13 Air requirements
a Balancing Tank, at 1 m3/m3/hr 375 SBR
Sludge Yield 0.3814 kg/BOD
b Sludge Digestor Sludge Produced 471.19 kg/d
Expected VS Destruction 30% Kg of BOD removed 1278.9 kg/d
VS destroyed 146.16 Nitrogen to be nitrified 534.69 kg/d
O2 required 2 Kg/kgVSr AOR 1342.4 kg/d
O2 required 292.32 SOR 3734.7 kg/d
AOR/SOR for fine bubble 0.4 Air Required 2382.7 m3/hr
SOR 730.8 kg/d Air required at Inlet 2586 nm3/hr
diffuser effeciency 29% Duty blowers 1
Air required 391.9749 m3/hr Each Blower 2586 m3/hr
Air supplied per m3 of digestor vol 0.433263 m3/m3/hr Fill time (Anoxic+Aerated) 3
Anoxic fill 0.5
Aerated fill time 2.5
Settel time 1
Decant time 1
Idle 0.5
available aeration time 0.5
Total aeration Time 3