Escolar Documentos
Profissional Documentos
Cultura Documentos
IPC2006-10288
PIPELINE OPERATION IN THE NORTH SEA AREA, STATOIL’S EXPERIENCE AND CHALLENGES
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
INTRODUCTION safe subsea launching, pig running and proper data collection for long
Statoil’s first operated trunk line is the Statpipe trunk distance pigging.
line system put in operation in 1986. Statpipe comprises 6 Statoil has actively promoted dual/multi-diameter pipeline
subsystems transporting dry, dense phase, natural gas from the design, amongst others by sponsoring in-line inspection (ILI)
Statfjord field to the gas processing plant at Kårstø and dry sales developments in two separate directions;
gas from Kårstø to Europe via the Draupner platform and the (1) Development of a Multi-Diameter Pipeline Tool (MDPT),
Norpipe trunk line system. The total length is 893km and the based on XHR magnetic flux technology
diameter is 28”-36”with conventional steel riser tie-ins to the (2) Development of a laser-based 2D/3D image optical tool,
offshore platforms. Offshore pipeline depth down to 300m. called Optopig.
The subsea pipelines enter and leave the island of Karmøy The development of XHR technology was based upon Statoil
via a landfall concrete (culvert) tunnel. The onshore pipeline is requirements for more cost effective and reliable detection of low
routed across the island before it crosses the strait between the level corrosion in heavy wall, long distance pipelines. On this basis
island and the mainland and two more fjords crossing through the XHR technology is challenging the necessity of the so-called
blasted rock tunnels underneath the strait and fjords before “baseline” inspection, necessary with the HR technology.
approaching the Kårstø gas processing plant. Subsea launching of internal inspection tools is also a challenge
A more recent typical trunk line is the Åsgard Transport with respect to the risk of creating hydrates. By developing very
pipeline, transporting dry, dense phase, natural gas from the reliable procedures and operational simulation models, Statoil has in
Haltenbanken fields to the gas processing plant at Kårstø with connection with the inspection of Åsgard Transport demonstrated the
first gas in 2000. The diameter of the pipeline is 42”, but the water ability of successful sub-sea pig launching at an acceptable risk level.
depth (370m) excluded a conventional 42” steel riser. Production In addition to the risk of subsea pig launching, pigging
is therefore achieved using a number of 14” flexible risers operation also represents a restriction in product flow velocity and
connected to a 28” subsea Export Riser Base (ERB), making consequently reduced product delivery. Pigging operation should
topside pig launching for pipeline inspection impossible. The 28” therefore be limited to what is absolute necessary to maintain an
ERB is connected to the 42” pipeline via a 28” expansion spool acceptable integrity risk level.
(70m) with mechanical connectors and a 28” to 42” transition The combination of MDPT/XHR-technology, Optopig/optical
piece. technology and developing very reliable product monitoring- and
The 684 km long 42” subsea pipeline enters the island of corrosion models, the frequency of internal inspections can be reduced
Karmøy via a blasted rock tunnel. The onshore pipeline is routed maintaining an acceptable risk level.
across the island before it crosses the strait between the island and As the size of Statoil’s pipeline network has grown, more and
the mainland. Two more fjords are crossed along the onshore more focus has been put on scale advantages and cost effectiveness.
section to the receiving facilities at Kårstø. Fjords and strait are This is done by challenging the quality, frequency and cost of internal
crossed by laying the pipeline on the bottom. Operating these and external inspection. In particular the development of cost effective
pipelines represents several challenges, and the accumulated subsea ROV-operations has been of great importance.
experience gained through successful operations of these pipelines The importance with regard to reliability and availability of the
has brought Statoil to the forefront within the pipeline industry. pipeline network is also challenging the contingency pipeline repair
Through comprehensive research and development Statoil system (PRS) with regard to response times and reliability in
has improved pipeline technology within several areas as executing repairs.
