A PROJECT REPORT
BACHELOR OF ENGINEERING
In
CIVIL ENGINEERING
By
PRAKASH V. SHIRSAT
Shri P. R. Puri
(2014)
Index
2 Definition 2
3.10 Conclusion 15
Annexure I 33
Annexure II 34
Structural Audit of Buildings
1. Introduction
There are number of buildings which are old and deteriorated due to ageing
effect and occupying such buildings may endanger the lives of the occupants
stability and carry out remedial measures for further extension of their useful
of all structures within their jurisdiction and issue notices to the buildings and
the structural audit is insisted for the structures which are more than 30 years
years old.
Structural audit is expected to investigate and highlight all critical areas of the
building and recommend immediate remedial and preventive measures for the
same. The audit covers structural analysis and finds critical elements for all
types of loadings.
Structural audit involves activities like study of drawings and data, visual
-1-
2. Definition
is an important tool for knowing the real status of the old buildings. The Audit
investigate all the risk areas, critical areas and tells whether the building
needs immediate attention. It also covers the structural analysis of the existing
frame and pinpoint the weak structural areas for static, wind & earthquake
loads.
following:
-2-
iii) Modifications, alterations and additions carried out in past.
the Society shall cause the ‘Structural Audit’ of the building as follows:
The first step in structural audit is to study the available architectural and
calculations can be studied and verified with the existing structure details.
-3-
If structural drawings are not available, as built drawings shall be prepared by
assessment.
The visual inspection report consists of following information along with the
institutional
-4-
a) Sub structure assessment : Settlement of columns or foundations,
Soil bearing capacity through trial pits or from adjacent soil data
staircase, lift and lift machine room, etc shall be verified and reported.
terrace, toilets, plumbing lines, drainage lines and overhead tanks shall be
-5-
3.3. Non Destructive Testing
tests (NDT) for concrete members are available to determine strength and
reasons. These tests have been put under four categories depending on the
iii) Core Sampling and Testing - Field cum lab test method to measure
concrete.
-6-
iii) Sulfate Test - To assess total water/acid soluble sulfates in the concrete.
embedded steel.
air.
iii) Infrared Camera Inspection - Infrared inspections are done with a thermal
out with industrial endoscopes or bore scopes through small access holes
-7-
inspected in this way, including cavity-walls, under-floor and between-floor
Sr.
Test Dependability Cost Time
No.
structure for seismic and gravity loading. The seismic evaluation of existing
It gives idea about the potential earthquake-caused risk to building and steps
-8-
The Earthquake Code IS 1893-2002 provides rigorous analysis and designs
possible to retrofit the old buildings, so that they do not collapse during
Earthquake.
Based on the above inspection, analysis and test results, the critical areas
that need immediate repairs and retrofitting are concluded in the report. For
repair of critical slab and beams, water proofing of terrace, toilet blocks,
Water stagnation, plaster cracking, paint peeling, fungus growth and cracking
Problems and their varieties vary from building to building and every problem
may be unique in nature. Some of the common problems are listed below.
iii) Cracks - Cracks on building facade, open cracks in beams and columns,
diagonal cracks in wall near window sills, mushy cracks on entire plaster,
-9-
iv) Deterioration in RCC - Falling of concrete and exposed corroded steel
bars, separation gaps in wall near RCC columns and beams, excessive
inaccessible areas.
v) Unauthorized modifications/alterations.
repairs and strengthening are carried out. According to ACI 546R-04, to repair
repair may be divided into structural repair and serviceability repair. The
concrete structure may also be influenced by factors like the size of individual
repairs, access for repair, relative cost, ease of application, available labor
- 10 -
ii) Micro concrete treatment.
on the structure.
ii) Carefully expose damaged plaster by plaster breaker or hammer & chisel.
iii) Expose the damaged RCC members wherever found loose including
iv) Passivate the cleaned reinforcement with rust passivator using Rusticide.
vi) Apply bonding coat to the entire surface (after watering the surface). Next
- 11 -
viii)Carry out strengthening and repairing of damaged R.C.C. members by
to the top of footing, top & bottom of beam/slab or up to the level as per
site conditions. Only required parts of the walls near columns shall be
iv) Apply 2 coats of Polymer coating with 1 part of Polymer mixed to 1.5 part
i) Identify the loose plaster pockets and break / dismantle the same.
ii) Apply jet of water and clean the opened loose plaster surfaces.
iii) Hack the joints and fill with cement mortar and cure.
- 12 -
iv) Apply one coat of cement slurry for old brick masonry.
v) For R.C.C. Members like column, beam, slab, chhajas, pardi etc. apply
vi) Apply two coats water proof plastering for external surfaces of walls.
ii) Clean reinforcement using wire brush, apply “RUSTICIDE” using cotton
mortar treatment.
