Você está na página 1de 18

Expected size of shielded fires in sprinklered office

buildings

Lougheed, G.D.

NRCC-40106

A version of this document is published in / Une version de ce document se trouve dans :


ASHRAE Transactions, v. 103, pt. 1, 1997, pp. 395-410

www.nrc.ca/irc/ircpubs
The following paper was published in ASHRAE Transactions, Vol.
103, Pt. 1.  1997 American Society of Heating, Refrigerating
and Air-Conditioning Engineers, Inc.

This posting is by permission of ASHRAE and is presented for


educational purposes only.

ASHRAE does not endorse or recommend commercial products or


services. This paper may not be copied and/or distributed
electronically or in paper form without permission of ASHRAE.
Contact ASHRAE at www.ashrae.org.
PH-97-2-1(RP-838)

Expected Size of Shielded Fires


in Sprinklered Office Buildings

Gary D. Lougheed, Ph.D.


Member ASHRAE

ABSTRACT and only two operating sprinklers, the heat release rate, radiant
flux, room temperatures, and buoyancy pressures were substan-
As part of a joint research project between ASHRAE and
tially reduced in a compartment. It was also noted that, although
the National Research Council of Canada (ASHRAE Research
total smoke production was reduced by the sprinklers, there were
project RP-838), the probability of occurrence and expected
still significant quantities of “cold” smoke produced and that this
size of shielded fires in sprinklered high-rise office buildings
smoke contained potentially harmful concentrations of carbon
were investigated. Phase 1 of the project included surveys of
monoxide.
typical office buildings to identify shielded fire situations and
The previous investigation (Mawhinney and Tamura 1994)
the fuel loads in the shielded areas. Based on these surveys,
identified a number of areas in which additional research was
medium- and full-scale fire tests were conducted. The results
needed. In 1994, a second joint research project was initiated
of these investigations are summarized in this paper. In partic-
between ASHRAE and NRCC (ASHRAE research project RP-
ular, the effect of a sprinkler system on heat release rate, com-
838). This current study was established to address one of the
partment temperatures, carbon monoxide (CO) production,
fundamental concerns about the previous study raised by the fire
and smoke generation and movement for fires in an open-plan
protection engineering community—namely, what are the prob-
office scenario are discussed. An initial analysis of the impli-
ability of occurrence and probable size of shielded, sprinklered
cations of a sprinkler system on a zoned smoke control system
fires in high-rise office buildings? The objective of the investi-
is also provided.
gations conducted in this second project was to provide infor-
mation that would answer those questions and thus improve
INTRODUCTION
confidence in the design of smoke management systems in
The ability of sprinkler systems to control and extinguish buildings protected by sprinklers. In particular, in this paper, the
unshielded fires is well established. However, in recent years, effect of a sprinkler system on heat release rate, compartment
concerns have been raised regarding shielded fires that are not temperatures, CO production, and smoke generation and move-
rapidly extinguished by sprinklers (Klote 1990). It was ment for fires in an open-plan office scenario are discussed. An
suggested that such fires could produce significant quantities of initial analysis of the implications of the sprinkler system on a
smoke and toxic fire gases; therefore, smoke control systems, in zoned smoke control system is also provided.
addition to the automatic sprinkler systems, may be useful for
life safety of building occupants. SHIELDED FIRE SCENARIOS
In 1991, a joint research project was initiated between the In phase 1 of the project, three tasks were completed:
American Society of Heating, Refrigerating and Air-Condition- • Surveys were conducted to quantify typical shielded fire
ing Engineers, Inc. (ASHRAE) and the National Research scenarios in high-rise office buildings.
Council of Canada (NRCC) to investigate the effects of sprin- • A review of North American fire loss databases was
klers on the performance of a zoned smoke control system undertaken to identify shielded fire incidents in sprin-
(ASHRAE research project RP-677). The results are docu- klered buildings.
mented in the final report for the project (Mawhinney et al. 1992) • Recent literature on fire statistics and full-scale tests with
and are summarized in a paper by Mawhinney and Tamura sprinklers and smoke management systems was
(1994). These investigations indicated that with shielded fires reviewed.

Gary D. Lougheed is a senior research officer at the National Fire Laboratory, Institute for Research in Construction, National Research Coun-
cil Canada, Ottawa, Ont.

ASHRAE Transactions: Symposia 395


The results of the phase 1 studies are fully documented in were a number of cases observed during the site visits where the
Lougheed and Mawhinney (1996). In the following sections, use of the space by the occupant did not conform to codes and
the typical fire scenarios found in high-rise office buildings standards and thus created or exacerbated the potential fire chal-
are summarized. lenge to the sprinkler system. For example, it should not be
expected that a sprinkler system designed for a light hazard occu-
Shielding by Tables and Desks pancy will provide adequate protection for areas that, in fact,
This was the shielding scenario most frequently observed in pose a more severe challenge or, if the sprinkler system is
office buildings (Lougheed and Mawhinney 1996). Typically, designed and installed properly, that it will provide adequate
the shielded fire scenario consisted of a desk or table producing performance if it is handicapped to the extent observed in some
a shielded area of approximately 0.9 m2 (9.6 ft2). The fuel loads of the site visits (Lougheed and Mawhinney 1996).
under a table or desk ranged between 30 and 150 kg (66 and 331 There were many examples of situations in which the
lb), excluding the furnishings, with the fuel consisting primarily assumed good performance of fire safety systems was compro-
of cellulosic material such as cardboard boxes, files, journals, mised. That does not mean, however, that the design criteria for
and reports. Varying quantities of plastic materials, such as ring fire protection systems should be adjusted to take into account all
binders and packing materials (bubble wrap and foam plastic), the extremes that can occur. In developing technical data for
and textiles, including clothing and duffel bags, were also noted input into design guides, a general application of good fire
in many scenarios. In addition, a chair was often partly posi- protection practice must be assumed. This includes the use of
tioned under the shielded area. “good housekeeping” and maintenance practices so that the
more extreme situations illustrated in the site reports provided in
Miscellaneous Storage the phase 1 report will not occur (Lougheed and Mawhinney
In surveys of both multi-tenanted buildings and single- 1996). Therefore, all the full-scale fire tests conducted as part of
occupant buildings, note was made of dedicated rooms or areas the investigations discussed in this paper conformed to the rele-
in buildings that were used for the storage of equipment and vant standards in force at the time of the tests.
supplies or the storage of documents and records. The storage
areas in single-occupant buildings were frequently isolated from Fire Scenarios Used for Full-Scale Tests
the main portion of the building; for example, large storage areas Shielding of fuel loads by tables and desks represented the
were found on basement levels with limited access by personnel. most common challenge observed during the site visits for a light
There were also situations in which large records storage hazard sprinkler system in an office building. As such, the
systems were found in open-plan office areas. For multi- primary series of full-scale tests was designed to investigate this
tenanted buildings, storage areas were found throughout the shielding scenario. An open-plan office furniture arrangement
building. The storage areas observed during the surveys would was used to investigate the impact of various parameters, includ-
be classified as “miscellaneous storage” based on section 1-4.2 ing fuel loading in the shielded areas, location of the test scenario
of NFPA 13 (NFPA 1994) and would be required to be protected relative to the sprinklers, and location of the ignition source. The
using a sprinkler system designed for an ordinary hazard (group results of this series of tests are the basis for the discussions in
2) occupancy, as defined in NFPA 13. this paper.
In addition to the open-plan office tests, limited tests were
Mercantile Occupancies conducted with two other shielded fire scenarios:
Retail and food services frequently occupy a portion of • Document Storage. A single test was conducted with a
mixed-occupancy buildings or building complexes. This document storage system similar to that observed in sev-
includes those situations in which mercantile occupancies, eral site visits. The storage scenario used for the tests con-
including malls, are linked to office complexes, as well as those sisted of documents stored on back-to-back metal shelving
cases in which the mercantile space is included in the lower units. The storage area was protected using an ordinary
levels of the building. In both situations, the mercantile areas are hazard (group 2) sprinkler system. The sprinklers were
frequently combined with walkways, concourses, and atrium able to control and eventually extinguish the fire. The heat
spaces and therefore constitute a problem that is outside the release rate, CO, and smoke production were limited by
scope of this project. However, since mercantile occupancies are the sprinklers (Lougheed and Carpenter 1996).
important elements in modern building complexes, typical • Single-Office Scenario. Two tests were conducted with a
shielded fire situations noted in mercantile areas were described full-scale single-office arrangement. A single sprinkler
in the phase 1 report (Lougheed and Mawhinney 1996). was used to protect the space. The sprinkler density was
approximately double the design density for a light hazard
Non-Code-Conformance occupancy. The sprinkler limited the heat release rate pro-
The site visits identified non-code-conformance as one of duced in this test to 250 kW or less. High CO and smoke
the critical issues that must be addressed in arriving at general levels were measured inside the compartment. However,
design criteria, not only for smoke management systems, but for limited smoke and CO were measured outside the com-
all fire protection systems for high-rise office buildings. There partment (Lougheed and Carpenter 1996).

