Você está na página 1de 12

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 24 (2006) 687–698
www.elsevier.com/locate/ijproman

Fundamental uncertainties in projects and the scope


of project management
Roger Atkinson a, Lynn Crawford b,c,*
, Stephen Ward d

a
Business School, The Institute of Business and Law, Bournemouth University, Christchurch House, Talbot Campus, Fernbarrow, Poole, BH12 5BB, UK
b
University of Technology, Sydney, P.O. Box 123, Broadway NSW 2007, Australia
c
ESC Lille, Avenue Willy Brandt, 59777 Euralille, France
d
School of Management, University of Southampton, Highfield, Southampton, SO17 1BJ, UK

Abstract

This paper builds on discussions that took place over a series of meetings in the UK of the Rethinking Project Management Network.
The management of uncertainty is seen as a necessary condition for effective project management. Sources of uncertainty are wide rang-
ing and have a fundamental effect on projects and project management. These sources are not confined to potential events, and include
lack of information, ambiguity, characteristics of project parties, tradeoffs between trust and control mechanisms, and varying agendas in
different stages of the project life cycle. Common project management practice does not address many fundamental sources of uncer-
tainty, particularly in ‘soft’ projects where flexibility and tolerance of vagueness are necessary. More sophisticated efforts to recognise
and manage important sources of uncertainty are needed. Such efforts need to encompass organisational capabilities, including some
aspects of organisation culture and learning.
Ó 2006 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Uncertainty management; Hard and soft projects; Trust; Organisational capabilities

1. Introduction the validity and usefulness of the authors’ work, in many


instances providing further related insights and questions.
This paper is concerned with the kinds of uncertainty Throughout network meetings the presence of uncer-
present in projects, and what might be done to manage tainty in a variety of forms was constantly recognised as a
them. The paper builds on discussions that took place dur- central issue. Initial deliberations about uncertainty focused
ing meetings of the UK EPSRC funded Network on on appreciating the variety of sources of uncertainty requir-
Rethinking Project Management over the period 2004– ing management attention and that go well beyond a set of
2006. Early on views about uncertainty in projects were possible events that might impair project performance. This
summarised in a series of learning propositions to orientate has implications for the development of formalised
further discussions. In developing this paper, previous approaches to project risk management. These approaches
work of the authors was an initial base, but perspectives need to recognise the full range of sources of significant
and issues that emerged from the network presentations uncertainty associated with any given project. Subsequent
including case studies and discussions, extended this base. network discussion reflected on the reasons why project
Follow up discussions after presentations largely supported management to date seemed to be lacking in attending to
all this uncertainty. One explanation is that conventional
*
project management is too focused on operational planning
Corresponding author. Address: University of Technology, Sydney,
P.O. Box 123, Broadway NSW 2007, Australia. Tel.: +61 2 9514 8730; fax:
and control. This prompted reflection on how projects with
+61 2 9968 1274. particularly problematic sources of uncertainty might be
E-mail address: Lynn.Crawford@uts.edu.au (L. Crawford). characterised, and what implications this has for modifying

0263-7863/$30.00 Ó 2006 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2006.09.011
688 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

or extending a conventional planning and control perspec- managers, that estimating activity for planning and control
tive on project management. In particular, there is a need purposes is a critical project management process. The
to recognise that many project contexts are characterised causes of uncertainty about estimates include one or more
by very high, difficult to quantify, levels of uncertainty of the following:
where management flexibility and tolerance of vagueness
are necessary. Following this line of thought, network dis-  lack of a clear specification of what is required;
cussions concluded that more attention needs to be given  novelty, or lack of experience of this particular activity;
to understanding and developing less tangible, but more  complexity in terms of the number of influencing factors
generic management processes associated with building and associated inter-dependencies;
trust, sense-making, organisation learning, and building  limited analysis of the processes involved in the activity;
an appropriate organisational culture better suited to oper-  possible occurrence of particular events or conditions
ating with high levels of uncertainty. which might affect the activity;
The structure of this paper follows the sequence out-  emerging factors unknowable at the start of the project;
lined above. Section 2 considers some key areas of uncer-  bias exhibited by estimators, typically optimism bias
tainty that warrant serious management attention in most [1,2].
projects. This has implications for the desirable scope of
common project risk management processes that augment Thus, uncertainty results from vagueness, ambiguity and
project management. Section 3 suggests that one obstacle contradictions associated with lack of clarity because of
to effective management of uncertainty is that conven- lack of data, incomplete and inaccurate detail, lack of
tional project management does not pay enough attention structure to consider issues, the working and framing
to conception and end stages of the project life cycle, or assumptions being used to consider the issues, known
to strategic aspects of projects. Section 4 describes a and unknown sources of bias, limited control of relevant
‘hard’/’soft’ typology of projects that highlights major project players, and ignorance about how much effort it
sources of ambiguity and vagueness that may be problem- is worth expending to clarify the situation [3].
atic using convention plan and control project manage-
ment. Section 5 briefly considers some implications of 2.2. Uncertainty associated with project parties
‘softness’ for the scope of project management processes,
including the role of trust. Section 6 identifies the impor- In many projects, particularly large ones, key perfor-
tance of organisation infrastructure and in particular the mance issues are often less related to technology, but rather
importance of organisational culture and capacity for are related to uncertainty introduced by the existence of
organisational learning. multiple parties and the associated project management
infrastructure.
2. Uncertainty management as part of project management While employees and other agents of a project owner are
essential to the achieving of project performance, they also
Much good project management practice can be thought contribute to uncertainty about future performance. This
of as effective uncertainty management, clarifying what can uncertainty arises from several factors associated with each
be done, deciding what is to be done, and ensuring that it project party, including [4]:
gets done as noted earlier. For example, good practice in
planning, coordination, setting milestones, and change con-  uncertainty about the level of performance that will be
trol procedures, seeks to manage uncertainty directly. How- achieved;
ever, common practice does not consider the range of  the objectives and motivation of each party;
sources of uncertainty present in projects or what a coordi-  the quality and reliability of work undertaken;
nated approach to proactive and reactive uncertainty man-  the extent to which each party’s objectives are aligned
agement can achieve. Three key areas of uncertainty with the project owner’s objectives, and the scope for
featured in network discussions: uncertainty associated with moral hazard where one party is motivated to do things
estimating, uncertainty associated with project parties, and which are not in the best interests of the project owner;
uncertainty associated with stages of the project life cycle.  the actual abilities of the party;
 availability of the party.
2.1. Uncertainty in estimates
In any organisational context including all projects, the
An obvious aspect of uncertainty in any project con- introduction of agents is prone to the three problems of:
cerns estimates of potential variability in relation to perfor- adverse selection, moral hazard and risk allocation. The
mance measures like cost, duration, or quality related to uncertainties presented by these problems can be substan-
particular planned activities. For example, we may not tial [5]. When these agents are different organizations, these
know how much time and effort will be required to com- problems can be particularly challenging. Where project
plete a particular activity. It was evident from network dis- owner and agent(s) belong to the same organization it
cussions, and all the case study presentations by project might be expected that such problems would be less likely
R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698 689