inspection, maintenance- and repair. Together with the To manage the challenge as outlined above a proper risk based
development of risk based condition (integrity) assessment, condition management system (PCMS) including risk based inspection
inspection and monitoring planning tools and work processes, and monitoring planning, has been developed As a part of the PCMS
these technology achievements have significantly improved Statoil has in cooperation with Det norske Veritas (DnV) developed
Statoil’s knowledge and understanding of the pipeline condition DnV’s software tool Orbit Pipeline for risk based pipeline condition
and associated risk levels. In addition a significant reduction in (integrity) assessment.
operating cost has been achieved. In the chapters below the paper is discussing the following
For the time being Statoil is installing the world’s largest topics related to the above challenges:
offshore pipeline called Langeled. The pipeline is 42” in diameter
and 1200km long and goes from from an export terminal at the 1. Internal inspection
Norwegian west cost via the Sleipner field to Easington in the a. Magnetic Flux Leakage (MFL) - Extra High Resolution
UK. (XHR) technology.
Since 2002 Gassco has been the Operator for transporting b. Multidiameter Pipeline Tool (MDPT)
Norwegian gas to continental Europe and the UK. Gassco is a c. Optopig–Optical in-line inspection tool
fully state owned company. Statoil is now TSP (Technical Service 2. External inspection
provider) for most of the trunk lines. a. ROV-Survey of submarine pipelines
b. Landfalls
CHALLENGES 3. Pipeline Repair System (PRS)
Being operator of its first pipeline system 20 yeas ago, a. PRS-pool of equipment
Statoil’s first technical challenge was to establish a proper system b. Remote pipeline repair system
for internal and external inspection together with a reliable subsea c. Remote hot-tapping system for subsea pipelines
pipeline repair system. After a few years Statoil also realized that 4. Pipeline Condition Management System (PCMS)
the landfall design also represented a major challenge with respect a. Orbit Pipeline
to the integrity management of the concrete tunnel. 5. Availability and cost effectiveness
The more recent design as the Åsgard Transport pipeline, is
first of all challenging the internal inspection technology with
regard to the development of dual diameter inspection tools for
2 Copyright © 2006 by ASME
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
1. INTERNAL INSPECTION
a) Magnetic Flux Leakage (MFL) - Extra High Resolution (XHR) Internal pitting metal loss:
technology. Diameter < 0.25 T : not defined
By improving the Magnetic Flux Leakage (MFL) Diameter > 0.25 T : 15% min dept. estimation, +/- 8% accuracy
technology to a level of eXtra High Resolution (XHR) compared Diameter > 0.5 T : 10% min dept. estimation, +/- 5% accuracy
to the previous High Resolution (HR) technology, Statoil has Diameter > 1 T : 8% min dept. estimation, +/- 5% accuracy
achieved to make metal loss measurements more reliable, accurate Diameter > 2 T : 5% min dept. estimation, +/- 5% accuracy
and credible.
External pitting metal loss:
Diameter < 1 T : not defined
Diameter > 1 T : 10% min dept. estimation, +/- 5% accuracy
Diameter > 2 T : 8% min dept. estimation, +/- 5% accuracy
Diameter > 3 T : 5% min dept. estimation, +/- 5% accuracy
Statoil initiated development of XHR technology in 1994 together b) Multi diameter pipeline tools (MDPT)
with Pipetronix/PII. The main development objective was to meet Conventional in-line inspection tools could not be used in
Statoil’s requirements for more cost effective and reliable Åsgard Transport due to the 28”/42”dual-diameters of the pipeline.
detection of low level corrosion in heavy wall, long distance Statoil initially evaluated a conventional 42” subsea launching facility
pipelines, including; against a 28”/42”diameter concept. A 42” launcher would enable the
- Pressure range (> 150 bar) use of conventional single diameter pigs, but at a high cost and high
- Heavy wall thickness inspection capability (up to 1,5”) risk related to the development of the Export Riser Base (ERB)
- Active range (up to 850 km) structure and development and operation of the belonging subsea pig-
- General metal loss: 5% min. depth estimation with +/- launching equipment. The ERB connects the flexible risers from the
5% detection accuracy floating production unit to the pipeline system.
