SCHEDULING OF ACTIVITIES FOR TUNNEL PROJECT IN MSP
START FINISH PREDECESSO
WBS ID NAME DURATION RESOURCE NAMES DATE DATE RS 1 1 Diversion Tunnel Project 263.75 days 30-08-2018 18-10-2019 1.1 2 Site Preparatory Works 8.75 days 30-08-2018 12-09-2018 1.1.1 3 Temporary Site Office Construction 1.5 days 30-08-2018 31-08-2018 Trailer Truck[2],Tyre-mounted Crane[2] Hydraulic Excavator[2],Tipper[4],Wheel 1.1.2 4 Construction of Haul Roads to Portal Sites 2.5 days 31-08-2018 05-09-2018 3 Loader[2] 1.1.3 5 Portal-1 Site Cleaning 2 days 05-09-2018 07-09-2018 4 Wheel Loader 1.1.4 6 Portal-2 Site Cleaning 2 days 05-09-2018 07-09-2018 5SS Wheel Loader Tyre-mounted Crane,Welding Machine,Trailer 1.1.5 7 Portal-1 Site Barricading 2 days 07-09-2018 11-09-2018 5 Truck Tyre-mounted Crane,Welding Machine,Trailer 1.1.6 8 Portal-2 Site Barricading 2 days 07-09-2018 11-09-2018 6 Truck 1.1.7 9 Shifting of Site Offices to Portal Sites 0.75 days 12-09-2018 12-09-2018 7,8 Trailer Truck[4],Tyre-mounted Crane[4] 1.2 10 Tunnel Preparatory Works 12 days 12-09-2018 02-10-2018 2 Hydraulic Excavator,Tipper[2],Wheel 1.2.1 11 Portal-1 Tunnel Face Surveying & Alignment 5 days 12-09-2018 20-09-2018 Loader,DG Set 40kVA Hydraulic Excavator,Tipper[2],Wheel 1.2.2 12 Portal-2 Tunnel Face Surveying & Alignment 5 days 12-09-2018 20-09-2018 11SS Loader,DG Set 40kVA Batching Plant,Concrete Pump,DG Set 1.2.3 13 Portal-1 Structure Construction 7 days 20-09-2018 02-10-2018 12 40kVA,DG Set 82kVA,Hydraulic Excavator,Tipper[2],Transit Mixer[2] Batching Plant,Concrete Pump,DG Set 1.2.4 14 Portal-2 Structure Construction 7 days 20-09-2018 02-10-2018 13SS 40kVA,DG Set 82kVA,Hydraulic Excavator,Tipper[2],Transit Mixer[2] 1.3 15 Tunnel Excavation 180 days 02-10-2018 11-07-2019 10 Hydraulic Excavator,Tipper[2],Wheel 1.3.1 16 Excavation and Muck Removal from Portal-1 Side 180 days 02-10-2018 11-07-2019 Loader,DG Set 40kVA Hydraulic Excavator,Tipper[2],Wheel 1.3.2 17 Excavation and Muck Removal from Portal-2 Side 180 days 02-10-2018 11-07-2019 16SS Loader,DG Set 40kVA 1.4 18 Shotcreting of Tunnel 180 days 03-10-2018 12-07-2019 Batching Plant,Lifter[2],Shotcrete 1.4.1 19 Shotcreting of Tunnel from Portal-1 Side 180 days 03-10-2018 12-07-2019 16SS+1d Machine,Transit Mixer[3],DG Set 40kVA,DG Set 82kVA Batching Plant,Lifter[2],Shotcrete 1.4.2 20 Shotcreting of Tunnel from Portal-2 Side 180 days 03-10-2018 12-07-2019 17SS+1d Machine,Transit Mixer[3],DG Set 40kVA,DG Set 82kVA 1.5 21 Supporting of Tunnel 210 days 05-10-2018 02-09-2019 DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas- Rib Supporting of Tunnel with girders and precast slabs 1.5.1 22 210 days 05-10-2018 02-09-2019 19SS+2d cutting Kit[4],Lifter[2],Trailer Truck,Tyre- from Portal-1 Side mounted Crane,Welding Machine[4] DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas- Rib Supporting of Tunnel with girders and precast slabs 1.5.2 23 210 days 05-10-2018 02-09-2019 20SS+2d cutting Kit[4],Lifter[2],Trailer Truck,Tyre- from Portal-2 Side mounted Crane,Welding Machine[4] Batching Plant,Concrete Pump[2],DG Set 40kVA,DG Set 82kVA[2],Fork 1.5.3 24 Concrete Lining of Tunnel from Portal-1 Side 180 days 11-10-2018 22-07-2019 22SS+3d Lift[2],Lifter[2],Trailer Truck,Transit Mixer,Tyre- mounted Crane Batching Plant,Concrete Pump[2],DG Set 40kVA,DG Set 82kVA[2],Fork 1.5.4 25 Concrete Lining of Tunnel from Portal-2 Side 180 days 11-10-2018 22-07-2019 23SS+3d Lift[2],Lifter[2],Trailer Truck,Transit Mixer,Tyre- mounted Crane 1.6 26 Finishing Works 30 days 02-09-2019 18-10-2019 21 DG Set 40kVA,DG Set 82kVA[2],Grout Mixer 1.6.1 27 Grouting of gaps and plugging of leakages 14 days 02-09-2019 24-09-2019 and Pump[4],Lifter[4] Air Compressor[2],DG Set 40kVA,DG Set 1.6.2 28 Cleanup of tunnel and demobilization of all equipment 3 days 24-09-2019 30-09-2019 27 82kVA[2],Fork Lift[2],Gas-cutting Kit[4],Lifter[4],Tipper,Welding Machine[4] DG Set 40kVA,DG Set 82kVA,Fork Lift[2],Gas- Setup of monitoring equipment within and outside the 1.6.3 29 7 days 30-09-2019 09-10-2019 28 cutting Kit[4],Lifter[2],Trailer Truck[2],Tyre- tunnel mounted Crane[2],Welding Machine[4] 1.6.4 30 Deconstruction of Site Offices 1 day 09-10-2019 11-10-2019 29 Trailer Truck[4],Tyre-mounted Crane[4] 1.6.5 31 Testing and handover of tunnel 5 days 11-10-2019 18-10-2019 30 DG Set 40kVA[2],DG Set 82kVA[2]