396 ASHRAE Transactions: Symposia


In both these latter cases, the scenario as tested would was a structural column located near the center of the test area.
produce less of a challenge for a smoke control system in a sprin- This column consisted of a steel section protected by rock fiber
klered building than the open-plan office tests. It should, insulation and 6 mm (¼ in.) thick concrete board. The column
however, be noted that the tests conducted on document storage had a square cross section of 455 mm by 455 mm (1.5 ft by 1.5
systems and single offices were limited and care should be taken ft). This column, and two columns located adjacent to the east
in extrapolating the results to other scenarios. For document stor- and west walls of the test facility, supported a structural steel
age, this would include the use of nonmetal shelving units, beam used to support the concrete slab ceiling of the test facility.
compact storage systems, and archival storage in boxes A suspended ceiling system, giving a clear height of
(Lougheed and Carpenter 1996). approximately 2.74 m (9 ft), was installed throughout the test
facility. The concrete floor of the test facility was sloped toward
EXPERIMENT DESCRIPTION the east wall to allow water to drain into a central trench for
disposal. The ceiling height was 2.74 m (9 ft) at the west wall of
Test Facility the test facility and 2.8 m (9.1 ft) at the highest point in the south-
The test facility used for the previous investigations on east corner. The ceiling system was constructed using 0.6 m by
shielded fires (Mawhinney et al. 1992; Mawhinney and Tamura 1.2 m (2 ft by 4 ft) waterproof gypsum board panels mounted on
1994) was modified and expanded for the full-scale tests. The steel tracks.
expanded test facility, shown in Figure 1, had an overall floor Concrete board (6 mm [¼ in.] thick) was used to line the test
area of approximately 94 m2 (1,012 ft2). The only obstruction facility and the upper 1.2 m (4 ft) of the exhaust hood canopy

Dimensions are in meters unless otherwise indicated.


Figure 1 Sketch of test facility.

ASHRAE Transactions: Symposia 397


extension to the facility. The lower portion of the extension was the fire by room contents was maximized, resulting in conser-
designed to be left open to provide ventilation air for the fire. vative test conditions.
However, an initial test with sprinklers indicated that, with the Standard response 74°C (165°F) pendant sprinklers with a
cooling and mixing produced by the sprinkler spray, the 13-mm (½-in.) orifice were used for all tests. Water flow rates
combustion products were distributed over the height of the test were calculated on the basis that the water spray density should
space and could have escaped through the opening and not been meet the requirements of a light hazard sprinkler system. A
collected by the hood system (Figure 1). As a result, the openings design density of 4.1 L/min·m2 was determined in consultation
in the east wall and the northeast and southeast corners were with the ASHRAE project monitoring subcommittee prior to the
covered by polyethylene sheeting, leaving only the ventilation tests. Using this design density, the calculated water flow rate per
openings on the north and south sides of the facility as shown in sprinkler was 86 L/min.
Figure 1. These openings were approximately 1.43 m (4.7 ft)
high and provided a total ventilation area of 15.2 m2 (164 ft2). Full-Scale Open-Plan Fire Test Scenarios
The air inflow through these openings produced by the fan used
for the products of the combustion system was sufficient to mini- Seven full-scale fire tests were conducted using a “typical”
open-plan office furniture arrangement. The test scenario was
mize the loss of combustion by-products through them.
representative of that found in a standard 3 m by 3 m (10 ft by 10
ft) open-plan office including 1.2 m (4 ft) high office partitions,
Sprinkler System
a desk, a second desk or table used as a computer workstation, a
With the expanded test facility, a four-sprinkler, light- table, bookshelves above the desk, two or three office chairs, and
hazard occupancy system could be installed using the maxi- two four-drawer filing cabinets. A typical test arrangement is
mum spacing from the walls (2.3 m [7.5 ft]) and between sprin- shown in Figure 2. Commercial-grade carpet was used to cover
klers (4.6 m [15 ft]) allowed by NFPA 13 (NFPA 1994). The the concrete floor in the 3 m by 3 m (10 ft by 10 ft) test area.
locations of the four sprinklers in the test facility are shown in Boxes containing paper stock were used as the fuel load under
Figure 1. This sprinkler arrangement gave the maximum each table and desk in the primary test area.
protected area per sprinkler (20.9 m2 [225 ft2]) allowed by Typical furniture (desks, bookshelves, and filing cabinets)
NFPA 13. By using the maximum sprinkler spacing and cover- was also included in the adjacent office areas, as shown in Figure
age areas allowed by the installation standard, the shielding of 2. This furniture served two purposes:

Figure 2 Test room layout and instrumentation.

