TITLE: Sea Water Intake Pipe and Head EPC Work for Track 4A CCGT
Power Plant PAGE: 1 OF 2
REQUISITION NO. : 16C2660C-SM6A.01
RESPONSIBILITY DIVISION
ITEM DESCRIPTION SUBCON-
CTCI REMARK
TRACTOR

1.0 Engineer Work


1.1 Basic Design (P&ID) V
1.2 Detail Design V GRP Pipe, Intake
Head and
foundation
design
1.3 Material Take-off V GRP Pipe, Intake
Head and
foundation
design

2.0 Procurement Work


2.1 Material purchasing according to Bill of Material V
2.2 Subcontractor list (If any) for approval V
2.3 Vendor/Supplier list for approval prior to V
purchase
3.0 CONTROL POINT ESTABLISHMENT V

4.0 TEMPORARY FACILITIES


4.1 Camp & house V
4.2 Field office, warehouse & work shop
- Area/space V V Office/Container
build up by
Subcon.
- Site temp. office ( Containers.) Tool storage V Fabrication
room, Material ware house , Worker rest area, equipment tools
Construction equipment and accessory tools and consumable
and furniture materials shall be
supplied by the
Subcontractor.
4.3 Local authority inspection and license V Authorities
application approval for
sea-related works
belong to
Subcontract.
4.4 Storage yard for materials V
4.5 Temporary water and power V

5.0 CONSTRUCTION EQUIPMENT & TOOLS V

6.0 MATERIAL’S SUPPLY


ANNEX-01
DIVISION OF WORK
TITLE: Sea Water Intake Pipe and Head EPC Work for Track 4A CCGT
Power Plant PAGE: 2 OF 2
REQUISITION NO. : 16C2660C-SM6A.01
RESPONSIBILITY DIVISION
ITEM DESCRIPTION SUBCON-
CTCI REMARK
TRACTOR
6.1 Pipes, Fittings and accessories V
6.2 Flanges V
6.3 Bolts V
6.4 Pipe supports, dead man (If required) V
6.5 Steel navigational light buoy V

7.0 SCOPE OF THE WORK


7.1 Fabrication of pipe spools V
7.2 Corrosion protection of pipes V Including
painting/lining
repair (if any)
7.3 Erection of pipe spools V
7.4 Field joining of pipes V
7.5 Installation of pipe support and dead man V If any
7.6 Excavation and backfill of U/G pipes V
7.7 As built dwg, including GRP design drawings, V Subcontractor to
the profile and location of GRP pipes and provide mark up
intake head, chlorination pipe, steel drawings
navigational light buoy detail drawings.
7.8 Demolish and reinstate existing embankment or V
shore protection structure when required
7.9 Intake head and all related Civil work V

8.0 OTHERS
8.1 Safety devices (Safety helmet, safety boot, V
safety net, safety belt, safety rope, and so on.)
8.2 The sanitation, safety and environment V
protection measures
8.3 Quality control of the work V
8.4 The fire-fighting devices during construction V