to arise, to the extent that the parties can share informa- Table 1
tion, responsibilities and objectives more readily. Unfortu- Typical uncertainty management issues in each stage of the project life
cycle (Chapman and Ward, [3]. Copyright John Wiley & Sons Ltd., used
nately, this is not always the case. In any of these ostensibly with permission)
cooperative situations, the different parties involved are
Stages of the PLC Uncertainty management issues
likely to have different performance objectives, or at least
different priorities and perceptions of objectives. One con- Conceive the product Level of definition
Definition of appropriate performance
sequence of this is that different parties will have different objectives
perceptions of risks associated with these objectives, and Managing stakeholder expectations
therefore may wish to adopt different strategies for manag-
Design the product Novelty of design and technology
ing related project uncertainty. This divergence will be strategically Determining ‘fixed’ points in the design
aggravated if different parties also have different knowledge Control of changes
and perceptions of the nature of sources of uncertainty and
Plan the execution Identifying and allowing for regulatory
different capabilities for managing them [3,6]. strategically constraints
Concurrency of activities required
2.3. Uncertainty associated with stages in the project life Capturing dependency relationships
cycle Errors and omissions
Allocate resources Adequate accuracy of resource estimates
Many significant sources of uncertainty that need to be tactically Estimating resources required
managed in projects are associated with the fundamental Defining responsibilities (number and scope
of contracts)
generic management processes that make up the project life Defining contractual terms and conditions
cycle. A fair number of sources are implicitly acknowl- Selection of capable participants (tendering
edged in lists of project management ‘key success factors’ procedures and bid selection)
such as those offered by Gallagher [7]. Potential sources Execute production Exercising adequate coordination and control
typically identified in this way are listed in Table 1 against Determining the level and scope of control
various stages of the project life cycle. (By presenting Table systems
1 we do not mean to imply that projects can be character- Ensuring effective communication between
participants
ised as a simple linear process, or simply in terms of the
Provision of appropriate organizational
stages listed, but the scope of stages and level of detail is arrangements
sufficient for present purposes. Ward and Chapman [8] Ensuring effective leadership
provide a more detailed description of project life cycle Ensuring continuity in personnel and
stages and possible complications in practice.) responsibilities
Responding effectively to sources which are
All of the uncertainty management issues in Table 1 are
realized
best addressed very early in a project and throughout the
project life cycle and should be informed by a broad appre- Deliver the product Adequate testing
Adequate training
ciation of the underlying ‘root’ uncertainties. Chapman Managing stakeholder expectations
and Ward [3] offer a six Ws framework for this purpose Obtaining licences to operate
based on the following six questions about a project:
Review the process Capturing corporate knowledge
Learning key lessons
1. who are the parties ultimately involved? Understanding what success means
2. what do the parties want to achieve? Support the product Provision of appropriate organization
3. what is it that each party is interested in? arrangements
4. which way (how) is each party’s work to be done? Identifying extent of liabilities
5. what resources are required? Managing stakeholder expectations
6. when does it have to be done?
ciently well-defined specifications for production. During
Understanding the uncertainty associated with each of execution this gives rise to difficulties necessitating addi-
these basic questions, and the implications of interactions tional design development and production planning, and
between them, is fundamental to effective identification consequently adverse effects on the performance criteria of
and management of project risk. Use of the six Ws frame- cost, time and quality. This problem of ‘premature defini-
work from the earliest stages of the project life cycle can tion’ can be most acute in novel, one-off projects involving
usefully inform development of project design and logistics new technology, particularly when key stakeholders attempt
by clarifying key sources of uncertainty. In particular, fail- to impose unrealistic completion dates or cost targets.
ure to clarify stakeholder expectations and priorities at an Sometimes this can be caused by politically motivated per-
early stage can cause major difficulties later in the project. formance criteria, targets, and operating constraints: e.g.
A common source of difficulty in projects is a failure to budgets too small to allow adequate resources to complete
carry out the design and plan stages thoroughly enough. the project by a stated time, or to a given level of function-
Thus a project proceeds through to execution with insuffi- ality [9]. In addition, some uncertainty about operating
690 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

