Escolar Documentos
Profissional Documentos
Cultura Documentos
Design Data :
Solution:
FLOW DESIGN -> ORGANIC LOAD -> PIPE DESIGN -> PRIMARY SCREEN -> PUMP STATION -> SECONDARY SCREEN -
-> GRIT/GREASE REMOVER -> BALANCING TANK -> ROTATING BIOLOGICAL CONTRACTOR (RBC) -> FINAL SEDIMENTATION - > SLUDGE TREATMENT
FLOW DESIGN:
P = 4.89
Qpeak = Fpeak*DWF
= 4342.75 m3/day
= 0.05026 m3/s
Qmin = DWF/Fpeak
= 278.752 m3/day
= 0.00323 m3/s
ORGANIC LOAD:
PIPE DESIGN:
Assumption Data:
Sewerage Type = cast iron where,
Manning's coefficient, n = 0.013 (cast iron) d = actual depth of sewage
sewerage slope,S = 1/600 = 0.00167 D = diameter of the sewerage
water flow = 70% q = actual flow rate of sewage at 70% full
d/D = 0.7 Qfull = Manning's flow rate at 100%
v = actual velocity of sewage at 70% full
Vfull = Manning's velocity at 100%
R = D/4
From Manning chart,
q/Qfull = 0.85
v/Vfull = 1.14
q = Qpeak
= 0.05026
Size of sewer:
Q = (1/n)*(A)*(R^(3/2))*(S^(1/2))
Q = Qfull
0.059133 = �
(1/0.013)*( /D^2)*((D/4)^(2/3))*((0.001667)^(1/2))
D^8/3 = 0.050263/0.9788
D = 0.34908 m
Try, D = 0.85 m (standard size cast iron pipe)
at maximum flow,
v/Vfull = 1.14
v = Vfull*1.14
= 1.27485 m/s [0.8m/s < v < 4.0m/sPass!
v = Vfull*(v/Vfull)
= 0.61506 m/s [0.6m/s < v < 1.0m/sPass!
PRIMARY SCREEN:
Design Requirement:
PE ≤ 5000 ,
Manual raked primary screen
Data:
(from table 4.10:Design parameter for primary screens)
Peak or Maximum Flow Rate, Qp = 0.050263 m3/s
Maximum clear spacing = 25 mm
Maximum flow through velocity at the screen face, V = 1 m/s
Width of blade, B = 10 mm
Size of opening (interval between blade), S = 25 mm
asumed Depth at Vmax, D = 0.6 m
Estimated volume of screenings per volume of waste water = 30 m3/10^6 m3
Quantity of Screenings,
Total volume of wastewater(7 days) = Qp(7days)
= 30399 m3
Assume:
Length, L 2
Ratio (L : W)
Width, W 1
Depth, D 1.0 m (Including freeboard)
Therefore,
2x²*(1m) = 0.9120 DESIGN OF THE PRIMARY SCREEN STORAGE TANK
x = 0.68 D = 2m
Width, W = 0.68 m
Thus, D = 1.0m
Length, L = 2W
= 2*0.68
= 1.35 m
W = 0.68 m
L = 1.35 m
Design requirement:
PE ≤ 5000 ,
Wet well pump station
Data:
(From table 4.11: Recommended design parameters for inlet pump station)
Number of pumps (all identical and work sequentiall = 2 (1 duty, 1 standby ;100%standby)
Pumps design flow (for pump sizing) = each at Qpeak
Maximum detention time at Qave = 30 min
Min pass through openings = 70 mm
Minimum suction and discharge opening = 100 mm
Pumping cycle (average flow conditions ) = 6 min start/hour
= 15 max
Lifting device = Lifting davit
Qp = 3.0158 m3/min
Volume, V = Qp*30
