ADMINISTRATION BUILDING TYPE 2

DRAWING ACTION STATUS STATUS


GUIDE Submitted to K&A AFC
EXCAVATION Submitted to K&A (24.12.2018) -
Shuttering Dwg Submitted to K&A (24.12.2018) -
REINFORCMENT DWG Submitted to K&A (24.12.2018) -
MECHANICAL Not Received FROM TML -

SECURITY & SAFTEY BUILDING TYPE 2


DRAWING ACTION STATUS STATUS
GUIDE Submitted to K&A B
EXCAVATION Submitted to K&A (20.12.2018) B
Shuttering Dwg Submitted to K&A (20.12.2018) C
REINFORCEMENT DWG Submitted to K&A (20.12.2018) C
MECHANICAL Not Received -

MOSUQE TYPE 1
DRAWING ACTION STATUS STATUS
GUIDE Submitted to K&A B
EXCAVATION Not Received FROM TML -
Shuttering Dwg Not Received FROM TML -
REINFORCEMENT DWG Not Received FROM TML -
MECHANICAL Not Received FROM TML -

SECURITY GUARD BUILDING


DRAWING ACTION STATUS STATUS
GUIDE Submitted to K&A AFC
EXCAVATION Submitted to K&A (25.12.2018) B
Shuttering Dwg Submitted to K&A (25.12.2018) C
REINFORCEMENT DWG Submitted to K&A (25.12.2018) C
MECHANICAL Not Received -