Você está na página 1de 7

PROCEEDINGS PAPER

A Monolithic Post-tensioned
Parking Structure
Presented at the Prestressed Concrete Institute Convention
October, 1961

by Carroll S. Delaney, Principal*


and Neil R. Runyan, Design Engineer*, P.E.
The Denver-United States Nation- are channelled along Lincoln Street.
al Bank Lincoln Street Addition now The bank felt that it was absolutely
under construction in downtown essential that these services not be
Denver will use more post-tension- completely interrupted. Therefore,
ing steel than any previous Denver it was necessary to build the Lincoln
building. The project will include Street tunnel with a minimum of
three underground levels, three traffic interference during construe-
levels above grade, and eventually tion. Two requirements of the design
when completed eleven levels above were to keep the street surface con-
ground (figs. l & 2). The new park- struction time to a minimum and to
ing structure will be located direct- keep one-half of the street open at
ly across the street from the existing all times. The solution to this was
bank building. The basements under to drill and pour the caissons and
the parking building will extend the basement columns to the street
three levels below grade. The two level first on one-half of the street
upper basement levels will extend and then construct one-half of the
under the street to connect with the street waffie slab. After the pouring
basement and first floor of the exist- of the first half of the street slab,
ing building, thereby creating con- the same procedure is to be used
tinuous banking floors approximately on the second half. Excavation and
two blocks long. The parking floors completion of the under-street base-
will be served by an adjoining spiral ment will follow the surface con-
ramp structure. struction without traffic interference.
Before describing the problems The parking structure has floors
connected with monolithic post-ten- 133 ft. wide by 225 ft. long. Except
sioning, the writers believe it worth- for some stair and elevator columns,
while to mention briefly some inter- the only columns within the interior
esting design features and problems of the building are a single line down
created by the connection with con- the center of the long direction of
ventional reinforced concrete por- the building, thus forming floor spans
tions of the building. of 66 ft. 6 in. These 66 ft. 6 in. spans
All the drive-up services for the were framed with 24 in. deep dia-
Denver-United States National Bank grid waffie slabs supported by beams
"CarrollS. Delaney & Associates, Inc. 30 in. deep. Post-tensioning was used
Denver, Colo. in the parking floors and in the ex-
December, 1961 53
Fig. 1-Denver·United States National Bank parking structure.
~AD W A'( I?UILD!NG_

...l--+--:-:-·:o··_.,:-~·-.~··.:-:-:.-::-~~.1·:.•:'-........_.~
~~= _;_:-~~;;,
I!Ir 1f-n_·fr!:rt:~ llu !] ..... J+···· ..........._,., ..,-~:,;.<,s_:;.-:;;:.
I ~~ h
~V...r ~ ~ ....................
• ·----- ;: 1 r If/

'--=-~~- -- ~;,;___ ___ j


I
---- iL--·_...+-':-'r~_......J,;
••;...____.I
_

I
TOWER bUiLDING 1} C!;.NIEK
/'"'-"'- ... '"'""

liRRACc i:>LD'G.
-r-~ ,....,. ..., ........

<iCON N .:CT ION


~,

MOTOR
\ bANK

Fig. 2-Eievation of the Bank and parking structure.


------ -----------------------------

terior curved ramp beam of the ad- where deflection might be excessive.
joining spiral ramp structure. Post- Almost all of the flexural members
tensioning was required to decrease were continuous, with the number of
deflections in the floor slabs and spans varying from two to nine. To
beams, and to increase the torsional simplify the calculations involved in
capacity of the curved ramp beam. designing the tendons, the design
Mild steel reinforcing was desired procedure selected was the method
throughout the structure to help of using the uplift caused by the
eliminate any cracks in the concrete tendon drape as an upward load on
which might be caused by shrinkage, the concrete. This uplift was made
unusual loading, or movement equal to the dead load on the mem-
caused by the stressing of other ber so that no dead load deflection
members. By using mild steel in all would occur in either a simple or
the beams, they became "partial pre- continuous span. Using this ap-
stressed" members; hence, it was not proach, continuous span tendons
convenient to design on a stress in- were sized almost as easily as simple
vestigation basis. The decision was span tendons. In most members,
made to design the flexural members grouted tendons were used for great-
by deflection and ultimate strength er ultimate strength, although un-
criteria. The deflection criterion was bonded tendons were used in those
an undeflected floor under dead load. cases where ungrouted tendons were
Live load deflection calculations adequate for ultimate strength.
were performed as a check in areas The structural floor system incor-

