Escolar Documentos
Profissional Documentos
Cultura Documentos
1 Scope................................................................ 2
2 Purpose............................................................. 2
3 Conflicts and Deviations……………………...…. 2
4 Applicable Documents....................................... 3
5 Definitions and Abbreviations............................ 4
6 Instructions……………………………………….. 6
7 Responsibilities................................................ 12
1 Scope
1.1 Minimum requirements for reporting inspection findings during Testing and
Inspection (T&I).
1.2 Minimum technical content for the pre-T&I, post-T&I and the Summary report
covering the pre- and post- T&I activities.
1.3 Mandate for a minimum of four reports namely Pre-T&I Report, Post-T&I
Report, T&I Summary Report and Repair Data Report.
2 Purpose
This SAEP provides a summary of minimum requirements for T&I reporting for
operating facilities to ensure:
2.1 Critical inspection information is documented and available for pre-, during, and
post- T&I work.
2.2 Critical inspection findings are recorded and reported in a consistent format for
planning and execution.
2.3 Documents are properly organized, controlled, safely stored, trackable and
retrievable in a manner consistent with the intent of 00-SAIP-78.
2.4 Reporting requirements are specified and standardized companywide for all
phases of the reporting period.
3.1 Conflicts
Any conflicts between this procedure and other applicable Saudi Aramco
Engineering Procedures (SAEP's), Saudi Aramco Engineering Standards
(SAES's), Materials System Specifications (SAMSS's), Standard Drawings
(SASD's), or industry standards, codes, and forms shall be resolved in writing by
the Company or Buyer Representative through the Chairman, Inspection
Engineering Standards Committee of Saudi Aramco.
Page 2 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
4 Applicable Documents
The requirements contained in the following documents apply to the extent specified in
this procedure:
Page 3 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Material Take Off List: List of materials identified for replacement at future T&I.
Page 4 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
PIU: Plant Inspection Unit in operating department. Same as Operations Inspection Unit.
T&I Reports
a) Pre-T&I Report: A summary report generated by the Plant Inspection Unit
twelve (12) months before T&I that contains the details of the intended work to be
executed during T&I. The format of this report shall be as per requirements of this
procedure. This report shall be uploaded to SAIF system.
b) Post T&I Report: A detailed report describing the scope, extent and findings of
testing and inspection activities completed including all associated NDT reports
and recommendations. The format of this report shall be as per requirements of
this procedure. This report shall be uploaded to SAIF system.
c) T&I Summary Report: A summary report generated by the Plant Inspection Unit
after the T&I which contains brief detail of the work done during T&I, short note on
lessons learned in the whole cycle
(from pre-T&I to box-up) and recommendations for future T&I. A recommended
format of this report is outlined in this procedure however, other formats acceptable
to proponent management can be used for the Summary Report only. The format
used shall be uploaded to the SAIF system.
d) Repair Data Report: A detailed report describing the repair work done during
T&I. This report shall be uploaded to SAIF system.
T&I (Testing and Inspection): Testing and Inspection (T&I) is a scheduled, time-
based activity governed by an approved Equipment Inspection Schedule (EIS) for
shutting down an equipment for a pre-determined period, to execute pre-determined,
well-defined inspection and maintenance tasks. The main purpose of T&I is to ensure
and document the mechanical integrity, operability and safety of the covered equipment
for continued operation. The T&I activities are performed at intervals determined by
SAEP-20 “Equipment Inspection Schedule”. Every plant equipment that is included in
the EIS is subject to a scheduled T&I. The T&I can involve a single piece of
equipment, multiple equipment and/or total plant shutdown. In SAIF, this is
represented by the T&I number.
Page 5 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
T&I Number: A T&I package number that is generated by the SAIF system, which
can contain one or multiple T&I notification.
6 Instructions
6.1.1 OIU shall prepare pre T&I reports which shall include:
a) Equipment number
b) Inspection findings and recommendations from previous T&I
c) On-Stream Inspection (OSI) recommendations as per SAEP-1135
d) Pending Inspection Defect Notifications (previously Work Sheets as
per 00-SAIP-76)
e) Revamps /project proposals and recommendations.