398 ASHRAE Transactions: Symposia


• additional shielding from the sprinkler spray for the fire • Gas inlets for acquiring gas samples to determine CO and
load, including by the office partitions used as the bound- carbon dioxide (CO2) concentrations were located at
ary for the primary fire test area; and three points in the test facility (Figure 2). The inlets were
• as a target for potential office-to-office fire spread. 0.15 and 1.2 m (0.5 and 4 ft) below the ceiling.
• Thermocouples were placed under each table and desk
There is a wide variation in materials used for office furni- located in the central fire area. The thermocouples were
ture, including solid wood (desks and tables), mixed materials located 50 mm (2 in.) below the desk or table top.
(e.g., steel-framed desks with wood tops and drawers), and solid
metal. For the tests conducted in this project, furniture with Products of Combustion Collector and Calorimeter
mixed materials was selected in the 3 m by 3 m (10 ft by 10 ft)
There was a 2.4 m by 4 m (7.8 ft by 13.1 ft) opening in the
fire area as being reasonably representative of the mix. This
ceiling in the southwest corner of the test facility connecting to
included the following:
a hood/duct system for a products-of-combustion calorimeter
1. A single- or double-pedestal desk with steel frame and wood (Figure 1). The bottom edge of the hood was flush with the
top and drawers (the total weight of the combustible mate- underside of the ceiling. The hood was connected through a 1.2-
rials was approximately 57 kg [126 lb] for a single-pedestal m3 (42.3-ft3) plenum to a 13 m (42.6 ft) long, 0.56 m (1.8 ft)
desk and 82 kg [181 lb] for a double-pedestal desk). diameter horizontal duct. A two-speed fan with a capacity of 3
2. A table with a wood top (37 kg [81.5 lb] combustible mate- to 4 m3/s (106 to 141 ft3/s) was connected to the downstream end
rial) or a single-pedestal desk (57 kg [126 lb]) with a wood of the duct. A thermocouple and a pitot-static velocity probe
top and drawers used as a computer workstation. were installed in the center of the exhaust duct, approximately 9
3. A table with a metal frame and a wood top (37 kg [81.5 lb] m (29.5 ft) from the center of the plenum. A pitot tube traverse
combustible material). test was conducted and a flow shape factor of 0.91 determined.
4. Two or three upholstered pedestal chairs with metal base An infrared smoke meter was located in the duct approxi-
(9.5 kg [21 lb] combustible material in each chair). mately 0.2 m (0.6 ft) downstream from the thermocouple loca-
5. Two four-drawer metal filing cabinets. tion. Provisions were made to continuously monitor CO, CO2,
6. Fabric-covered office partition (1.2 m by 1.5 m [4 ft by 5 ft]) and O2 concentrations at the centerline of the duct, 9.3 m (30.5
with fiber insulation, a wood frame, and a heavy metal mesh ft) from the center of the plenum. The duct measurements were
structural element (the textile covering and insulation were used to determine the heat release rate using the oxygen deple-
fire retarded and were difficult to burn in tests without tion method (Huggett 1980).
sprinklers).
7. A computer including monitor and keyboard (the computers Test Procedure
used for all except one test were of recent vintage and had All tests were conducted using the same procedure.
steel cases).
1. The data-acquisition system was started at time zero and
Details regarding the dimensions and location of the furniture recorded ambient conditions for two minutes prior to igni-
and other fuel loads for each full-scale open-plan office test tion of a propane T-burner used as the ignition source. All
are provided in the report for phase 2 of the project (Lougheed plots provided in this paper include data taken during the
and Carpenter 1996). two-minute pretest period.

Instrumentation for Open-Plan Office Fire Tests 2. At two minutes, the propane burner was ignited. The burner
design and heat release rate (approximately 25 kW) were
Instrumentation for the full-scale open-plan fire tests based on the ignition source used for standard tests for
included the following: furniture (ASTM 1994).
• Seven thermocouple trees were located in the test facility 3. At five minutes, the propane burner was shut off.
as shown in Figure 2. The thermocouples on each tree
4. The sprinklers were allowed to activate normally and the
were located 0.15, 0.61, 1.22, and 1.83 m (0.5, 2, 4, and
water flow rate was adjusted manually to provide the
6 ft) below the ceiling. Metal shields (approximately 400
required flow rate.
mm by 400 mm [1.3 ft by 1.3 ft]) were placed above each
thermocouple to shield it from direct water spray from 5. All tests were continued until the temperatures measured in
the sprinkler. the shielded areas indicated minimal fire remained in these
• Thermocouples were located adjacent to the fusible ele- locations.
ment of each of the four sprinklers (Figure 1).
• Pressure taps to measure the differential pressure MEDIUM-SCALE FIRE TEST RESULTS
between the test facility and the burn hall were located at A series of 23 medium-scale fire tests was conducted with
three heights on the west wall of the test facility (Figure a horizontal shielded area representative of a typical table or desk
2). The pressure taps were located 0.15, 1.22, and 2.29 m (0.9 m2 [9.6 ft2]). The medium-scale tests were conducted with
(0.5, 4, and 7.5 ft) below the ceiling. selected portions of the fuel packages used for the full-scale fire

