Escolar Documentos
Profissional Documentos
Cultura Documentos
net/publication/309167373
CITATION READS
1 303
4 authors, including:
Murat Gunduz
Qatar University
67 PUBLICATIONS 447 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Ahmed Senouci on 10 November 2016.
To cite this article: Ahmed Senouci , Ahmed Alsarraj , Murat Gunduz & Neil Eldin (2016):
Analysis of change orders in Qatari construction projects, International Journal of Construction
Management, DOI: 10.1080/15623599.2016.1211973
Article views: 6
Download by: [University of Houston], [Dr Ahmed Senouci] Date: 17 October 2016, At: 07:10
International Journal of Construction Management, 2016
http://dx.doi.org/10.1080/15623599.2016.1211973
a
Associate Professor, Construction Management Department, University of Houston, Houston, United States; bMaintenance Engineer,
Electricity Network Affairs, Qatar General Electricity and Water Corporation, Doha, Qatar; cProfessor, Civil and Architectural
Engineering Department, Qatar University, Doha, Qatar; dProfessor and Interim Dean, College of Technology, University of Houston,
Houston, Texas, United States
Change orders affect the performance of construction projects and may induce significant cost overruns. The paper
identifies the main causes/factors that lead to change orders in Qatari construction projects. It also quantifies the cost
overrun impact of these change orders in Qatari construction projects. A total of 1122 change orders were collected from
22 Qatari residential and commercial construction projects. The collected data was analyzed using statistical methods such
as Pearson correlation and analysis of variance (ANOVA). The analysis results were used to quantify the change order
impacts on cost overruns in Qatari construction projects. Regression analysis models were also developed to predict
change order cost overruns with respect to project size/contract value. Finally, recommendations were developed to
address change order impacts on cost overruns in the Qatari construction industry.
Keywords: change orders; Qatari construction industry; ANOVA, cost overruns; change order causal factors
Introduction
The construction industry is one of the largest industries in the world. Developing countries allocate a significant portion of
their annual budgets to the construction sector. Qatar has experienced a high rate of economic growth and urban development
in the last two decades. The growth rate of its gross domestic product (GDP) is currently among the fastest in the world. The
Qatari construction industry budget is expected to double to reach US $15 billion per year by 2021 (ECHarris 2013). To
host the 2022 World Cup, Qatar plans to invest billions of US dollars in infrastructure projects such as a new airport, a rail-
way network, nine stadiums, hotels, and highways. Moreover, residential, commercial, and office buildings are being built to
accommodate the large number of foreign companies and workers brought to complete these infrastructure projects.
A change order, which is usually an alteration in the construction project scope, may have a significant impact on cost,
time, safety, labor productivity, and work quality. Moreover, the impacts of these change orders on Qatari construction
projects are still not well quantified. Delays and cost overruns have occurred in several major Qatari construction projects
such as the new Doha airport and Musheireb. Thus, the study of the impact of change orders on Qatari construction proj-
ects is timely and worthwhile.
This paper identifies the main causes/factors of change orders in the Qatari construction industry. It also quantifies the
impact of these change orders on cost overruns. Regression analysis models were also developed to predict change order
cost overruns with respect to project size/contract value. Finally, recommendations were developed for the construction
industry to reduce the cost impacts of change orders.
Literature review
An extensive literature review was performed to identify the major factors causing change orders in building construction
projects. Change order impacts on cost overruns were also analyzed and quantified.
Table 1. Major change order causal factors for Qatari construction projects.
flow and financial problems, and (3) inefficient site management. Yehiel (2014) performed a root-cause analysis on cost over-
run factors in general, considering about 146 factors mentioned in the literature. The author used ‘event analysis’ to identify
root causes that triggers cost overruns. He reported 15 universal root causes out of the 146 factors initially considered. Du
et al. (2015) present an object-oriented discrete event simulation (DES) model to investigate the change order management
process. A case study has been performed to investigate the change order management process at a Midwestern land-grant uni-
versity with the proposed simulation model, where the bottlenecks of as-is process have been identified and improved.
Data analysis
The data for 1122 change orders was collected from 22 construction projects in Qatar (i.e., 11 residential and 11 commer-
cial). The change orders were issued in the design and construction phases. The change order data included the following
information: description, specialty or trade, project stage (e.g., design or construction phases), and the party responsible
for it. Moreover, it included the percent cost overruns as shown in Table 2. The percent cost overrun was computed using
the following equation:
The change orders were arranged into the following specialty/ trade categories:
Civil: construction work (i.e., walls, beams, excavation, road works, concreting, ducting, etc.).
Design: design work (i.e., drawings, specifications, etc.)