This dual/multi-diameter pipeline technology development was
Comparison between XHR and HR tools: therefore initiated by the need to obtain reduced capital costs, by
- Higher data sampling/more sensors (504 vs. 200 sensors allowing reduced size on offshore risers and near platform lines (save
for a 40” configuration) weight & money) and reduced size main valves (better reliability and
- Improved magnetization (1000 Hz vs. 600 Hz for a 40” save weight & money).
configuration) It was consequently decided to develop a 28”/42” multi
- Advanced data processing/sizing routines diameter in-line pipeline inspection tool based upon the MFL-XHR
technology together with necessary launching tools and operational
procedures. The 28”/42” MDPT development project started in 1997
with the following main design premises (Åsgard transport gas export
system):
- Pipeline length 707 km
- 200 bar operating pressure
- Wall thickness 42”- 31 mm
- Wall thickness 28”- 25 mm
- 5 D bend
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
Tow section Magnetizer
Data section No corrosion was detected during the 2005 inspection. 236
metal loss defects (< 12 % of WT), 24 within 10-12% of WT, was
detected. An amount of: ~ 715 G-byte uncompressed data was stored
Battery section in the MDPT during the operation.
MDPT/XHR is presently available in 28/42” configuration only,
Fig 4: The 28”/42” Multi Diameter Pipeline Tool (MDPT) in but different configurations can be made, dependent on demand.
42” mode.
c) OPTOPIG - Optical in-line inspection tool
The MDPT concept’s main features are:
- Four units comprising tow section, magnetizer section, battery Introduction
section, electronic section (data collection/storage) The development of the Optopig introduces a new range of
- True multi-diameter 28”- 42” covering in-line inspection in all optical-electronic in-line inspection tools. The technology
diameters between 28” and 42” incorporated into the tools includes a laser-based 3D-imaging
- Total length 7.8 m technology providing enhanced resolution and detection capabilities
- Total weight 4.1 tons for the inspection of the internal surface of a pipeline. The types of
- XHR technology anomalies detected and sized with precision include geometric flaws
as well as internal corrosion. The data collected provides valuable
The tool has been tested several times as follows: information, especially for the integrity assessment of gas pipelines.
- September 2000 - First Run, Dornum-Emden 42”/~50km The tool design also includes the capability to inspect multi-diameter
- September 2002 – Inspection of Zeepipe IIB 42”/ ~300 km pipelines incorporating the MDPT-technology for the carrier unit. The
- Winter 2003 - three test runs in Zeepipe IIB tool can be applied in a large variety of different types of pipelines,
- Summer 2003 - test run in Zeepipe IIA 42”/~300 km however initially the major focus regarding its application is gas
pipelines.