conditions and related factors outside the control of the pro- focus on threats will not adequately address many sources
ject manager will always remain. Inevitably, judgments have of variability and ambiguity. Risk management processes
to be made about the degree of detail and accuracy that is concerned with threats and opportunities will do better,
practicable in the design and plan stages. but will still tend to be focussed on uncertain events or cir-
The allocate stage of the project life cycle is a significant cumstances. This does not facilitate consideration of
task involving decisions about project organization, identi- aspects of variability that are driven by underlying ambigu-
fication of appropriate agents by the project owner, and ity and lack of information.
allocation of tasks between them. The sources of uncer- To address all sources of significant uncertainty requires
tainty and risk associated with this stage of any project a more explicit focus on uncertainty management as part of
are considerable, primarily due to the three agency prob- managing projects. Particular attention needs to be paid to
lems of: adverse selection, moral hazard and risk allocation the parties involved in a project and their respective objec-
mentioned earlier. Risk allocation is particularly important tives in three ways.
because it can strongly influence the motivation of princi-
pal and agent, and the extent to which uncertainty is 2.4.1. Treat the definition of objectives as a key part of
assessed and managed. Insofar as principal and agent per- managing projects
ceive risks differently, and have different abilities and moti- Selecting relevant performance criteria, formulating
vations to manage sources of uncertainty, then their objectives for these criteria, and modifying objectives,
approach to risk management will be different as noted ear- should be regarded as important, even fundamental aspects
lier. In particular, either party is likely to try to manage of project management.
uncertainty primarily for their own benefit, perhaps to
the disadvantage of the other party. Even in the same orga- 2.4.2. Project management should clarify and manage
nisation, there can be significant issues in allocating risk in desired trade-offs between multiple performance objectives
a hierarchical structure or between different units in the Typically, in any given project context, there is more
same organisation. Chapman and Ward [6, Chapter 6] than one performance criterion and associated objective,
explore ‘internal contracts’ to address such issues. often even a hierarchy of objectives. The implication is that
A common source of uncertainty in the execution stage is variations in performance on each criterion are possible
the introduction of design changes. Such design changes can and measurable, and hence that uncertainty exists in
lead to disruption of schedules and resourcing, and affect respect of each of these performance criteria. A simple
cost, time and quality measures of performance directly to example is the common presentation of project perfor-
an extent that is difficult to predict. A potentially serious mance in terms of cost, time and quality related objectives.
concern is that changes are introduced without a full appre- The cost criterion might be addressed in terms of capital
ciation of the knock-on consequences. Apart from direct cost or ‘whole life’ cost, and the quality attribute might
consequences, indirect consequences can occur. For exam- be divided into technical specification, functionality, reli-
ple, changes may induce an extension of schedules, allowing ability, and appearance, each of which may be ‘at risk’ to
contractors to escape the adverse consequences of delays in different degrees. Objectives may be set for each of these
works unaffected by the change. Changes may have wider performance attributes, and the project will be ‘at risk’ to
technical implications than first thought, leading to subse- different degrees with respect to each objective.
quent disputes between client and contractor about liability Active management for performance usually involves
for costs and consequential delays [10–12]. Standard project making trade-offs between objectives because different
management practice should establish product change con- courses of action involve different combinations of uncer-
trol procedures that set up criteria for allowable changes tainty in respect of the various performance criteria. Fail-
and provide for adequate coordination, communication ure to recognise these trade-offs and articulate preferred
and documentation of changes. trade-offs can result in ineffective and often inappropriate
In the plan stage, looking forward to the deliver and management of risk. For example, to ensure that a project
support stages, and developing appropriate responses for is completed on time is it really sensible to adopt any
key sources of uncertainty, can reduce or eliminate poten- course of action whatever the cost?
tial later problems at relatively low cost. The key here is In the extreme, performance criteria that are not readily
identifying which issues need this attention in the plan quantified may be treated as inviolate constraints for man-
stage, and which do not. agement purposes. This may lead to neglect of uncertainty
in these performance criteria and failure to manage associ-
2.4. Extending project risk management ated risk, even though these criteria represent important
aspects of performance.
Effective uncertainty management needs to address
uncertainty in a broad sense, with the early consideration 2.4.3. Ownership of uncertainty needs explicit consideration
of all sources of significant uncertainty and associated Decisions should be made about how uncertainty and
responses. Even when integrated with project management, associated issues should be allocated to various project par-
formal project risk management processes that adopt a ties, recognising as noted earlier, that different parties have
R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698 691

different objectives, different perceptions of project risk, useful in the right place. However, they too reinforce a
and different capabilities for managing associated sources focus on operational planning and control with consequent
of uncertainty. lack of attention to strategic issues and associated funda-
mental uncertainty management issues.
3. The limited scope of conventional project management A view expressed in network discussions was that con-
ventional (common practice) project management pro-
An emergent conclusion from network discussions was cesses are concerned with legitimising the project plan,
that common perceptions of projects and project manage- and uncertainty (particularly from fundamental sources)
ment practice do not encompass all the stages of the project is played down. The project manager is regarded as a con-
life cycle shown in Table 1. This is another reason why venient recipient of project risk, providing psychological
common risk management practice often fails to address relief to the project owner (if not actual physical relief)
basic sources of uncertainty that drive problems in the pro- from the burden of uncertainty and risk bearing, and some-
ject life cycle. In particular, professional guidelines mini- one who subsequently unwillingly serves as scape-goat if
mise the role of conception at the front end of the life things fail to turn out as desired by the project owner.
cycle and support at the tail end. An associated boundary
problem is clearly delineating the conception stage and 4. Hard and soft projects
understanding explicitly how this stage is linked to subse-
quent project life cycle stages (especially design and plan- In considering the appropriate scope for project man-
ning) in relation to determining appropriate objectives, agement and associated uncertainty management, it is use-
performance requirements, and constraints. ful to characterise the range of project types and contexts
Even in other life cycle stages, professional guidelines in terms of the scope of uncertainty involved. Conventional
often fail to distinguish between strategic, whole project project management approaches may be more effective for
considerations, and lower level, operational procedures. some kinds of project than others.
Ward and Chapman’s [8] depiction of the design, plan In practice, the concept of ‘project’ has been broadened
and allocate stages as highly iterative processes comprising from an initial focus on management of largely unitary,
a number of development steps, goes some way towards standalone projects with well defined and agreed goals
drawing this distinction. However, it seems as if the more and end products, to include multiple projects and pro-
procedural (teachable?) elements of these stages receive grammes that are multidisciplinary, and which are ‘‘not
more attention from trainers of project managers and in pre-defined’’ but ‘‘permeable, contested and open to rene-
project management text books, than the more strategic gotiation throughout’’ [13, p. 4]. These two ends of a spec-
issues. Unfortunately, it is the latter that includes the most trum are often referred to as ‘hard’ and ‘soft’ but in reality
important, fundamental sources of uncertainty. The result there are a number of dimensions of hardness and softness
is that project management is commonly regarded as con- of projects [14,15]. Projects and programmes may simulta-
cerned with ensuring things get done right, assuming that neously exhibit both hard and soft characteristics on these
there is a well defined remit of what needs to get done. With dimensions and these characteristics may change through-
this view, project management is not concerned with think- out a project life cycle.
ing about whether the right things are being done, why the Crawford and Pollack [14] identify seven dimensions of
project should proceed, or what performance criteria hardness and softness of projects based on: previous
would be appropriate. This may explain why it has been research [16,17], use of the terms ‘hard’ and ‘soft’ in project
possible for the subjects such as ‘whole life costing’ and management practice and literature, and differences in the
‘value management’ to emerge somewhat separately from philosophical basis of the hard/soft dichotomy [18]. These
traditional project management concepts. seven dimensions of hardness and softness are illustrated in
Perhaps the conventional common view of project man- Fig. 1.
agement is essentially to see the project task as a set of pro- For some projects, goals are generally clear and well
cesses to ensure a project meets its (predetermined) defined and goals may be ‘given’ at the start. At the other
objectives. Then the whole raison d’etre of project manage- end of the spectrum, projects may have multiple purposes
ment is to remove (or substantially reduce) uncertainty and there may be differing views and expectations of the
about meeting specified objectives. However, project man- outcome of a project. Consequently, goals may be initially
agement in this sense is a castle built on shifting sands if in ill-defined, emerging as a result of negotiation and consen-
practice objectives are unclear, contradictory, or impossi- sus building throughout the project. There is also the
ble. Many endeavours recognised and ‘managed’ as pro- uncertainty that the ‘real’ purpose for a project is hidden
jects experience problems for this reason. for political, economic, social or technical reasons, while
A common interpretation of a project plan is that it is an only the secondary or declared reason is being managed.
attempt to define an intended future. Project design and Projects that have tangible end products such as build-
planning activity creates a set of plausible working assump- ings, equipment and machinery, can be represented as phys-
tions as a basis to move the project forward. The tools and ical models and prototypes, providing a basis for clarity in
techniques of conventional project management are very terms of what will be produced. Clarity and agreement
692 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