ID Project type Project value (QR) Cost overrun (QR) Final project value (QR) Cost overrun (%)
Finishes: internal construction work (i.e., doors, windows framing, painting, kitchen and toilet, etc.)
Mechanical, electrical and plumbing (MEP): HVAC, water supply, and electrical wiring.
The parties that cause change orders were defined as owners, contractors, and design consultants.
increase (%)
Change of plans or scope by owner 16.64
Differing site conditions 10.96
Contractor’s lack of judgment and experience 10.82
Local governments 8.80
Specified material became unavailable 8.42
User needs 8.08
Suggestions to initiate more quality 7.45
Change in design request 6.28
Owner dissatisfaction 5.19
Inadequate design 5.08
Utility companies 3.54
Inconsistencies 2.66
Significant changes in the quantities of work 1.34
Mechanical and electrical provision 1.15
Consultant’s lack of judgment and experience 1.15
Noncompliance of design with owner’s requirements 0.87
Design errors 0.78
Plan errors 0.38
Technology changes 0.27
Delays in the project 0.14
Safety considerations 0.02
International Journal of Construction Management 5
phase cost more than those made during the design phase. The changes in the regulations and rules made by the Qatari
Civil Defense authority also contributed to the results.
Design errors
Changes in design request
Inadequate design
Significant changes in quantity of work
Change of plan or scope by owner
Differing site conditions
Utility companies
Mechanical and electrical provisions
6 A. Senouci et al.
Analysis Variables Mean Variance F-Value P-Value F-critical ANOVA result Conclusion
Project phase Construction 0.55 0.13 0.81 0.37 4.07 F < F-critical null Similar sample means
Design 0.45 0.13 hypothesis is accepted
Causal party Consultant 0.1853 0.0346 5.1745 0.0281 6.0727 F > F-critical null Sample means not similar
Contractor 0.3668 0.1057 hypothesis is rejected
Owner 0.4479 0.1270 9.3873 0.0038 4.0727 F > F-critical null Sample means not similar
Consultant 0.1853 0.0346 hypothesis is rejected
Contractor 0.3668 0.1056 0.6214 0.4350 4.0727 F < F-critical null Similar sample means
Owner 0.4479 0.1270 hypothesis is accepted
Construction Civil 0.4294 0.1910 16.0649 0.0002 4.0727 F > F-critical null Sample means not similar
trade Design 0.0429 0.0134 hypothesis is rejected
Civil 0.4294 0.1911 1.9136 0.1739 4.0727 F < F-critical null Similar sample means
Finishes 0.2583 0.1455 hypothesis is accepted
Civil 0.4294 0.1911 1.7479 0.1933 4.0727 F < F-critical null Similar sample means
MEP 0.2694 0.1309 hypothesis is accepted
Design 0.0429 0.0135 6.4219 0.0151 4.0727 F > F-critical null Sample means not similar
Finishes 0.2583 0.1455 hypothesis is rejected
Design 0.0429 0.0135 7.8189 0.0078 4.0727 F > F-critical null Sample means not similar
MEP 0.2694 0.1309 hypothesis is rejected
Finishes 0.2583 0.1456 0.0099 0.9213 4.0727 F < F-critical null Similar sample means
MEP 0.2694 0.1309 hypothesis is accepted
If the F-value is greater than the F-critical-value and the P-value is less than 0.05, then null hypothesis is rejected. This
means that the group variances are not equal and a significant difference exists between them. If the F-value is less than
the F-critical-value and the P-value is greater than 0.05, then the null hypothesis is accepted. This means that the group
variances are equal and no significant difference exists between them. The following groups were used in the ANOVA:
(1) project stage (i.e., design or construction), (2) change order causal party (i.e., owner, contractor, or consultant), and
(3) construction category (i.e., civil, design, MEP, or finishes).
Table 6 summarizes the ANOVA results. The analysis results show the following findings:
(1) The cost impact of change orders in the construction phase was higher than that in the design phase and the means
were statistically similar.
(2) The cost impact of change orders caused by the contractor was higher than that caused by the consultant and the
means were statistically different.
(3) The cost impact of change orders caused by the owner was higher than that caused by the consultant and the
means were statistically different.
(4) The cost impact of change orders caused by the owner is higher than that caused by the contractor and the means
were statistically equal.
(5) The change orders in the civil work category had a higher cost impact than those in the design category and the
means were statistically different.
(6) The change orders in the civil work category had a higher cost impact than those in the finishes category and the
means were statistically similar.
(7) The change orders in the civil work category have a higher cost impact than those in the MEP category and the
means were statistically similar.
(8) The change orders in the finishes category had a higher cost impact than those in the design category and the
means were also statistically different.
(9) The change orders in the MEP category had a higher cost impact than those in the design category and the means
were also statistically different.