Fig. 3-Precast concrete pans for the diagrid waffle slab.


56 PCI Journal
porates 10 in. wide, 24 in. deep, and parabolic live loads.
45 degree diagonal waflle slab joists, Electronic computers were used
and 30 in. deep beams. Pans were extensively in the designs to reduce
needed for the diagrid waflle slabs the man hours of laborious calcula-
which were of greater depth than tions. One computer program was
those commercially available. To designed to size joist tendons for the
provide larger pans, precast concrete diagrid slabs. Beam shears, moments,
pans were designed which become and deflections were calculated by
a part of the floor slab (fig. 3). The another computer program. A mo-
diagrid slab structure produces an ment distribution program (available
attractive ceiling and a very stiff to the public from the University of
floor system. For efficiency it was Houston) helped reduce the work
necessary to place the beams so as involved in the beam designs.
to create diagrid bays of nearly equal In the preliminary designs an at-
sides. The post-tensioning of the dia- tempt was made to design the col-
grid waflle slabs caused a redistribu- umns for live load moments plus the
tion of the dead load to the beams moments induced in them by the
different than that normally encoun- shortening of the floor due to post-
tered in conventionally reinforced tensioning. This approach was not
concrete. In a conventional slab the feasible for the large, perimeter col-
loads are distributed to the supports umns because of the amount of mo-
in approximately a parabolic man- ment anticipated in the floors. In
ner, but in the undeflected post-ten- fact, the bending stiffness of some
sioned diagrid slabs, the dead load of the columns would have caused
is distributed approximately uni- them to resist almost all of the beam
formly to the support beams. In the post-tensioning force resulting in
beam designs and in the column very little beam compression.
load calculations, it was found that The decision was made to pour
excessive error was incurred when all of the columns, except some near
the slab live load was distributed the center of the building, after the
uniformly, or trapezoidally; there- floor above the columns has been
fore, for the beam and column de- post-tensioned. The construction
signs, the slab-to-beam loads were technique developed by the engi-
calculated as uniform dead loads neer to handle this problem entails
the use of 6 in. diameter steel pipe
sleeves installed in the floors at each
column location to permit the pour-
ing of the columns through the
floors. In order to reduce the possi-
bility of the column concrete settling
below the bottom of the floors, the
columns are to be poured in two
stages. In the first stage the concrete
is poured to within two feet of the
beam soffit. In the second stage,
which is to be poured at least three
hours after the first stage, the col-
umn pour will be completed.
Fig. 4-Spiral reinforcement for the bearing
It was impractical to prestress
plates. some areas of the building, such as
December, 1961 57
the elevator areas. These areas of ter of the section.
reinforced concrete were designed Theoretically, the tendon friction
to seat or key into the prestressed loss would be extremely high in the
floors after the post-tensioning had post-tensioned curved ramp beam. A
been completed. Although it would curved test beam was made in order
have been possible to design mild to determine the curvature friction
steel capable of carrying the tension coefficient, f-t, for the 1f4 in. wire
caused by the post-tensioning move- mastic coated tendons (fig. 5). This
ment that would occur, it would model consisted of a semi-circular
probably be rather difficult to avoid curved beam containing a four-wire
some unsightly cracking. The best tendon and an eight-wire tendon.
approach to this problem seemed to The tendons were jacked alternately
be to pour these areas after the post- from each end, with readings taken
tensioning was complete. simultaneously from opposite ends,
In the areas where it was practi- in order to determine the loss of
cal, the post-tensioning pockets were force due to friction.
