Escolar Documentos
Profissional Documentos
Cultura Documentos
Keywords: Differential Protection, Cable Models, Cable b. Cable construction is complex consisting of many layers
Protection, Charging Current Compensation, EMTP-RV of dielectrics and conductors.
c. Cables are generally laid in close proximity and this
Abstract makes interaction between the phases more complex.
Various models have been developed for transmission lines
This paper presents performance of two charging current and HV cables. Most commonly used models are Frequency
compensation methods used in commercially available Dependent (FD) model [1], the Constant Parameter (CP) [2]
differential relays. This paper appreciates importance of cable model, Wide Band (WB) [3] model and the Equivalent PI
models on protection and settings application studies and on model [4]. Each model has advantages and disadvantages. FD
estimation of performance of charging current compensation and WB models are computationally extensive but have a
methods. The problem is split in to a) Significance of Power higher degree of accuracy. Both models show good frequency
Cable Modelling and b) Protection performance evaluations. response ( as they consider frequency dependent parameters )
Models available in EMTP-RV are considered. Transient and are widely used for the transient studies involving cables.
performance of each of models is evaluated to determine Accuracy of the CP model and equivalent PI model is
which are most suitable for protection application studies. dependent on the shift from base frequency. CP and
Single core, 3 phase, 132 kV crossbonded cables of various equivalent PI models are relatively easy to build.
lengths are considered. However, the methodology can be
extended to any cable arrangement including pipe type/ 2 Need for Proper cable model - A Quantitative
Multicores cables. Single and three phase external faults are
considered. Such a study would be useful for long cables i.e.
Insight
in offshore transmission system and in densely populated Shunt capacitance associated with HV cable can create
urban areas where land costs restricts the construction of significant errors if it is not properly accounted. This is
overhead lines. demonstrated through a simple but relevant example. This
example considers a single phase cable. The single line
1 Introduction diagram and cable parameters are shown in the figure -1.
NEGATIVE ERROR
POSITIVE ERROR
BASE VALUE
NEGATIVE ERROR
POSITIVE ERROR
Figure -2: Variation of Sending and receiving current magnitudes with the shunt admittance.
As observed from figure -2, error in estimation of the shunt b. Shunt admittance directly proportional to area of cross
admittance can significantly influence sending and receiving section of the cable so a 2500 sq.mm cable was
end current magnitudes. It is also observed that the error has considered.
opposite impact on sending and receiving end currents. This The case study considers single core cables, but the results
means that differential error varies at much faster rate and can and methodology can be applied to Multicores cables. For
become significant consideration when differential protection such long distances cables are cross bonded and are either
is applied. This simple demonstrates the significance of the transposed or are laid in tight trefoil formation. In this paper it
proper cable modelling in determination of appropriate is assumed that cables are laid in trefoil formation as shown
settings. in figure -3
Approximation of cable construction requires some correction This method is used in atleast three of the commercial relays
factors to be applied which are [5]. [7],[8],[9]. Charging current drawn by the cable is related to
voltage at cable ends and the shunt admittance of the cable.
a. Correction for Resistivity. The simplified mathematical model is explained
b. Correction for Permittivity. Let VA be voltage at the end ‘A’ ; VB be voltage at the end ‘B
These construction details were passed on to EMTP-RV ; yC be shunt admittance per unit length; L be the length of the
utility to generate models. Same input details were used to cable; the charging current flowing into cable at each end is
generate the four different types of models allowed by calculated by following relations
Figure -5: Transient Response of the Models
Figure -6: Ratio of Differential Currents to Restraint currents for an external fault for algorithm-1
1_PH and 3_PH: Imply one phase to earth and 3 phase earth fault
ti l
Figure -7: Ratio of Differential Currents to Restraint currents for an external fault for algorithm-2
c. Efficacy of this algorithm is also dependent on the a. This algorithm is very effective in compensating cable
system conditions at which charging current was charging current.
determined. Error increases if pre fault system b. This algorithm needs VT inputs in addition to current
conditions are different from conditions at which inputs.
charging current is determined. c. Effectiveness/ accuracy of this algorithm is
d. Sensitivity of the alogorithm-1 is much better then independent of the length of cable.
uncompensated case but lower than algorithm -2. d. Accuracy of the algorithm is directly related to the
Algorithm -2 accuracy with which shunt admittance is calculated.
Figure -8: Ratio of Differential Currents to Restraint currents for an internal fault for algorithm-1
6. Conclusions Disclaimer
Cable shunt capacitance can significantly influence The views presented in this paper are that of author and
through fault current. Protection application and setting not of organisation for which the author is working.
studies should consider shunt admittance of the cable. For
long cables, total shunt admittance may not be simple References
product of length of the cable and shunt admittance per
unit length. Cable shunt admittance should be determined [1]. L. Marti.: “ Simulations of Transients in underground
either by running measurements during the first cables with frequency dependent modal
energisation or by using suitable modelling techniques. transformation matrices”. IEEE transactions on
Transient performance of four different cable models was Power Delivery, Volume 3, issue 3 July 1988, pp
considered. Results from PI, FD and WB model were in 1099-1110
closed agreement. Constant Parameter model appears to be [2]. H.W.Dommel. : “Digital Computer Solution of
least accurate for single core cables in trefoil formation Electromagnetic Transients in singe and multiphase
and flat formation. networks”. IEEE Transactions, Vol PAS-88, Pages
Two different algorithms for cable charging current 388-399, April 1969.
compensation were considered in this paper. Both the [3]. Morched A, Gsutaven B. And Tartibi M.: “An
algorithms improve performance of Differential relays. universal model for accurate calculation of
Algorithm -2 which requires cable end voltages has much Electromagnetic transients on overhead lines and
better accuracy for cable lengths of 50 km or more. It can underground”. IEEE transactions on Power Delivery,
neutralise the charging current to practically zero. It does Volume 14, issue 3 July 1999, pp 1032-1032
exhibit some errors during transients. When algorithm -1 is [4]. P.Kundur.: “ Power System Stability and control”.
used on cables with lengths of 50 km or more, slope of EPRI, Power System Series 1994, pages 206-209.
differential characteristic should be increased to [5]. C.F.Jensen et al.: “Switching studies for the Horns
compensate for error. Rev 2 windfarm main cable”. IPST-11, paper no.
For cable lengths of 50 km or less, both the algorithms 182.
perform as expected. For cable lengths of 50 km or less [6]. ABB, “Application Manual RED 670”, 2012, pages
algorithm –1 has advantage as it does not require voltage 109-110.
inputs. This may be significant advantage in cases where [7]. Alstom.: “ Technical Reference Manual MiCOM
VT inputs are not available. P545”, 2011, Section 6.2.2.
Settings should be worked out using relay, cable and [8]. GE.: “L90 Line Differential Relay UR Series
detailed system models including the source impedances. Instruction Manual”. 2006, Section 8.1.18.
Some feasible system depletion scenarios should be [9]. Siemens.: “ Application Manual for 7SD 522/523”.
considered for determination of appropriate settings. 2009, Page 94
Appendix – A 132 kV cable parameters1