ASHRAE Transactions: Symposia 399


tests. The term “medium-scale” is used to differentiate these tests 600 kW. This was consistent with tests conducted by
from typical small bench-scale fire tests used for hazard assess- Madrzykowski and Vettori (1992a, 1992b). The subse-
ment. The results of these tests are documented in the phase 2 quent decrease in heat release rate with sprinklers oper-
report for the project (Lougheed and Carpenter 1996) and are ating also was consistent with the results measured in the
summarized as follows. tests conducted by Madrzykowski and Vettori.
• Fuel packages with paper stock stored in cardboard boxes • For tests with office furniture and a paper stock fuel load in
for use as fuel loads in areas shielded by desks and tables the shielded area, CO was produced throughout the test,
were developed. The basic fuel package used for the tests with the initial CO production attributed to the furniture.
was a cardboard box filled with cellulosic material. The
boxes were standard document storage units that were
FULL-SCALE OPEN-PLAN OFFICE
365 mm by 500 mm by 305 mm (1.9 ft by 1.64 ft by 1.0
FIRE TEST RESULTS
ft) high. They included a separate lid and had a hand
opening in each end. Each box was filled to approxi- Seven full-scale fire tests (tests 23, 25, 26, 28, 29, 30, and
mately 50% capacity with loose paper in manila folders 31) were conducted using an open-plan office scenario. The
and bound material (reports, journals, and magazines). same general furniture arrangement shown in Figure 2 was used
The total weight per box was 9.5 kg (21 lb) including the for each test. This furniture arrangement was representative of a
box. Typical fuel loads were produced by using 4, 8, and general fuel package in a standard 3 m by 3 m (10 ft by 10 ft)
12 boxes in the shielded area. These fuel packages pro- open-plan office. It included three pieces of furniture that could
vided consistent peak heat release rates of approximately provide shielded areas (a desk, a second desk or table used as a
150, 275, and 400 kW, respectively. An initial high heat workstation, and a table).
release rate was produced followed by a decay to a steady Three main parameters were investigated using the open-
plateau phase with a lower heat release rate. plan office tests:
• The sprinklers were able to reduce the heat release rate
produced by the paper stock fuel loads in a shielded area. • Fuel load in shielded area. The fuel package under the
However, they were unable to completely extinguish the table(s) and desk(s) included a chair, a paper stock fire
fires in the shielded areas. Steady heat release rates of up load similar to those tested in the medium-scale tests, and
to 100 kW were measured with the heavier fuel loads a computer. The paper stock fuel load was varied to
under sprinklered conditions. include tests with light, medium, and heavy paper stock
• The paper stock fuel packages produced minimal CO fuel packages in selected areas. The heavier paper stock
during the initial stages of the fire. However, in later fuel packages were used under the table at the back of the
stages, once the paper stock became the predominant space. The fuel packages under the main desk and the
fuel, there was a rapid increase in the CO production. The workstation were limited to light to medium loads (two to
sprinklers did not decrease the CO production even eight boxes of paper stock). The total fuel packages in the
though there was a decrease in the heat release rate. shielded areas in the seven tests can be categorized as
• Tests with small quantities of plastic materials (packing light, medium, or heavy as summarized in Table 1.
materials) in the fuel packages resulted in a small • Location of test scenario relative to sprinklers. Four
increase in the heat release rate measured in tests with test arrangements were studied: (a) centered at the west
sprinklers. However, there was no increase in CO or wall between the southwest and northwest sprinklers, (b)
smoke production. with the table in the main office area centered under the
• Medium-scale tests with office furniture (chair, desk, and northwest sprinkler, (c) at the center of the four sprin-
office dividers) indicated peak heat release rates of 500 to klers, and (d) in the northwest corner of the test facility.
TABLE 1 Test Conditions for Full-Scale Open Plan Office Tests
First Sprinkler Heat Release Rate Number of
Fire Load in Test Ignition Activation First Sprinkler Sprinklers
Test Shielded Area Location Location Fire Extent (s) (kW) Activated
23 light A A table, work station 108 N/A 2
25 light A A table, work station, desk 220 500 1
26 light B A table, work station, desk 106 240 4
28 heavy C B table, work station, desk 140 240 4
29 medium D B table, work station, desk 134 180 1
30 heavy A B table, work station, desk 122 460 2
31 medium C B table, work station 162 N/A 4

400 ASHRAE Transactions: Symposia


The locations of the test arrangements used for the tests the office dividers were heavily fire resistant (textile covering
are summarized in Table 1. and fiber insulation). It required considerable time (more than 10
• Location of ignition source. All seven tests were con- minutes) to penetrate the barriers under nonsprinklered condi-
ducted using a propane T-burner as an ignition source. tions with direct fire exposure. It may be possible that, with other
Two different ignition scenarios were used in the full- office dividers, the fire could spread through the barriers to the
scale tests. In scenario A, the propane burner was placed shielded areas in adjacent offices. However, the fire scenarios
near the center of the paper stock fuel load located under used for the open-plan office tests were arranged such that the
the table at the back of the test arrangement. The burner fire could propagate to at least two, and in some cases three,
was located approximately 25 mm (1 in.) from the face of shielded areas. As such, the results of these tests are representa-
the boxes and approximately 50 mm (2 in.) above the tive of situations in which the sprinkler system is placed under a
floor. With this scenario, the initial fire involved a single severe challenge. The probability is considered low, even with
shielded area and could subsequently spread to the two lower fire-resistant office dividers, that the fire would involve
other areas, depending on the effectiveness of the sprin- more than three shielded areas. This assumption is consistent
kler system. In scenario B, the propane burner ignition with the results of a post-fire analysis conducted in the U.K.
source was used to ignite two boxes containing paper (Morgan and Hansell 1985). Those studies indicated that an
stock in the northwest corner of the test arrangement office fire in a sprinklered building was typically limited to an
between the table and the table/desk used as the worksta- area of 16 m2 (172 ft2) or less.
tion. With this scenario, the initial fire spread simulta-
neously into two shielded areas before sprinkler Heat Release Rate
activation. The fire could subsequently spread to the third The heat release rates for the seven full-scale open-plan
area, depending on the effectiveness of the sprinkler in office tests are shown in Figure 3. Some of the trends are as
controlling fire spread. The location of the ignition follows:
source for each test is summarized in Table 1. • For the tests such as test 26 using ignition scenario A with
The other parameters that impacted on the test results were the the primary ignition limited to the table, the sprinkler was
extent of fire spread during the tests and the number of sprin- able to limit the initial heat release rate to approximately
klers activated. The number of sprinklers activated and the 500 kW. However, as the fire spread to the two other
shielded areas involved in the fire in each test are noted in shielded areas (the desk and the workstation), there was a
Table 1. secondary peak in the heat release rate at approximately
The results of the full-scale open-plan office tests are docu- 10 to 12 minutes into the test. If both secondary shielded
mented in the report for phase 2 of the project (Lougheed and areas were involved in the fire, this secondary heat
Carpenter 1996). In this paper, the discussion is limited to the release rate was slightly higher (approximately 600 kW)
general trends for those parameters that can have an impact on than that produced by the first area involved in the fire.
the design of a smoke control system for a high-rise office build- • For the tests such as test 30 using ignition scenario B with
ing. This includes the sprinkler activation time and the extent of the propane burner located in the corner between the
fire spread, compartment temperatures, heat release rate, CO table and the workstation, there was a rapid increase in
production rate, smoke generation, and smoke movement. the initial heat release rate as the two areas became
involved in the fire. The location of the test arrangement
Sprinkler Activation in the center of the sprinkler array also tended to mini-
The time and approximate heat release rate at which the first mize the effectiveness of the first sprinkler activated and
sprinklers activated are shown in Table 1. The sprinkler activa- allowed rapid initial fire growth. With this arrangement,
tion times noted in the table are relative to the ignition time, the fire in the shielded areas was shielded not only by the
which was two minutes after the start of the test. table and the desks but also by the office dividers.
The activation time for the first sprinkler depended on the • For test 30, a peak heat release rate of 800 kW was mea-
location of the test scenario and ranged from 106 to 220 seconds. sured. This test also included a computer with a plastic
The heat release rate at activation of the first sprinkler was case under the main desk. This resulted in continued
between 200 and 500 kW. In several tests, the first sprinkler acti- higher heat release rates at the end of the test. The test
vated was able to localize the fire to the shielded areas but was was discontinued at 30 minutes due to excessive water in
unable to stop fire growth and spread in the shielded area. With the test facility.
the continued increase in heat release rate, further sprinklers • Only one sprinkler activated in test 25 and the sprinkler
were activated, with up to four sprinklers operating in some tests flow rate was set at approximately double that required to
(Table 1). provide the design density. However, even with the high
In all tests, the fire did not spread beyond the boundary of flow rate, there was continued fire growth, with a peak
the 3 m by 3 m (9.8 ft by 9.8 ft) office area, even though the heat release rate of approximately 900 kW. The video
temperatures in the shielded areas reached up to 800°C records and temperature profiles in the shielded areas
(1472°F). It should be noted, however, that the materials used in indicated that the main fire source was located in the

