ID Task Name Duration Start Finish Mar 24, '13 Mar 31, '13

S M T W T F S S M T W T F S
1 Construction of Three-Storey Office Building 383 days Mon 4/1/13 Fri 6/20/14
2 Mobilize on Site 10 days Mon 4/1/13 Thu 4/11/13
3 Install temporary power 2 days Mon 4/1/13 Tue 4/2/13 Install temporary power
4 Install temporary water service 2 days Mon 4/1/13 Tue 4/2/13 Install temporary water service
5 Set up site office 3 days Wed 4/3/13 Fri 4/5/13 Set up site office
6 Set line and grade benchmarks 3 days Sat 4/6/13 Tue 4/9/13 Set line and grade benchmarks
7 Prepare site - lay down yard and temporary fencing 2 days Wed 4/10/13 Thu 4/11/13 Prepare site - lay down yard and tempo
8 Site Grading and Utilities 41 days Fri 4/12/13 Wed 5/29/13
9 Clear and grub site 3 days Fri 4/12/13 Mon 4/15/13
10 Stone site access and temporary parking area 2 days Tue 4/16/13 Wed 4/17/13 Stone site
11 Rough grade site (cut and fill) 1 wk Thu 4/18/13 Wed 4/24/13
12 Install storm drainage 2 wks Thu 4/25/13 Wed 5/8/13
13 Install exterior fire line and building fire riser 2 wks Thu 4/25/13 Wed 5/8/13
14 Perform final site grading 2 wks Thu 5/9/13 Wed 5/22/13
15 Erect building batter boards and layout building 1 wk Thu 5/23/13 Wed 5/29/13
16 Foundations 35 days Thu 5/23/13 Tue 7/2/13
17 Excavate foundations 2 wks Thu 5/23/13 Wed 6/5/13
18 Excavate elevator pit 2 days Thu 5/23/13 Fri 5/24/13
19 Form column piers and spread foundations 4 days Thu 6/6/13 Mon 6/10/13
20 Rough-in electric and plumbing in elevator 4 days Sat 5/25/13 Wed 5/29/13
21 Form elevator pit walls 4 days Thu 5/30/13 Mon 6/3/13
22 Set reinforcing and anchor bolts 4 days Tue 6/11/13 Fri 6/14/13
23 Pour column piers and foundations 5 days Sat 6/15/13 Thu 6/20/13
24 Pour concrete elevator walls 1 day Tue 6/4/13 Tue 6/4/13
25 Cure elevator wall concrete 7 days Wed 6/5/13 Wed 6/12/13
26 Cure piers and foundations 7 days Fri 6/21/13 Fri 6/28/13
27 Strip wall forms 1 day Thu 6/13/13 Thu 6/13/13
28 Strip column piers and foundation forms 3 days Sat 6/29/13 Tue 7/2/13
29 Install pneumatic tube in elevator pit 3 days Fri 6/14/13 Mon 6/17/13
30 Prepare and pour concrete floor in elevator pit 1 day Tue 6/18/13 Tue 6/18/13
31 Steel Erection 54 days Wed 7/3/13 Tue 9/3/13
32 Erect steel columns, beams and joist - 1st and 2nd floors 2 wks Wed 7/3/13 Tue 7/16/13
33 Erect steel columns, beams and joist - 3rd floor and roof 2 wks Wed 7/17/13 Tue 7/30/13
34 Install miscellaneous iron and bracing - 1st and 2nd floors 2 wks Wed 7/17/13 Tue 7/30/13
35 Install miscellaneous iron and bracing - 3rd floor and roof 2 wks Wed 7/31/13 Tue 8/13/13
36 Install stairs and miscellaneous iron railing 2 wks Wed 8/14/13 Tue 8/27/13