The tool has been in service several times as follows:
- Autumn 2003 – One onshore 36”/42” gas pipeline Principle of Operation
inspection (3 x 36” river crossings) (Gasunie) Statoil initiated the development of the Optopig together
- Autumn 2005 – Onshore 32”/40” gas pipeline inspections with Norsk Elektro Optikk AS. The Optopig has been designed to
(Ruhrgas) provide an accurate and cost-effective solution for the inspection of
- The MDPT was finally accepted by the Åsgard Transport the internal surface of pipelines and consists of a highly compact
partners and the Norwegian authorities for use in the optical system built into a suitable mechanical pig frame. As with
Åsgard transport pipeline in 2004. During the summer of other in-line inspection tools the mechanical components must
2004 the MDPT was launched and run through the Åsgard incorporate a drive unit, house the energy supply and provide room for
Transport pipeline successfully facing the following the measurement and data storage devises. Use of conventional video
operational challenges: proves to be impractical for other than very short pipe lengths, due to
severe power and data storage limitations. The solution to these
Minimize reduction in ÅT production during MDPT challenges came with the introduction of a novel line scan camera and
installation and inspection laser illumination technology. Figure 6 shows the principle applied. A
Installation of 44 tonnes heavy subsea pig launcher requiring continuously moving laser line illuminates the inner pipe wall. The
strict weather limitations reflected high intensity light is projected onto camera/optical sensors
Tie–in to a live gas system at 300 meter water depth which are aligned at angles between 30º and 60º to the wall. By
Removal of sea water – risk of hydrates utilizing a triangulation principle on a two-dimensional sensor, the
350 valve operations and 700 procedure steps system can both measure the position of an anomaly and its intensity,
High focus on HSE&Q and Risk Management as can be seen in figure 7. By combining these two measurements, a
A success criterion was the development of a software three-dimensional image of the pipe surface can be displayed.
training model for the ROV-pilots. (Colour coded PI&D’s,
3D models, animations).
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
Fig. 7: Triangulation Principle
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
and survey depth. By organizing tender documents and contracts for
competition, significant improvement in quality and cost effectiveness
has been achieved. At the moment Statoil has frame-agreements with
several survey contractors which are subject to regularly competition.
2. EXTERNAL INSPECTION
a) ROV-survey of submarine pipelines
With several thousand kilometre of sub sea pipelines to be
inspected in the harsh environment of the North Sea, Statoil has
encourage the improvement of sub sea pipeline survey by use of
ROV, in particular with regard to instrumentation, survey speed
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
serving the needs of ca. 8000 km of subsea pipelines, whose diameters
range from 3.5" to 44".
This is by far the world’s largest and most experienced
emergency pipeline repair tool facility. It has almost 20 years of
experience using the tools and a team of dedicated personnel for
planned and emergency repair operations.
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
Fig.16: Coupling spread - Coupling Installation Frame
(CIF).
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
4. PIPELINE CONDITION (INTEGRITY) MANAGEMENT
SYSTEM (PCMS/PIMS)
Statoil’s maintenance strategy emphasis that all pipeline systems
shall undergo maintenance in order to maintain the function of
equipment, structures and systems in accordance with regulatory
requirements and internal requirements for safe and efficient
operation.
Pipeline regulations and codes are normally based on a safety-
or risk philosophy. The design requirements are established so as to
fulfil the objectives of the safety philosophy. The set of design criteria
may thus be seen as the practical interpretations of it. A given pipeline,
as established through the design, and installed accordingly, then is a
Fig.21: Remote hyperbaric welding of sleeve realisation of a structure which, along its whole length, meets the
connecting pipeline and spool together. applicable safety objectives.
In pipeline operations, inspection and monitoring are ongoing
c) Remote hot-tapping system for subsea pipelines activities for the purpose of assessing the condition and integrity of the
Subsea hot-tapping is a method for connecting new pipeline as the internal and external environment changes and affect
pipelines to existing pipelines without depressurising the system. the pipeline system, i.e. verifying that the pipeline remains in a safe
Hot-tapping is a well-known method, involving the drilling a hole condition. On this basis maintenance programs including inspection-
into a live production pipeline. Subsea applications are extremely and monitoring programs are established.
limited with only two examples to date on the Norwegian Scope and frequency of maintenance are established in
continental shelf and seven in the whole North Sea area - all using accordance with risk analysis principles and shall be condition-based
divers. as far as possible, where condition-based maintenance refers to
Foreseeing the need for remotely operated (diverless) maintenance activities which are based on knowledge of condition and
approaches, work on the new hot-tap system began in 1999 as part are carried out before the maintenance objects (equipment, structures,
of a development programme for PRS. This technology makes it systems) fail. As opposed to corrective maintenance which refers to
possible to tie-in new pipelines to existing infrastructures, even in activities carried out in order to restore functionality to a maintenance
very deep water. object which has already failed.
