GREEN COLOUR : EQUIPMENT INSTALLED

LEGEND:
YELLOW COLOUR : EQUIPMENT NOT INSTALLED YET

Nos Of Equipments
65 2535.75 ton
EQUIPMENT TONNAGE POSITION CLASSIFICATIONS DRAWING MATERIAL LIFTING PLAN INSTALLATION RELEASE TO OTHERS

ITEM CODE REMARKS WEIGHT (TON) AREA CVS FDN TYPE FDN TAG EL.+ TIER EQP. SEATING EL.+ STR ROW STR FRAME CLASS INCLUDED IN TYPE CONFIGURATION STATUS RFI REV. STATUS DATE RECEIVED WEIGHT CLASS REQUIREMENT REASON STATUS INSTALLATION DATE STATUS HANDOVER DATE

3215-V-231 149.00 3215-111 STR-1102 STR STR-1102 123.500 - 131.000 2 148.800 A-B 1-2 STATIC VESSEL VERTICAL RECEIVED IFC 3 RECEIVED 31-May-18 CRITICAL REQUIRED > 100TON INSTALLED 1-Jun-18
3215-R-121 140.00 3215-111 STR-1103 STR STR-1104 116.500 - 123.500 1 117.500 A-B 6-7 STATIC REACTOR VERTICAL RECEIVED IFC 2 RECEIVED 7-May-18 CRITICAL REQUIRED > 100TON INSTALLED 10-May-18 HANDOVERED 1-Aug-18
3215-R-122 140.00 3215-111 STR-1103 STR STR-1104 116.500 - 123.500 1 117.500 A-B 5-6 STATIC REACTOR VERTICAL RECEIVED IFC 2 RECEIVED 7-May-18 CRITICAL REQUIRED > 100TON INSTALLED 11-May-18 HANDOVERED 1-Aug-18
3215-R-123 140.00 3215-111 STR-1103 STR STR-1104 116.500 - 123.500 1 117.500 A-B 4-5 STATIC REACTOR VERTICAL RECEIVED IFC 2 RECEIVED 7-May-18 CRITICAL REQUIRED > 100TON INSTALLED 11-May-18 HANDOVERED 1-Aug-18
3215-A-611 B 93.21 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-611 B 108.500 - 115.500 0 108.500 A-G 18 - 19 PACKAGE 3215-A-611 PACKAGE N/A NOT RECEIVED YET RECEIVED 18-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 6-Oct-18
3215-A-611 A 89.07 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-611 A 108.500 - 115.500 0 108.500 A-G 18 - 19 PACKAGE 3215-A-611 PACKAGE N/A NOT RECEIVED YET RECEIVED 18-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 9-Oct-18
3215-A-221-D-01 70.00 3215-111 STR-1102 STR STR-1102 123.500 - 131.000 2 123.700 A-B 2-4 PACKAGE 3215-A-221 DRYER HORIZONTAL RECEIVED IFC 0 RECEIVED 10-Mar-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 7-Sep-18
3215-V-131 62.00 3215-111 STR-1103 STR STR-1104 116.500 - 123.500 1 117.500 A-B 2-3 STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 25-May-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 25-May-18 HANDOVERED 1-Aug-18
3215-V-352 58.00 3215-113 SHL-1102 CIVIL 3215-V-352 108.300 - ABOVE 0 108.800 B-C 2-3 STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 25-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 11-Jul-18
3215-E-312 equipment on site 56.50 3215-112 STR-1101 STR STR-1101 131.500 - 136.500 4 137.500 C-D 4-5 STATIC S&T HEAT EXCHANGERS VERTICAL RECEIVED IFC 1 RECEIVED 24-Jul-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-611 C 51.77 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-611 C 108.500 - 115.500 0 108.500 A-G 18 - 19 PACKAGE 3215-A-611 PACKAGE N/A NOT RECEIVED YET RECEIVED 18-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 4-Oct-18
3215-A-611 E 50.97 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-611 E 108.500 - 115.500 0 108.500 A-G 18 - 19 PACKAGE 3215-A-611 PACKAGE N/A NOT RECEIVED YET RECEIVED 18-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 4-Oct-18
3215-A-611 D 49.37 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-611 D 108.500 - 115.500 0 108.500 A-G 18 - 19 PACKAGE 3215-A-611 PACKAGE N/A NOT RECEIVED YET RECEIVED 18-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 4-Oct-18