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 1
ID Task Name Duration Start Finish Mar 24, '13 Mar 31, '13
S M T W T F S S M T W T F S
37 Touch-up paint on steel 1 wk Wed 8/28/13 Tue 9/3/13
38 Form and Pour Concrete - Floors and Roof 80 days Wed 7/31/13 Thu 10/31/13
39 Form 2nd floor including all floor openings 5 days Wed 9/4/13 Mon 9/9/13
40 Install rebar and in-floor utilities (inc mechl, elect, plumbing) 5 days Wed 7/31/13 Mon 8/5/13
41 Pour 2nd floor slab 4 days Tue 9/10/13 Fri 9/13/13
42 Cure 2nd floor slab 7 days Sat 9/14/13 Sat 9/21/13
43 Strip forms from 2nd floor slab 2 days Mon 9/23/13 Tue 9/24/13
44 Form 3rd floor including all floor openings 5 days Mon 9/23/13 Fri 9/27/13
45 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
5 days Mon 9/23/13 Fri 9/27/13
46 Pour 3rd floor slab 4 days Sat 9/28/13 Wed 10/2/13
47 Cure 3rd floor slab 7 days Thu 10/3/13 Thu 10/10/13
48 Strip forms from 3rd floor slab 2 days Fri 10/11/13 Sat 10/12/13
49 Form roof slab including all floor openings 5 days Fri 10/11/13 Wed 10/16/13
50 Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
5 days Fri 10/11/13 Wed 10/16/13
51 Pour roof slab 4 days Thu 10/17/13 Mon 10/21/13
52 Cure roof slab 7 days Tue 10/22/13 Tue 10/29/13
53 Strip forms from roof slab 2 days Wed 10/30/13 Thu 10/31/13
54 Form 1st floor 4 days Wed 9/25/13 Sat 9/28/13
55 Install electrical underground 1 wk Wed 9/25/13 Tue 10/1/13
56 Install plumbing underground 1 wk Wed 9/25/13 Tue 10/1/13
57 Install rebar and in-floor utilities 4 days Wed 9/25/13 Sat 9/28/13
58 Pour 1st floor slab 4 days Thu 10/17/13 Mon 10/21/13
59 Cure 1st floor slab 7 days Tue 10/22/13 Tue 10/29/13
60 Strip forms from 1st floor slab 2 days Wed 10/30/13 Thu 10/31/13
61 Carpentry Work 18 days Fri 11/1/13 Thu 11/21/13
62 Install exterior sheathing and metal studs 3 wks Fri 11/1/13 Thu 11/21/13
63 Masonry Work 122 days Wed 8/14/13 Thu 1/2/14
64 Rough-in plumbing at toilets and masonry walls 4 wks Fri 11/1/13 Thu 11/28/13
65 Lay masonry at core, mechanical, and toilets 4 wks Wed 8/14/13 Tue 9/10/13
66 Install exterior masonry work 5 wks Fri 11/22/13 Thu 12/26/13
67 Install roof drains 2 days Fri 12/27/13 Sat 12/28/13
68 Install tile in toilet rooms 2 wks Fri 11/29/13 Thu 12/12/13
69 Clean masonry 1 wk Fri 12/27/13 Thu 1/2/14
70 Clean toilet room tile 1 wk Fri 12/13/13 Thu 12/19/13
71 Roofing 33 days Fri 12/27/13 Mon 2/3/14
72 Install flashing at parapet walls 4 days Fri 12/27/13 Tue 12/31/13

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 2
ID Task Name Duration Start Finish Mar 24, '13 Mar 31, '13
S M T W T F S S M T W T F S
73 Pour lightweight concrete roof fill 2 days Wed 1/1/14 Thu 1/2/14
74 Install seamless roofing material 5 days Thu 1/9/14 Tue 1/14/14
75 Spread stone ballast on seamless roof 5 days Wed 1/15/14 Mon 1/20/14
76 Set rooftop equipment 2 wks Tue 1/21/14 Mon 2/3/14
77 Window wall and store front closures 72 days Fri 12/27/13 Thu 3/20/14
78 Install window wall aluminum and glass 5 wks Fri 12/27/13 Thu 1/30/14
79 Install interior stud walls and drywall 5 wks Fri 1/31/14 Thu 3/6/14
80 Install interior doors and hardware 2 wks Fri 3/7/14 Thu 3/20/14
81 Install store front doors and hardware 3 wks Fri 12/27/13 Thu 1/16/14
82 Building Finishes 96 days Fri 1/31/14 Thu 5/22/14
83 Install millwork and wood trim 3 wks Fri 3/7/14 Thu 3/27/14
84 Paint walls and woodwork 4 wks Fri 3/28/14 Thu 4/24/14
85 Install conduit at ceiling plenum space 3 wks Fri 1/31/14 Thu 2/20/14
86 Install duct in ceiling plenum space 3 wks Fri 3/7/14 Thu 3/27/14
87 Install ceiling grid 2 wks Fri 3/28/14 Thu 4/10/14
88 Install ceiling tile 2 wks Fri 4/11/14 Thu 4/24/14
89 Hang wallpaper 2 wks Fri 4/11/14 Thu 4/24/14
90 Install building carpet 4 wks Fri 4/25/14 Thu 5/22/14
91 Install hardware and accessories 3 wks Fri 4/25/14 Thu 5/15/14
92 Complete interior and exterior sod and plantings 2 wks Fri 4/25/14 Thu 5/8/14
93 Pave, curb, and stripe parking lot 2 wks Fri 5/9/14 Thu 5/22/14
94 Elevators 48 days Wed 9/11/13 Tue 11/5/13
95 Set elevator equipment in shafts 4 wks Wed 9/11/13 Tue 10/8/13
96 Set equipment in mechanical room 2 wks Wed 10/9/13 Tue 10/22/13
97 Test and align doors and equipment 2 wks Wed 10/23/13 Tue 11/5/13
98 Plumbing 108 days Fri 1/3/14 Thu 5/8/14
99 Rough-in plumbing in drywall walls 4 wks Fri 1/31/14 Thu 2/27/14
100 Tie-in fire line riser and set valves 2 wks Fri 1/3/14 Thu 1/16/14
101 Set plumbing fixtures and trim 3 wks Fri 2/28/14 Thu 3/20/14
102 Flush, test, and clean piping and fixtures 2 wks Fri 4/25/14 Thu 5/8/14
103 Electrical 150 days Fri 11/1/13 Thu 4/24/14
104 Rough-in electrical in masonry walls 4 wks Fri 11/1/13 Thu 11/28/13
105 Rough-in electrical in drywall walls 4 wks Fri 1/31/14 Thu 2/27/14
106 Pull wire in conduit and set area transformers 3 wks Fri 2/21/14 Thu 3/13/14
107 Install and terminate electrical devices 3 wks Fri 3/14/14 Thu 4/3/14
108 Make electrical terminations for HVAC equipment 2 days Fri 3/14/14 Sat 3/15/14