3.8.5. Waterproofing
- 13 -
i) Existing waterproofing, parapet wall plaster should be removed & cleaned
carefully.
ii) The slab surface should be cement grouted. After saturation, apply base
iv) 9” x 9” brick-bat watta should be provided at the junction of parapet wall &
slab.
replaced.
vi) RCC coping at the top of the parapet wall should be provided.
vii) Watta finishing along with “Nose” formation in parapet wall plaster should
viii)The top surface should be finished in IPS using cement: sand: metal no. 1:
- 14 -
3.9. Structural Engineer - Qualifications and Expectations
the properties of general repair materials, artificial materials used for repairs
The structural engineer shall exercise reasonable diligence and take active
and personal interest in the planning and carrying out of the inspection of the
building. He shall not delegate the inspection work to his assistant or another
person who is not a registered professional engineer in the civil and structural
experience.
3.10. Conclusion
The structural diagnosis is vast, important and highly responsible job which is
out the periodical structural audit of the buildings by professional experts and
- 15 -
Owner (Societies or Individual), Engineer and Contractor are three important
occupies / capitalizes the building and intends to use the building for their
entire life but also expects the same to perform for next generation. Engineer
plays the role of identifying the need of repair, writing the specifications,
supervision and execution at the building repair project. The third element
Contractor and his Workers are physically in contact with the building repair
work. The owner should understand the need of timely maintenance and
However, structural audit itself is not sufficient. It is important that the findings
***
- 16 -
CASE STUDY
- 17 -
EXECUTIVE SUMMARY
2 Immediate Propping No
3 Evacuation No
(polycarbonate) chhajjas.
Drawings
structure
- 18 -
9 Type of Repairs Major / Minor / Structural / Non - Structural / N.A.
provided
provided
life of Building in
years
Repairs
- 19 -
1. General Information of Building:
The age of the buildings is more than 50 years. Hence it is necessary to carry
out structural audit of the building as per government norms and to decide the
3. Mode of use:
4. Type of building:
The said building is a ground plus two storied structure with 4 flats on each
- 20 -
Front elevation of building
Water logging : No
side. The results indicate that the minimum compressive strength of the tested
- 22 -
iii) Variation in Moisture Content - Strata not adversely affected due to
noticed
i) Masonry & Plaster - Minor & Major cracks in external plaster & walls are
- 23 -
Deteriorated External Plaster & Vegetation Growth
ii) Plumbing – Some of the soil pipe joints are loose & leaking.
iii) Staircase • Cracks in staircase wall are observed. External plaster required
Crack in Wall
shrubs again.
- 24 -
Deteriorated Mumty Room, Uneven Terrace Finishing & Cracked
vii) Leakage - Leakage from external wall due to damaged plaster is observed
i) Beams - External beams of some of the flats show cracks. The beams
ii) Chhajja - Chhajjas of almost all the flats are deteriorated. The chhajjas
- 25 -
8.5. General Observations inside the Flats –
i) Flat No.1 –
jacketing.
removed and redone. Kitchen slab shows bulging. Internal beam shows
repairs.
should be removed and redone with tiling. WC-bath slab shows bulging.
for the distressed slab repairs. Kitchen chhajjas are deteriorated. The
i) Flat no.5 –
Kitchen - Kitchen slab shows bulging and minor cracks. Internal beam
- 27 -
WC-Bath - Plaster of bathroom walls is deteriorated. The plaster should
be removed and redone with tiling. WC-bath slab shows minor cracks.
Flat no.6 –
Living room - Living room slab shows bulging. The slab should be
Living room - Living room external wall shows seepage. Plaster of both
treatment.
Living room - Living room walls show seepage. Plaster of both the sides
should be redone.
Kitchen - Kitchen external beam shows cracks. About 25% of kitchen slab
PMM treatment.
Crack in wall
- 29 -
8.5.3. Second Floor:
i) Flat no.9 –
Kitchen - Kitchen slab shows minor cracks. The slab should be repaired
WC-Bath - WC-bath lofts are damaged. The lofts should be removed and
recast.
Crack in column
Kitchen - About 25% of kitchen slab shows minor cracks. External beam
- 30 -
seepage. Plaster of both the sides should be redone. Kitchen shows
WC-Bath - WC-bath lofts are damaged. The lofts should be removed and
recast.
Kitchen - About 25% of kitchen slab shows minor cracks. External beam
should be redone.
Kitchen - Kitchen slab shows minor cracks. External beam shows cracks.
both the sides should be redone. Kitchen shows leakage from top. Terrace
- 31 -
WC-Bath - WC slab shows minor cracks. PMM treatment is recommended
for slab repairs. WC-bath shows leakage from top. Terrace waterproofing
should be repaired.
9. RECOMMENDATION
b. The structural members proposed for repairs should be repaired with PMM
treatment.
c. All the chhajjas at all the floors should be repaired or replaced with light
weight material.
- 32 -
Annexure I
- 33 -
Annexure II
Ground Floor
1 Column no.1 29.43 22
2 Column no.2 24.56 15
3 Column no.3 29.92 23
4 Column no.4 30.93 25
5 Column no.5 29.08 22
6 Column no.6 27.27 19
7 Column no.7 30.27 24
8 Column no.8 33.08 >25
9 Column no.9 34.86 >25
First Floor
10 Column no.9 26.4 18
11 Column no.10 26.5 18
12 Column no.11 27.33 20
Second Floor
13 Column no.9 30.62 24
14 Column no.11 26.5 18
Average 22
- 34 -