Você está na página 1de 10

Cost Model: Crashing of Network

Article shared by : <="" div="" style="margin: 0px; padding: 0px;


border: 0px; outline: 0px; font-size: 16px; vertical-align: bottom; background:
transparent; max-width: 100%;">
Time aspect is the main and significant aspect in a network. Its
primary object is to complete the project at an earliest to get quicker
realisation of benefits of the project.

Activities on critical path and sub-critical path needs special attention


either to complete the project as per schedule or to reduce the
completion time. To reduce the scheduled time, non-critical activities
can be considered as potential pools of resources for diverting to
critical or near critical activities.

In some projects, it is desirable to cut down the total project time, even
if it leads to increase in cost. It is generally desired where cost
considerations are unimportant or less important than completing the
project in absolute minimum time e.g., defence works in emergency.

Generally it is possible to reduce the project duration by changing the


resources allocated to it. The increase or decrease of the project
duration results in decrease or increase in the cost of the project. For
this purpose, time and costs are analysed in a systematic way. This
analysis also helps in determining optimum duration of the project.

For studying the project time and cost analysis, we shall fast discuss
about project costs and time-cost relationship.

Project Costs:
There are two types of costs associated with a project:
(i) Direct costs:
It represents the expenditure which can be allocated to different
activities in a project, like manpower, material etc.

(ii) Indirect costs:


It represents the expenditure on those items which are shared by more
than one activity and cannot be directly allocated to individual activity
of a project.

Indirect costs of a project are those expenditures which cannot be


apportioned or clearly allocated to the individual activity. These
include the expenditure related to the administration and
establishment charges, overhead, supervision, loss of revenue etc.

Indirect cost rises with increased duration. Relationship between


indirect cost and project duration is shown in Fig. 29.1. This
relationship would be represented by a straight line, with a slope equal
to daily overhead.

When there is a loss of profits due to inability to meet the demand or


some penalty due to delay, a corresponding cost increase (known as
outage loss), must be added to the cost of overheads, as shown in the
Fig. 29.2.
Total cost of a project is the sum of the direct and the indirect costs.
These costs are plotted in Fig. 29.3.

With the help of above curves, we can determine optimum duration,


which is also referred as target duration. If the critical path is equal or
shorter than this optimum duration, there is no need to reduce the
network, i.e., crashing the duration of any activity. If however, the
critical path is longer than the project’s optimum duration, and then
there is need to reduce the duration of some activities, so that the
critical path is equal to the optimum duration.
In order to understand the effect of duration on the total cost of the
project, Fig. 29.4 is drawn.

These curves help the management to determine following


aspects for taking future decisions about the project
duration and resource allocation:
(а) Determining the project duration, for which the cost is least, i.e.,
optimum duration of the project at which the cost is optimum.

(b) Determining the least cost of a reduction in project duration from a


stipulated date. This is done when the stipulated date is earlier than
the optimum time for the project.

(c) Determining the time-cost-risk relationship. In this, risk involved


in eliminating any activity is calculated. This time-cost risk helps the
management to take a decision about most economical solution, based
on the circumstances and the objectives of a particular situation.

This shows that the network technique is an analytical tool for better
planning, scheduling, monitoring and decision-making.

Crash Point and Normal Point:


Fig. 29.5 shows variation in the cost of an activity with time. The figure
also indicates that there is critical point in time beyond which it will
become probably expensive to try to shorten the time schedule of an
activity.
It also indicates that lengthening of an activity more than a certain
time duration results in negligible cost savings. First such point is
“Crash Point” while second such point is known as “Normal Point”, as
shown in the Fig. 29.5.

Cost Slope:
In actual practice, we assume the time-cost curve to be linear between
crash point A and Normal point B. The curve has shown in Fig. 29.5
shows that, there is a change in cost for change in time. The term ‘cost-
slope’ is defined as the “increase in the cost of the activity per
unit decrease in the time”.
Mathematically, we can say,

Cost slope = Crash cost – Normal cost/Normal time – Crash time

In simple words, we can say that cost slope of an activity is the


increase in cost of an activity by reducing the duration by one unit.

Conducting a crash programme usually result in an increase in cost of


those activities that are constructed under the crash programme. In
order to keep the total increase in cost to a minimum, it is necessary to
crash those activities which permit reduction in construction time at
the least total increase in cost. The reduction in time for a project can
be achieved by reducing the duration of one or more activities lying on
the critical path.

Crashing Procedure:
The cost slope concept helps in finding lowest cost solution by
sequential compressing the activities having lowest cost slope, i.e.,
having lowest incremental cost, on critical path.

Sometimes by crashing one activity, critical path is shifted; therefore,


at each shift of the critical path, it will be necessary to calculate the
cost-slopes of the activities on new critical path. Then the activity
having the lowest cost slope needs to be compressed on this new
critical path. This process is repeated until the project crash point is
reached.

Procedure for crashing a project is explained hereunder:


(i) The ratio of increase in cost to decrease in time for each activity
that can be crashed on the critical path is calculated and compared.

(ii) The activity having the lowest ratio is reduced to the next lower
time value.

(iii) The critical path for the network is again calculated using the new
time for the crashed activity.

(iv) Repeat step (ii) and (iii) until the critical path is equal to optimum
project duration or equal to prescribed project duration.

Example 1:
For a network shown in Fig. 29.6, Normal time, Crash time, Normal
cost and Crash costs are given in the table. Contract the network by
crashing it to optimum value and calculate the optimum project cost.
Indirect cost is given as Rs. 100 per day.
Solution:
By drawing the network with normal duration, we see (from following
figure) that critical path is 1-2-3-4-5.

The project duration is, therefore, equal to 18 days. On this path,


Crash time = 13 days (from given data on critical path).

Normal cost and crash cost can now be calculated by adding values of
all the activities, given in the table.

Normal cost = Rs. 4100 and Crash cost = Rs. 4900.

To construct the network, in first stage we should identify those


activities on critical paths, which have cost-slopes less than the
indirect cost. For this purpose cost slopes are calculated hereunder
Critical path activities 2-3 and 4-5 have least cost slopes. Therefore,
these activities are first crashed and network is again drawn (Refer
Fig. 29.8).

This network shows that, after crashing activities 2-3 by 2 days and 4-
5 by 1 day, the critical path is same, i.e. 1-2-3-4-5 and have 15 days
duration.

Now in second stage, the least cost slope in remaining activities is for
activity 3-4 on the critical path.
By crashing this activity, we see that two paths become
critical path, 1-2-3-4-5 and 1-2-4-5 as shown in Fig. 29.9
below:

Now we see that after crashing activities 2-3, 4-5 and 3-4, there is no
other activity on both the critical paths which have cost slopes less
than indirect cost. This shows that this is the optimum network and
hence optimum project duration is 14 days.

Total direct project cost for this optimum duration

= Direct cost for all activities on the network

= Cost on activities 1-2; – 2-3; 2-4; 2-5; 3-4; 4-5

= 300 + 520 + 2100 + 400 + 360 + 520 = Rs. 4200.

And indirect cost for 14 days @ Rs. 100 per day = Rs. 1400

Total project cost after crashing = 4200 + 1400 = 5600.

Whereas total cost with all normal activities was (i.e. without crashing)

= Normal cost + Indirect for 18 days = 4100 + 1800

= Rs. 5900.

Thus the optimum cost of the project is Rs. 5600. By crashing to


optimum value, we could save Rs. 300. If we further crash the project
beyond optimum value, the project shall become costlier.

Você também pode gostar