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 3
ID Task Name Duration Start Finish Mar 24, '13 Mar 31, '13
S M T W T F S S M T W T F S
109 Install light fixtures - test and clean 2 wks Fri 4/11/14 Thu 4/24/14
110 Heating and Ventilating - AC 206 days Wed 9/11/13 Thu 5/8/14
111 Set equipment in mechanical room 2 wks Wed 9/11/13 Tue 9/24/13
112 Rough-in mechanical in masonry walls 4 wks Fri 11/1/13 Thu 11/28/13
113 Rough-in mechanical in drywall walls 2 wks Fri 1/31/14 Thu 2/13/14
114 Install duct in building chase 3 wks Fri 1/31/14 Thu 2/20/14
115 Set HVAC trim and test and balance system 4 wks Fri 4/11/14 Thu 5/8/14
116 Final Clean-up and Occupancy 71 days Fri 3/7/14 Wed 5/28/14
117 Install hard tile flooring in common areas 1 wk Fri 3/7/14 Thu 3/13/14
118 Clean hard tile floors 4 days Fri 3/14/14 Tue 3/18/14
119 Remove debris from building and do final clean-up 4 days Fri 5/23/14 Tue 5/27/14
120 Substantial completion date 1 day Wed 5/28/14 Wed 5/28/14
121 Complete Final Inspections 21 days Wed 5/28/14 Fri 6/20/14
122 Complete elevator inspection and certification 3 days Wed 5/28/14 Fri 5/30/14
123 Perform architect's inspection 1 day Sat 5/31/14 Sat 5/31/14
124 Perform local building agency inspection 1 day Mon 6/2/14 Mon 6/2/14
125 Perform Fire Marshal's inspection 1 day Tue 6/3/14 Tue 6/3/14
126 Complete punch list items from all inspections 2 wks Wed 6/4/14 Tue 6/17/14
127 Obtain certificate of occupancy 2 days Wed 6/18/14 Thu 6/19/14
128 Issue final completion documents including warranties 1 day Wed 6/18/14 Wed 6/18/14
129 Issue final request for payment 1 day Fri 6/20/14 Fri 6/20/14

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 4
Apr 7, '13 Apr 14, '13 Apr 21, '13 Apr 28, '13 May 5, '13 May 12, '13 May 19, '13
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

orary fencing

Clear and grub site


e access and temporary parking area
Rough grade site (cut and fill)
Install storm drainage
Install exterior fire line and building fire riser
Perform final site grading
Erect building batter boards and layout build