ASHRAE Transactions: Symposia 401


workstation area that was on the side of the test arrange- Three heat release rate models are proposed in the litera-
ment with the active sprinkler. As such, the fire was ture for sprinklered office fires. In the following, the results of
shielded from the sprinkler spray not only by the desk but the full-scale open-plan office tests are compared to each of
also by the office divider, minimizing the sprinkler spray those models.
able to reach the fire zone.
1. U.K. Design Fire (Hansell and Morgan 1994). In the
• The lowest heat release rates were measured in test 29. U.K., steady-state fires for use in the design of smoke control
In this case the test arrangement was located in the systems have been developed. These fires were based on a
northwest corner of the test facility. The protection was review of fire incidents in the U.K. A steady-state fire is
provided solely by the northwest sprinkler. However, assumed, as it is considered to provide a conservative basis for
this sprinkler was located within the perimeter of the the design of a smoke control system. For an office building, the
test arrangement and the sprinkler spray had good design fire is assumed to be 6 MW for a nonsprinklered building
access to the fire under the table and the workstation. and 1 MW for a sprinklered building (Morgan and Hansell
The highest heat release rate was measured later in the 1985). The area of the fire is assumed to be 16 m2 (172 ft2) and
test when the fire propagated to the main desk area clos- 47 m2 (506 ft2) for the sprinklered and nonsprinklered cases,
est to the sprinkler. respectively. A comparison with the full-scale test results shown
• During the initial fire growth phase, the fire did involve in Figure 3 indicates that, in the initial phase, the U.K. design fire
fuel placed on the desk and table surfaces. Once the sprin- provides a conservative estimate (10% to 20% higher) of the
klers activated, the fires in the full-scale tests were limited initial peak heat release rate. However, at the later stages, there
to the fuel packages under the shielded areas. As such, the is a continuous decrease in the measured heat release rate, with
heat release rates measured in the full-scale tests can be the result that the steady-state design curve becomes increas-
considered a superposition of the heat release rates pro- ingly conservative.
vided by fires in two or more shielded fuel packages. 2. NFPA 92B (NFPA 1995). In NFPA 92B, it is suggested
for atrium applications that, for sprinklered buildings, an
The heat release rates measured in the full-scale tests are increasing heat release rate should be assumed for a fire until the
consistent with those obtained in the medium-scale tests. The sprinklers are activated. Subsequently, the heat release rate is
medium-scale tests indicated a peak heat release rate in the range assumed to be constant. For the present tests, the first sprinkler
of 300 to 600 kW for each shielded area, depending on the time activated for heat release rates in the range of 200 to 500 kW,
of activation and effectiveness of the sprinkler(s). The medium- depending on the location of the ignition source relative to the
scale tests also indicated a decay in the heat release rate to 50 to sprinkler. This is assuming that a steady-state heat release rate in
100 kW for a shielded area at 15 to 20 minutes after ignition. this range would not provide a conservative estimate of the heat

Figure 3 Heat release rates.

402 ASHRAE Transactions: Symposia


release rates measured in the full-scale tests. In particular, the vides a conservative estimate of the heat release rate measured
NFPA procedure would not take into account the continued fire in the full-scale open-plan office tests.
growth after first sprinkler activation and the potential for the fire This suggested heat release rate for a design fire was based
spreading to secondary shielded areas. It should be noted, on a series of full-scale tests that included factors that would
however, that the NFPA 92B design fire for sprinklered appli- potentially increase the challenge for the sprinkler system. These
cations was developed for atrium applications and not necessar- included:
ily for office areas. • an initial fire involving two shielded areas,
3. NIST Office Tests (Madrzykowski and Vettori 1992a, • a secondary fire involving two shielded areas,
1992b). Based on a series of office fire tests, Madrzykowski and • medium to heavy fuel loads in the shielded areas under
Vettori developed an estimate for the heat release rate from a the tables and desks,
sprinklered office scenario. An empirically based sprinkler fire • operation of the sprinkler system at the design density,
suppression algorithm was developed in which it was assumed • use of a sprinkler system with the maximum allowable
that, subsequent to sprinkler activation, the heat release rate spacing between sprinklers and coverage areas allowed
would decrease exponentially. This estimate for the heat release by standards, and
rate provided a conservative estimate for all the tests conducted • use of fire scenarios in which the spray from the initial
by Madrzykowski and Vettori except the secretarial scenario, sprinkler activated was shielded by both horizontal
which included a paper stock fuel package under a desk. This (desk/table) and vertical (office partitions) obstructions.
model, in its present form, would not provide a conservative esti-
Based on the above factors, it is suggested that the composite
mate of the heat release rates measured in the full-scale open-
heat release rate for a sprinklered office fire shown in Figure 3
plan office tests. As with the NFPA 92B model, this model does
would provide a conservative basis for the design of smoke
not take into account the continued fire growth after first sprin-
control systems in an office building in areas protected by a
kler activation and the potential for the fire spreading to second-
sprinkler system designed for a light hazard occupancy. It is
ary shielded areas. Also, as discussed by Madrzykowski and
less conservative than the steady-state heat output commonly
Vettori, the sprinkler fire suppression algorithm they developed
used in the U.K. (Hansell and Morgan 1994). It is, however,
did not take into account fuel loads stored under desks and tables.
more conservative than the heat release rates based on the tests
Design Fire for Sprinklered Office Buildings conducted by Madrzykowski and Vettori (1992a, 1992b) or on
present NFPA (1995) requirements.
The Madrzykowski and Vettori model, along with the U.K.
design fire, provide a basis for developing a general design fire Temperature and Pressure
for smoke control applications in a sprinklered office building as
Accepted practice for the design of zoned smoke control
follows:
systems in sprinklered buildings requires that a pressure differ-
• For t < 240 seconds after ignition, a steady-state fire with
ence of at least 12.5 Pa be maintained across a smoke barrier
a heat release rate of 1,000 kW could be assumed. Alter-
separating the fire zone from a protected zone (NFPA 1993;
natively, a t-squared fire could be assumed for the initial
Klote and Milke 1992). For sprinklered buildings, the minimum
fire growth. The growth constant for a fast fire scenario
pressure difference is independent of ceiling height. For compar-
(α = 0.04689 giving a growth time to 1,000 kW of 150
ison, a minimum required pressure difference of 25 Pa is
seconds [NFPA 1995]) provides a conservative estimate
suggested for an unsprinklered building with a ceiling height of
of the fire growth measured in the full-scale tests.
2.74 m (9 ft). The unsprinklered case is calculated using the
• For t > 240 seconds after ignition, the peak heat release
following equation assuming a gas temperature of 925°C
rate of 1,000 kW is decreased using an exponential decay
(1697°F) adjacent to the smoke barrier:
equation similar to that used by Madrzykowski and Vet-
tori (1992a, 1992b). In order to take into account the fire ∆P = Ks ( 1 ⁄ T o – 1 ⁄ T f )H (1)
in the shielded areas at later times, a smaller decay con-
stant of 0.00155 could be used compared with the 0.0023 where
used by Madrzykowski and Vettori. ∆P = pressure difference across the smoke barrier (Pa),
The heat release rate based on the above relations is shown in Ks = coefficient (3460),
Figure 3 with the heat release rates measured in the full-scale To = ambient or reference temperature (K),
tests. The estimated heat release rate uses the t-squared Tf = temperature of fire gas at smoke barrier (K), and
approximation for the initial phase of the fire. The starting
H = ceiling height (m).
time for the simulated heat release rate is taken as 2 minutes,
40 seconds, on the time scale used for the plots. This takes into The ceiling temperatures measured 150 mm (6 in.) below the
account the ignition time, which was at 2 minutes for all tests, ceiling of the test facility at the thermocouple tree locations
and the approximate 40-second delay in the heat release rate shown in Figure 2 are given in Figure 4 for a typical test (test
measurements as a result of transit time in the duct and gas 30). The highest temperature (up to 325°C [617°F]) was mea-
analysis system. The composite heat release rate curve pro- sured at the ceiling in the immediate area of the fire for a dura-