about the end product are far harder to achieve where the assume more of the characteristics at the soft end of the
end products of the project are intangible, as in information spectrum in Fig. 1, the use of many of the tools and tech-
systems development and organisational and cultural niques of traditional project management for dealing with
change initiatives. Stakeholders are likely to have different uncertainty become more difficult, less reliable and further
interpretations and expectations of what will be produced. removed from reality.
Judgement concerning project success is far more difficult For some projects it is assumed that there is one best
to assess in projects with intangible products. Further, if solution generally developed by technical experts. At the
success is to be measured, it will be more likely to rely on soft end of the spectrum, multiple world views and perspec-
qualitative rather than quantitative measures that once tives are recognised and solutions are developed through
again will be susceptible to differing interpretations and per- negotiations and debate between multiple stakeholders.
ceptions. Initiatives to extend the ‘Iron Triangle’ of cost, Where the project involves refinement of a single solution,
time and quality to include benefits and value criteria have the path to the known and agreed best solutions is man-
been addressed by such as Atkinson [19]. aged. Projects at the soft end may require facilitation of a
Where the boundaries of the project are defined by con- process for identifying and agreeing on possible solutions.
tracts, relationships and project boundaries are defined, The degree of stakeholder involvement and the expecta-
and exchange between the project and its environment is tions of stakeholders in terms of interaction will also affect
amenable to control. At the other end of the spectrum the ability to reduce uncertainty in the interests of achiev-
are projects where the boundaries are unclear and perme- ing clarity and control.
able. An example is an organisational change project where A general observation that arises from the conceptuali-
it is difficult to identify where the project starts and ends. In sation of projects in terms of Fig. 1 dimensions is that pro-
such cases, scope may be difficult to define. Project bound- jects closer to the hard end of the spectrum are more
aries may be moved or redefined, or subject to differing amenable to uncertainty reduction than those at the soft
interpretations by different stakeholders. Such projects end of the spectrum where the primary emphasis may be
are often undertaken by staff internal to an organisation on reduction of ambiguity. This suggests different
who are not isolated from their environment by contractual approaches for dealing with uncertainty and stakeholder
structures. Staff are often shared with other projects and expectations depending on the nature of the project or pro-
with functional or line positions, further blurring the gramme in terms of hard and soft dimensions. The softer
boundaries of the projects. Such projects can be highly sus- the project against these dimensions, the greater the degree
ceptible to external influence. of flexibility, tolerance of vagueness but less so ambiguity,
Projects that have clear boundaries providing a degree and acceptance of residual uncertainty that will be required
of isolation from environmental influences allow for the of stakeholders in assessing the progress and success of the
use of tools and techniques of project management such project. Where uncertainty about future events is high, tol-
as network planning, risk analysis, and computerised erance of uncertainty may be particularly necessary. Flexi-
resource allocation and task coordination. As the bound- bility is necessary in projects where the goals are unclear or
aries of the project become more permeable and projects open to negotiation, strategy is emergent and the project is

Goals/objectives 1. Goal Clarity Goals/objectives highly


0 100
clearly defined ambiguously defined

2. Goal Tangibility
0 100
Physical artefact Abstract concept

Only quantitative 3. Success Measures Only qualitative


0 100
measures measures

Not subject to 4. Project Permeability Highly subject to


0 100
external influences external influences

Refinement of 5. Number of Solution Options Exploration of many


0 100
single solution alternative solutions
Expert practitioner, Facilitative practitioner,
0 6. Participation and Practitioner Role 100 high stakeholder
no stakeholder
participation involvement

Values technical 7. Stakeholder Expectations Values relationships,


0 100
performance and culture and meaning,
efficiency, manages by manages by negotiation
monitoring and control and discussion

Fig. 1. Depiction of the hard and soft dimensions framework [14].


R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698 693

highly subject to external influences. Keeping options open,

ft
and adopting a flexible, robust approach may be much

So
more effective than prematurely crystallising plans and

High
relying on conventional control mechanisms to deliver
performance. Ongoing

Ambiguity
Sensemaking
Analysis of projects against this hard/soft dimensions Conversations & Value Analysis
framework provides a basis for questioning assumptions
about the nature of projects. When examined in this way, Ongoing Risk Analysis &
even projects that may initially be considered hard (e.g. Operations Problem Solving

Low
construction projects) and therefore amenable to tradi-
tional control approaches for dealing with uncertainty

d
ar
and managing expectations, may be found to have some

H
characteristics towards the soft end of the spectrum and
visa versa. Low High
Uncertainty

5. Implications of ‘softness’ for the scope of project Fig. 2. Uncertainty – ambiguity relationship in change situations –
management adapted from Thiry [20].

