that industry tends to react to regulation through
to sets aside funds each year to cover the eventual cost of compliance it is strongly recommended that legislation needs to
closure proportional to the amount disturbed on a 3–5 year
be amended, such that the grant of an Environmental Authority
rolling average ahead of disturbance. On completion
would be conditional on an independent audit of LOM financial
of progressive rehabilitation there would be an annual
estimates within the project feasibility by a competent person
drawdown of the provision for closure to profit and loss
with responsibility for the reserve statement. Then, as with
accounts or control budget.
other financial data, closure costs should be audited by an
•• Reporting progress annually to shareholders and independent reviewer for the financial institution to ensure
community as part of Australian Securities Exchange finance for a project would be contingent on a viable whole-
financial requirements. of-life project cost. This would require that corporations
law and regulations, such as Australian Securities Exchange
CONCLUSION listing rules Guidance note 31 (2013); JORC Appendix 5A
The Domains Concept approach, applied early in the project’s (2012) subsection 40 and Table 1 Sub-sections environmental,
existence at the exploration phase to adequately investigate infrastructure and other, be revised to ensure that detailed LOM
and understand the landscape, is a tried systematic approach to development for environmental purposes and closure costs
manage and implement mine closure from pre-evaluation to lease are adequately addressed in feasibility documents, pursuant to
relinquishment. Using the domain concept process and identified Australian Securities and Investments Commission (ASIC, 2011)
spatial units mine closure can be modelled and scheduled using Regulatory Guideline 111.114. Due consideration of disclosure
current project management software, treating each spatial unit of all LOM costs should reflect the intention and consideration
as a defined cost centre with a suite of defined tasks, specifications of Section 729 of the Corporations Act 2001.
and assigned resources. It is straightforward, reasonably simple The administrative process for mining tenure also needs urgent
and need not be assigned to the too-hard basket. review as mining leases tend to represent arbitrary rectangular
This approach laid the foundation for Red Dome to demonstrate polygons superimposed over a landscape. To deal with mine
compliance and build a bottom-up environmental management development and closure appropriately, planning needs to be
system. The resultant spatially explicit data allowed the site to undertaken within the context of local and regional catchments.
meet its desired final land use objectives and effectively meet the If necessary, mining lease boundaries should allow for the best
nominated rehabilitation success criteria and commitments seven placement of landforms and infrastructure within the landscape
Rehabilitation of mining and resources projects as it relates to Commonwealth responsibilities
Submission 70
8 From start to finish: a life-of-mine perspective

to fully take into account the Domain Concept and optimise Australian Securities and Investments Commission (ASIC), 2011.
closure effectiveness. Regulatory Guide 111: Content of expert reports, March.
Clearly, the possibilities and real opportunities of using the Department of Environment and Heritage Protection, 2012. Rehabilitation
requirements for mining projects, Guideline 18, Queensland
Domains Concept to produce robust LOM plans and value to the
Government, Brisbane.
shareholder have not been fully grasped, or have been overlooked
in the past 20 years. Department of Trade and Investment, 2013. ESG3: Mining Operations
Plan (MOP) guidelines, New South Wales Government.
Through the proper use of the Domains Concept approach at
International Council on Mining and Metals (ICMM), 2008. Planning for
project inception and use of straightforward landscape assessment
Integrated Mine Closure: Toolkit [online]. Available from: <http://
to define domains, there is potential to usher in an era of optimised www.icmm.com/document/310>.
cost-effective whole-of-mine life cycle planning. The resultant
JORC, 2012. The Australasian Code for Reporting of Exploration Results,
project framework would provide robust and detailed cost estimate
Mineral Resources and Ore Reserves (The JORC Code) [online].
data, which could be used as input into more robust financial Available from: <http://www.jorc.org> (The Joint Ore Reserves
models than are currently common. There is an opportunity to Committee of the Australasian Institute of Mining and Metallurgy,
deliver real project transparency for both investors and community, Australian Institute of Geoscientists and Minerals Council Australia).
and potential to significantly mitigate legacy issues.
Mackenzie, W and Cusworth, N, 2007. The use and abuse of feasibility
The NPV concept pays dividends for shareholders and mining studies, pp 65–76, in Proceedings Project Evaluation Conference 2007
companies, but frequently at the expense of governments, (The Australasian Institute of Mining and Metallurgy: Melbourne).
taxpayers and communities. This is why it is time for the mining McCarthy, P, 2013. The mining life cycle, presentation to AusIMM
industry to adjust how it approaches financial modelling: Melbourne Branch, June 2013.
encompass all LOM costs including relinquishment, and create McLeary, M B, 2009. Striving for walkaway – focusing an expert group on
a way of assessing project value that replaces NPV and the the ‘holy grail’ of mine closure, in Proceedings Fourth International
deferment of costs. The industry needs to modify its closure Conference on Mine Closure (ed: A Fourie and M Tibbett), pp 359–374
approach and associated valuation in the 21st century to more (Australian Centre for Geomechanics: Perth).
readily reflect the transparency required by the public, and take Nethery, B, 2003. The role of feasibility studies in mining ventures,
advantage of smarter ways to operate mines more cost-effectively Conference Board of Canada, Structuring More Effective Mining
with an outcome for greater sustainability. Ventures (AMEC Mining and Metals: Vancouver).
Project Management Institute, 2013. A Guide to the Project Management
Body of Knowledge Guildelines, fifth edition, 589  p (Project
Management Institute: Pennsylvania).
Robertson, A M, 2013. The six tenets of sustainability for mining [online],
EnviroMine: environmental technology for mining. Available from:
<http://www.technology.infomine.com/enviromine/issues/sustain_
tenets.html>.
REFERENCES Tinsley, R, 2007. Project finance risks – due diligence matters, in
ASX Group, 2013. ASX Listing Rules, Guidance note 31 [online], p 8. Proceedings Project Evaluation 2007, pp 77–86 (The Australasian
Available from: <http://www.asx.com.au/documents/rules/ Institute of Mining and Metallurgy: Melbourne).
guidance_note_31_reporting_on_mining_activities.pdf>. VALMIN, 2015. Australasian Code for Public Reporting of Technical
Australian Corporations Act, 2001. Section 729 [online]. Available from: Assessments and Valuations of Mineral Assets (The VALMIN Code)
<http://www.austlii.edu.au/au/legis/cth/consol_act/ca2001172/ [online]. Available from: <http://www.valmin.org/docs/VALMIN_
s729.html> Code_2015_final.pdf>.

Você também pode gostar