Excavate foundatio
Excavate elevator

Rough-in electric and plumbing

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 5
Apr 7, '13 Apr 14, '13 Apr 21, '13 Apr 28, '13 May 5, '13 May 12, '13 May 19, '13
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 6
Apr 7, '13 Apr 14, '13 Apr 21, '13 Apr 28, '13 May 5, '13 May 12, '13 May 19, '13
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 7
Apr 7, '13 Apr 14, '13 Apr 21, '13 Apr 28, '13 May 5, '13 May 12, '13 May 19, '13
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 8
May 26, '13 Jun 2, '13 Jun 9, '13 Jun 16, '13 Jun 23, '13 Jun 30, '13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

lding

ions
r pit
Form column piers and spread foundations
g in elevator
Form elevator pit walls
Set reinforcing and anchor bolts
Pour column piers and foundations
Pour concrete elevator walls
Cure elevator wall concrete
Cure piers and foundations
Strip wall forms
Strip column piers and foundation forms
Install pneumatic tube in elevator pit
Prepare and pour concrete floor in elevator pit

Erect steel columns, beams and joist - 1st and 2nd floors
Erect steel c
Install miscell

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 9
May 26, '13 Jun 2, '13 Jun 9, '13 Jun 16, '13 Jun 23, '13 Jun 30, '13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 10
May 26, '13 Jun 2, '13 Jun 9, '13 Jun 16, '13 Jun 23, '13 Jun 30, '13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 11
May 26, '13 Jun 2, '13 Jun 9, '13 Jun 16, '13 Jun 23, '13 Jun 30, '13
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 12
Jul 7, '13 Jul 14, '13 Jul 21, '13 Jul 28, '13 Aug 4, '13 Aug 11, '13 Aug 18, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

columns, beams and joist - 3rd floor and roof


llaneous iron and bracing - 1st and 2nd floors
Install miscellaneous iron and bracing - 3rd floor and roof
Install stairs and miscellaneous iron railing

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 13
Jul 7, '13 Jul 14, '13 Jul 21, '13 Jul 28, '13 Aug 4, '13 Aug 11, '13 Aug 18, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Install rebar and in-floor utilities (inc mechl, elect, plumbing)

Lay masonry at core, mechanical, and toilets

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 14
Jul 7, '13 Jul 14, '13 Jul 21, '13 Jul 28, '13 Aug 4, '13 Aug 11, '13 Aug 18, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 15
Jul 7, '13 Jul 14, '13 Jul 21, '13 Jul 28, '13 Aug 4, '13 Aug 11, '13 Aug 18, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 16
'13 Aug 25, '13 Sep 1, '13 Sep 8, '13 Sep 15, '13 Sep 22, '13 Sep 29, '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 17
'13 Aug 25, '13 Sep 1, '13 Sep 8, '13 Sep 15, '13 Sep 22, '13 Sep 29, '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Touch-up paint on steel

Form 2nd floor including all floor openings

Pour 2nd floor slab


Cure 2nd floor slab
Strip forms from 2nd floor slab
Form 3rd floor including all floor openings
Install rebar and in-floor utilities (including mechanical, electrical, plumbing)
Pour 3rd floor slab
Cure 3rd floor slab
Stri
Form roof slab i
Install rebar and in-floor utilities (including mec

Form 1st floor


Install electrical underground
Install plumbing underground
Install rebar and in-floor utilities

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 18
'13 Aug 25, '13 Sep 1, '13 Sep 8, '13 Sep 15, '13 Sep 22, '13 Sep 29, '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Set elevator equipment in shafts


Set equipment i

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 19
'13 Aug 25, '13 Sep 1, '13 Sep 8, '13 Sep 15, '13 Sep 22, '13 Sep 29, '13
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Set equipment in mechanical room

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 20
Oct 6, '13 Oct 13, '13 Oct 20, '13 Oct 27, '13 Nov 3, '13 Nov 10, '13 Nov
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 21
Oct 6, '13 Oct 13, '13 Oct 20, '13 Oct 27, '13 Nov 3, '13 Nov 10, '13 Nov
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

trip forms from 3rd floor slab


b including all floor openings
chanical, electrical, plumbing)
Pour roof slab
Cure roof slab
Strip forms from roof slab

Pour 1st floor slab


Cure 1st floor slab
Strip forms from 1st floor slab

Install exterior sheathing and metal studs

Rough-in plumbing at toilets and masonry walls

Install exterior

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 22
Oct 6, '13 Oct 13, '13 Oct 20, '13 Oct 27, '13 Nov 3, '13 Nov 10, '13 Nov
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

t in mechanical room
Test and align doors and equipment

Rough-in electrical in masonry walls

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 23
Oct 6, '13 Oct 13, '13 Oct 20, '13 Oct 27, '13 Nov 3, '13 Nov 10, '13 Nov
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S

