Escolar Documentos
Profissional Documentos
Cultura Documentos
The Ring lock scaffolding system is a modular system. It is mainly consists of:
Standard configuration according to EN 12810 for a scaffold assembly: 24 m high plus maximum spindle
extension / internal brackets at every level / external brackets / pavement gantries / bridging / nets /
tarpaulins.
Standard configuration according to EN 12810 for a scaffold assembly: 24 m high plus maximum spindle
extension / internal brackets at every level / external brackets / pavement gantries / bridging / nets /
tarpaulins.
2.2.4 Ring lock fixed towers
Dimensions: The uniform grid dimensions in both vertical and horizontal directions allow almost any
adjustments to be made to suit site conditions. Vertical grid dimensions which can be achieved by the rings
supplied every 50cm. Horizontal grid every 30cm.
The Ring lock mobile towers are equipped by polyurethane wheels with braking mechanism to facilitate
moving the tower.
It describes stair towers with the staircase units in the same direction and stair towers with alternating
staircase units as a means of access for temporary work to be carried out on working areas situated above
ground level.
Permissible loads:
For stair flights and decking 2.0 kN/m2
2.3 Instructions
2.3.1 General instructions
1. The contractor-user- has to ensure that the applied loads don’t exceed the permissible loads specified for
the system configuration used; also the wind loads mustn’t exceed the designed velocity pressure of (1.1
kN/m²).
2. The ground and the wall supporting the scaffold are sufficiently solid to carry the loads imposed on them
from ties and base plates.
3. Couplers used must comply with EN74, ties made up of galvanized steel S235JR with minimum
dimensions Ø 48.3*3.2mm.
4. Any deviations from the standard configuration or instructions provided in this guide may only be carried
out after a separate assessment has been implemented by ACROW construction.
5. All country-specific laws, standards and other safety regulations are to be taken into account.
6. Materials used should be original ACROW materials, and they should be in perfect working conditions.
1. All components are to be inspected before each use and any damaged components mustn’t be
used.
2. During unfavorable weather conditions, suitable precautions and measures are to be taken in order
to ensure both working safety and stability.
3. In no case the user will remove ties or other structural elements from the scaffolding.
4. The working areas have to be safe and secured and can be safely accessed. Areas of risk must be
cordoned off and clearly marked, openings on accessible working areas must be kept closed during
working operations.
5. The elements must not suffer strong knocks and excessive crushing during use, manipulation,
storage and transport.
6. Make sure that the rope used in lifting elements is in good condition.
7. When moving the components, make sure they are lifted and set down so that any unintentional
tilting over, falling apart, sliding or rolling away is avoided.
8. Do not leave objects strewn in the circulation routes, and do not handle objects in areas where this
would pose a risk to third parties.
9. Never move the mobile tower when personnel or materials are on the tower.
10. The tower should be moved slowly and smoothly, and it should be hitched for pulling from the
lowest point possible.
11. Assure that all protections are properly set up in the material storage and handling areas.
12. When assembling and disassembling, follow the ACROW technical instructions on assembly.
13. If working under other conditions, consult the Technical Department.
3. System components
Plain base
Code 6221177000851
Weight 1.16 Kg
Code 6221177013127
Weight 3.77 Kg
Code 6221177013103
Weight 5.30 Kg
Code 6221177012304
Weight Kg
Code 6221177087289
Weight Kg
Ring lock standards
Code
Weight 3.91 Kg
Console bracket 706
Code
Weight 6.69 Kg
Cantilever brace
Pedestrian frame
Code
Weight 36.25 Kg
Guardrails
Bridging girder
Code
Weight 60.70 Kg
Code
Weight 3.82 Kg
Code
Weight Kg
Transom with couplers
Code
Weight 3.40 Kg
Code
Weight 9.79 Kg
Guardrail post
Code
Weight 5.68 Kg
Double couplers
Code
Weight Kg
Ladder
Code
Weight Kg
Polyurethane wheel
Code
Weight Kg
2. Place the base standards on the post head jacks with the spigots upwards; the use of these standards
facilitates the alignment and leveling of the base; and also to decrease the level of the first ring from
the ground by 200mm.
3. Form a base frame by connecting the base standards transversely with the decking transom (0.75m
or 1.05m) and longitudinally with the ledgers. Insert the wedge in the corresponding holes in the
lower rings of the standard. Ensure all ledgers and decking transoms are leveled by adjusting the post
head jacks. Then securely fix all the wedges.
Console brackets are used to extend the working area of the scaffold.
Internal brackets must be installed at every level of the scaffold.
Erection of brackets takes place from the lower level, first fit the bracket end
connector into the ring and secure the wedge by a hammer blow. Before
accessing the next level, install the platforms on the consoles.
