Escolar Documentos
Profissional Documentos
Cultura Documentos
1
Shire task to check operation of control valve.
6 monthly
2
Action
Shire task to check operation
Monthly
3
Potential fatality.
Action
Shire task to check operation of safety valve.
6 monthly
4
1D5 Gauge fails
Incorrect pressure reading
Action
Shire task to check gauge reading
Monthly
5
1E4 Reducing valve EP5 type fails to maintain set steam
pressure.
Plant stopped
Action
Shire task to check operation
6 monthly
6
1F3 Gauge fails
Incorrect pressure reading
Action
Shire task to check gauge reading
Monthly
7
Monthly
8
Shire task to check for missing insulation.
Monthly
9
Action
Shire task to check operation of control valve.
6 monthly
10
Unable to stop steam in an emergency.
Action
Shire task to check operation
Monthly
11
1J6 Pressure relief valve fails. Set at 4.0 bar
Potential fatality.
Action
Shire task to check operation of safety valve.
6 monthly
12
2A5 Non return valve fails
Steam line will fill with condensate on shutdown
Action
Shire task to check valve.
3 monthly
13