made with the top open to the top Tables I and II show the results
of the floor in order to reduce the of the friction tests.
construction labor involved in pour-
ing the pockets after post-tensioning. TABLE 1
The reinforcement behind each 4 Wire Tendon
tendon bearing plate consists of a 6
in. diameter spiral (fig. 4) . These
Jack force (kips) _l!o Loss
spirals have been used for this pur- Jack No.1 Jack No.2
10. 5.9 41
pose on previous designs with suc- 15. 9.1 39
cess. They are easier to install and 20. 12.4 38
require less steel than a reinforcing
bar grid. TABLE 2
8 Wire Tendon
Curved Prestressed Beam
Post-tensioning of a nearly semi-
circular horizontally curved beam
was a new use of prestressed con-
crete, as far as the writers can de-
termine. The outside (up) ramp
beam is free of columns through an
arc of 147 degrees and has a diam-
eter of 96 ft. The post-tensioning is
beneficial in increasing the torsional
capacity of the concrete and in de-
creasing the deflections. The method
of using the uplift caused by the ten-
don drape as an upward load on
the concrete does not entirely de-
scribe the effect of a tendon on a
curved member. It is also necessary
to consider the radial forces acting
on the member. Twisting of the
member will result where the ten- Fig. 5-Curved test beam for determining fric-
don is above or below the shear cen- tion loss.
58 PCI Journal
siderably more difficult than for
Jack force (kips) %Loss
straight members.
Jack No.1 Jack No.2 This structure emphasizes the fact
20. 11.2 44
30. 17.7 41 that the shallower depths with long-
40. 27.1 32 er spans are economically feasible
50. 31.8 36 with a monolithic post-tensione(l
structure. The additional stiffness
The curvature friction loss coeffi- and material savings usually found
cient may be determined by assum- in continuous floor systems are pos-
ing a "K" (wobble) coefficient and sible in a post-tensioned slab and
calculating the f.L value from the beam floor. However, many prob-
formula: lems do occur which must be studied
F 2 _ -,uo-KL with care. The problem of the mo-
- -e
F1 ' ments developed in the columns due
The friction model tendons had to the post-tensioning deformations
the following dimensions: will occur in any monolithic concrete
L = 14 ft. 10 in. structure. In some structures, small
II = 7r
concrete or steel columns can be de-
Taking a friction loss value of 40% signed to withstand these deforma-
again, but assuming a "K" value of tion moments. In tall multistory
.003 gives a 1'- value of 0.148. Clearly buildings it will often be necessary
the 1'- value is in the range of 0.15 to relieve or eliminate these column
for these mastic coated tendons. moments by some construction pro-
This is much lower than the recom- cedure, such as pouring the columns
mended values generally in use to- after the post-tensioning of the floor
day. above is complete, or by some type
A 1:12 scale model of the post- of sliding connection between the
tensioned curved ramp beam was columns and beams.
constructed and tested to verify the A post-tensioned structure will
general behavior and failure charac- probably always require more field
teristics (Fig. 6). The beam was supervlSlon and inspection than
made of light weight concrete using many other types of construction,
Idealite aggregate and type III Port- but certainly this is truer on today's
land cement. The 96 in. diameter jobs because of the workers' lack of
model, which had a rectangular cross experience with this type of con-
section of 2 in. by 5 in., carried a struction.
total uniformly distributed load of
1,914 lbs. at failure. The beam had
almost reached its ultimate bending
capacity when it failed suddenly in
torsion at the "quarter point". The
only reinforcement in the model was
a single Y4 in. diameter high-strength
post-tensioning wire. BrieRy, the re-
sults of the model test show that the
prestressing greatly increases the
torsional capacity of a horizontally
curved beam, and that deflections
may be reduced by the use of pre-
stressing. The analysis of the cam- Fig. 6-Sule model of the curved ramp beam
ber due to prestressisg was con- tested to failure.
December, 1961 59

Você também pode gostar