Escolar Documentos
Profissional Documentos
Cultura Documentos
I. Earthworks
Qty Unit Item Description Unit Price Amount
378 cu. m. Excavation 385.00 145,530.00
227 cu. m. Backfill 330.00 74,910.00
79 cu. m. Buga 330.00 26,070.00
Total = 246,510.00
B. Footing
Qty Unit Item Description Unit Price Amount
1816 bags Portland Cement 240.00 435,840.00
76 cu. m. Wash Sand 660.00 50,160.00
152 cu. m. Wash Gravel 1,000.00 152,000.00
552 pcs. 20 mm dia. x 9.0 m RSB 616.00 340,032.00
552 pcs. 16 mm dia. x 9.0 m RSB 532.00 293,664.00
387 kls. # 16 G.I. Wire 70.00 27,090.00
Total = 1,298,786.00
C. Wall Footing
Qty Unit Item Description Unit Price Amount
80 bags Portland Cement 240.00 19,200.00
7 cu. m. Wash Sand 660.00 4,620.00
9 cu. m. Wash Gravel 1,000.00 9,000.00
30 pcs. 12 mm dia. x 9.0 m RSB 406.00 12,180.00
24 pcs. 12 mm dia. x 6.0 m RSB 290.00 6,960.00
1 kls. # 16 G.I. Wire 70.00 70.00
Total = 52,030.00
D. Tie Beams
Qty Unit Item Description Unit Price Amount
338 bags Portland Cement 240.00 81,120.00
15 cu. m. Wash Sand 660.00 9,900.00
30 cu. m. Wash Gravel 1,000.00 30,000.00
216 pcs. 25 mm dia. x 9.0 m RSB 1400.00 302,400.00
24 pcs. 25 mm dia. x 6.0 m RSB 1000.00 24,000.00
680 pcs. 12 mm dia. x 9.0 m RSB 406.00 276,080.00
1 kls. # 16 G.I. Wire 70.00 70.00
Total = 723,570.00
E. Beams
Qty Unit Item Description Unit Price Amount
942 bags Portland Cement 240.00 226,080.00
50 cu. m. Wash Sand 660.00 33,000.00
90 cu. m. Wash Gravel 1,000.00 90,000.00
64 pcs. 25 mm dia. x 9.0 m RSB 1400.00 89,600.00
184 pcs. 20 mm dia. x 9.0 m RSB 616.00 113,344.00
63 pcs. 20 mm dia. x 6.0 m RSB 440.00 27,720.00
93 pcs. 16 mm dia. x 9.0 m RSB 532.00 49,476.00
27 pcs. 16 mm dia. x 6.0 m RSB 380.00 10,260.00
499 pcs. 10 mm dia. x 9.0 m RSB 175.00 87,325.00
501 pcs. 10 mm dia. x 6.0 m RSB 125.00 62,625.00
159 kls. # 16 G.I. Wire 70.00 11,130.00
Total = 800,560.00
F. Slab
Qty Unit Item Description Unit Price Amount
1036 bags Portland Cement 240.00 248,640.00
44 cu. m. Wash Sand 660.00 29,040.00
87 cu. m. Wash Gravel 1,000.00 87,000.00
714 pcs. 10 mm dia. x 9.0 m RSB 175.00 124,950.00
1872 pcs. 10 mm dia. x 6.0 m RSB 125.00 234,000.00
589 kls. # 16 G.I. Wire 70.00 41,230.00
Total = 764,860.00
G. Stairs
Qty Unit Item Description Unit Price Amount
129 bags Portland Cement 240.00 30,960.00
6 cu. m. Wash Sand 660.00 3,960.00
11 cu. m. Wash Gravel 1,000.00 11,000.00
132 pcs. 16 mm dia. x 9.0 m RSB 532.00 70,224.00
90 pcs. 10 mm dia. x 6.0 m RSB 125.00 11,250.00
28 kls. # 16 G.I. Wire 70.00 1,960.00
Total = 129,354.00
B. Cement Plaster
Qty Unit Item Description Unit Price Amount
282 bags Portland Cement 240.00 67,680.00
24 cu. m. Wash Sand 660.00 15,840.00
Total = 83,520.00
C. Floor Tiles
Qty Unit Item Description Unit Price Amount
20,155 pcs. .20 x .20 m Unglazed Vitrified Floor Tiles 32.02 645,363.10
70 bags Adhesive Cement 320.00 22,400.00
402 packs Tile Grout 90.00 36,180.00