(10) The change orders in the finishes category had a higher cost impact than those in the MEP category and the means
were statistically similar.
8 A. Senouci et al.
6,541,250 4.55
6,765,000 2.42
9,082,534 1.98
19,212,093 0.94
22,639,414 9.04
23,089,179 0.58
28,500,000 7.75
44,215,115 8.17
49,400,000 3.77
50,439,823 24.1
62,175,940 23.17
64,873,781 1.16
81,631,412 4.24
88,435,781 77.77
91,810,138 32.43
139,169,727 11.62
151,000,000 3.48
158,000,000 10.05
185,000,000 9.67
245,000,000 13.74
278,950,000 22.98
478,032,233 3.02
Regression analysis
Regression analysis was used to find a relationship between cost overruns and project contract values/sizes. Moreover,
relationships between different change order groups and project costs were also found. The project size and cost overrun
were selected as the independent and dependent variables in this research, respectively. If a high value of R2 could not be
obtained, the project cost can be divided into several ranges. All scattered data was plotted in one chart. Then, the outliers,
if any, were removed. The contract cost varies between 6 and 280 million QAR (Qatari Riyals) (1 US$ D 3.65 QAR).
Table 7 summarizes the cost overrun percentage in each project. Figure 1 shows the variation of the percent cost overrun
versus the project contract value. The regression analysis yielded a very low R2 value. Figure 2 shows the cost overrun
regression model after removing the outliers marked as triangular shape in Figure 1. The regression model also yielded a
very low R2 value of 0.159. To improve the regression analysis results, two ranges for the project value were considered
as follows.
1 – Project values between 0 and 100 million Qatari Riyals:
The regression analysis yielded an R2 value of 0.34. The rate of cost overrun increase is 0.2% per one million Qatari
Riyal increase in the project value (Figure 3).
2 – Project values between 100 and 300 million Qatari Riyals:
The regression analysis yielded an R2 value of 0.68. The rate of cost overrun increase is 0.09% per million QAR
increase in project value. This is lower than the rate in the first interval which is 0.2%. It shows that the rate of increment
of cost overrun is higher if the project size is between (100–300 million) (Figure 4).
Discussion of results
The purpose of the ANOVA was to determine whether the means of the different groups of construction projects were sim-
ilar. First, the project phases (i.e., construction or design) were compared. The analysis results showed that the cost overrun
means in both phases behaved in a similar way. This is because the design errors and revisions may have caused more cost
International Journal of Construction Management 9
overruns than change orders during the construction phase and vice versa. Although the construction phase cost overruns
are slightly higher, errors in the design can generate change orders with cost overruns as high as those in the construction
phase. For example, plan revisions caused more than 85% of the cost overruns in project 15.
The cost impacts of the change orders that were caused by the construction stakeholders (i.e., owner, consultant, and
contractor) were also analyzed. It was found that the means of cost overruns caused by the contractor and the consultant
were statistically similar. This is due to the fact that change orders are mainly due to an owner change of scope or a con-
tractor attempt to increase project profits. The results show that on average more than 80% of cost overruns are caused by
either the owner or contractor. Thus, the means of cost overruns of the consultant is different than those of the owner and
contractor. We can conclude that owners and contractors should make efforts to avoid change orders.
Figure 3. Cost overrun regression model (contract values between 0 and 100 million QR).
The results showed that change orders in the civil, MEP and finish work categories are statistically similar. This is
because removal and reconstruction of civil or MEP work will cost more than design changes. The new requirements and
regulations set by the Qatari Civil Defense authority have also increased cost overruns with a higher rate.
The results also showed that civil work changes did cost more on average than MEP and finish work. Change orders in
the civil work caused 42% of the project cost overrun. Therefore, it is recommended to take all necessary precautions to
avoid change orders before starting the construction process.
Figure 4. Cost overrun regression model (contract values between 100 and 300 million QR).
International Journal of Construction Management 11
The Pearson’s correlation coefficient analysis was used to find the strength of the relationship between a project cost
overrun and the causal factors. The factors strongly related to the increase in project cost were: (1) design errors, (2)
changes in design request, (3) significant changes in quantity of work, (4) change of plan or scope by owner, (5) differing
site conditions, (6) utility companies, and (7) mechanical and electrical provisions.
Design errors and changes in design request were usually associated with high cost overruns because they will lead to
work repetition and reconstruction activities. Significant changes in the work quantity and scope changes by the owner are
common problems in the Qatari construction industry. Thus, they were highly correlated with project cost overruns.
The new rules and requirements set by the Qatar Civil Defense authority generated a high number of change orders.