Statoil has developed and qualified a subsea remote hot- The Pipeline Condition Management System (PCMS/PIMS) is
tapping system that provides equipment for carrying out subsea consequently defined as the management system established to obtain
hot-tapping in water depths down to 2000m of pipeline systems the knowledge of the condition and to carry out the maintenance and
(8”-42”) containing pre-installed hot-tap T-junctions. Maximum repair as described.
pipeline pressure during tapping operations is 250 bar and The main management element is the pipeline condition
maximum rotation for pre-installed T-junctions is 30deg. from the assessment based upon design-, inspection- and monitoring data.
vertical position. Cut hole diameter is limited to 400 mm. These data are all stored in purpose built databases.
The next phase to develop and qualify a retrofit Tee is The software tool “Orbit Pipeline”, assist in organizing and
ongoing. This will make it feasible to remotely hot tap on live analyzing data related to
pipelines, originally unprepared for such hot tap. relevant failure mechanisms based upon risk analysis principles where
the probability of failure together with the consequence of failure
constitute the risk element. The acceptable level of risk defines the
basis for establishing & updating monitoring-, inspection and
maintenance programs.
Statoil has through the last years promoted and been a major
premise provider for the development of DnV’s Orbit Pipeline. In this
way the Orbit Pipeline software tool has been tailor-made for Statoil to
be a key tool in Statoil’s PCMS/PIMS. Developments are still
ongoing.
Statoil’s PCMS/PIMS principles has been developed and
materialized into a system of work processes (e.g. inspection,
monitoring,..), databases and software tools (e.g. Orbit Pipeline,..)
which are linked together.
The objective is to make Statoil’s pipeline condition
management system (PCMS/PIMS) process as reproducible and as
person independent as possible. The main objective is nevertheless to
find the acceptable risk- and safety level with the belonging
minimized maintenance, inspection and monitoring programs. This
should be the optimum way of operating the pipeline systems, right
safety level at the lowest cost.
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
a) Orbit pipeline program or given as an input profile. The free-spans can be ranked
ORBIT Pipeline consist principally of data storage and according to risk.
administration and various integrity assessment modules. ORBIT
Pipeline may also include assessments from more specialised or On-bottom stability
advanced case by case evaluation performed outside ORBIT The On-Bottom Stability assessment as implemented in ORBIT
Pipeline. ORBIT Pipeline will, however, be useful in defining the Pipeline is based on DNV’s Recommend Practice RP E305 On-Bottom
cases where such detailed evaluations are necessary and for later Stability Design of Submarine Pipelines. DNV RP E305 provides
implementation and interpretation of the results from the assessment models at various levels. The simplest model “Simplified
assessment studies. Stability Analysis” has been selected. In addition to the stability
check, soil bearing capacity (sinking of the pipeline into the soil) and
Data storage and administration floating of the pipeline, are checked.
- Data may and will be taken from many data sources, and in
most cases, duplicate data sources will exist. Hence it is Upheaval buckling
important to notify where the data are taken from. A Pipelines sometimes buckle upwards or sideways under the
reference system has therefore been implemented. influence of axial compressive forces developed by the operating
- Pipeline design, fabrication and installation data together temperature and pressure. This form of buckling can severely over-
with results from pipeline monitoring and inspection form stress the pipeline. The Upheaval Buckling Assessment as
the basis for condition/integrity and risk assessment. These implemented in ORBIT Pipeline has primarily been based on
data is input to the assessment module. The time- Germanischer Lloyd’s “Rules for Classification and Construction”.
development of monitoring and inspection results can also be This methodology is further based on OTC Paper 6335 “Design of
examined Submarine Pipelines against Upheaval Buckling”.
