Escolar Documentos
Profissional Documentos
Cultura Documentos
All users of the PERI TRIO system will be provided initial supervised
training from PERI Australia Pty. Ltd.
TRIO PANELS
- Section 1 Loading page 3
- Section 2 Unloading page 3
- Section 3 Assembly of shutters page 4
- Section 4 Erection of Shutters page 5
- Section 5 Stripping of Shutters. page 6
Page 1 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
CONDITIONS – GENERAL
The actual working practice of the contractor in his use of the equipment is
beyond the control of PERI but the following points should be noted as
follows:
The equipment is offered for sale or hire and it is the responsibility of the user
to ensure his working practice complies with Peri literature, local laws and all
relevant codes of practice.
For any add on items not supplied by PERI as standard system components
e.g. handrailing, planking, support for soffit of forms etc. These items must be
designed and installed by the contractor to suit any relevant Australian
Standards or local Authority requirements. These items must be detailed in
the contractors work method statement and PERI takes no responsibility for
these add on items.
The scaffold brackets must be fully planked out and handrailing must be
properly installed.
Base fixings for Push pulls props are the responsibility of the contractor. PERI
takes no responsibility for the design of this fixing. These items must be
detailed in the contractors work method statement
Page 2 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
For weights of all components and safe working loads of boxes refer PERI
literature.
TRIO PANELS
Section 1 LOADING;
Section 2 UNLOADING;
Page 3 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
Page 5 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
Section 5 STRIPPING OF SHUTTERS;
1. Locate working area with good crane access and no overhead obstructions
near wall large enough to take ganged shutter assembly. Also, ensure there is
safe access to this area, area is safe, clear and proper PPE is maintained.
2. The assembled panels will be broken down to suit the sizes of the ganged
panels as per Section 3 Assembly of Shutters. Ensure weight of ganged
shutter does not exceed capacity of lifting equipment or crane. (Weights as
per PERI TRIO range brochure)
3. Stripping is to start from the shutter side that is not propped/braced. Attach
PERI lifting equipment to ganged shutter, extent of ganged shutter is as per
step 2. Ganged panel is also to have attached a tagline. (Note: Ensure proper
PPE is maintained to attach lifting gear to panel) Loosen ties from panel and
remove from ganged section to be stripped only. (Ties to be placed in box
immediately to avoid trip hazard). Release/remove BFD alignment couplers
and other accessories/items which were installed in Section 4 Erection of
shutters items 3 and 4 only. (Place in box immediately to avoid trip hazard).
Lever corner of shutter with a pinch bar and crane out panel section out to
step1.
4. If shutter is removed as 90 degree ganged shutter, stand ganged shutter up
ensuring it is on placed on a level surface and is sufficiently braced to avoid
overturning. Crane and lifting equipment cannot be detached from ganged
panel until panel is securely braced. If shutter is removed as a straight
ganged form place down on a clean level surface. Lifting gear and crane can
be removed.
5. Repeat steps 3 & 4 until all required shutters are stripped for the shutters that
are not propped/braced.
6. Stripping can then start on shutter side that is propped/braced. Attach PERI
lifting equipment to ganged shutter, extent of ganged shutter is as per step 2
Ganged panel is also to have attached a tagline. (Note: Ensure proper PPE is
maintained to attach lifting gear to panel) Remove fixings at base for
props/braces and connection to panels. (To be placed in box immediately to
avoid trip hazard). Release/remove BFD alignment couplers and other
accessories/items which were installed in Section 4 Erection of shutters items
3 and 4 only. (Place in box immediately to avoid trip hazard). Lever corner of
shutter with a pinch bar and crane out panel section out to step1.
7. If shutter is removed as 90 degree ganged shutter, stand ganged shutter up
ensuring it is on placed on a level surface and is sufficiently braced to avoid
overturning. Crane and lifting equipment cannot be detached from ganged
panel until panel is securely braced. If shutter is removed as a straight
ganged form place down on a clean level surface. Lifting gear and crane can
be removed.
8. Repeat steps 6 & 7 until all required shutters are stripped for the shutters that
are propped/braced.
Page 6 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
PERI FORMWORK RISK ASSESSMENT AND SAFE WORK PROCEDURE
Page 7 of 8
MPM Constructions P/L
2-4 Wentworth St Manly
5 August 5, 2004
TRAINING REGISTER
By signing the following you are stating that you have been inducted into
the use of the PERI TRIO formwork system on this site.
Page 8 of 8