Total = 703,943.10
V. Roofing
Qty Unit Item Description Unit Price Amount
31 pcs. Ls - 50 x 50 x 6 960.00 29,760.00
20 pcs. Ls - 50 x 50 x 9 1344.00 26,880.00
120 pcs. LC - 150 x 50 x 20 1,440.00 172,800.00
160 sheets 32" x 12' Corrugated G.I. Sheets 350.00 56,000.00
18 kg. G.I. Rivets 60.00 1,080.00
49 kg. G.I. Washers 60.00 2,940.00
84 kg. Lead Washers 63.00 5,292.00
10 pcs. Fabricated Ridge Roll 295.00 2,950.00
20 pcs. Fabricated Gutter 325.00 6,500.00
31 pcs. 12 x 300 mm FICEM Fascia Board 370.00 11,470.00
Total = 315,672.00
VI. Painting
Qty Unit Item Description Unit Price Amount
59 gal Flat Latex Primer 500.00 29,500.00
49 gal Semi-Gloss Latex Top Coat 650.00 31,850.00
Total = 61,350.00
SUMMARY
I. Earthworks 246,510.00
II. Concrete Works
A. Column 1,113,860.00
B. Footing 1,298,786.00
C. Wall Footing 52,030.00
D. Tie Beams 723,570.00
E. Beams 800,560.00
F. Slab 764,860.00
G. Stairs 129,354.00
III. Masonry Works
A. Wall 456,967.00
B. Cement Plaster 83,520.00
C. Floor Tiles 703,943.10
IV. Doors and Windows 336,348.00
V. Roofing 315,672.00
VI. Painting 61,350.00
VII. Electrical Works 435,000.00
VIII. Plumbing/Drain Pipes 150,000.00
IX. Forms and Scaffoldings 270,000.00
X. Decorative Ceilings 50,000.00
XI. Move In/Move Out 100,000.00
Material Cost = 8,092,330.10
40% Labor Cost = 3,236,932.04
Total Labor and Material Cost = 11,329,262.14
Permit and Licenses = 50,000.00
15% Contractor's Profit = 1,699,389.32
15% Supervision Fee = 2,023,082.53
10% Contegency = 1,132,926.21
Grand Total/Probable Project Cost = 16,234,660.20
6
6 9
10 125 10 175
12 290 12 406
16 380 16 532
20 440 20 616
25 1000 25 1400
Cost of Activities
1. Clearing/Grabbing/Move-in 50,000.00
40% Labor Cost 20,000.00
Total 70,000.00
2. Excavation/Backfilling 246,510.00
40% Labor Cost 98,604.00
Total 345,114.00
3. Fabrication and Installation of Steel Bars for Footings, Tie-Beams and Columns-1
Footings 660,786.00
Tie-Beams 602,550.00
Columns-1 201,510.00
40% Labor Cost 585,938.40
Total 2,050,784.40
11. Fabrication and Installation of Forms and Steel Bars for Slab-1
Forms (40%) 27,000.00
Steel Bars 100,045.00
40% Labor Cost 50,818.00
Total 177,863.00
16. Fabrication and Installation of Forms and Steel Bars for Slab-2
Forms (40%) 27,000.00
Steel Bars 100,045.00
40% Labor Cost 50,818.00
Total 177,863.00
25. Fabrication and Installation of Forms and Steel Bars for Slab-3
Forms (40%) 27,000.00
Steel Bars 100,045.00
40% Labor Cost 50,818.00
Total 177,863.00
34. Fabrication and Installation of Forms and Steel Bars for Slab-4
Forms (40%) 27,000.00
Steel Bars 100,045.00
40% Labor Cost 50,818.00
Total 177,863.00
35. Electrical, Plumbing, and Water Pipe Connection (4th floor)
Electrical 108,750.00
Plumbing and Water Pipes 37,500.00
40% Labor Cost 58,500.00
Total 204,750.00
43. Fabrication and Installation of Steel Bars for CHB Wall 127,470.00
40% Labor Cost 50,988.00
Total 178,458.00