“Management & Care of Intercepted Irregular Immigrants Project Phase 2”

Construction Coordination Meeting

Minutes of Meeting
 
Date& Location of Meeting:  1 April 2013/ IOM office at Batam  
Agenda: 
1. Progress Report (General Progress) 
2. Review update of Last Meeting 
3. Safety Issues 
4. Contractual Issues 
5. Field/ Construction Issues 
6. Other Issues 
 
Participants: 
 
Contractor – Utomo Ladju  Consultant ‐ BITA  IOM 
 Didik Suwandhono    Ries Munandar   Male Bobby  Rihidara 
 Johannes P.   Zayadi   Roslinda Perangin‐angin  
 Tri Aji S. 
 Wijatno D. 
 Yusmar 
 

General Progress 

General Progress 
Date  :   April 1, 2013  
Actual  :   3,851 %     
Plan  :   4,267  %  
    0,416 % delay 
   
Summary of Meeting Agreements & Discussions 
Review status of Last Meeting Issues
I. Field / Construction Issues 
1  Contractor must send steel  Contractor must submit the  PT. Utomo Ladju 
reinforcement sample  to third party  certification 
(testing agency) for testing 
2  Clarify  PLN’s  survey  schedule  with  PLN will conduct survey  on  IOM and BITA 
owner  and  consultant  to  upgrade  the 6th week 
power in temporary office 
3  Mock‐up  for  connection  and  bending  Ongoing status:   PT. Utomo Ladju 
reinforcement  should  be  prepared  by  Contractor will provide it on   
contractor  the 6th week 
4  Planning  to  cut  Manggo  tree  near  the  On going :  PT. Utomo Ladju 
back wall  ‐ Contractor will do survey   
based on the drawing to 
decide if it’s needed to cut 
the mango tree or not 
sometimes this week 
‐ Contactor  shall provide 
the photo of tree before and 
after cutting for evidence to 
KLH 
II. Safety Issues 
1  Contractor  must  provide  the  trash  bin  Ongoing status:  PT. Utomo Ladju 
in site area to keep the site area clean  Contractor will provide it 
and healthy  ASAP 
III. Contractual Issues 
1  Employment  contract  with  the  The latest update from  IOM 
Contractor must be resolved. Once it’s  Contractor, the employment 
completed,  the  insurance  (Jamsostek)  contract currently being 
will be submitted by Contractor  reviewed in Legal 
Department at IOM Jakarta. 
It will be approved on the 6th 
week 
2  Contractor must  prepare and submit  Ongoing status  PT. Utomo Ladju 
Monthly Report for compiling one       
month activities 
IV.  Other Issues 
1  IOM requested Contractor and  Contractor will complete it  PT. Utomo Ladju 
consultant to submit names, photos,  on the 6th week 
specimen signatures, email addresses 
and mobile phone numbers 
       
V. Next Meeting Agenda 
  Will  be  held  on  Monday,  8th  April     
2013,  at  10.00  am  –  onwards  at 
Temporary Office, MCIIP II, Sekupang ‐ 
Batam   
 
 
Meeting Discussion
A. Field / Construction Issues 
1  Contractor is planning to conduct  It is planned on the 6th week  PT. Utomo Ladju 
testing trial mix design  K300 at Testing 
agency (Third party). Contractor also 
must check the calibration date of 
machine 
2  Some pile can not erection follow  Consultant will send the data  BITA 
specification 3,5m depth min.  of piles point have problem  
to Penta on week 6. 
 
3  Contractor is planning to undertake  It will be scheduled on the 6th  PT. Utomo Ladju 
several works:   week 
1. Completion the retaining wall 
ASAP 
2. Preparation for PDA test 
3. Reviewing the foundation 
design 
4  One of PTUN’s staff was complained  Consultant, Contractor &  PT. Utomo Ladju, BITA & 
on noisy caused by pilling work on the  IOM will meet head of PTUN  IOM 
5th week  to discuss on the complaint 
B. Safety  issues 
1  HSE Officer must provide a location  It is planned on the 6th week  PT. Utomo Ladju 
for  master point  
2  Contractor shall make guidance  It is scheduled on the 6th  PT. Utomo Ladju 
direction to location for Consultant‐ week 
IOM Office, Contractor Office & 
Evacuation  Area 
 

Signed and agreed by 

IOM         PT.BITA Consultant      PT. Utomo Ladju 