Many projects were already in the construction phase when the new rules were issued. Thus, electrical and mechanical pro-
visions were highly correlated with cost overrun. This can be seen in projects 4 and 19 where they caused more than 90%
of cost overruns.
Conclusions
This paper investigated the impact of change orders on cost overruns in Qatari construction projects. An extensive litera-
ture review was conducted to determine the main factors that cause change orders and cost overruns. The change order
data, which was collected from 22 Qatari construction projects, was analyzed using Pearson’s correlation coefficient, sin-
gle-factor ANOVA, and linear regression. The research identified a total of 21 factors that cause change orders in Qatari
construction projects. Pearson’s correlation coefficient method was used to analyze the relationship between the causal fac-
tors of change orders and project cost overruns. The analysis showed that the following causal factors had the highest cor-
relation: (1) design errors, (2) changes in design request, (3) significant changes in quantity of work, (4) change of plan or
scope by owner, (5) differing site conditions, (6) utility companies, and (7) mechanical and electrical provisions. The
ANOVA showed that change orders in the design stage had a similar cost overrun impact to those in the construction
phase. The analysis also showed that the project owner is the main causal party of change orders in Qatar. This is due to
the owner’s frequent changes of project scope and requirements. Differing site conditions and lack of experience of con-
tractors were major causal factors of change orders in Qatar. Moreover, the analysis showed that change orders of the civil
category had the largest impact on cost overruns.
Recommendations to reduce the impact of the major causal factors on change orders and cost overruns are listed below.
Disclosure statement
No potential conflict of interest was reported by the authors.
ORCID
Ahmed Senouci http://orcid.org/0000-0003-0735-9473
Neil Eldin http://orcid.org/0000-0002-0344-3670
International Journal of Construction Management 13
References
Abdul Rahman I, Memon AH, Tarmizi Abd. Karim A. 2013. Significant factors causing cost overruns in large construction projects in
Malaysia. J Appl Sci. 13: 286–293.
Al-Dubaisi AH. 2000. Change orders in construction projects in Saudi Arabia. MSc Thesis. Saudi Arabia: Faculty of College of Gradu-
ate Studies, King Fahad University of Petroleum and Minerals.
Al-Jurf NA, Beheiry S. 2010. Qatar residential construction projects. Second engineering systems management and its applications inter-
national conference (ICESMA). IEEE,p. 1–6.
Al-Najjar J. 2008. Factors influencing time and cost overruns on construction projects in the Gaza Strip. MS Thesis, Gaza Strip: Islamic
University of Gaza.
Alnuaimi AS, Taha RA, Al Mohsin M, Al-Harthi AS. 2010. Causes, effects, benefits, and remedies of change orders on public construc-
tion projects in Oman. J Constr Eng Manage. 136. Available from: 10.1061/(ASCE)CO.1943-7862.0000154, 615–622.
Du J, El-Gafy M, Zhao D. 2015. Optimization of change order management process with object-oriented discrete event simulation: case
study. J. Constr. Eng. Manage. 10.1061/(ASCE)CO.1943–7862.0001092, 05015018.
Serdar D, Ismail S, Abu Bakar N. 2012. Factors causing cost overruns in construction of residential projects; case study of Turkey. Int J
Sci Manage.1 : 3–12.
Egan JJ, Seder JE, Anderson DL. 2012 Practices in construction change order management. J Cost Eng. (March/April issue). 12–17.
ECHarris built asset consultancy 2013. Avoiding the inflation bubble, Qatar inflation construction forecast. Available from: http://www.
echarris.com/pdf/8503_Qatar_Inflation_Report_FINAL.pdf, September 2013.
Eshofonie FP. 2008. Factors affecting cost of construction in Nigeria. M. Sc thesis.Akoka, Lagos: University of Lagos.p. 5–7.
Gunduz M, Hanna AS. 2005. Benchmarking change order impacts on productivity for electrical and mechanical projects. Build Environ.
40: 1068–1075.
Ismail A, Pourrostam T, Soleymanzadeh A, Ghouyounchizad M. 2012. Factors causing variation orders and their effects in Roadway
Construction Projects. Res J Appl Sci, Eng Technol. 4: 4969–4972.
Mahamid I, Dmaidi N. 2013. Risks leading to cost overrun in building construction from consultants’ perspective. Organization, Tech-
nology & Management in Construction: An International Journal. 5: 860–873.
Moubaydeen S, Pope J, Tuck J, Walker M, Mackay N. 2013. Construction and projects in Qatar: Overview. Construction and Projects
Multi-jurisdictional Guide(2013/2014), Qatar: Dentons & Co.
Yehiel R. 2014. Root-Cause analysis of construction-cost overruns. J Constr Eng Manage. Available from: 10.1061/(ASCE) CO.1943-
7862.0000789, 04013039.