Widely available and promoted project and risk man-


agement methodologies, tools and techniques have been Ability to formulate qualitative success measures for
developed to deal with uncertainty in projects with charac- projects is another tool that should be added to the project
teristics primarily at the hard end of the spectrum described management armoury to assist in managing softer projects.
above. Associated with these approaches to project man- Projects with low uncertainty and ambiguity can generally
agement are expectations of clarity and certainty that be assessed using quantitative success measures such as
may not be either feasible or desirable for projects with time and cost performance, and measures related to their
characteristics that are at the soft end of the spectrum. tangible end products. Projects at the soft end of the spec-
Such projects may require both different approaches and trum require different forms of performance evaluation
levels of performance expectation. For example, Thiry that recognise the validity of different perspectives and
[20] proposes (see Fig. 2) the use of sense-making and value worldviews. This calls for ability to develop sensitive per-
analysis for projects that are at the soft end of the spectrum formance evaluation frameworks that match the complex-
where both uncertainty and ambiguity are high. As Fig. 2 ity of the project.
suggests, Thiry [20] makes a clear distinction between
uncertainty and ambiguity/equivocality. According to 5.1. The role of trust
Thiry, uncertainty is defined by the difference between the
data required and the data already possessed; it is a ‘lack As projects take on more ‘soft’ characteristics, the
of information’. Ambiguity, on the other hand, means importance of project parties as contributors to project
the existence of multiple and conflicting interpretations; it uncertainty increases. Then much depends on the motives
is linked to confusion and lack of understanding. Whereas of different parties, the incentives operating, and the level
uncertainty warrants the acquisition of objective informa- and type of trust between parties.
tion and the answering of specific questions, ambiguity A root problem is that a project context is more tempo-
warrants sense-making, the exchange of views and the def- rary than ongoing operations where routinisation, learning
inition of situations/problems. from past experiences, memory of past experiences is easier
Such sense-making is particularly important in the con- (more available), the parties are relatively constant, and
cept stage of the project life cycle, and during preliminary experimenting and the evolution of optimum practice is
design and planning activities where uncertainty is high possible. The subject matter of the project may involve
and a strategic perspective of context possibilities is the creation of artefacts outside the project owner’s capa-
important. Unfortunately, if the need for ongoing sense- bility (buildings, physical infrastructure, software etc) and
making is not acknowledged, later pressures to crystallise this necessitates the involvement of outside parties, who
plans and subsequent reification of the project plan, may be unfamiliar to the project owner. Such new and
together with escalating commitment, may increasingly temporary relationships increase the importance of trust,
preclude further sense-making as the project progresses. since project parties may have little or no prior knowledge
Additionally, lack of time and limited resources may dis- of the other parties’ technical or fiduciary standards, and
courage sense-making efforts. Further, such sense-making there is a lack of time for familiarity to develop from
that takes place may be limited by being inherently retro- shared experiences or demonstrations of non exploitation
spective rather than forward looking, and political consid- of vulnerability.
erations may produce more concern for plausibility than A further problem is that total control over the activ-
accuracy. ities of project parties is neither possible nor desirable.
694 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

An understandable reliance on controls can lead project building workshops is often fiduciary, while decision mak-
staff to feel that they are not trusted (and vice versa), ing in projects can often be influenced by rational eco-
and this can have adverse consequences of a moral hazard nomic reasons. Meyerson et al. [27] have termed the
nature. Moreover, any lack of trust can produce a trust involved in such circumstances ‘swift trust’. When
dynamic that serves to ratchet up control mechanisms’, team members have little knowledge of other team mem-
thus preventing success Coopey [21]. The problem with bers’ likely actions, ‘swift trust’ is entered into as team
trust is that it can spiral, both positively and negatively members know that they have to trust others in order
[22], consequently there is always a balance to be struck to move a project forward, but have little evidence of
between the use of controls and trust. An increase in the level of their vulnerability as they do not know other
one implies a compensating reduction in the other. Handy team members. Meyerson et al. [27] studied temporary
[23] argues that where you cannot trust, you have to groups (such as found in weak matrix project structures)
check all the systems of control involved, to ensure that and concluded that swift trust is found in high risk, high
any gaps in trust are replaced with controls. However, stake projects, where there is a lack of normative struc-
while acknowledging that a mixture of trust and controls tures and institutional safeguards to minimise things
are needed, O’Neill [24] argues that ‘all guarantees are going wrong.
incomplete’ and so ‘. . . elaborate measures to ensure that To help create trust, Cook [28] advises that uncertainty
people keep agreements and do not betray trust must, in can be reduced by knowing the competence of other staff
the end, be backed by trust’. while vulnerability can be decreased by the use of enforce-
There are a number of benefits related to uncertainty able contracts and insurance schemes. Heimer [29] explains
reduction from using trust in place of controls. These the method required to promote a trust strategy ‘. . .
include [25]: worked by reducing uncertainty’ while a distrust strategy
is ‘. . . worked by reducing vulnerability’. Overall, Heimer
 more accurate risk calculations (through more open suggests that the trust problem can be solved by manipulat-
communications between project parties), ing vulnerability and uncertainty about intentions and
 reduced control costs (through for example faster and competence. Similarly, Munns [22] proposed a ‘Graduated
more effective contracting), and Reciprocated Initiatives in Tension reduction’ (GRIT)
 teams more effective (through improved confidence), model to be followed in a process of continual building of
 improved planning (through more honest specifications mutual trust during a project.
and estimates). In an attempt to improve the success rate of projects,
trust (which takes several forms) should be included for-
Zaghloul and Hartman [26] discuss the problems of mis- mally within the discipline of project management. Trust
trust within construction projects, in terms of the cost sav- does not figure in the current APM Bok version 4 [30]
ings that can be obtained through reducing the use of nor the BS 6079 [31]. One way in which trust could be used
exculpatory clauses in contracts and building trust via: by practitioners is to include an audit of trust as an element
of uncertainty management.
 understanding project risks and who owns them, A framework for such a trust audit proposed by Atkin-
 allowing sufficient time to manage or mitigate the risks, son [32] contains the following factors:
 building trust through negotiations prior to a written
contract,  vulnerability (to the action of others),
 risk-sharing and the design of appropriate risk-reward  credibility (related to both ‘can do’ and ‘will do’),
systems.  culture (of the organization),
 visibility (and openness of information).
If a relationship is to start in a state of mutual trust, it
requires prior confidence in the reliability of the other Each factor relates to different types of trust, and ques-
party, otherwise those involved are being asked to trust tions related to those topics enable a comprehensive view
without evidence that it is safe to do so. One requirement of the trust within a project team to be obtained. These fac-
for trust to exist is to have it built-up over time. This can tors could be considered by different project stakeholders
be observed to be taking place when individuals do what such as: the Project Manager, Project Board, Quality, Sup-
they say they will do, thus creating a basis of trust build- port, Development and the Users to develop as complete
ing. However, with project work, there is often limited an audit as possible.
time to build trust between parties and there is often no By including a trust audit as part of an uncertainty man-
history of their behaviour, but the parties still have to agement process, practical measures of governance can be
work together to achieve the project objectives. Hence included to ensure that the balance of trust and control is
formal team-building exercises are often used to build known and that appropriate measures are put into place.
trust as an alternative to something which would have If there is an over reliance on controls in place of trust,
naturally occurred over time. But there can be a problem organisations must expect and prepare for the dysfunc-
with these, in that the type of trust operating in team tional behaviour that will follow.
R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698 695

