Você está na página 1de 3

ANALISA HARGA SATUAN PEKERJA

1 1 m³ Galian tanah biasa


pekerja = 0.7500 OH Rp 50,000.00 Rp 37,500.00
mandor = 0.0250 OH Rp 67,500.00 Rp 1,687.50
Jumlah Rp 39,187.50

2 1 m³ Bongkaran Pasangan
Pekerja = 2.0000 OH Rp 50,000.00 Rp 100,000.00
Mandor = 0.1000 OH Rp 67,500.00 Rp 6,750.00
Jumlah Rp 106,750.00

3 1 m³ Pasangan Batu Belah ad. 1pc : 4psr


Batu belah = 1.1000 m³ Rp 120,000.00 Rp 132,000.00
Pasir Pasang = 0.5200 m³ Rp 125,000.00 Rp 65,000.00
Semen pc/50Kg = 3.2600 ZAK Rp 62,500.00 Rp 203,750.00
Pekerja = 1.5000 OH Rp 50,000.00 Rp 75,000.00
Tukang Batu = 0.6000 OH Rp 65,000.00 Rp 39,000.00
Kepala Tukang Batu = 0.0600 OH Rp 67,500.00 Rp 4,050.00
Mandor = 0.0750 OH Rp 67,500.00 Rp 5,062.50
Jumlah Rp 523,862.50

4 1 m² Plesteran 1pc : 3psr (tebal 15 mm)


pc/50Kg = 0.1304 ZAK Rp 62,500.00 Rp 8,150.00
Pasir Pasang = 0.0194 m³ Rp 125,000.00 Rp 2,425.00
Pekerja = 0.4000 OH Rp 50,000.00 Rp 20,000.00
Tukang Batu = 0.2000 OH Rp 65,000.00 Rp 13,000.00
Kepala Tukang Batu = 0.0200 OH Rp 67,500.00 Rp 1,350.00
Mandor = 0.0200 OH Rp 67,500.00 Rp 1,350.00
Jumlah Rp 46,275.00

5 1 m² Siaran 1pc : 2psr


pc/50Kg = 0.1054 ZAK Rp 62,500.00 Rp 6,587.50
Pasir Pasang = 0.0085 m³ Rp 125,000.00 Rp 1,062.50
Pekerja = 0.3600 OH Rp 50,000.00 Rp 18,000.00
Tukang Batu = 0.1200 OH Rp 65,000.00 Rp 7,800.00
Kepala Tukang Batu = 0.0120 OH Rp 67,500.00 Rp 810.00
Mandor = 0.0180 OH Rp 67,500.00 Rp 1,215.00
Jumlah Rp 35,475.00

6 1 m² Pasangan Batu Bata 1pc : 5psr


Batu Bata =
pc/50Kg =
Pasir Pasang =
Pekerja =
Tukang Batu =
Kepala Tukang Batu =
Mandor =
Jumlah
7 1 m² Pengecetan 2x
Cat Minyak = 0.2000 Kg Rp 45,000.00 Rp 9,000.00
Minyak Cat = 0.1500 Ltr Rp 7,000.00 Rp 1,050.00
Kuas 3" = 0.0500 Bh Rp 7,500.00 Rp 375.00
Pekerja = 0.2000 OH Rp 50,000.00 Rp 10,000.00
Tukang cat = 0.3000 OH Rp 65,000.00 Rp 19,500.00
Kep. Tukang Cat = 0.0300 OH Rp 67,500.00 Rp 2,025.00
Mandor = 0.0100 OH Rp 67,500.00 Rp 675.00
Jumlah Rp 42,625.00

Beton Bertulang ad 1pc : 2psr : 3koral


I 1 m³ Cor Beton
Semen pc/50Kg = 6.72 ZAK Rp 62,500.00 Rp 420,000.00
Split/Koral = 0.81 m³ Rp 250,000.00 Rp 202,500.00
Pasir Beton = 0.54 m³ Rp 150,000.00 Rp 81,000.00
Pekerja = 2 OH Rp 50,000.00 Rp 100,000.00
Tukang Batu = 0.35 OH Rp 65,000.00 Rp 22,750.00
Kep. Tukang Batu = 0.035 OH Rp 67,500.00 Rp 2,362.50
Mandor = 1 OH Rp 67,500.00 Rp 67,500.00
Peralatan ts Rp 15,000.00
Jumalh Rp 911,112.50

II 1 Kg Besi Beton
Besi Beton = 1.0500 Kg Rp 9,500.00 Rp 9,975.00
Kawat Beton = 0.0150 Kg Rp 17,000.00 Rp 255.00
Pekerja = 0.0070 OH Rp 50,000.00 Rp 350.00
Tukang Besi = 0.0070 OH Rp 65,000.00 Rp 455.00
Kep. Tukang Besi = 0.0007 OH Rp 67,500.00 Rp 47.25
Mandor = 0.0003 OH Rp 67,500.00 Rp 20.25
Jumlah Rp 11,102.50
Jadi 1 m³ Beton memerlukan 110,0000 kg besi beton
= 110.0000 Kg Rp 11,102.50 Rp 1,221,275.00

III 1 m² Cetakan Begisting


Kayu Begisting = 0.0400 m³ Rp 2,500,000.00 Rp 100,000.00
Paku = 0.4000 Kg Rp 15,000.00 Rp 6,000.00
Minyak Begisting = 0.2500 Ltr Rp 30,000.00 Rp 7,500.00
Pekerja = 0.3200 OH Rp 50,000.00 Rp 16,000.00
Tukang Kayu = 0.3300 OH Rp 65,000.00 Rp 21,450.00
Kep. Tukang Kayu = 0.0330 OH Rp 67,500.00 Rp 2,227.50
Mandor = 0.0060 OH Rp 67,500.00 Rp 405.00
Jumlah Rp 153,582.50
1 m³ beton bertulang memerlukan 10 m² cetakan
= 10 m² Rp 153,582.50 Rp 1,535,825.00
pekerja (membongkar = menyiram) 4,0000 OH
= 4.0000 OH Rp 50,000.00 Rp 200,000.00
jumlah Rp 1,735,825.00

Jadi 1 m³ Beton tulangan 1;2;3 = I + II + III =


I = Rp 911,112.50
II = Rp 1,221,275.00
III = Rp 1,735,825.00
Rp 3,868,212.50