Cantilevers are used when obstacles in the wall to cover make it necessary to change
direction, in the vertical plane, of the scaffolding. The cantilever is comprised of 2 parts
(cantilever transom and cantilever brace). The two components must be joined before
proceeding to assembly (pre-assembly).
Assemble the scaffolding according to the basic assembly instructions up to the level
where the change of direction is indicated. Tie off the scaffolding to the wall on the two
levels covered by the cantilever. On the last platform, pre-assemble the cantilever.
Insert it in the corresponding position. This should be done with two scaffolders on two
different levels.
After completing the next level, platforms and toe boards on the
cantilever level can be removed, except in the access bay and
end guardrails are required to be fitted to the access bay and
basic scaffold. Erect diagonal bracing in the outer bays before
removing plat forms and side protection.
3. Assembly of pedestrian frame
To bridge openings or entrances of buildings of spans greater than (3m) bridging girders (50 or 70 cm depth)
can be used depending on the loads to be carried. Only couplers complying with DIN EN 74 may be used.
21 cm
Fix right angled couplers to the vertical standards at the required height. Lift the girder
(distance between top chord and the ring upper face is 21cm), attach the top chord to
the couplers and secure, then connect the bottom chord of the girder to the vertical
standard with right angled couplers.
Form a pre-assembly, insert 2 bridging base standards into 2 bridging tubes, then connect
them with a ring lock transom while join the lower ends of the bridging tubes with a
transom with couplers.
Then from the same safe position slide this assembly on the
top chord of the bridging girder using the ledger and the
platform into the middle of the span. Then fit them into the
already erected bay.
Complete the platform and side protection.
Use a fourth corner vertical standard to form a corner tower continued up to the top of the scaffold; join the
corner standard to the whole scaffold using transoms to hold the platforms.
For out-side corners; complete the side protection and the toe boards.
4.3 Forming corners
Corners are often required to complete the full width of the scaffold to provide safe and easy circulation
through the scaffold.
Use a fourth corner vertical standard to form a corner tower continued up to the top of the scaffold; join the
corner standard to the whole scaffold using transoms to hold the platforms.
For out-side corners; complete the side protection and the toe boards.
4.4 Assembly of staircase
5. Criteria for Design
5.1 Façade scaffold 75cm width
Self-weight of components
Wind loads:
-Working velocity pressure = 0.2 KN/m²
To make allowance for equipment or materials which are on the working area, a
nominal reference area of 400mm high measured from the level of the working area
level over its full length.
-Maximum velocity pressure= 1.1 KN/m² at height 24m in accordance with EN12810-
clause (8.3)-figure (3)
To make allowance for equipment or materials which are on the working area, a
nominal reference area of 200mm high measured from the level of the working area
level over its full length.
Reduction factor for time rate =0.7 for maximum win loading.
Solidity ratio for open façades ɸ=0.4, corresponding to 60% openings
Imperfections = Ѱ*Ned
- Ѱ is the angular deviation at the joints between vertical components.
- Ned is the design value of the compression force.
*The uniform distributed load shall be taken as zero if its consideration leads to more
favorable results.
6. Tying Instructions and Anchor Forces
6.1 Tying general criteria
Ties type A
The type A ties are fixed to the inner
vertical standards only using right
angled couplers. Anchor forces are Ties Type A
Ties type B
The type B ties are fixed to both inner
and outer vertical standards using right
angled couplers. Anchor forces are
carried normal and parallel to the façade. Ties Type B
6.3 Façade scaffold 75cm width
2000
4000
2000
2000
4000
2000
2000
4000
2000
2000
4000
2000
8000mm
2000
4000
2000
2000
4000 4000mm
2000 300mm
750mm
FRONT VIEW
SECTION VIEW
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
TOP VIEW
2000
4000
2000
2000
4000
2000
2000
4000
2000
24000mm
2000
4000
2000
8000mm
2000
4000
2000
2000
4000 4000mm
2000 300mm
750mm
FRONT VIEW
SECTION VIEW
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
TOP VIEW
2000
4000
2000
2000
4000
2000
2000
4000
2000
24000mm
2000
4000
2000
8000mm
2000
4000
2000
2000
4000 4000mm
2000 300mm
750mm
FRONT VIEW
SECTION VIEW
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
TOP VIEW
2000
4000
2000
2000
4000
2000
2000
4000
2000
24000mm
2000
4000
2000
2000
4000 4000
2000
2000
4000
2000 2000 300mm
750mm
FRONT VIEW
SECTION VIEW
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
TOP VIEW
2000
4000
2000
2000
4000
2000
2000
4000
2000
24000mm
2000
4000
2000
2000
4000
2000
2000 2000
4000
2000 2000 300mm
750mm
FRONT VIEW
SECTION VIEW
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
TOP VIEW