Rough-in mechanical in masonry walls

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 24
17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec 29, '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 25
17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec 29, '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

or masonry work
Install roof drains
Install tile in toilet rooms
Clean masonry
Clean toilet room tile

Install flashing at parapet walls

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 26
17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec 29, '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Pour lightweight concrete roof fill
Instal

Install window wall aluminum and glass

Install store front doors and hardware

Tie-in fire line riser and set val

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 27
17, '13 Nov 24, '13 Dec 1, '13 Dec 8, '13 Dec 15, '13 Dec 22, '13 Dec 29, '13
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 28
Jan 5, '14 Jan 12, '14 Jan 19, '14 Jan 26, '14 Feb 2, '14 Feb 9, '14
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 29
Jan 5, '14 Jan 12, '14 Jan 19, '14 Jan 26, '14 Feb 2, '14 Feb 9, '14
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 30
Jan 5, '14 Jan 12, '14 Jan 19, '14 Jan 26, '14 Feb 2, '14 Feb 9, '14
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

all seamless roofing material


Spread stone ballast on seamless roof
Set rooftop equipment

Install interior stud walls and drywall

Install conduit at ceiling plenum space

Rough-in plumbing in drywall walls


lves

Rough-in electrical in drywall walls


Pull wire in conduit and se

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 31
Jan 5, '14 Jan 12, '14 Jan 19, '14 Jan 26, '14 Feb 2, '14 Feb 9, '14
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

Rough-in mechanical in drywall walls


Install duct in building chase

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 32
Feb 16, '14 Feb 23, '14 Mar 2, '14 Mar 9, '14 Mar 16, '14 Mar 23, '14 Mar 30, '14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 33
Feb 16, '14 Feb 23, '14 Mar 2, '14 Mar 9, '14 Mar 16, '14 Mar 23, '14 Mar 30, '14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 34
Feb 16, '14 Feb 23, '14 Mar 2, '14 Mar 9, '14 Mar 16, '14 Mar 23, '14 Mar 30, '14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Install interior doors and hardware

Install millwork and wood trim


Paint walls and woodwork

Install duct in ceiling plenum space


Install ceiling grid

Set plumbing fixtures and trim

set area transformers


Install and terminate electrical devices
Make electrical terminations for HVAC equipment

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 35
Feb 16, '14 Feb 23, '14 Mar 2, '14 Mar 9, '14 Mar 16, '14 Mar 23, '14 Mar 30, '14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T

Set HVA

Install hard tile flooring in common areas


Clean hard tile floors

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 36
Apr 6, '14 Apr 13, '14 Apr 20, '14 Apr 27, '14 May 4, '14 May 11, '14
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 37
Apr 6, '14 Apr 13, '14 Apr 20, '14 Apr 27, '14 May 4, '14 May 11, '14
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 38
Apr 6, '14 Apr 13, '14 Apr 20, '14 Apr 27, '14 May 4, '14 May 11, '14
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Install ceiling tile


Hang wallpaper
Install building carpet
Install hardware and accessories
Complete interior and exterior sod and plantings
Pave, curb, and stripe parking lot

Flush, test, and clean piping and fixtures

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 39
Apr 6, '14 Apr 13, '14 Apr 20, '14 Apr 27, '14 May 4, '14 May 11, '14
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Install light fixtures - test and clean

AC trim and test and balance system

Remove debris from buildi

Co

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 40
May 18, '14 May 25, '14 Jun 1, '14 Jun 8, '14 Jun 15, '14 Jun 22, '14 Jun 29, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 41
May 18, '14 May 25, '14 Jun 1, '14 Jun 8, '14 Jun 15, '14 Jun 22, '14 Jun 29, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 42
May 18, '14 May 25, '14 Jun 1, '14 Jun 8, '14 Jun 15, '14 Jun 22, '14 Jun 29, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 43
May 18, '14 May 25, '14 Jun 1, '14 Jun 8, '14 Jun 15, '14 Jun 22, '14 Jun 29, '
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M

ing and do final clean-up


Substantial completion date

omplete elevator inspection and certification


Perform architect's inspection
Perform local building agency inspection
Perform Fire Marshal's inspection
Complete punch list items from all inspections
Obtain certificate of occupancy
Issue final completion documents including warranties
Issue final request for payment

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Project 5 CONSTRUCTION O
Progress Rolled Up Milestone Group By Summary
Date: Mon 8/5/13
Milestone Rolled Up Progress Deadline
Summary Split

Page 44