PROJECT PROBLEM: REDESIGN THE CURRENT DRAINAGE SYSTEM TO SOLVE THE FLOOD
PROBLEM
Figure 1: Sediment laden runoff from a development site has caused inconvenience to
neighboring residents whenever rain falls
Instructions:
1. A project group MUST ONLY consists of a MAXIMUM of FIVE (5) members.
2. Project question:
Due to the new development, the percentage of impervious layer has increased
significantly. The increasing of impervious layer will increase the runoff values because
the water cant infiltrate into the soil and this could lead to the flood problem (Figure 1).
Figure 2 shows the relationship of rainfall intensity, duration, and frequency (IDF)
developed from historical rainfall record obtained from the rain station within the site.
Considering rainfall duration of 30 minutes, propose a temporary drain to help the
developer and contractor solve the problemHowever, there is at least one limitation. The
width of the channel should not be greater than 1 m wide.
4. Additional information:
4.1 For development of an area of 80 hectare or less, rational method can be used to
calculate for peak discharge by DID (2012). Rational method is given as
CIA
Q (1)
360
1
where, Q = peak flow (m3/s); C = runoff coefficient (see Table 1); I = average
rainfall intensity (mm/hr) (Figure 1); and A = drainage area (ha).
4.2 For the purpose of channel design, the rate of flow Q can be obtained from the
continuity equation, i.e.
Q AV (2)
2
where, V = mean velocity of flow (m/s), and A = area of flow (m ).
5.3 Project presentation carried out either through presentation in class, video-
presentation or interview-based, is subjected to the instructor requirement. During
submission/presentation of the report, all members of the group must be present
where questions will be posed to each member of the group (see assessment
rubric).
2
Note: Please refer to your instructor if any doubt arises during project implementation as the
assessment and grading will be carried out by the class instructor.
3
Table 1: Recommended runoff coefficients for various landuses (DID, 2012)
Runoff coefficient C
Landuse For minor system For major system
( 10 year ARI) (> 10 year ARI)
Residential
Bungalow 0.65 0.70
Semi-detached bungalow 0.70 0.75
Link and terrace house 0.80 0.90
Flat and apartment 0.80 0.85
Condominium 0.75 0.80
Commercial and Business Centres 0.90 0.95
Industrial 0.90 0.95
Sport Fields, Park and Agriculture 0.30 0.40
Open Spaces
Bare soil (no cover) 0.50 0.60
Grass cover 0.40 0.50
Bush cover 0.35 0.45
Forest cover 0.30 0.40
Roads and Highways 0.95 0.95
Water Body (Pond)
Detention pond (with outlet) 0.95 0.95
Retention pond (no outlet) 0.00 0.00
4
Table 2: Values of Manning roughness coefficent n for open channels (Chow, 1959; DID,
2012)
Drain/pipe Manning roughness n
Grassed drain
Short grass cover (< 150 mm) 0.035
Tall grass cover ( 150 mm) 0.050
Lined drain
Concrete
Smooth finish 0.015
Rough finish 0.018
Stone pitching
Dressed stone in mortar 0.017
Random stones in mortar or rubble masonry 0.035
Rock riprap 0.030
Brickwork 0.020
Pipe material
Vitrified clay 0.012
Spun precast concrete 0.013
Fibre reinforced cement 0.013
UPVC 0.011
References:
Chow, V. T. (1959). Open-Channel Hydraulics. USA: McGraw-Hill Book Co., Inc.
DID (Department of Irrigation and Drainage Malaysia) (2012). Urban Stormwater
Management Manual for Malaysia. Kuala Lumpur: DID.
5
BFC21103 Hydraulics Project Assessment Rubric
CLO1: Explain the concept of uniform and non-uniform flows in open channel (C4, PLO4)
Assessment Criteria Subcriteria Level 1 2 3 4 5 Weight Score
Application of suitable
Use of correct C3 1.0
equations
variables and
Analyses done through step
equations C4 1.0
by step methodology
Use appropriate Analyses the direction of
C4 1.0
concept and flow for chosen alignment
Report
methodology to Provide suitable sizing of
C4 1.0
interpret data channel
Justification on Synthesizes all data in
C5 0.5
methodology, sizing & aligning channel
assumption & Justify the use of all
C6 0.5
limitation in study variables
Total (%) 5 /25.0
CLO2: Discuss technically the given open channel hydraulics problem (P3, PLO2)
Assessment Criteria Subcriteria Level 1 2 3 4 5 Weight Score
Descriptions on study area
Technical P1 0.5
based on provided data
investigations on
Extracting data for use in
study area P2 1.5
calculation and analyses
Careful selection of equations
Utilizing information P3 1.5
based on instructions
and equations in
Report & Solutions are clearly
sizing channel P3 1.5
Presentation described
Calculations carried out are
P4 1.5
ensured correct (validated)
Use/adapt appropriate
Choice on complexity of
channel size for the P5 0.7
design variables selection
study area
Adapting appropriate
P6 0.3
channel size technically
Total (%) 7.5 /37.5
CLO3: Respond in group effectively in solving uniform and non-uniform flows problems (A3, PLO5)
Assessment Criteria Subcriteria Level 1 2 3 4 5 Weight Score
Follows given format of
A1 1.5
project report
Convey information Shows contribution from all
A2 1.5
in group members
Demonstrate the utilization
A3 1.5
Report & of provided information
Presentation Demonstrate the importance
A3 2.0
of documented information
Convey spoken ideas Organisation of group work
A4 0.7
in group and presentation
Support members in Q&A
A5 0.3
session
Total (%) 7.5 /37.5
6
FACULTY OF CIVIL AND ENVIRONMENTAL ENGINEERING
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Week: _________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
(you may attach additional sheet if required)
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
(you may attach additional sheet if required)
7
FACULTY OF CIVIL AND ENVIRONMENTAL ENGINEERING
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
1. Content
2. Learning Activities
3. Instructor (s)
8
4. Group Members
5. Generic/Soft Skills
6. Overall/Others