6. Supporting organisational capabilities Accepting that culture can operate as an organisational


control mechanism, the quality of uncertainty management
All project management activity takes place in a wider undertaken as part of project management can be driven or
organisation context, and how the organisation operates at least influenced by the organisation culture prevailing in
will have a major impact on what can be achieved by its associated business units. This culture can be manifest in a
members in terms of project management. Organisation variety of ways, such as attitude to: planning, formal pro-
structure, co-ordination and control systems, environmen- cedures, regulations, criticism, mistakes, uncertainty, and
tal scanning capability, communications and information risk. These cultural characteristics can either facilitate or
systems, knowledge management, and support for organi- hinder the development of uncertainty management.
sation learning, all affect the quality and scope of project Chapman and Ward [6, Chapter 12] argue that some of
management undertaken [33]. Such factors define the basic the most significant barriers to effective uncertainty man-
resources that project management must work with, and agement are based on unfavourable features of organisa-
they set the tone for how project management will be able tional culture. Sometimes these barriers are induced
(or allowed) to operate. Such factors can enable project from outside the organisation in the form of convictions,
management to flourish, or can present barriers to its prejudices, biases, and routines of professional groups
development no matter how capable and determined the that can blinker thinking. These may arise from a wish
champions of project management effort. Consequently, to make decisions efficiently in a particular context
efforts to improve and broaden the scope of project man- according to recognised scientific or professional stan-
agement need to consider the organisational infrastructure dards. Such professionally based convictions can strongly
that facilitates project management as much as the partic- influence different groups within the same organisation,
ular processes for specific projects. making it very difficult to adopt effective uncertainty man-
Organisations which have efficient and effective systems agement processes. However, most organisations also
for co-ordination and control, environmental scanning, exhibit a number of more generic culture based behav-
and organisation learning will be comparatively well placed iours or conditions inimical to effective uncertainty man-
to foster efficient and effective uncertainty management. agement such as ‘conspiracies of optimism’, ‘macho
Unfortunately, many organisations exhibit deficiencies in management’, blame culture, and ‘management by misdi-
their approach to uncertainty and learning which can act rection’ [6, Chapter 12]. Essentially such behaviours seem
as barriers to the development of uncertainty management. to evidence the difficulty management has in coping with
Sometimes shortcomings in organisational capabilities are complexity and uncertainty. In particular, these behav-
not evident until systematic attempts to identify and man- iours can reflect an inability or unwillingness on the part
age uncertainty are made. The following extract from the of managers or groups to recognise the difference between
executive summary of the Space Shuttle Columbia Acci- (a) bad management and poor performance due to factors
dent Investigation Board [34] is instructive of the issues that are not under a manager’s control; and (b) good
involved: managers who apply proactive uncertainty management
to reduce problems and enhance performance, and man-
The organisational causes of this accident are rooted in
agers who are just lucky. Addressing such conditions
the Space Shuttle Program’s history and culture, includ-
can be one of the most significant benefits of formal
ing the original compromises that were required to gain
uncertainty management processes.
approval for the Shuttle, subsequent years of resources
constraints, fluctuating priorities, schedule pressures,
6.1. Learning by experience
mischaracterization of the Shuttle as operational rather
than developmental, and lack of an agreed national
Knowledge management and learning, both organisa-
vision for human space flight. Cultural traits and organ-
tional and individual, are major contributors to uncer-
isational practices detrimental to safety were allowed to
tainty management in a variety of ways. At a very
develop, including: reliance on past success as a substi-
practical level, readily accessible repositories of data from
tute for sound engineering practices (such as testing to
past projects either specific to the organisation or available
understand why systems were not performing in accor-
from industry sources, are fundamental to the quality of
dance with requirements); organisational barriers that
estimates. Availability of reliable data for the estimating
prevented effective communication of critical safety
and planning of projects in itself contributes to the reduc-
information and stifled professional differences of opin-
tion of uncertainty. However, many organisations fail to
ion; lack of integrated management across program ele-
collect such data on projects, and even where it is collected
ments; and the evolution of an informal chain of
it is often not made available for those embarking on new
command and decision making processes that operated
projects or is not analysed and presented in a form that is
outside the organisation’s rules.
useful for such purposes. The problem is compounded
The Board concludes that NASA’s current organisation
where new project types are undertaken by organisations.
. . . has not demonstrated the characteristics of a learn-
The level of uncertainty may be higher for management
ing organisation.
of projects in some organisations than in others due to lack
696 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