ASHRAE Transactions: Symposia 403


Figure 4 Temperatures 150 mm below ceiling—Test 30.

tion of less than one minute. At this temperature, the pressure door to the stairshaft was opened, the stairshaft was rapidly
at or shortly after initial sprinkler activation would exceed the contaminated with smoke, even at the low buoyancy pressures
12.5 Pa minimum pressure difference recommended in NFPA produced by the sprinklered fires.
92A (NFPA 1993). However, the time during which the pres- In addition to the temperatures measured in the test facility,
sure exceeded 12.5 Pa (temperature increase > 200°C the temperatures were also measured in the duct in tests with and
[392°F]) was only approximately 60 seconds. After this initial without the exhaust operating. Peak temperatures were up to
high-temperature spike, the temperature increase at the ceiling 125°C (257°F) at, or shortly after, sprinkler activation. Full-scale
was less than 200°C (392°F) and, in many cases, less than tests with a propane burner system indicated that heat release
100°C (212°F) even in the immediate fire area. These results rates of more than 1,000 kW would be required to sustain
indicate that the 12.5 Pa minimum design pressure suggested temperatures in excess of 100°C (212°F) in the duct with the
by NFPA 92A (NFPA 1993) would be adequate for zone sprinkler system operating (Lougheed and Carpenter 1996).
smoke control applications in sprinklered office buildings. In
fact, in most cases, a lower pressure (approximately 7 Pa) CO Concentrations
would still exceed the pressure produced by the fire gases. Incapacitation by CO depends upon the dose accumulated
The temperature/pressure results measured in the full- over a period until carboxyhemoglobin concentrations exceed
scale tests are consistent with those obtained by Mawhinney incapacitation levels (Purser 1995). The intake of CO is a func-
and Tamura (1994) in the tests conducted in a single compart- tion of a number of factors, including the level of activity of the
ment under steady-state conditions. They measured pressure subject. Estimates for tenability for incapacitation by CO
differences of 4 to 6 Pa in the tests in a compartment with the provided by Purser (1995) are: 6,000 to 8,000 ppm (0.6% to
sprinkler system providing the design density for a light hazard 0.8%) for 5-minute exposures and 1,400 to 1,700 ppm (0.14% to
occupancy. 0.17%) for 30-minute exposures.
It is accepted practice to only pressurize adjacent floor The CO concentrations measured at the ceiling at the north-
zones and to rely on mechanical exhaust from the fire zone and west corner and southeast/center of the room are shown in
leakage from the pressurized floors into a stairshaft to develop a Figures 5 and 6, respectively. The CO levels measured in these
pressure differential between the stairshaft and the fire floor. tests were in the range that could produce incapacitation with
Tests conducted in a 10-story tower facility (Mawhinney and extended exposure. They were, however, by a factor of two to
Tamura 1994) indicated that a zoned smoke control system with three lower than the peak levels measured by Mawhinney and
a pressure difference of 12.5 Pa was able to prevent smoke Tamura (1994). There are a number of factors that can affect the
spread into a stairshaft or between floors from a shielded fire as CO levels, including the heat release rate from the fire, the type
long as the door to the fire floor was closed. However, when the of fuel, the volume of the test space, and the ventilation rate.

404 ASHRAE Transactions: Symposia


Figure 5 CO concentrations—NW top corner of room—open-plan office tests.

Figure 6 CO concentrations—top center of room—open-plan office tests.

Further analysis is required to fully assess the differences production as the primary fuel load changed from the cardboard
between the two results. boxes to the paper stock contents. As with the full-scale tests, the
In the current tests, the CO levels remained relatively rate of CO production did not decrease even though there was a
constant over an extended period (20 to 30 minutes) even though decrease in the heat release rate with the sprinklers activated
the heat release rate was decreasing. The CO2 levels, measured (Lougheed and Carpenter 1996).
at the same locations in the test facility as the CO measurements, The CO results obtained from the full- and medium-scale
indicated that there was a higher concentration of the fire gases tests do not indicate an increase in CO production in an office fire
in the upper corners of the test facility. However, the general with sprinklers. In fact, taking into consideration recent studies
trend showed a decreasing concentration consistent with the that indicate that, for furniture (Sundström 1995), the rate of CO
decrease in heat release rate (Lougheed and Carpenter 1996). As production is related to the heat release rate, a considerably
such, the steady-state CO results indicate that, although there higher rate of CO production would be expected for an uncon-
was a reduction in the heat release rate with decreasing fire load trolled office fire without sprinklers.
in the shielded area and from the effects of the sprinklers, the Further analysis of the full-scale test results is required
smoldering fire in the paper stock in the shielded areas, which before a CO production rate based on the suggested design fire
was the primary source of CO, was not affected by the sprinklers. can be determined. However, initial estimates can be determined
These observations are consistent with the results obtained using the CO concentrations measured in the exhaust duct
in the medium-scale tests with paper stock fuel loads. In the (Figure 7). For the tests with the fan operating, CO concentra-
medium-scale tests, it was noted that there was an increase in CO tions were 0.05% to 0.15% in the duct. Assuming an air density

ASHRAE Transactions: Symposia 405


Figure 7 CO concentrations—exhaust duct—open-plan office tests.

of 1 kg/m3 (a temperature of approximately 350 K) and a flow 0.2 OD/m, respectively, for subjects not familiar and
rate of 3 m3/s in the exhaust duct, the CO measurements indicate familiar with an escape route.
approximately 0.1 to 0.5 g/s of CO were produced in the full- • Rasbash (1975) suggested a 10-m (33-ft) visibility limit,
scale tests. The initial CO production rate is consistent with the which is equivalent to 0.08 OD/m.
results of furniture calorimeter tests on office chairs conducted • Babrauskas (1979) suggested a tenability limit of 0.5
by Sundström (1995). Office chairs with peak heat release rates OD/m.
of 486 kW and 829 kW produced peak CO rates of 0.33 and 0.46 • Wakamatsu (1968) suggested a tenability limit of 0.043
g/s, respectively. OD/m, which was assumed to be 1:100 of the optical den-
sity in the fire region.
Smoke Production and Movement
The smoke obscuration measured in the full-scale open-plan
The smoke obscuration for an open-plan office test office tests indicated the smoke levels in the test facility were
measured in the northwest and southeast corners of the test facil- in the range of 1 to 10 OD/m. These levels were higher than
ity is shown in Figures 8 and 9, respectively. The smoke obscu- the generally accepted tenability limits (0.045 to 0.5 OD/m)
ration measured in the exhaust duct is shown in Figure 10. suggested above.
Various tenability limits for smoke obscuration have been There is limited information available regarding the maxi-
proposed as follows: mum level of smoke likely to be found in fires. Tamura (1994)
• Jin (1981) suggested tenability limits of 0.06 OD/m and suggests, based on a review of existing data, that 4 to 10 OD/m

Figure 8 Smoke obscuration—nw corner of test room—open-plan office tests.