6.1.2 The Pre-T&I Report shall be issued prior to T&I start date as required by
proponent department manager but not later than three (3) months prior,
in the absence of proponent management mandate; to:
a) Maintenance T&I planning
b) Operations division head
c) Maintenance division head (to be added as interested party for the
T&I notification (I5) in SAIF)
d) Engineering division head (shall be added as interested party for the
T&I notification (I5) in SAIF)
6.1.3 The Pre-T&I report shall contain all scheduled T&I in SAIF.
6.1.4 The Pre T&I planning shall be based upon the information obtained from:
a) Pending Defect Notifications (Work Sheets).
b) External inspection reports.
c) Previous T&I recommendations and material take off list.
d) On-Stream Inspection (OSI) records.
e) Risk Based Inspection (RBI) report recommendation – SAEP-343.
f) Leaks history.
g) Number of OSI (CML) locations at Tmin or below and corrosion
service class as per SAEP-1135.
Page 6 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
6.1.5 The contents of the Pre T&I report shall include but not limited to:
a) Facility and the plant description.
b) Processing unit description.
c) Details on individual equipment scheduled in the T&I
d) Details of the work flow for internal and external maintenance work
including the following requirements:-
i. Blinding equipment.
ii. Scaffolding requirements.
iii. Lighting requirements.
iv. Requirements for removal/addition of insulation.
v. Method(s) for cleaning, specifying the special requirements
based upon the normal contents of the equipment, material of
fabrication, future operation needs, internal attachment
details, etc.,
vi. Details of the internal attachments to be dismantled for
inspection and repair.
vii. Details of the repairs already known from the operation
history, inspection reports, previous T&I recommendations
and the pending worksheets.
viii. Welding procedures and details on consumables, if already
known.
ix. Details of the coating requirements, including the removal of
existing coating, type and extent of the blasting/cleaning
requirements, stating the appropriate coating type and
procedure.
x. Details of the expected repairs based upon previous
experience and the operational history of the equipment.
xi. Inspection Test Plans showing planned inspection hold points
during the opening, dismantling of the internal attachments,
Page 7 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
6.2.1 All reports shall have the following information on the front page, as
applicable:
a) Report number and date prepared
b) Equipment No. & Service, Location/Area, Plant No.
Page 8 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
6.2.4 The Post T&I Report shall include, as-found condition, defect/damage
mechanisms found, repairs completed (partial and/or full repairs) and
recommendations for the future such as:
a) Full details of any repairs or renewals which were carried out and
forecast probable repairs or renewals which will be required at the
next inspection.
b) Areas not accessible for inspection and reasons why.
c) Details on inspection techniques used, including procedures where
appropriate and areas inspected.
Page 9 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
6.3.2 Shall summarize all of the work done during the T&I, and the
recommendations for the next T&I. The specification and other
descriptive details of each piece of static equipment inspected in the T&I
will be separately tabulated.
6.3.3 T&I summary report shall be issued by OIU Supervisor within 60 days
after completion of the T&I.
Page 10 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
6.3.4 The contents of the Post T&I Summary report shall include but not
limited to:
a) Plant number and name.
b) Processing unit description.
c) Details for each of the individual pieces of static equipment involved
in the T&I.
d) Brief summary of inspection activities performed on individual
pieces of static equipment and piping during the T&I.
e) Summary of the repair work performed on individual pieces of static
equipment and piping involved in the T&I.
f) The recommendations for the next T&I, including the list of
temporary repairs performed or deferred until the next T&I.
g) Material take-off list.
h) Process improvement recommendations.
6.4.7 Data, sketches and diagrams relevant to the T&I including findings and
defects which are covered in the following appendices, shall be
maintained:
a) Appendix A: list the defect types and the data required to evaluate
and size each defect.
Page 11 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
b) Appendix B: list the Basic Data Record Forms required for each
equipment and shall be updated after each T&I inspection.
c) Appendix C: Fired Heater Inspection Results Information
d) Appendix D: Heat Exchanger Inspection Results Information
e) Appendix E: Pressure Vessel Inspection Results Information
f) Appendix F: Critical Input Data
g) Appendix G: Tank Data Recording Requirements
6.5.1 Report formats available in SAIF shall be used to comply with the
requirements of this procedure with the exception of the T&I Summary
Report.
6.5.2 Quality of T&I data uploaded into SAIF shall be validated by a reviewer
assigned by OIU Supervisor.
7 Responsibilities
7.1.1 Review, approve and issue the reports mentioned in the Scope,
including:
a) Pre-T&I Report to Superintendent, Operations, prior to T&I start
date.
b) Post T&I Report to Superintendent, Engineering within 45 days of
T&I completion date with a copy to the division heads of Operations
and Maintenance as well as T&I Planning Unit Supervisor. A copy
of relevant sections shall be saved in each equipment file.
c) T&I Summary Report to Superintendent, Operations, not later than
60 days after completion of T&I date. The report shall include an
executive summary, T&I recommendations, listing of any materials
identified for replacement at future T&I (material take off list) and a
summary of findings for each single equipment inspected. A copy of
this report shall be sent to the division heads of Maintenance and
Engineering as well as T&I Planning Unit Supervisor.
