SCHEDULING OF ACTIVITIES FOR TUNNEL PROJECT IN MSP

START FINISH PREDECESSO


WBS ID NAME DURATION RESOURCE NAMES
DATE DATE RS
1 1 Diversion Tunnel Project 263.75 days 30-08-2018 18-10-2019
1.1 2 Site Preparatory Works 8.75 days 30-08-2018 12-09-2018
1.1.1 3 Temporary Site Office Construction 1.5 days 30-08-2018 31-08-2018 Trailer Truck[2],Tyre-mounted Crane[2]
Hydraulic Excavator[2],Tipper[4],Wheel
1.1.2 4 Construction of Haul Roads to Portal Sites 2.5 days 31-08-2018 05-09-2018 3
Loader[2]
1.1.3 5 Portal-1 Site Cleaning 2 days 05-09-2018 07-09-2018 4 Wheel Loader
1.1.4 6 Portal-2 Site Cleaning 2 days 05-09-2018 07-09-2018 5SS Wheel Loader
Tyre-mounted Crane,Welding Machine,Trailer
1.1.5 7 Portal-1 Site Barricading 2 days 07-09-2018 11-09-2018 5
Truck
Tyre-mounted Crane,Welding Machine,Trailer
1.1.6 8 Portal-2 Site Barricading 2 days 07-09-2018 11-09-2018 6
Truck
1.1.7 9 Shifting of Site Offices to Portal Sites 0.75 days 12-09-2018 12-09-2018 7,8 Trailer Truck[4],Tyre-mounted Crane[4]
1.2 10 Tunnel Preparatory Works 12 days 12-09-2018 02-10-2018 2
Hydraulic Excavator,Tipper[2],Wheel
1.2.1 11 Portal-1 Tunnel Face Surveying & Alignment 5 days 12-09-2018 20-09-2018
Loader,DG Set 40kVA
Hydraulic Excavator,Tipper[2],Wheel
1.2.2 12 Portal-2 Tunnel Face Surveying & Alignment 5 days 12-09-2018 20-09-2018 11SS
Loader,DG Set 40kVA
Batching Plant,Concrete Pump,DG Set
1.2.3 13 Portal-1 Structure Construction 7 days 20-09-2018 02-10-2018 12 40kVA,DG Set 82kVA,Hydraulic
Excavator,Tipper[2],Transit Mixer[2]
Batching Plant,Concrete Pump,DG Set
1.2.4 14 Portal-2 Structure Construction 7 days 20-09-2018 02-10-2018 13SS 40kVA,DG Set 82kVA,Hydraulic
Excavator,Tipper[2],Transit Mixer[2]
1.3 15 Tunnel Excavation 180 days 02-10-2018 11-07-2019 10
Hydraulic Excavator,Tipper[2],Wheel
1.3.1 16 Excavation and Muck Removal from Portal-1 Side 180 days 02-10-2018 11-07-2019
Loader,DG Set 40kVA
Hydraulic Excavator,Tipper[2],Wheel
1.3.2 17 Excavation and Muck Removal from Portal-2 Side 180 days 02-10-2018 11-07-2019 16SS
Loader,DG Set 40kVA
1.4 18 Shotcreting of Tunnel 180 days 03-10-2018 12-07-2019
Batching Plant,Lifter[2],Shotcrete
1.4.1 19 Shotcreting of Tunnel from Portal-1 Side 180 days 03-10-2018 12-07-2019 16SS+1d Machine,Transit Mixer[3],DG Set 40kVA,DG
Set 82kVA
Batching Plant,Lifter[2],Shotcrete
1.4.2 20 Shotcreting of Tunnel from Portal-2 Side 180 days 03-10-2018 12-07-2019 17SS+1d Machine,Transit Mixer[3],DG Set 40kVA,DG
Set 82kVA
1.5 21 Supporting of Tunnel 210 days 05-10-2018 02-09-2019
DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas-
Rib Supporting of Tunnel with girders and precast slabs
1.5.1 22 210 days 05-10-2018 02-09-2019 19SS+2d cutting Kit[4],Lifter[2],Trailer Truck,Tyre-
from Portal-1 Side
mounted Crane,Welding Machine[4]
DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas-
Rib Supporting of Tunnel with girders and precast slabs
1.5.2 23 210 days 05-10-2018 02-09-2019 20SS+2d cutting Kit[4],Lifter[2],Trailer Truck,Tyre-
from Portal-2 Side
mounted Crane,Welding Machine[4]
Batching Plant,Concrete Pump[2],DG Set
40kVA,DG Set 82kVA[2],Fork
1.5.3 24 Concrete Lining of Tunnel from Portal-1 Side 180 days 11-10-2018 22-07-2019 22SS+3d
Lift[2],Lifter[2],Trailer Truck,Transit Mixer,Tyre-
mounted Crane
Batching Plant,Concrete Pump[2],DG Set
40kVA,DG Set 82kVA[2],Fork
1.5.4 25 Concrete Lining of Tunnel from Portal-2 Side 180 days 11-10-2018 22-07-2019 23SS+3d
Lift[2],Lifter[2],Trailer Truck,Transit Mixer,Tyre-
mounted Crane
1.6 26 Finishing Works 30 days 02-09-2019 18-10-2019 21
DG Set 40kVA,DG Set 82kVA[2],Grout Mixer
1.6.1 27 Grouting of gaps and plugging of leakages 14 days 02-09-2019 24-09-2019
and Pump[4],Lifter[4]
Air Compressor[2],DG Set 40kVA,DG Set
1.6.2 28 Cleanup of tunnel and demobilization of all equipment 3 days 24-09-2019 30-09-2019 27 82kVA[2],Fork Lift[2],Gas-cutting
Kit[4],Lifter[4],Tipper,Welding Machine[4]
DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas-
Setup of monitoring equipment within and outside the
1.6.3 29 7 days 30-09-2019 09-10-2019 28 cutting Kit[4],Lifter[2],Trailer Truck[2],Tyre-
tunnel
mounted Crane[2],Welding Machine[4]
1.6.4 30 Deconstruction of Site Offices 1 day 09-10-2019 11-10-2019 29 Trailer Truck[4],Tyre-mounted Crane[4]
1.6.5 31 Testing and handover of tunnel 5 days 11-10-2019 18-10-2019 30 DG Set 40kVA[2],DG Set 82kVA[2]