3215-V-241 A 44.82 3215-411 STR-4101 STR STR-4101 108.300 - ABOVE 1 118.235 STATIC SILO VERTICAL NOT RECEIVED YET RECEIVED 6-Sep-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 6-Sep-18 HANDOVERED 28-Sep-18
3215-V-241 B 44.82 3215-411 STR-4101 STR STR-4101 108.300 - ABOVE 1 118.235 STATIC SILO VERTICAL NOT RECEIVED YET RECEIVED 7-Sep-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 7-Sep-18
3215-A-321 42.00 3215-112 SHL-1101 CIVIL 3215-A-321 108.500 - 115.500 0 108.800 C-E 1-2 PACKAGE 3215-A-321 PACKAGE N/A RECEIVED IFC 1 RECEIVED 19-Jul-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-351 40.50 3215-113 SHL-1102 CIVIL 3215-A-351 108.300 - ABOVE 0 108.800 A-C 1-3 PACKAGE 3215-A-351 PACKAGE N/A RECEIVED IFR B RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 12-Sep-18
3215-A-352 35.50 3215-112 SHL-1101 CIVIL 3215-A-352 108.500 - 115.500 0 108.800 A-A 1-2 PACKAGE 3215-A-352 PACKAGE N/A RECEIVED IFR B RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 8-Oct-18
3215-V-332 A 35.00 3215-112 STR-1101 CIVIL 3215-V-332 A 115.500 - 121.500 1 117.500 D-E 5-6 STATIC VESSEL VERTICAL RECEIVED IFC 1 RECEIVED 9-Apr-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 9-Apr-18 HANDOVERED 2-Sep-18
3215-V-332 B 35.00 3215-112 STR-1101 CIVIL 3215-V-332 B 115.500 - 121.500 1 117.500 B-C 5-6 STATIC VESSEL VERTICAL RECEIVED IFC 0 RECEIVED 9-Apr-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 9-Apr-18 HANDOVERED 2-Sep-18
3215-V-531 A 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 26-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 26-Jul-18 HANDOVERED 1-Sep-18
3215-V-531 B 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 27-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 27-Jul-18 HANDOVERED 1-Sep-18
3215-V-531 C 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 28-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 28-Jul-18 HANDOVERED 1-Sep-18
3215-V-531 D 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 29-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 28-Jul-18 HANDOVERED 1-Sep-18
3215-V-531 E 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 30-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 30-Jul-18 HANDOVERED 1-Sep-18
3215-V-531 F 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 8-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 8-Aug-18 HANDOVERED 1-Sep-18
3215-V-571 A 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 9-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 9-Aug-18 HANDOVERED 2-Sep-18
3215-V-571 B 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 10-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 10-Aug-18 HANDOVERED 2-Sep-18
3215-V-571 C 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 10-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 10-Aug-18 HANDOVERED 2-Sep-18
3215-V-571 D 34.40 3215-421 STR-4201 STR STR-4201 108.300 - ABOVE 1 121.800 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 11-Aug-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 11-Aug-18 HANDOVERED 2-Sep-18
3215-E-314 32.00 3215-112 STR-1101 STR STR-1101 115.500 - 121.500 1 121.500 B-C 4-5 STATIC REBOILER VERTICAL RECEIVED IFC 1 RECEIVED 13-Mar-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 6-Jun-18