of data from past projects. Such data may or may not be then it is more likely that an environment conducive to
available from other organisations or industry sources. openness and learning can be created. Further, the learning
Even where data on past performance is available, a extracted is likely to be more reliable and useful in reducing
major challenge is failure to access such inputs during the uncertainty in future projects.
planning of new projects and therefore failing to learn from
experience. There are a number of factors that contribute 7. Conclusions
to this including the organisational culture as discussed
above, time pressures and the attitudes and behaviours of Discussions of the UK EPSRC funded Network on
project management personnel. Certainly the non-repeti- Rethinking Project Management raised many issues with
tive nature of project work in the context of temporary implications for the fundamental uncertainties of projects
organisations presents a particular challenge for knowledge and the scope of project management. The network pro-
management, and transfer of learning. posed rethinking of the traditional view of projects as hav-
‘‘Lessons learned’’ is a popular term in the project man- ing a linear life cycle involving a set of apolitical processes
agement literature and amongst practitioners, yet it often undertaken to achieve an objective or goal ‘given’ at the
masks payment of lip service only to the idea of learning start, to reflect the actuality of projects as social processes
from experience. The capture and re-use of learning from requiring ongoing construction of the appearance of cer-
one project to another is generally accepted as something tainty and clarity in the midst of complex uncertainty
that should be done but it often goes no further than cap- and ambiguity [36]. Some but not all aspects of uncertainty
ture. It is often associated with post project reviews where can be categorised and treated as risks, and risk, generally
learning has significant potential to reduce uncertainty. considered as a threat to achievement of project objectives,
However, the value of these reviews may be undermined receives far more overt attention than the broader concept
by factors outlined earlier in this paper, including failure of uncertainty in the traditional view of projects and their
to report important lessons for the future due to cultural management. An inescapable conclusion from the network
issues, especially those surrounding perceptions of failure. meetings was that management of uncertainty is a neces-
When a project is finished, the lessons learned are linked sary condition for effective project management, but that
to whether the project was delivered on time within cost management of uncertainty needs to be given more atten-
and to the agreed quality. The benefits of value manage- tion and be rather more sophisticated than current com-
ment may not be realised for some time after the project mon practice. This paper has outlined directions for
is finished. The question is who writes a post implementa- development of project uncertainty management.
tion review when the team have been disbanded, who pays, Sources of uncertainty are wide ranging and have a fun-
and who would the circulation list of readers be? The damental effect on projects and project management. These
excitement of a new project contains energy to get it started sources are not confined to potential events, and include
while at the end of a project that energy is reduced. How- lack of information, ambiguity, characteristics of project
ever, while Senge [35] presents the need for reflection and parties, tradeoffs between trust and control mechanisms,
reviews, unless those lessons change working practices, and varying agendas in different stages of the project life
no organizational learning has taken place. Now compare cycle. Risk management processes that focus on identifying
that with the notion that projects can be described as a potential events as threats (or opportunities) will not
temporary organisation: the problems involved in learning address many important sources of uncertainty. Further,
within project work start to become evident. So a new common practice project management tends not to address
method of learning from projects needs to be explored many fundamental sources of uncertainty, particularly in
since this is different from typical organisational learning. the conception and post delivery stages of the project life
Potential benefits from learning from experience may be cycle, or in ‘soft’ projects where flexibility and tolerance
affected by the nature of different types of projects and of vagueness are necessary. More sophisticated efforts to
their contexts. As outlined in Section 5 above, the nature recognise and manage important sources of residual uncer-
and degree of uncertainty reduction and therefore control tainty are needed.
that is possible in projects that satisfy mainstream and a Such efforts within a given organisation require some
primarily ‘hard’ conception of projects, may not be either attention to organisational culture, capabilities, and the
feasible or desirable for ‘soft’ projects involving higher lev- development of appropriate infrastructure [4,33]. At a
els of abstraction, stakeholder involvement, and residual basic level, there is a need to understand stakeholder toler-
ambiguity. The same levels of performance expectation, ance or intolerance of uncertainty in processes and out-
and therefore measures of success, may not be appropriate comes. Why is uncertainty tolerated? By whom?
when applied to different types of projects, and this may Inexperienced project owners may be inappropriately intol-
lead to adverse effects in terms of learning. For instance, erant of uncertainty, particularly if they hope to transfer
projects may be categorised as failures due to unrealistic risk and responsibility for managing uncertainty to agents,
expectations. This may lead to transfer of lessons that are and projects exhibit a significant degree of ‘softness’. This
misleading or discourage honest transfer of learning due intolerance of uncertainty may induce project management
to the stigma of failure. If uncertainty is acknowledged, behaviours such as cautious/safe ways of working and
R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698 697