- Results from product and corrosion monitoring can also be
stored in ORBIT Pipeline. The objective has been to design a Cathodic Protection (Anodes)
general framework for collection, evaluation and The cathodic protection design can be verified against DNV-RP-
presentation of basis data needed to estimate / evaluate B401. Anode depletion measurements are plotted against the expected
internal corrosion. usage from design.
- There is an event and history log for registration of events,
operational changes etc. that is important for the assessment Risk assessment
of the pipeline integrity. The pipeline can be divided into sections, usually based on type
(riser, pipeline, etc.) or most critical damage cause, say a part of the
Integrity assessment pipeline with many long free-spans. The risk assessment is done for
Different modules serve as a calculation tool for code each section separately. The pipeline section is one of the basic
compliance, condition, integrity and defect assessments. The concepts in ORBIT Pipeline. The section risk is the highest risk of the
integrity assessment is currently divided into two main categories. associated damage causes at a specific time. As an example, the
Defect Assessment: Integrity implications of defects, i.e., section risk may be driven by a single corrosion defect or a free span,
corrosion defects based on commonly used codes (guidelines). which extensions are very short compared to the length of the section.
Evaluation of cracks and dents will be added as part of this In order to bring the focus to these high-risk elements, it is possible to
module. The Probability of Failure (PoF) is estimated for a given sub-section the pipeline. Components (valves, flanges, crossings, etc.)
defect versus time. Two limit states are considered: burst and may be defined along the pipeline. The risk assessment of components
leakage limit states. The PoF, CoF and Risk are estimated for all follows the same principals that apply for a section.
defects in a given Kp-range. 1
Pressure containment
The utilisation of the pipeline due to pressure containment
can be calculated according to the DNV Offshore Standard OS-
F101 and the ASME standards B31.4 and B31.8.
Free span
The screening criterion as outlined in DNV-RP-F105 has Re-sectioning Re-assessment
New inspection results
been implemented in ORBIT Pipeline. The screening criteria
proposed apply to fatigue damage caused by Vortex Induced
Vibrations (VIV) and direct wave loading in combination with Fig.23: Orbit Pipeline Working Process.
current and wave loading. Sensitivity studies can be performed by
varying every relevant input parameter. Inspection planning
The design check gives an overview of all span lengths An “Inspection Planning Module” has been implemented in
(span gaps) compared to allowable span length (allowable span ORBIT Pipeline. The input to this module is based on two primary
gap). The allowable span length can either be calculated by the sources:
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm
1) Past inspections, i.e., historical overview of all performed ACKNOWLEDGMENTS
inspections. Statoil acknowledge the contribution and cooperation of
2) Results from pipeline and component assessment in terms of Pipetronix/PII, Norsk Elektro Optikk AS, Det norske Veritas,
time to next inspection (initiated from exceeding risk-limit or StoltSubsea7 JV, Isotek, Sintef, Cranfield, Hydratight, Technomarine,
maximum time between inspections). Deep Ocean AS, Stolt Offshore AS.
Activities
Planned activities (repairs, interventions, analyses, etc.) can
be registered along the pipeline system and followed-up in the
activities module.
Reporting
The reporting module comprises of the following pre-
defined reports: General print-preview, Pipeline data,
Event/History Log, Survey and Inspection Results, Defect
assessment, Portfolio Assessment, Pipeline Assessment,
Component Assessment, Condition Evaluation Summary,
Inspection Plan, Activities, References and Pictures, Report
Merger (merge selection of the above reports into one file),
Access Reports (user-designed database reports).
30
25
25
Inspection
Operating agreements
20 18 19
% of total cost
incl.chemicals
Product mngt.
15 13 Condition assesment
13
PRS cont.
10 8
Corrective & Condition
based maintenance
4 Other (Business
5
overhead, support, etc.)
0
1
Activities
Downloaded 26 Oct 2010 to 116.212.199.202. Redistribution subject to ASME license or copyright; see http://www.asme.org/terms/Terms_Use.cfm