3215-A-721 30.12 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-721 108.500 - 115.500 0 108.650 A-C 17 - 19 PACKAGE 3215-A-721 PACKAGE COMPLEX N/A RECEIVED IFR B RECEIVED 15-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-C-311 29.85 3215-112 STR-1101 STR STR-1101 115.500 - 121.500 1 122.610 A-B 4-5 STATIC COLUMN VERTICAL RECEIVED IFC 2 RECEIVED 3-Feb-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 23-Mar-18
3215-E-128 29.40 3215-111 STR-1103 STR STR-1103 131.000 - 136.500 3 134.740 A-B 2-3 STATIC S&T HEAT EXCHANGERS HORIZONTAL RECEIVED IFC 1 RECEIVED 13-Mar-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 10-Sep-18 HANDOVERED 3-Oct-18
3215-V-211 28.90 3215-111 STR-1102 STR STR-1102 116.500 - 123.500 1 128.800 B-C 2-3 STATIC VESSEL VERTICAL RECEIVED IFC 1 RECEIVED 26-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 26-Jun-18
3215-A-711 (SKID 1) 26.60 3215-112 STR-1101 STR STR-1101 137.500 - 145.500 5 137.500 B-C 3-4 PACKAGE 3215-A-711 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 15-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-V-122 Pending structure completion 25.70 3215-111 STR-1104 STR STR-1104 131.000 - 136.500 3 133.500 A-B 6-7 STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 2-Aug-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-V-121 Pending structure completion 25.40 3215-111 STR-1104 STR STR-1104 131.000 - 136.500 3 133.500 A-B 6-7 STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 2-Aug-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-V-124 24.30 3215-111 STR-1103 STR STR-1103 116.500 - 123.500 1 117.500 A-B 1-2 STATIC VESSEL VERTICAL RECEIVED IFC 1 RECEIVED 2-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 2-Jul-18
3215-V-311 23.80 3215-112 STR-1101 STR STR-1101 131.500 - 136.500 4 137.500 D-E 4-5 STATIC VESSEL VERTICAL RECEIVED IFC 1 RECEIVED 26-Jun-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-S-211 B 23.40 3215-111 STR-1102 CIVIL 3215-S-211 B 131.000 - 136.500 3 137.000 A-B 2-3 PACKAGE 3215-S-211 PACKAGE COMPLEX N/A RECEIVED IFR A RECEIVED 20-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-S-211 A 23.40 3215-111 STR-1102 CIVIL 3215-S-211 A 136.500 - 148.500 4 141.100 A-B 2-3 PACKAGE 3215-S-211 PACKAGE COMPLEX N/A RECEIVED IFR A RECEIVED 20-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-S-211 C 23.40 3215-111 STR-1102 CIVIL 3215-S-211 C 136.500 - 148.500 4 141.100 A-B 2-3 PACKAGE 3215-S-211 PACKAGE COMPLEX N/A RECEIVED IFR A RECEIVED 20-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-711 (SKID 2) 23.05 3215-112 STR-1101 STR STR-1101 137.500 - 145.500 5 137.500 B-C 3-4 PACKAGE 3215-A-711 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 15-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-V-566 22.40 3215-311 STR-3101 CIVIL 3215-V-566 108.500 - 113.500 0 117.000 A-B 4-5 STATIC SILO VERTICAL RECEIVED IFC 2 RECEIVED 3-Sep-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 3-Sep-18
3215-C-712 A 22.20 3215-112 STR-1101 STR STR-1101 131.500 - 136.500 4 137.500 D-E 3-4 STATIC TOWER VERTICAL RECEIVED IFC 2 RECEIVED 27-Jan-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-C-712 B 22.20 3215-112 STR-1101 STR STR-1101 131.500 - 136.500 4 137.500 D-E 3-4 STATIC TOWER VERTICAL RECEIVED IFC 2 RECEIVED 27-Jan-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-351 (SKID A) 21.30 3215-113 SHL-1102 CIVIL 3215-A-351 108.300 - ABOVE 0 108.800 A-C 1-3 PACKAGE 3215-A-351 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 12-Sep-18