406 ASHRAE Transactions: Symposia


Figure 9 Smoke obscuration—SE corner of test room—open-plan office tests.

Figure 10 Smoke obscuration—exhaust duct—open-plan office tests.

could be considered as the limiting level for adverse fire condi- concentration measured in the duct were in the range of 1 to 2
tions. As such, the smoke levels measured in the test facility are OD/m and 0.2% to 0.25%, respectively (Figures 7 and 10).
comparable to those noted in the literature for tests without sprin-
These results are consistent with those obtained by
klers. Taking into consideration the lack of mobility of cold
Mawhinney and Tamura (1994). They noted that, in the tests
smoke, this result is not unexpected and, as with the CO gener-
conducted in the tower facility, the use of a zoned smoke control
ation, does not indicate that smoke production is comparable to
system confined the smoke to the fire floor when the door to the
that of the unsprinklered fires.
stairshaft was closed. For these tests, a mechanical system was
In test 31, there was smoke flow through the exhaust duct
used to exhaust the fire floor at a rate of 4.8 to 5.1 air changes per
even though the fan was not operating. The volumetric flow rate
hour (ACH). However, for tests without smoke control, smoke
is shown in Figure 11. The duct was connected to the outside of
did spread to floors above the fire floor through leakage open-
the main test building, with the initial airflow produced by the
ings. Also, the stairshaft became smoke-logged within minutes
temperature difference between the test facility and outside
after opening the door, with complete loss of visibility and
ambient conditions. The volumetric flow measurements indicate
temperatures of more than 65°C (149°F).
a peak flow rate of up 0.25 m3/s (8.82 ft3/s) through the duct.
Since the duct had a cross-sectional area of 0.25 m2 (2.7 ft2), For the tests with the smoke control system, the mechanical
these results indicate a maximum smoke flow rate of approxi- exhaust of the fire floor was not sufficient to prevent the spread
mately 1 m3/s (35.3 ft3/s) per square meter (square foot) of leak- of smoke into the stairshaft when the door on the fire floor was
age area across a smoke barrier. For approximately 10 minutes opened. The flow of smoke into the stairshaft could be stopped
after first sprinkler activation, the smoke obscuration and CO by providing a minimal flow of air into the stairshaft by either

ASHRAE Transactions: Symposia 407


Figure 11 Volume flow rate in duct—Test 31 (fan not running).

opening one of the doors on a pressurized floor or by opening the furniture arrangement. The results of these tests, including the
door to the building exterior at the bottom of the shaft. impact on zoned smoke control systems, are summarized as
The potential impact of the smoke flow through leakage follows.
areas will depend on smoke movement and dilution in the build-
1. Fire Spread. The sprinklers were able to control the fire
ing outside the fire zone. Without computer modeling, it is diffi-
within the limits of the 3 m by 3 m (10 ft by 10 ft) office area.
cult to assess the extent of the smoke hazard in a multistory office
However, the fire was able to spread to secondary shielded areas
building. Computer studies similar to those conducted by Waka-
in the same office while the sprinklers were operating. After the
matsu (1968) and McGuire et al. (1970) for nonsprinklered
first sprinkler was activated, the fire was localized in the areas
buildings are required. The full-scale open-plan office tests can
shielded by the desks and tables.
be used to determine the conditions (heat release rate, tempera-
ture, pressure, CO production rate, and smoke generation) for a 2. Heat Release Rate. Peak heat release rates of up to 800
design fire for use with a multizone model, such as CONTAM to 900 kW were measured for tests that initially involved two
(Walton 1993), to investigate the extent of the hazard in a sprin- shielded areas (desk/table). The heat release subsequently
klered office building. decayed exponentially, with heat release rates of 100 to 200 kW
measured 25 to 30 minutes after ignition. The heat release rates
SUMMARY measured in the open-plan office tests were consistent with those
Zoned smoke control systems are used to limit smoke flow measured in a series of medium-scale tests and with the office
through cracks in floors and partitions and through nonpressur- tests conducted by Madrzykowski and Vettori (1992a, 1992b).
ized shafts that threatens life and damages property at locations Based on the heat release rates measured in the open-plan office
remote from the fire (NFPA 1993; Klote and Milke 1992). In fire tests, a heat release rate for a design fire for use in sprinklered
addition, measures to limit fire size (mass burning rate) can be office buildings was developed. This design fire is consistent
used to increase the reliability and viability of such systems with the suppression algorithm developed by Madrzykowski
(NFPA 1993). Methods to limit fire size include fuel control, and Vettori (1992a, 1992b) and the steady-state heat release rate
compartmentation, and automatic sprinklers. In this paper, the used in the U.K. (Hansell and Morgan 1994) (see Figure 12). The
effects of a sprinkler system on heat release rate, compartment proposed design fire, in principle, assumes an initial fire involv-
temperatures and pressures, CO production, and smoke genera- ing two shielded areas subsequently spreading to two secondary
tion and movement were summarized based on the results of a shielded areas and thus could be considered a conservative chal-
series of full-scale open-plan office fire tests. lenge for a light hazard sprinkler system in an office building.
Seven full-scale open-plan office tests were conducted The proposed heat release rate curve, determined on this basis,
using a “typical” 3 m by 3 m (10 ft by 10 ft) open-plan office is less conservative than the U.K. steady-state design fire but

408 ASHRAE Transactions: Symposia


Figure 12 Heat release rate for design fires.