missed opportunities, the mindless/uncritical/mechanical [10] Williams TM, Eden C, Ackerman F, Tait A. The effects of design
application of project management principles and tech- changes and delays on project costs. Journal of the Operational
Research Society 1995;46:809–18.
niques, and actions designed to avoid apportionment of [11] Williams TM, Eden C, Ackerman F, Tait A. Vicious circles of
blame when things do not turn out as hoped. Conversely parallelism. International Journal of Project Management 1995;13:
contractors may be inappropriately tolerant of uncertainty 151–5.
because of optimism, the felt need to accept risk and asso- [12] Cooper KG. Naval ship production: a claim settled and a framework
ciated uncertainty in order to win work, or because of igno- built. Interfaces 1980;10(6):20–36.
[13] Winter, Mark, Smith, Charles. Making sense so far: emerging
rance about the scope of uncertainty present. directions and future research: Interim Report May 2005.
Replacing ambiguity with vagueness is one possible <www.rethinkingpm.org.uk>. 2005; (accessed on 17 June 2005).
method of reducing uncertainty. Managing stakeholder [14] Crawford L, Pollack J. Hard and soft projects: a framework for
expectations is a further method of bringing uncertainty analysis. International Journal of Project Management 2004;22(8):
into project discussions. While this might mean that some 645–53.
[15] Crawford LH, Hobbs JB, Turner JR. Project Categorization
stakeholders are mildly disappointed at the end of a pro- Systems: Aligning Capability with Strategy for Better Results,
ject, this is preferable to having stakeholders being sur- Newtown Square. Pennsylvania: Project Management Institute;
prised by the final outcome of a project. Managing 2005.
expectations transfers the uncertainty of surprise into pos- [16] Crawford L, Costello K. Towards a transferable methodology for
sible disappointment, thus not eliminating the problem, but managing strategic change by projects. In: Crawford L, Clarke CF,
editors. IRNOP IV Conference - Paradoxes of Project Collaboration
transferring the nature of the problem to a different more in the Global Economy: Interdependence, Complexity and Ambigu-
manageable form. ity. Sydney, Australia: University of Technology; 2000.
Uncertainty is created in part by the quality and com- [17] Costello K, Crawford L, Bentley L, et al. Connecting soft systems
pleteness of information, diversity of interests and suscep- thinking with project management practice: an organizational change
tibility to external influences in a project; all of which case study. In: Ragsdell G, editor. Systems Theory and Practice in the
Knowledge Age. New York: Kluwer Academic/Plenum Publishers;
makes us vulnerable to the action of others. The most eco- 2002. p. 002.
nomic method of compensating for gaps in information is [18] Midgley G. Systemic Intervention: Philosophy, Methodology, and
through trust, of which there are many types and levels, Practice. New York: Kluwer Academic / Plenum Publishers; 2000.
each requiring different coping strategies. However, com- [19] Atkinson RW. Project management: cost, time and quality, two
plex projects require the controls of governance. The out- best guesses and a phenomenon, its time to accept other success
criteria. International Journal of Project Management 1999;17(6):
come is for a balance of trust and control, with an 337–42.
acceptance that trust will be ultimately overarching due [20] Thiry M. Combining value and project management into an effective
to the lack of a guarantee of controls. For the practitioner, programme management model. International Journal of Project
the link and dynamics between uncertainty, control and Management 2002;20(3):221–7.
trust could be improved if the factors of trust were included [21] Coopey J. Learning to trust and trusting to learn. Management
Learning 1998;29(3):365–82.
in uncertainty management processes. [22] Munns AK. Potential influence of trust on the successful completion
of a project. International Journal of Project Management
References 1995;13(1):19–24.
[23] Handy C. Trust and the virtual organization. Harvard Business
[1] Buehler R, Griffin D, Ross M. Inside the planning fallacy: the causes Review 1995(May-June):40–50.
and consequences of optimistic time predictions. In: Gilovich T, [24] O’Neill O, A question of trust [Web Page]. <http://www.bbc.co.uk/
Griffin D, Kahneman D, editors. Heuristics and Biases – the radio4/reith2002/1.shtml.2002; (Accessed on 15 April 2002).
Psychology of Intuitive Judgment. Cambridge University Press; 2002. [25] F. Hartman, Smart trust: a foundation for more effective project
[2] Armor DA, Taylor SE. When predictions fail: the dilemma of management, in: Proceedings of 15th IPMA World Congress on
unrealistic optimism. In: Gilovich T, Griffin D, Kahneman D, editors. Project Management, London, 22–25 May 2000, London, IPMA,
Heuristics and Biases – the Psychology of Intuitive Judgment. 2000.
Cambridge, UK: Cambridge University Press; 2002. [26] Zaghloul R, Hartman F. Construction contracts: the cost of mistrust.
[3] Chapman CB, Ward SC. Project Risk Management: Processes, International Journal of Project Management 2003;21:419–24.
Techniques and Insights. second ed. John Wiley & Sons; 2003. [27] Meyerson D, Weick KE, Kramer RM. Swift trust and temporary
[4] Ward SC. Requirements for an effective risk management process. groups. In: Kramer RM, Tyler TR, editors. Trust in Organisations.
Project Management Journal 1999(September):37–42. London: Sage Publications; 1996. p. 166–95.
[5] Eisenhardt KM. Agency Theory: An Assessment And Review. The [28] Cook KS. Trust in society. In: Cook KS, editor. Trust in Society.
Academy of Management Review 1989;14(1):57–74. New York: Russell Sage Foundation; 2001. p. xi–xxviii.
[6] Chapman CB, Ward SC. Managing Project Risk and Uncertainty: A [29] Heimer CA. Solving the problem of trust. In: Cook KS, editor. Trust
Constructively Simple Approach to Decision Making. Chichester, in Society. New York: Russell Sage Foundation; 2001. p. 65–73.
UK: John Wiley & Sons Ltd.; 2002. [30] Dixon M. APM Project Management Body of Knowledge. fourth
[7] Gallagher K. Chaos: project success factors, In: Proceedings of ed. Peterborough, England: Association for Project Management;
Implementing Technology and Project Management Conference, 2000.
September, 1995, pp. 21–36. [31] British Standards Board Guide to project management: BS6079.
[8] Ward SC, Chapman CB. Risk management and the project life cycle. London, British Standards Board, 1996.
International Journal of Project Management 1995;13(3):145–9. [32] Atkinson RW. Information System’s Project Management and the
[9] Flyvbjerg B, Bruzelius N, Rothengatter W. Megaprojects and Risk: Phenomenon of Trust. PhD Thesis. Bournemouth University.
An Anatomy of Ambition. Cambridge: Cambridge University Press; [33] Ward SC. Risk Management Organisation and Context. London:
2003. Witherbys; 2005.
698 R. Atkinson et al. / International Journal of Project Management 24 (2006) 687–698

[34] CAIB Columbia Accident Investigation Board Report, Washington, [36] Smith, Charles, Winter, Mark C. EPSRC Network 2004–2006:
DC, CAIB, NASA and Government Printing Office, 2003. Rethinking Project Management: Meeting 5: Actuality and Uncer-
[35] Senge PM. The Fifth Discipline: The Art and Practice of the Learning tainty: Sensemaking Paper 5 [Web Page]. <http://www.mace.man-
Organisation. London: Bantam Doubleday Dell Publishing Group, chester.ac.uk/project/research/management/rethinkpm/pdf/papers/
Inc.; 1992. actuality_uncertainty.pdf>. 2005; (Accessed on 21 May 2006).

Você também pode gostar