3215-E-613 A equipment on site 19.60 3215-231 JWS CIVIL 3215-E-613 A 108.300 - ABOVE 0 108.650 - - STATIC PLATE HEAT EXCHANGERS HORIZONTAL NOT RECEIVED YET RECEIVED 5-Feb-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-E-613 B equipment on site 19.60 3215-231 JWS CIVIL 3215-E-613 B 108.300 - ABOVE 0 108.650 - - STATIC PLATE HEAT EXCHANGERS HORIZONTAL NOT RECEIVED YET RECEIVED 5-Feb-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-E-613 C equipment on site 19.60 3215-231 JWS CIVIL 3215-E-613 C 108.300 - ABOVE 0 108.650 - - STATIC PLATE HEAT EXCHANGERS HORIZONTAL NOT RECEIVED YET RECEIVED 5-Feb-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-351 (SKID B) 19.20 3215-113 SHL-1102 CIVIL 3215-A-351 108.300 - ABOVE 0 108.800 A-C 1-3 PACKAGE 3215-A-351 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 10-Sep-18
3215-E-313 19.10 3215-112 STR-1101 STR STR-1101 131.500 - 136.500 4 132.950 C-E 4-5 STATIC S&T HEAT EXCHANGERS HORIZONTAL RECEIVED IFC 1 RECEIVED 7-Apr-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 27-Sep-18
3215-M-121 18.60 3215-111 STR-1103 EQP 3215-R-121 136.500 - 148.500 4 136.650 A-B 6-7 ROTATING 3215-R-121 AGITATOR N/A RECEIVED IFR A RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-M-122 18.60 3215-111 STR-1103 EQP 3215-R-122 136.500 - 148.500 4 136.650 A-B 5-6 ROTATING 3215-R-122 AGITATOR N/A RECEIVED IFR A RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-M-123 18.60 3215-111 STR-1103 EQP 3215-R-123 136.500 - 148.500 4 136.650 A-B 4-5 ROTATING 3215-R-123 AGITATOR N/A RECEIVED IFR A RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-A-352 (SKID A) 18.00 3215-112 SHL-1101 CIVIL 3215-A-352 108.500 - 115.500 0 108.800 A-A 1-2 PACKAGE 3215-A-352 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 8-Oct-18
3215-E-311 17.90 3215-112 STR-1101 STR STR-1101 121.500 - 125.000 2 122.600 D-E 3-4 STATIC S&T HEAT EXCHANGERS HORIZONTAL RECEIVED IFC 0 RECEIVED 31-Mar-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 12-Jul-18 HANDOVERED 14-Aug-18
3215-A-352 (SKID B) 17.50 3215-112 SHL-1101 CIVIL 3215-A-352 108.500 - 115.500 0 108.800 A-A 1-2 PACKAGE 3215-A-352 SKID MOUNTED 0 NOT RECEIVED YET RECEIVED 12-Jun-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 5-Oct-18
3215-V-415 17.10 3215-221 TANK CIVIL 3215-V-415 108.300 - ABOVE 0 109.800 - - STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 21-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 22-Jul-18 HANDOVERED 2-Sep-18
3215-V-417 16.90 3215-221 TANK CIVIL 3215-V-417 108.300 - ABOVE 0 111.800 - - STATIC VESSEL VERTICAL RECEIVED IFC 2 RECEIVED 21-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 27-Jul-18 HANDOVERED 2-Sep-18
3215-A-721 (SKID 2) 16.80 3215-112 RCK-1104 BS 116-101 CIVIL 3215-A-721 108.500 - 115.500 0 108.650 A-C 17 - 19 PACKAGE 3215-A-721 0 NOT RECEIVED YET RECEIVED 15-Sep-18 HEAVY REQUIRED > 15TON < 100TON NOT INSTALLED YET
3215-C-312 A 16.70 3215-112 STR-1101 STR STR-1101 125.000 - 131.500 3 131.500 A-B 1-2 STATIC TOWER VERTICAL RECEIVED IFC 2 RECEIVED 30-Jan-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 19-Sep-18
3215-C-312 B 16.70 3215-112 STR-1101 STR STR-1101 125.000 - 131.500 3 131.500 B-C 1-2 STATIC TOWER VERTICAL RECEIVED IFC 2 RECEIVED 30-Jan-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 22-Sep-18
3215-V-341 16.30 3215-112 STR-1101 CIVIL 3215-V-341 108.500 - 115.500 0 109.850 D-D 4-5 STATIC VESSEL HORIZONTAL RECEIVED IFC 1 RECEIVED 21-Jul-18 HEAVY REQUIRED > 15TON < 100TON INSTALLED 21-Jul-18 HANDOVERED 2-Sep-18