= 90.474 m3
Assumption data
Tank depth, D = 1 m
Length : Width = 3:1
Therefore,
(3x)(x)(1) = 90.47405
3x² = 90.47405
x = 5.491631
x ≈ 5.5 PUMP STATION
Width, W = 5.5 m
Thus, D = 1m
Length, L = 3W
= 3*5.5
= 16.5
t = Vactual/ Qp
= 30 ≤ 30 min acceptable
Design Requirement:
PE ≤ 5000 ,
Manual raked secondary screen
Data:
(from table 4.13:Design parameter for primary screens)
Peak or Maximum Flow Rate, Qp = 0.050263 m3/s
Maximum clear spacing = 12 mm
Maximum flow through velocity at the screen face, V = 1 m/s
Width of blade, B = 20 mm
Size of opening (interval between blade), S = 12 mm
asumed Depth at Vmax, D = 0.6 m
Slope to vertical = 45 degree
Screening skip storage capacity = 7 days
(Obtained from Figure 4.12:Screening chart)
Screening of Sewage = 48 m3/10^6 m3
Quantity of Screenings,
Total volume of wastewater(7 days) = Qp(7days)
= 30399 m3
Assume:
Length, L 2
Ratio (L : W)
Width, W 1
Depth, D 1.0 m (Including freeboard)
Therefore,
2x²*(1m) = 1.4592 DESIGN OF THE SECONDARY SCREEN STORAGE TANK
x = 0.85 D = 2m
Width, W = 0.85 m
Thus, D = 1.0m
Length, L = 2W
= 2*0.85
= 1.71 m
W = 0.85 m
L = 1.71 m
Design Requirement:
PE ≤ 5000 ,
Duty Manual 1 unit @ design flow
Chamber type; Horizontal flow (2 unit required for duty and stanby during cleaning) vortex also acceptable
Data:
(from table 4.14:Design parameter for Grit removal system)
Qp = 3.0158 m3/min
V = Qp*t
= 9.0474 m3
Assumption data:
x3 = 9.0474 m3
x = 2.08373 m
≈ 2.1 m
So,
GRIT CHAMBER
tank depth, D = 1.05 m
width, W = 2.1 m
length, L = 4.2 m
D = 1.05m
Volume of the Grit Chamber, Vdesign = 1.05*2.1*4.2
= 9.261 m3
W = 2.1
As = L*W
= 8.82 m2 L = 4.2m
Ah = W*D
= 2.205 m2
Checking:
Horizontal velocity, Vh = Q p / Ah
= 1969.5 m/day
= 0.0228 m/s < 0.2, OK
Qp = 180.948 m3/hours
V = Qp*t
= 271.422 m3
Assumption data:
9x2 = 271.422 m3
x = 5.49163 m DESIGN OF THE BALANCING TANKS
≈ 5.5 m
So,
As = L*W
= 90.75 m2
Ah = W*D
= 16.5 m2
Checking:
Horizontal velocity, Vh = Q p / Ah
= 0.00305 m/s
O.L = DWF*BOD/A
= 0.00584kg/m2.day
= 5.83701 g/m2.day 5 < O.L < 10 (Acceptable)
For 3 series,
W=5 m
Retemtion time, t = (Number of stages*Vdesign)/DWF L = 20 m
= 0.68166 day
= 16.3599 hours
Qp = 4342.75 m3/day
Qavg = 1100.25 m3/day
Assumption data:
L:W = 2 :1
Depth, D = 3m
Retention time = 2 hours
Retention time,
t = V/Qp
V = t*Qp FINAL SEDIMENTATION TANK
= 361.896 m3
V = W*2W*D
6W^2 = 361.896
W = 7.76634 m
≈ 7.8 m
D = 3m
L = 3W
= 23.4 m
tank depth, D = 3 m W = 7.8m
width, W = 7.8 m
length, L = 23.4 m L = 23.4m
Checking:
Sludge disposal,
%SS = 60 %
= 0.6
SS = 0.3 kg/m3
Length, L = 3x L = 7.59 m
= 7.59