more conservative than the suppression algorithm developed by Higher smoke levels were measured in the duct in test 31 when
Madrzykowski and Vettori. the fan was not operated. Also in this test, there was smoke flow
3. Temperature and Pressure. The highest temperatures through the duct during the test. These results indicate that the
in the test compartment were measured at or shortly after the operation of a sprinkler system is not sufficient to completely
activation of the first sprinkler. The highest temperatures stop smoke flow through leakage areas in a smoke barrier.
measured at the ceiling in the immediate fire zone were up to However, the potential impact of such smoke flow will depend
325°C (617°F). Such temperatures could result in pressures on the smoke movement and dilution in the building outside of
slightly higher than the 12.5 Pa generally required by standards the fire zone. Computer studies similar to those conducted by
for smoke control systems in office buildings. However, the Wakamatsu (1968) and McGuire et al. (1970) would be required
duration for temperatures in excess of 200°C (392°F) was to determine the extent of the hazard of the smoke in a multistory
limited to less than 60 seconds. As such, the 12.5 Pa minimum office building.
design pressure suggested by NFPA 92A (NFPA 1993) should 6. Opposed Airflow. The airflow through the ventilation
be adequate for zoned smoke control system design. In most openings produced by the exhaust fan was sufficient to keep the
cases, a minimum design pressure of 7 Pa would be sufficient. smoke produced by the sprinklered fires from leaking through
4. CO Concentrations. The CO levels (0.1% to 0.5%) the openings. However, this may be due, in part, to the effect of
measured in the test facility were generally higher than the long- the exhaust system on temperatures at lower levels (Lougheed
term tenability limits. The CO concentrations remained rela- and Carpenter 1996). Based on temperatures measured in test 31
tively constant throughout the test, with the CO produced in the and the equation for opposed airflow in NFPA 92B (NFPA
latter stages of the test attributed to fires in the paper stock in the 1995), airflow velocities of 0.5 to 1.0 m/s (1.64 to 3.28 ft/s) may
shielded areas. The initial CO production rate was consistent be required to keep the smoke from entering adjacent areas. The
with peak rates measured in furniture calorimeter tests for office results are consistent with the recommendation by Mawhinney
chairs (Sundström 1995). and Tamura (1994) that small airflows between the area to be
5. Smoke Levels and Smoke Movement. Smoke levels in protected and the fire zone were helpful in preventing the spread
excess of the normally accepted tenability limits were measured of smoke.
throughout the test facility shortly after the first sprinkler acti-
ACKNOWLEDGMENTS
vated. With the exhaust fan operating, lower smoke obscuration
was measured in the exhaust duct than in the test facility. It was This research was carried out as a joint research project
suggested that the smoke entering the duct was diluted by fresh supported by the American Society of Heating, Refrigerating
air entering the test room through the ventilation openings. and Air-Conditioning Engineers, Inc., and the National

ASHRAE Transactions: Symposia 409


Research Council of Canada. Appreciation is extended to J.R. Madrzykowski, D., and R. Vettori. 1992b. A sprinkler fire
Mawhinney for his help in conducting the studies in phase 1 of suppression algorithm. J. of Fire Prot. Engr. 4: 151-164.
the project and in setting up the sprinkler system for the full-scale Mawhinney, J.R., and G.T. Tamura. 1994. The effect of
tests. Appreciation is also extended to D.W. Carpenter, M. automatic sprinkler protection on smoke control sys-
Wright, M. Ryan, R. Onno, P. Richardson, and P. Leroux, who tems. ASHRAE Transactions 100(1): 494-513.
were instrumental in setting up the test facility, conducting the Mawhinney, J.R., D.W. Carpenter, R.A. MacDonald, and
tests, and plotting the data. G.T. Tamura. 1992. Experiments involving shielded,
sprinklered fires in a building equipped with a zoned
REFERENCES smoke control system. Report CR-6470.7. Ottawa, Ont.:
National Research Council Canada.
ASTM. 1994. Test method for fire testing of real scale
McGuire, J.H., G.T. Tamura, and A.G. Wilson. 1970. Fac-
upholstered furniture items. E 1537. Philadelphia:
tors in controlling smoke in high buildings. In ASHRAE
American Society for Testing and Materials.
Symposium Bulletin SF-70-2, Fire Hazards in Build-
Babrauskas, V. 1979. Technical note 1103. Gaithersburg, ings, pp. 8-13. Atlanta: American Society of Heating,
Md.: National Institute of Standards and Technology. Refrigerating and Air-Conditioning Engineers, Inc.
Hansell, G.O., and H.P. Morgan. 1994. Design approaches Morgan, H.P., and G.O. Hansell. 1985. Fire sizes and sprin-
for smoke control in atrium buildings. BR 258. Bore- kler effectiveness in offices—Implications for smoke
hamwood, U.K.: Building Research Establishment. control design. Fire Safety Journal 8: 187-198.
Huggett, C. 1980. Estimation of heat release by means of NFPA. 1993. NFPA 92A, Recommended practice for smoke-
oxygen consumption measurements. Fire and Materials control systems. Quincy, Mass.: National Fire Protec-
4: 61. tion Association.
Jin, T. 1981. Studies of emotional instability in smoke from NFPA. 1994. NFPA 13, Standard for the installation of
fire. Journal of Fire and Flammability 12: 130-142. sprinkler systems. Quincy, Mass.: National Fire Protec-
Klote, J.H. 1990. Fire experiments of zoned smoke control at tion Association.
the Plaza Hotel in Washington, DC. NISTIR 90-4253. NFPA. 1995. NFPA 92B, Guide for smoke management sys-
Gaithersburg, Md.: National Institute of Standards and tems in malls, atria, and large areas. Quincy, Mass.:
Technology. National Fire Protection Association.
Purser, D. 1995. Toxicity assessment of combustion prod-
Klote, J.H., and J.A. Milke. 1992. Design of smoke manage-
ucts, The SFPE handbook of fire protection engineer-
ment systems. Atlanta: American Society of Heating,
ing. Quincy, Mass.: National Fire Protection
Refrigerating and Air-Conditioning Engineers, Inc.
Association.
Lougheed, G.D., and D.W. Carpenter. 1996. Probability of Rasbash, D.J. 1975. Sensitivity criteria for detectors used to
occurrence and expected size of shielded fires in sprin- protect life. Fire International 5: 30.
klered buildings—ASHRAE RP-838—Phase 2, Full- Sundström, B. 1995. Fire safety of upholstered furniture—
scale fire tests. Report A4201.10. Ottawa, Ont.: Final report on the CBUF research programme. London:
National Research Council Canada. Interscience Communications Limited.
Lougheed, G.D., and J.R. Mawhinney. 1996. Probability of Tamura, G.T. 1994. Smoke movement and control in high-
occurrence and expected size of shielded fires in sprin- rise office buildings. Quincy, Mass.: National Fire Pro-
klered buildings—ASHRAE RP-838—Phase 1. Report tection Association.
A4201.5. Ottawa, Ont.: National Research Council Can- Wakamatsu, T. 1968. Calculation of smoke movement in
ada. buildings. Research Paper Number 34. Tokyo: Building
Madrzykowski, D., and R. Vettori. 1992a. A sprinkler fire Research Institute.
suppression algorithm for the GSA engineering fire Walton, G. 1993. CONTAM93: User manual. NISTIR 5385.
assessment system. NISTIR 4833. Gaithersburg, Md.: Gaithersburg, Md.: National Institute of Standards and
National Institute of Standards and Technology. Technology.

410 ASHRAE Transactions: Symposia

Você também pode gostar