Page 12 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
7.1.2 Assign individuals or a team that will record and validate the inspection
activities for each equipment in a retrievable format in SAIF.
7.1.3 Ensure that adequate, detailed and auditable inspection reports of all
items of equipment requiring inspection are maintained. All Inspection
reports shall be formally reported and the reports placed in the
equipment file.
7.1.5 Establish and revise inspection reports, forms and records to comply
with relevant requirements of applicable Saudi Aramco standards and
procedures.
7.3.3 Maintain a permanent and progressive set of records (e.g., Eddy Current,
Magnetic Flux Leakage, Acoustic Emission, IRIS reports, etc.) for each
Page 13 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
7.3.5 Create a T&I number and package for each notifications under it in
SAIF. Package may be for one or a combination of Notifications.
7.3.6 Compile the equipment inspection final report, T&I recommendation for
equipment, material take-off list for the review and approval for the Field
Supervisor within 7 days of the T&I completion.
Compile all NDT reports and submit to the responsible P&E inspector for
compiling the inspection final reports within 3 days of the T&I completion.
7.5.2 Assign engineer or team that will be responsible for developing any
required repair package. Inspection hold points shall be defined in any
repair plan provided.
7.5.3 Review the following and provide recommendations for Pre-T&I Report.
a) List of temporary repairs planned for upgrade to permanent repairs
b) OSI (CML) locations at Tmin or below.
c) List of Technical Alerts awaiting action.
d) Cathodic Protection (CP) inspection reports recommendation.
e) Operational upsets history.
f) Previous T&I recommendations and material take off list.
g) On-Stream Inspection (OSI) records.
h) Risk Based Inspection (RBI) report recommendation.
i) Leaks history.
Page 14 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Revision Summary
26 March 2015 Major Revision.
Revised the "Next Planned Update" and reaffirmed the content of the document.
Validated content of forms in procedure.
Re-arrange content according to SAEP-134.
Referenced SAIF as required for data management.
Added tanks calibration reporting requirement to comply with GI-0405.001 and GI-0405.007
and SAEP-22 mandates for storage tanks used for Royalty/custody measurement.
Page 15 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 16 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 17 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Equipment data:
Shell Material: Design Pressure, Kg/ cm²g or psig:
Shell thickness (mm/ in) Design Temp. °C or °F:
Cladding/ Lining (mm/ in) Corrosion Allowance (mm or in)
SUMMARY:
Commentary Note: include major highlights within 150 words
Internal:
Commentary Note: This section highlights internal condition, attachment such as tray, supports, bolts etc.
REPAIRS/RENEWAL:
Commentary Note: type of repair, material, PMI PWHT, etc.
TESTS:
Commentary Note: Scale sample test report, PMI, Insitu Metallography, etc.
NDT:
Commentary Note: UT, PT, RT, HT WFMPI, etc.
Hydrostatic:
Commentary Note type of test, waiver
RECOMMENDATIONS:
Commentary Note: Highlight required action for the future in bullet form
a
References
1. SAES-A-004 General requirement for pressure testing
2. SAES-D-008 Repair, Alteration, Re rating of process equipment
3. SAEP-20 Equipment Inspection Schedule
4. SAEP-317 Testing and Inspection of shell and tube heat exchangers
5. SAEP-325 Inspection requirement for pressurized equipment
Page 18 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 19 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 20 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 21 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
In addition to the previous table, the following are required for the tubes of heat exchangers:
Page 22 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 23 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
Page 24 of 25
Document Responsibility: Inspection Engineering Standards Committee SAEP-1161
Issue Date: 26 March 2015
Next Planned Update: 26 March 2020 Testing and Inspection (T&I) Reporting Procedure
G.3 Calculations
G.3.a Minimum height for required hydrotest (API 653)
G.3.b Calculate and highlight where plate thickness is G5% of nominal thickness
G.3.c Minimum shell plate thickness based on height (API 653)
G.3.d Date of next inspection (calculated)
G.3.e Internal pressure at max. service height
G.3.f Minimum floor plate thickness
G.3.g Minimum thickness for annular plate ring
G.3.h Minimum thickness for the shell based on height
G.3.i Minimum Remaining Thickness (MRT) at the end of the in-service period of operation until the next
T&I as per SAES-D-108 or API 653.
Page 25 of 25